KOH PICH CONSTRUCTION COMPANY

CAMBODIA-CHINA POLYTECHNIC UNIVERSITY


DAILY ACTIVITIES REPORT

Main Contractor: KPCC


Issued Date: Monday, June 01, 2020 Issued No: CCPUI-031/2020
GROUP POSITION ATTENDANT DESCRIPTION
Project manager 1 Office and Site Management

Site supervisor 1 Site labor managerment

Arc. supervisor 1 Arc. drawing and technical management

QS engineer and Assistance 2 Prepare document such as payment claim, drawing, contract, other proposal and site inspection

Office MEP engineer and Assistance 2 Prepare document such as as-built,drawing, boq, other proposal and site inspection

Site engineer staff and Assistance 4 Follow up site progression, make report and site inspection

Surveyor engineer 1 Set up and checking coordinate for site installation,

Admins and Assistance 2 Prepare fix Asset, Prepare workers and Staff's OT, tick attendance, transfer request to central, prepare other proposal

Warehouse staff and Assistance 5 Stock Control, Material Purchasing.

Site Safety Safety 8 Strengthen discipline and safety in site

Site survey Survey 2 Follow up site progression, check level and coordination for site installation and do report.

Site MEP MEP 19 Standby for M&E, electrical work & AC system

Tower crane S.Workers 1 Standby for tower crane

Headman 1 Brick work at 6th floor

S56 S.Workers 18 Brick and platering work at top roof left of the building

Workers 5 Site cleaning area

Headman 1 Making and installing steel handrail and gutter

S18 S.Workers 10 Site cleaning area

Workers 6

Headman 1 Installing pebble stone for curb garden, Moulding work for main gate

D27 S.Workers 21 Exterior platering work at behind of the building

Workers 16 Interior platering work at side of the building from 6th to 1st floor, Site cleaning area

Headman 1 Installing scaffolding for dimond at top roof installing

S55 S.Workers 3 Site cleaning area


KPCC

Workers 1

Headman 1 Brick and platering work for wood panel at roof main entrance

S13 S.Workers 4 Site cleaning area

Workers 5

Headman 1 Brick and platering work for frame window behind the building from 6th to 1st floor

S26 S.Workers 9 Site cleaning area

Workers 2

Headman 1 Cutting and platering for frame window

S16 Koh pich S.Workers 3 Site cleaning area

Workers 0

Headman 0 Brick and platering work at top roof right of the building

S19 S.Workers 9 Site cleaning area

Workers 5

Headman 0 Brick and platering work sanitary room in the building

T67 S.Workers 6 Site cleaing area

Workers 6

Headman 1 Curb ramp installing

S15 S.Workers 5 Site cleaing area

Workers 1

Headman 1 Brick and platering work for wood panel at top roof at the side of the building

S87 S.Workers 12 Installing dimond for top roof at the side of the building

Workers 3 Site cleaing area

Headman 0 Site cleaning and site material preparation

Team site cleaning S.Workers 0

Workers 7

Driver S.Workers 2 Standby for material and worker mobilization

Page1
Headman 0 Platering for roof ridge
Moulding
S.Workers 6 Cleaning area
decoration
Workers 0

Headman 0 Painting ceiling board at 1st and 2nd floor

Ceiling S.Workers 8 Cleaning areas

Workers 0

Headman 0 Installing marb for staircase

Marble work S.Workers 4 Cleaning areas

Workers 0

Headman 0 Interior Skimcoat Work at 5th floor


Subcon.

Interior painting S.Workers 4 Cleaning areas

Workers 0

Headman 0 Exterior platering

Exterior painting S.Workers 7 Apply plastic for protect glass window

Workers 0 Cleaning areas

Headman 0 Installing frame and glass for window

Diamond glass S.Workers 5 Cleaning areas

Workers 0

Headman 0 Installing frame and door

CID S.Workers 5 Cleaning areas

Workers 0

DESCRIPTION Number Labor

Brick work, plaster, installing and uninstalling scaffolding, KPCC Internal Subco. External Subco.
KPCC
Concrete work, tile roof, site arrangement and material preparation
Summary

