Neepco Project Report-003
Neepco Project Report-003
Neepco Project Report-003
AGARTALA, TRIPURA
AN INPLANT WINTER TRAINING REPORT ON
135MW AgGBPS, NEEPCO Ltd.
CERTIFICATE
This is to certify that TUSHAR DEB, B.Tech (6th semester), reg. no:
2113461 of the department of mechanical engineering of National
Institute of Technology, Agartala, Tripura has successfully completed this
industrial training from 16/12/2023 to 30/12/2023 under my close
supervision. During the training period he has successfully submitted
report on “Industrial training at AgGBPS, NEEPCO” related to various
plant and instruments used in power plant division. While during the
training period in AgGBPS, NEEPCO, trainee TUSHAR DEB was seen
to be punctual, sincere and hardworking and his behavior is very good.
We wish him all success in life.
I would like to express our gratitude to Dr. Pritam Das (H.O.D), Dept.
of mechanical engineering National Institute of Technology Agartala,
Tripura for allotting this training and supporting us throughout the work.
I would like to express a deep sense of gratitude and thanks to Mr. Nanda
Basumatary, H.O.P of AgGBPS, NEEPCO without whose permission
and wise counsel and able guidance, it would have not been possible to
pursue my training. In this manner the help rendered by Mr. Nirup
Sarma DGM (E/M) and Mr. Gopal Karmakar DGM (E/M), for
experimentation is greatly acknowledged. I would also like to thanks Er.
Joydeep Bhattacharjee (Dy. Manager), Er. Atanu Saha (Asst. Engr.)
and Er. Abhijit Lodh (Asst. Engr.)
Finally, I would also like to express my indebtedness to all who have
directly or indirectly contributed to successful completion of industrial
training. At last, but not the least I would like to thanks all the staff
members of NEEPCO who helped me immensely during my stay.
Sincerely
TUSHAR DEB
3rd Year, 6th semester B.Tech. Mechanical Engineering
National Institute of Technology Agartala, Tripura
3|P age
Abstract
4|P age
➢ Table of contents:
SL NO Description Page no
• Introduction
➢ NEEPCO 8-11
1. ➢ Agartala Gas Based Power
Station (AgGBPS)
➢ Specifications
➢ Combined cycle power station
5|P age
• Water treatment facilities (for
steam turbine)/DM PLANT
6|P age
• Electrical systems
➢ Generator
➢ Switch yard
➢ Transformers
➢ Bus duct
8. ➢ Unit auxiliary transformer (UAT)
➢ Emergency Diesel Generator (EDG) 48-55
➢ Lightening arrestor (LA)
➢ Isolator
➢ Current transformer (CT)
➢ Potential transformer (PT)
➢ Bus bar
9. • Conclusion
56
11. • References.
58
7|P age
1. Introduction
➢ NEEPCO
:-North Eastern Electric Power Corporation Limited (NEEPCO) is a schedule -A
‘MINI RATNA'
The total production capacity of all NEEPCO plants combined is 2057 Mw.
8|P age
➢ AGARTALA GAS BASED POWER STATION(AgGBPS)
The plant has been converted to combined cycle power plant with installation
& commissioning of 4 Nos. HRSG of Thermax make and 2 Nos. Steam Turbine
of Siemens make of capacity 25.5 MW each. The project was financed through
internal resource and external commercial borrowings from SBI, Singapore
with 30:70 debt equity ratio. The plant is presently running as a combined cycle
unit with 2 (two) modules consisting of two Gas Turbines, two HRSGs and one
Steam Turbine in each module.
9|P age
Specification
GTG-1 1-April-1998
GTG-2 1-April-1998
GTG-3 1-April-1998
GTG-4 1-August-1998
STG-1 1-September-2015
STG-2 29-July-2015
10 | P a g e
➢ Combined Cycle Power Plant
Combine cycle is a power producing engine or plant that employs more than one
thermodynamic cycle. Heat engine are only able to use a portion of the energy of
their generation usually less than 50%. The remaining heat from combustion Is
generally wasted.
power plant (CCPP) or combined cycle gas turbine (CCGT) plant, as gas turbine
generator generates electricity, and waste heat is used to make steam to generate
additional electricity via a steam turbine, this last step enhances the efficiency of
electricity generation. As a rule, in order to achieve high efficiency, the
temperature difference between the input and output heat levels be as high as
possible. This is achieved by combining the Brayton (gas) and Rankine (steam)
thermodynamics cycle.
