Slab Casting Schedule 16-02-2024

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 1

Activities Planned Actual Concrete Casting Dates Expected Dates for Concrete Slab Cycle in Days Remarks

Completion as Casting
per baseline Part-1 Part-2 Part-1 Part-2
Sub-Structure and Grade Slab 16 OCT 2023 13 Oct 2023 23 Oct 2023 Completed

Podium Slab 17 NOV 2023 01 Nov 2023 21 Nov 2023 29 Completed

1st Floor Slab 18 DEC 2023 12 Nov 2023 26 Dec 2023 35 Completed

2nd Floor Slab 09 JAN 2024 02 Jan 2024 09 Jan 2024 14 Completed

3rd Floor Slab 03 Feb 2024 15 Jan 2024 20 Jan 2024 11 Completed

4th Floor Slab 29 Feb 2024 26 Jan 2024 01 Feb 2024 12 Completed

5th Floor slab 28 Mar 2024 09 Feb 2024 16 Feb 2024 15 Completed

6Th Floor Slab 25 Apr 2024 22 Feb 2024 28 Feb 2024 12

Roof Slab 24 May 2024 05 Mar 2024 09 Mar 2024 10

Mumty Roof Slab 14 Jun 2024 15 Mar 2024 6

Client Consultant Contractor

Project: Samana Miami-1 Subject: Slab Casting Schedule Date of the update: 16 February 2024
Revised