Slab Casting Schedule 16-02-2024
Slab Casting Schedule 16-02-2024
Slab Casting Schedule 16-02-2024
Completion as Casting
per baseline Part-1 Part-2 Part-1 Part-2
Sub-Structure and Grade Slab 16 OCT 2023 13 Oct 2023 23 Oct 2023 Completed
1st Floor Slab 18 DEC 2023 12 Nov 2023 26 Dec 2023 35 Completed
2nd Floor Slab 09 JAN 2024 02 Jan 2024 09 Jan 2024 14 Completed
3rd Floor Slab 03 Feb 2024 15 Jan 2024 20 Jan 2024 11 Completed
4th Floor Slab 29 Feb 2024 26 Jan 2024 01 Feb 2024 12 Completed
5th Floor slab 28 Mar 2024 09 Feb 2024 16 Feb 2024 15 Completed
Project: Samana Miami-1 Subject: Slab Casting Schedule Date of the update: 16 February 2024
Revised