At NEEPCO AgGBPS a combined cycle facility Is set up. The facility consists
of 4 Gas Turbines and 2 Steam Turbines. The gas turbines use natural gas as fuel
for electricity generation. The heat ejected from the gas turbine is not released
into the atmosphere rather it is recovered using
Heat Recovery Steam Generators (HRSG) and is further used to heat water in
the boilers to make steam to run the steam turbines. There is one HRSG for every
gas turbine.
11 | P a g e
2. Gas Turbine and Power
generation
➢ Working principle
“The gas turbine basically operates on the principle of the Brayton cycle,
where compressed air is passed and mixed with the fuel, and burned under
constant pressure conditions. The resulting hot gas is allowed to expand
through a turbine to perform work.”
The Gas turbine engines derive their power from burning fuel in a combustion
chamber and using the fast-flowing combustion gases to drive a turbine in much
the same way as the high-pressure steam drives a steam turbine. A simple gas
turbine is comprised of three main sections a compressor, a combustor, and a
power turbine.
12 | P a g e
Fig: Gas Turbine at AgGBPS
- The air at atmospheric pressure is drawn by the compressor through an air filter
which removes the dust from the air. The rotatory blades of the compressor
push the air between the stationary blades to increase the pressure. Therefore,
the air at high pressure is available at the output of the compressor.
2. Combustion chamber:
- The combustion chamber is an apparatus used to increase the temperature
of the compressed air. Here, the air at high pressure from the compressor is
brought to the combustion chamber through the regenerator.
- In the combustion chamber, heat is added to the compressed air by burning
of fuel oil. The fuel oil is injected through the burner into the combustion
chamber at high pressure to ensure the atomisation of oil and its thorough
mixing with the air. Consequently, the combustion chamber attains a very
high temperature (about 1700 °C). The gases produced by the combustion
are suitably cooled to 700 °C to 800 °C and then delivered to the gas turbine.
3. Starting motor:
- Before starting the gas turbine, the compressor has to be started. For this
purpose, an electric motor (M) is mounted on the shaft of the turbine. This
motor is energized by the batteries. However, once the power plant is
started, a part of mechanical power of the turbine drives the compressor and
13 | P a g e
there is no need of the auxiliary motor now.
4. Gas Turbine:
- The gas turbine is a device which converts heat energy of hot gases into
mechanical energy. The products of combustion consisting of a mixture of
gases at high temperature and pressure are expanded in the gas turbine and
does the mechanical work, i.e., it converts the heat energy into mechanical
energy.
5. Alternator:
- Each alternator is coupled to a steam turbine and converts the mechanical
energy of the turbine into electrical energy. The alternator may be hydrogen
or air-cooled. The necessary excitation is provided by means of main and
pilot exciters directly coupled to the alternator shaft.
14 | P a g e
➢ Thermodynamic Explanation of working
of the gas turbine:-
-“The working of the gas turbine is completely based and performed on the
basis of the Braton Cycle where combustion and heat release are done at
constant pressure rate”.
- The thermodynamic process used by the gas turbine is known as Brayton cycle.
According to the carnot cycle in which efficiency is maximized by increasing the
temperature difference of the working fluid between the input and output of the
machine, where as in the Brayton cycle the efficiency is maximized by increasing
the pressure difference across the machine.
The gas Turbine is basically comprised of the three main parts: Compressor
(Axial), Combustor and a turbine.
Working: The working fluid, air is compressed in the compressor (Adiabatically
compression- no heat gain or loss), then the air and fuel is mixed and burned
by using an ignition under constant pressure condition in the combustion chamber
(constant pressure heat addition). The resulting hot gas is then expanded
thoroughly through the turbine to perform work (adiabatic expansion).
