Koh Pich Construction Company Cambodia-China Polytechnic University Daily Activities Report
Koh Pich Construction Company Cambodia-China Polytechnic University Daily Activities Report
Koh Pich Construction Company Cambodia-China Polytechnic University Daily Activities Report
QS engineer and Assistance 2 Prepare document such as payment claim, drawing, contract, other proposal and site inspection
Office MEP engineer and Assistance 2 Prepare document such as as-built,drawing, boq, other proposal and site inspection
Site engineer staff and Assistance 4 Follow up site progression, make report and site inspection
Admins and Assistance 2 Prepare fix Asset, Prepare workers and Staff's OT, tick attendance, transfer request to central, prepare other proposal
Site survey Survey 2 Follow up site progression, check level and coordination for site installation and do report.
Site MEP MEP 19 Standby for M&E, electrical work & AC system
S56 S.Workers 18 Brick and platering work at top roof left of the building
Workers 6
Headman 1 Installing pebble stone for curb garden, Moulding work for main gate
Workers 16 Interior platering work at side of the building from 6th to 1st floor, Site cleaning area
Workers 1
Headman 1 Brick and platering work for wood panel at roof main entrance
Workers 5
Headman 1 Brick and platering work for frame window behind the building from 6th to 1st floor
Workers 2
Workers 0
Headman 0 Brick and platering work at top roof right of the building
Workers 5
Workers 6
Workers 1
Headman 1 Brick and platering work for wood panel at top roof at the side of the building
S87 S.Workers 12 Installing dimond for top roof at the side of the building
Workers 7
Page1
Headman 0 Platering for roof ridge
Moulding
S.Workers 6 Cleaning area
decoration
Workers 0
Workers 0
Workers 0
Workers 0
Workers 0
Workers 0
Brick work, plaster, installing and uninstalling scaffolding, KPCC Internal Subco. External Subco.
KPCC
Concrete work, tile roof, site arrangement and material preparation
Summary
Page2
KPCC Project CAMBODIA-CHINA POLYTECHNIC UNIVERSITY
Daily Report
Task Description Unit Quantity Today's work (%) Completion's work (%)
Page 2
KPCC Project CAMBODIA-CHINA POLYTECHNIC UNIVERSITY
Daily Report
Photo Photo
Page1
KPCC Project CAMBODIA-CHINA POLYTECHNIC UNIVERSITY
Daily Report
Plastering work at the side of the building Corner plaster behind of the building
Page2
KPCC Project CAMBODIA-CHINA POLYTECHNIC UNIVERSITY
Daily Report
Photo
Front View
Back View
Page1
KPCC Project CAMBODIA-CHINA POLYTECHNIC UNIVERSITY
Daily Report
Photo
East View
West View
Page2