CLIENT: CONSULTANT: CONTRACTOR:

DAILY REPORT
Report No. J220/RC/DR/262

Project: Samana Miami-1 Date: 15-Apr-24

Client SAMANA SIA HOLDINGS LIMITED Weather : Sunny Cloudy Rainy


Consultant AREC ENGINEERING Temperature: Max: 29° Min: 20°
Main Contractor Reliant Contracting LLC Humidity: High Medium Low

Manpower Equipment
Office Staff No. Production Workers No. Type Qty Manpower Hours Worked
GENERAL Manager 1 Carpenter 38 Power Generator 1
PROJECT Manager 1 Steel Fixer 17 Bobcat 1
Site Engineer 2 Mason 6 Welding Machine 1
Asst. Const. Manager - Labor/Helper 7 Tower Crane 1
Planning Engineer 1 Electrician 4 Bar bending Machine 1
MEP Coordinator 1 Painter 4 Vibrator 1
QA/QC Engineer 1 Mechanic Compactor 1
Safety Officer. 1 Plumber 1 Boom Loader 1
Civil Forman 2 Crane Operator 1 Bar Cutting Machine 1
Electrical Forman 1 Rigger 1 1 ton Roller
Plumb. Forman - 6 ton Roller
Driver 4 Excavator
Sub-Contractors:
Office Boy/Cleaner 1 Shovel
Security/Watchman 1 PT Anglo East

Store/Time Keeper 1 Aroos Al Saeed Block & Plaster

Almamr Alnader Technical


HR/Document Controller 1 Works L.L.C
12
Safety Officer.Asst.. AK Building Contracting 21
Surveyor 1 Swad Allail General Contracting 2
Surveyor Asst. 1 Jehanzeb Technical Service 2
Trade Foreman -

Total 21 116 9 137 Total= 1465

Work Target for Today:


1. Roof to Upper Roof Core wall-1 Shuttering Upper Roof
2. 1st Floor Swimming Pool Decking Area Curing (Casting Date: 06-April-2024) 1st Floor
3. 1st, 2nd & 3rd Floor Block work Curing 1st Floor
4. 1st Floor Cutting & Chasing 1st Floor
5. 1st Floor Plaster Guide Point Completed 1st Floor
6. 2nd Floor Plaster Guide Point Completed 2nd Floor
7. 2nd Floor Cutting & Chasing 2nd Floor
8. 4th Floor Block work Fixing & Curing 4th Floor
9. 5th & 6th Floor Block Work Layout Completed
10. 5th to 6th Floor Staircase-2 Curing (Casting Date: 06-April-2024) 6th Floor
11. Roof Floor Cleaning Roof
12. Safety & Site Cleaning work in progress
Work Target for Next day:
1. Roof to Upper Roof Core wall-1 Casting Upper Roof
2. 1st Floor Cutting & Chasing 1st Floor
3. 1st Floor Plaster Guide Point Completed 1st Floor
4. 2nd Floor Plaster Guide Point Completed 2nd Floor
5. 2nd Floor Cutting & Chasing 3rd Floor
6. 4th Floor Block work Fixing & Curing 4th Floor
7. 5th & 6th Floor Block Work Fixing
8. Substation Door & Windows Fixing & I.R Submission
9. Roof to Upper Roof Slab Shuttering & Steel Fixing Upper Roof
10. Roof Floor Cleaning Roof
11. Safety & Site Cleaning work in progress
Material at Site
1. Plywood
2. Scaffolding
3. 3"x3" Timber
4. Blocks
5. Sikanjas.
6. Post Tension Cables
7. Reinforcement Steel
8. Cement
9. Tower crane sections.
Note:
Consultant Eng.: Cont. Engineer: Eng. Sameer Alzebdeh