15 | P a g e
➢ Advantages and Limitation of the Gas
Turbine
• Advantages:
- It is simple to design and construct as compare to steam turbine
- In gas turbine boiler are not required so they are compact and much smaller
in size as compare to steam turbine.
• Limitations:
- The net output of the gas turbine is low since greater power is used for
driving the compressor.
- The overall efficiency of the plant is low as 20% because of the exhaust
gases still containing heat.
- We can increase the efficiency by using the combine cycle to use that
exhaust gas efficiently as compare to release it into atmosphere.
16 | P a g e
3. Heat Recovery Steam Generator
(HRSG)
The HRSG is basically a heat exchanger, or rather a series of heat exchangers, It
is also called a boiler, as it creates steam for the steam turbine by passing the hot
exhaust gas flow from a gas turbine or combustion engine through banks of heat
exchanger tubes, The HRSG can rely on natural circulation or utilize forced
circulation using pumps. As the hot exhaust gases flow past the heat exchanger
tubes in which hot water circulates, heat is absorbed causing the creation of steam
in the tubes. The tubes are arranged in sections, or modules, each serving a
different function in the production of dry superheated steam. These modules are
referred to as economizers, evaporators, superheaters/reheaters and preheaters.
17 | P a g e
➢ Principle Of Operation:
The economizer is a heat exchanger that preheats the water to approach
the saturation temperature (boiling point), which is supplied to a thick-
walled steam boiler. The boiler is located adjacent to finned evaporator
tubes that circulate heated water. As the hot exhaust gases flow past the
evaporator tubes, heat is absorbed causing the creation of steam in the
tubes. The steam-water mixture in the tubes enters the steam boiler where
steam is separated) from the hot water using moisture separators and
cyclones. The separated water is recirculated to the evaporator tubes.
Steam boilers also serve storage and water treatment functions
In some designs, duct burners are used to add heat to the exhaust gas
stream and boost steam production, they can be used to produce steam
even if there is insufficient exhaust gas flow.
18 | P a g e
Saturated steam from the steam boilers or once-through system is sent to the
super-heater to produce dry steam, which is required for the steam turbine.
Preheaters are located at the coolest end of the HRSG gas path and absorb energy
to preheat heat exchanger liquids, such as water/glycol mixtures, thus extracting
the most economically viable amount of heat from exhaust gases.
The superheated steam produced by the HRSG is supplied to the steam turbine
where it expands through the turbine blade imparting rotation to the turbine shaft.
The energy delivered to the generator drive shaft is converted into electricity.
After exiting the steam turbine, the steam is sent to a condenser which routes the
condensed water back to the HRSG.
19 | P a g e
➢ PARTS OF HRSG:
• Economizer:
The Economizer sections raise the boiler food water to a suitable approach
temperature. Evaporator: The HP and LP evaporator systems are of natural
circulation. Each pressure evaporator section consists of evaporator heat transfer
section, steam boiler, down comers, and risers. The heat transfer section consists
of multiple rows of finned tubes, Lower and upper headers, manifolds, vents and
drains are included.
20 | P a g e
• Boiler Feed Pump (BFP):
The boiler feed pump is employed to feed the water from LP drum to HP drum
through Economizer. NEEPCO uses16 stage feed pump which is powered by a
250 KW motor rotating at a speed of 2970 rpm. The speed of the pump is
controlled by hydraulic coupling or scoop. Mechanical sealing is provided to the
boiler feed pump. To maintain a stable thrust on the boiler a balancing line is
installed in the BFP stuffing box, NEEPCO have arranged two BFP for each of
the HRSG, among which one is employed to service & another is kept in standby.
21 | P a g e
• Dosing system:
- A chemical dosing system to dose phosphate solution to the boiler water
has been provided to condition the boiler water to control scale forming
components. Under these two types of dosing is done namely HP
dosing& LP dosing.
22 | P a g e
• High pressure (HP) Steam Drum:
• The steam drums are steam/water separators, storage tanks, and water
treatment sites for steam purity control. The steam/water mixture
entering the drum from the riser tubes usually 5-10% steam
depending on the boiler load and pressure. In the steam drum,
saturated steam is separated from the steam/water mixture. The
separator steam rises up through the drum as feed water enter the
drum from economizer.
• The separated water from the steam/water mixture is then recirculate
together with the feed water to the heat absorbing evaporator tubes
through the circulation loop. The water flows down the cylinder wall
by gravity and is discharged from the cyclone through an annulus
located below the water level. The separated water returns to the
boiler cycle virtually free of steam. Each steam drum head includes
an elliptical manhole, providing access to drum internals and
connections for the remote level indicators, level gauges, and other
control instruments. Each steam drum also contains. Connections for
pressure safety relief valves, vents, pressure indicators, nitrogen
blankets, downcomers, riser pipes, continuous blow down, chemical
feeds and other control instruments. The drum vents are used to vent
air during boiler filling and venting non- condensable gas during start
up. Its rated pressure is 66Kg/cm²
23 | P a g e
initial filling. To increase its efficiency the water is taken through
CPH when generation reaches 7MW. It also consists of drum vent.
Its rated pressure is 6kg/cm.
24 | P a g e
4. WATER TREATMENT FACILITY
(DM PLANT)
Sources of Water:
• There are 3 types of sources of water:-
1. Surface water-River water, lake water, pond water etc.
2. Ground water -Bore water, well water.
3. Sea water-Sea Water.
NEEPCO- AgGBPS uses ground water (bore water) for steam production.
➢ Reservoir:
- Reservoir is used for water storage purpose. Water is taken from here
for DM water process work. High-Rate Solid Contact Clarifier: This
clarifier is a high rate, solid contact, sludge re- circulation type
clarifier, which is minimum time and space and using a minimum
amount of Chemicals, produces an effluent of the highest quality, it
is used principally for clarification, lime softening, silica reduction
or organics reductions of water and waste water containing
suspended solids, colour and organic impurities. As such, it provides
a means for chemical addition and mixing, Flocculation and up flow
clarification in a single unit.
25 | P a g e
Fig: Reservoir
➢ Water Treatment Process:
- In power plant water is known as the heart of the plant, so it is most
necessary to supply salt free water for process. The demineralization
is the process of removing mineral salts from water by using ion
exchange process. The D.M water reduces the scale formation,
Deposition and corrosion of tubes. It increases the life of pipes and
tubes in plant. It prevents the deposition of minerals in turbine
blades. It removes Mineral salts in the form of cations such as
sodium, calcium, iron, copper and anions such as chloride, sulphate,
nitrate etc. Also, various other parameters of water like hardness, pH
(acidity-alkalinity), conductivity, etc. are check to make the water
have optimum characteristics for steam production.
2) Pre-Treatment
1) De-Mineralization
26 | P a g e
➢ Pre-Treatment:
• First water is extracted from natural underground reserves using
bore-well and stored in reservoir. This water contains a lot of
impurities specially mud, silica, salts, and other solid and gaseous
impurities in dissolved and suspended form.
• The water is then treated with Alum and lime. Alum acts as a
coagulant and removes suspended solids from water. Lime
acts as pH booster.
Fig: Degasser/Aerator
28 | P a g e
• Activated Carbon filtering:
- After activated carbon filtering, the water is sent for Strong Acid
Cation (SAC) treatment in SAC tanks. These tanks contain strong
acid cation resins. The strongly acidic cation exchange resins are
bead-like products which have a sulfonic acid group in the cross-
linked styrene frame. SAC is a cation exchange process. There are
two SAC tanks in the DM plant to carry out this operation. After
SAC treatment the hardness of water is removed and pH of water
obtained is less than 3.5.
