1) Issuance of Building and Ancillary Permits
1) Issuance of Building and Ancillary Permits
1) Issuance of Building and Ancillary Permits
The Office of the Building Official (OBO) regulates the construction, repair, and improvement of
various structures in the City of Antipolo based on the guidelines provided in P.D. 1096 otherwise
known as the National Building Code of the Philippines. All applications are subject for evaluation of
technical requirements and inspection prior to payment of permit fee and release of approved permit.
I. NEW APPLICATION
A. DOCUMENTARY No. of Copies
1. Locational / Zoning Clearance 2
2. Proof of Ownership
a) Certified true copy of Transfer Certificate of Title 2
In case the TCT is not yet in the name of the applicant:
In addition to the above:
a) Deed of Absolute Sale / Contract of Sale, or 2
b) Lease Agreement (with consent of the lessor), or 2
c) Contract of Lease (with consent of the lessor) 2
3. Signatories
a) Registered Owner
b) If not under the applicant's name, either of the
following documents, duly notarized)
b.1) Special Power of Attorney – SPA 2
b.2) Secretary's Certificate / Board Resolution 2
(if under Corporation)
b.3) Consent of co-owners if TCT is under 2
multiple ownership
4. Clearance from other agencies/departments
a) Fire Safety Clearance (Bureau of Fire Protection) 2
b) Tax Declaration (certified true copy) 2
c) Tax Clearance and Tax Receipt (updated) 2
d) DPWH Clearance (if structure is fronting 2
National Road or adjacent to creek/river)
e) DOLE Clearance 2
f) For Commercial / Industrial (if applicable and
upon evaluation)
f.1) LLDA Clearance – (Visit llda.gov.ph for their 2
requirements)
f.2) EMB Clearance – (Visit emb.gov.ph for their 2
requirements)
f.3) DOH Clearance – (Permit to Construct for 2
Clinics/Hospitals)
f.4) DOTC Clearance – Department of 2
Transportation
f.5) DENR Clearance – (Permit to cut trees) 2
f.6) Clearance from the Civil Aviation Authority 2
of the Philippines (CAAP)
f.7) Clearance from the Mines and Geosciences 2
Bureau
3. Payment
1. Application
4. Issuance
Submit two (2) Check the Official Receipt, receive 3 minutes Frontline
photocopies of the the photocopies and advise the Personnel
Official Receipt to client of the release date of the
OBO for the issuance permit.
of Wiring Permit and
CFEI. Assign permit number and register 5 minutes Frontline
the application in the database. Personnel
Present the follow-up Check the documents, request the 3 minutes Frontline
stub, valid ID and client to sign in the Release Personnel
authorization letter, if Logbook and issue the Wiring
applicable, to claim the Permit and CFEI.
Wiring Permit and
CFEI
1. Application
3. Payment
4. Issuance
Proceed to the Antipolo (Antipolo City Fire Station) (depends on City Fire Marshal
City Fire Station Check the requirements and the ACFS’s
(ACFS) and secure Fire issue Fire Safety Clearance. processing
Safety Clearance. Conduct inspection if the time)
application so requires.
1. Application
Receive the Notice of Request the client to sign in the 3 minutes Frontline
Inspection and copy of Release Logbook and issue Personnel
the Mission Order. Notice of Inspection and copy of
the Mission Order.
3. Payment
4. Issuance
Return to OBO and Check the Official Receipt and 1 minute Frontline
present the Official forward to the Enforcement and Personnel
Receipt for the Inspection Division.
issuance of Certificate
of Annual Inspection. Prepare the Certificate of Annual 5 minutes Staff,
Inspection. Enforcement
and Inspection
Division
1. Application
3. Payment
4. Issuance
Present the follow-up Approve and sign the Permit. 5 minutes Building Official
stub, valid ID and
authorization letter, if Check the documents, request 3 minutes Frontline
applicable, to claim the the client to sign in the Personnel
approved Mechanical Release Logbook and issue
Permit the Mechanical Permit
: Based on the New Schedules of Fees and Other Charges #9 Accessory Fees, (h) of the
IRR of PD 1096
1. Application
3. Payment
4. Issuance
B. If applied separately
1. All requirements under Item A
2. Photocopy of a certified true copy of Transfer Certificate of Title (TCT) or Deed of
Absolute Sale
3. Lease Agreement together with a duly authorized consent/authority from the lot
owner to construct the fence wall
4. Barangay Clearance
5. Homeowners Association (HOA) Clearance, if applicable
6. Tax Declaration
7. Updated Real Property Tax Receipt
8. Affidavit of Undertaking (if necessary)
9. Lot plan with vicinity map, location plan and topographic survey signed and
sealed by a licensed geodetic engineer
10. Certificate of Actual Lot Survey from registered geodetic engineer (for non-
subdivision project)
11. Survey Permit from the Zoning Administrator (for non-subdivision project and
which lot area being applied for fencing permit is 1,000 sqm and above)
12. DOLE Clearance (if the materials to be used for fencing is reinforced concrete or
CHB and if height is more than 2 meters)
: Based on the New Schedules of Fees and Other Charges #9 Accessory Fees, (h) of the
IRR of PD 1096
1. Application
3. Payment
: Based on the New Schedules of Fees and Other Charges #9 Accessory Fees, (h) of the
IRR of PD 1096
1. Application
3. Payment
3. Payment
4. Issuance