Moulding decoration around, installing frame and glass window 185 16 23


Internal Subco
Installing wood door

Ceiling work, apply primer for exterior painting Total Labor


External Sub
Marble work, interior painting work 224

Project Manager Reported By:

RITH RAVIN LAY SAMBO

Page2
KPCC Project CAMBODIA-CHINA POLYTECHNIC UNIVERSITY
Daily Report

CCPU Project Work Report


Name: Daily Report
 ※Details of performance (specifical description) 01.06.2020 Weather (Hot) ○
【Today's Work】
Description Work time Number worker
Brick and platering work at top roof left of the building 7:00 - 17:00 18
Brick work at 6th floor 7:00 - 17:00 6
Making and installing steel handrail and gutter 7:00 - 17:00 17
Installing pebble stone for curb garden, Moulding work for main gate 7:00 - 17:00 8
Exterior platering work at behind of the building 7:00 - 17:00 10
Interior platering work at side of the building from 6th to 1st floor 7:00 - 17:00 20
Installing scaffolding for dimond at top roof installing 7:00 - 17:00 5
Brick and platering work for wood panel at roof main entrance 7:00 - 17:00 10
Brick and platering work for frame window behind the building from 6th to 1st floor 7:00 - 17:00 12
Cutting and platering for frame window 7:00 - 17:00 4
Brick and platering work at top roof right of the building 7:00 - 17:00 14
Brick and platering work sanitary room in the building 7:00 - 17:00 12
Curb ramp installing 7:00 - 17:00 7
Brick and platering work for wood panel at top roof at the side of the building 7:00 - 17:00 10
Installing dimond for top roof at the side of the building 7:00 - 17:00 6
Site cleaning and site material preparation 7:00 - 17:00 7
Platering for roof ridge 7:00 - 17:00 6
Painting ceiling board at 1st and 2nd floor 7:00 - 17:00 8
Installing marb for staircase 7:00 - 17:00 4
Interior Skimcoat Work at 5th floor 7:00 - 17:00 4
Exterior platering and apply plastic for protect glass window 7:00 - 17:00 7
Installing frame and glass for window 7:00 - 17:00 5
Installing frame and door 7:00 - 17:00 5
Standby for MEP, electrical work & AC system 7:00 - 17:00 19
Total labour 224
【Plant and Machinery Name】 Description Work time
EX81 Soil preparation 7:00-17:00
B61 Soil preparation 7:00-17:00
DT60 Soil transportation 7:00-17:00
Morning Afternoon Rain Hours
【Rainy Report】
None None

【Percentage of progress for CCUPI 】

Task Description Unit Quantity Today's work (%) Completion's work (%)

Brick wall work Sq.m 8331.4 85%


Interior painting Sq.m 13955.00 50%
Exterior painting Sq.m 3779.10 9%
Ceilling work Sq.m 7068.00 75%
Tile work Sq.m 6577.87 70%
Glass work Sq.m 2069.25 70%
Door work Ls 149.00 15%
Moulding decoration work Sq.m 660.00 80%
Handrail work Sq.m 178.16 50%
Marble work Sq.m 1000.37 85%

Page 2
KPCC Project CAMBODIA-CHINA POLYTECHNIC UNIVERSITY
Daily Report

CONSTRUCTION DAILY PHOTO FOR CCPU PROJECT

Photo Photo

Exterior painting work Exterior painting work

Ceiling board painting Ceiling board painting

Wood door installation Wood door installation

Page1
KPCC Project CAMBODIA-CHINA POLYTECHNIC UNIVERSITY
Daily Report

CONSTRUCTION DAILY PHOTO FOR CCPU PROJECT


Photo Photo

Installing wood door Installing wood door

Curb pebbles stone Pebbles stone

Plastering work at the side of the building Corner plaster behind of the building

Page2
KPCC Project CAMBODIA-CHINA POLYTECHNIC UNIVERSITY
Daily Report

CONSTRUCTION FIX POINT FOR CCPU PROJECT


30/05/2020

Photo

Front View

Back View

Page1
KPCC Project CAMBODIA-CHINA POLYTECHNIC UNIVERSITY
Daily Report

CONSTRUCTION FIX POINT FOR CCPU PROJECT

Photo

East View

West View

Page2

You might also like