ONITSHA.
Table 1.2: RATIO TEST WITH POTENTIAL AT THE PRIMARY SIDE [33KV]
ry 430v
yb 432v
br 433v
rn 242v
yn 241v
bn 243v
ry 0.9
yb 0.7
br 0.8
rn 0.8
1
yn 0.6
bn 0.7
TEST KV
First 56
Second 60
Third 60
Fourth 60
Fifth 58
Sixth 60
Average is 59.1KV PASS
OBSERVATION
1. No oil leakage
2. The earth pit is WET, which is recommended
3. The transformer sub-station is OK
ITEM REPLACE/ADD:
1. Silica gel
RECOMMENDATION:
REMARKS:
2
TRANSFORMER 11[FACTORY]
Table 1.2: RATIO TEST WITH POTENTIAL AT THE PRIMARY SIDE [33KV]
ry 420v
yb 422v
br 420v
rn 232v
yn 236v
bn 234v
ry 0.8
yb 0.8
br 0.7
rn 0.8
3
yn 0.8
bn 0.7
TEST KV
First 60
Second 59
Third 60
Fourth 60
Fifth 60
Sixth 60
Average is 59.8KV PASS
OBSERVATION
4. No oil leakage
5. The earth pit is WET, which is recommended
6. The transformer sub-station is OK
ITEM REPLACE/ADD:
1. Silica gel
REMARKS: