Cumulator Coomey
Cumulator Coomey
Cumulator Coomey
Do
MANIFOLD not tighten and compress the packing.
Step 1: Turn the discharge side to face up. (This
is the side with the least number and shortest studs.) NOTE
Insert new valves (4) and check to see that each It is recommended to apply an anti-
anti-seize
valve (4) moves freely, place the new valve springs thread compound to the stuffing box (15)
(5) on top of each valve. thread.
Step 2: Inspect the gasket sealing deck area for Step 7: Clean and inspect each plunger (20)
any gouges, dings, or pits; then install the new assembly. If there are pits, cracks, or longitudinal
discharge valve cover gaskets (6). scoring lines, discard and replace with new plungers
(20). Also, examine the plunger coupling nut (21)
Step 3: If reusing the discharge valve stops (7), and plunger retaining ring (22). Loose fitting plunger
clean and inspect for any gouges, dings, or pits that retaining rings (22) should be discarded and
would prevent the parts from properly sealing. Next, replaced with new ones. The plunger retaining ring
place the discharge valve stop (7) over each valve (22) should be replaced any time the plunger (20) is
spring (5) with the small end down and the threaded replaced.
hole up.
Step 8: Apply a thin film of lubricant to the surface
Step 4: Replace the discharge valve cover (9) and of the plunger (20) and insert through the stuffing
the nuts (8) to secure the assembly. Nuts (8) should box gland nut (19) into the gland follower (18) until
be torqued to the recommended load as shown in engaging the packing (17). Push, or lightly tap with
the Torque Specification Table (Chart 3.1). a rubber mallet, to drive the plunger (20) past the
packing (17).
3.4.4 REASSEMBLY OF SUCTION
MANIFOLD 3.4.5 MOUNTING FLUID CYLINDER
Step 1: Turn the suction or stuffing box side to ASSEMBLY
face up. (This is the side with the highest number Step 9: Attach a sling and use a power lift to return
and longer studs.) Insert new valves (4) and check the fluid cylinder (1) assembly to the power frame.
to see that each valve (4) moves freely; place the Insert the cylinder tie studs (10) through the holes
new valve spring (5) on top of each valve (4). provided on the power frame and carefully guide, but
do not force, the fluid cylinder (1) assembly onto the
Step 2: Inspect the gasket sealing deck area for guide pins located on the front of the power frame.
any gouges, dings, or pits; then install the new Use the nuts (8) to secure the fluid cylinder (1) to the
stuffing box gaskets (13). power frame. Be sure to pull the sides of the fluid
cylinder up to the power frame equally; avoid
Step 3: If reusing the suction valve stops (12), cocking at an angle as this could shear the
clean and inspect for any cracks or excessive wear alignment pin.
and place the suction valve stops (12) in the port on
top of the valve spring (5) with the open end up and Step 10: Bring the plunger (20) and the crosshead
the blocked end down. stub together and thread the plunger coupling nut
(21) onto the crosshead stub. Tighten securely, but
Step 4: Place the previously repacked stuffing avoid over tightening.
boxes (15) onto the fluid cylinder (1). Prior to
installation, inspect the sealing face of the stuffing
box (15) to insure there are no gouges, dings, or pits
to prevent proper sealing.
RPM 1001
06/2002
NO. 1 & 1-
1-1/2 FLUID CYLINDER EXPLODED VIEW
RPM 1001
06/2002
ILLUSTRATION 3.1
BEAR PUMP & EQUIPMENT, INC.
BILL OF MATERIAL
CX-5 D UPL EX and BX-10 TRIPL EX FL UID CYL INDER
NO. 1 CYLINDER (UP TO 1” PLUNGER)
NON-
NON-LUBRICATED STUFFING BOX ASSEMBLIES:
15 2 3 Stuffing Box, Non-
Non-Lubricated (Steel) **
B337B0628900 To 5/8” Plunger
B337B0612900 To 1” Plunger
16 2 3 Throat
Throat Bushing (Cast Iron) **
B341A0740102 For 1/2” Plunger
B341B0669401 For 5/8” Plunger
B341B0669402 For 34” Plunger
B341B0669403 For 7/8” Plunger
B341B0669404 For 1” Plunger
17 2 3 Packing Set (As Specified by Customer)
18 2 3 Gland Follower (Cast Iron) **
B339A0740002 For 1/2” Plunger
B339B0669701 For 5/8” Plunger
B339B0754801 For 3/4” Plunger
B339B0669703 For 7/8” Plunger
B339B0669704 For 1” Plunger
* ITEM 1 INCLUDES
INCLUDES ITEMS 2, 3, 4, 5, 8, 10, & 11
** OTHER MATERIALS AVAILABLE ON REQUEST
CHART 3.33.3
(cont’d. on next page)
RPM 1001
06/2002
BEAR PUMP & EQUIPMENT, INC.
BILL OF MATERIAL
CX-5 D UPL EX and BX-10 TRIPL EX FL UID CYL INDER
NO. 1 CYLINDER (UP TO 1” PLUNGER)
CHART 3.3
3.3
RPM 1001
06/2002
BEAR PUMP & EQUIPMENT, INC.
BILL OF MATERIAL
CX-5 D UPL EX and BX-10 TRIPL EX FL UID CYL INDER
NO. 1-1/2 CYLINDER (UP TO 1-5/8” PLUNGER)
NON-
NON-LUBRICATED STUFFING BOX ASSEMBLIES:
15 2 3 Stuffing Box, Non-
Non-Lubricated (Steel) **
B337B0613600 To 1-
1-1/4” Plunger
B337B0611600 To 1-
1-5/8” Plunger
16 2 3 Throat Bushing (Cast Iron) **
B341B0669405 For 1-
1-1/8” Plunger
B341B0669406 For 1-
1-1/4” Plunger
B341B0669407 For 1-
1-3/8” Plunger
B341B0669408 For 1-
1-1/2” Plunger
B341B0669409 For 1-
1-5/8” Plunger
17 2 3 Packing Set (As Specified by Customer)
18 2 3 Gland Follower (Cast Iron) **
B339B0669705 For 1-
1-1/8” Plunger
B339B0669706 For 1-
1-1/4” Plunger
B339B0669707 For 1-
1-3/8” Plunger
B339B0669708 For 1-
1-1/2” Plunger
B339B0669709 For 1-
1-5/8” Plunger
CHART 3.43.4
(cont’d. on next page)
page)
RPM 1001
06/2002
BEAR PUMP & EQUIPMENT, INC.
BILL OF MATERIAL
CX-5 D UPL EX and BX-10 TRIPL EX FL UID CYL INDER
NO. 1-1/2 CYLINDER (UP TO 1-5/8” PLUNGER)
CHART 3.4
3.4
RPM 1001
06/2002
NO. 2 FLUID CYLINDER EXPLODED VIEW
ILLUSTRATION 3.3
RPM 1001
06/2002
BEAR PUMP & EQUIPMENT, INC.
BILL OF MATERIAL
CX-5 D UPL EX and BX-10 TRIPL EX FL UID CYL INDER
NO. 2 CYLINDER (UP TO 2” PLUNGER)
CHART 3.5
RPM 1001
06/2002