- After SAC treatment the water is sent for Strong Base Anion
(SBA) treatment in SBA tanks. It contains strongly basic anion
exchange resin with quaternary ammonium groups
Incorporated into the styrene frame. SBA is an anion
exchange process. There are two SBA tanks in the DM plant
to carry out this operation. After SBA treatment Silica content
In water is less than 0.2 pm, Conductivity less than 5 micro
siemens and pH obtained is 7.8 to 8
29 | P a g e
• Mixed Bed Treatment:
30 | P a g e
Fig: ACF Tank, SAC Tank, SBA Tank
• Degasser:
31 | P a g e
Fig: Bleaching Powder Fig: Retention Chamber
32 | P a g e
Quality of Effluent Water:
The quality of effluent water of SAC, Degasifier, SBA & MB will have
the following property.
pH at 25 ℃ 2.8 to 3.5
pH at 25 ℃ 7.5 to 9.0
33 | P a g e
MB Outlet Water Parameter
pH at 25 ℃ 6.8 to 7.2
34 | P a g e
5. STEAM TURBINE AND POWER GENERATION
➢ Steam Production:
Steam is most essential to run a steam turbine. Steam in a power plant is
produced by heating water in boilers. In NEEPCO-AgGBPS the water
required for steam production is obtained from underground natural
reserves using bore well and is purified by the DM plant and then
supplied to boiler. The heat required to make the steam is obtained from
gas turbines by the use of Heat Recovery Steam Generators (HRSG).
There are also Boiler Feed Pumps (BFP) to assist the process. The steam
produced is of two types i.e., Low Pressure (LP) Steam and High Pressure
(HP) steam. Hence two types of Boilers are used i.e., LP Steam drum (For
producing LP steam) and HP Steam drum (for producing HP steam). Both
LP and HP steams are used to run the turbine. After the steam has passed
over the turbine it is condensed to form water which is then again heated
to make steam for the turbine and hence forms a cyclic process. However,
if quality of steam produced is less it can be recovered by allowing de-
mineralized water to enter the boilers from DM plant.
35 | P a g e
➢ Energy absorption from steam
-When turbine blades get rotated by high pressure high temperature
steam, the steam loses its energy. This in turn will result in a low pressure
and low temperature steam at the out of the turbine. Here steam is
expanded till saturation point is reached. Since there is no heat addition or
removal from the steam, ideally entropy of the steam remains same. This
change is depicted in the following PV and T-s diagrams. If we can bring
this low pressure, temperature steam back to its original state, then we can
produce electricity continuously.
36 | P a g e
➢ Condenser Heat Rejection - Cooling Tower:
-In order to reject heat from the condenser a colder liquid should
make contact with it. In a thermal power plant continuous supply
of cold quid is produced with the help of a cooling tower. Cold
fluid from the cooling tower absorbs heat from a condenser and
gets tested, this heat is rejected to the atmosphere via natural
convection with the help of a cooling tower
37 | P a g e
minimum 15- 17 hours to increase the casing temperature and to
avoid the expansion of turbine blades. This happen if the HP steam is
directly fed to stationary turbine blades by opening the Emergency
Stop Valve (ESV). Bearing gear is rotates at turbine shaft ata speed
of 108 rpm during starts up Bearing gear is said to an auto engaged
mode so that when the turbine gets tripped it starts automatically.
Bearing gear gets auto engaged when the turbine shaft reaches at a
speed of 350 rpm while shutdown.
There are two Steam Turbines at NEEPCO-AgGBPS. Each turbine
produces 25.5 Mw electricity and in total both produce 51 Mw of
electricity.
When turbine blades get rotated by high pressure high temperature
steam, the steam loses its energy. This in turn will result in a low
pressure and low temperature steam at the outlet of the turbine.
Here steam is expanded till saturation point is reached. Since there
is no heat addition or removal from the steam, ideally entropy of
the steam remains same. If we can bring this low pressure, low
temperature steam back to its original state, then we can produce
electricity continuously.
• Condenser:
Compressing a fluid which is in gaseous state requires a huge
amount of energy, so before compressing the fluid it should be
converted into liquid state. A condenser is used for this purpose,
which rejects heat to the surrounding and converts steam into
liquid. Ideally there will not be any pressure change during this
heat rejection process, since the fluid is free to expand in a
condenser.
38 | P a g e
• Pump:-
At exit of the condenser fluid is in liquid state, so we can use a
pump to raise the pressure. During this process the volume and
temperature (2-3 °C rise) of fluid hardly changes, since it is in
liquid state. Now the fluid has regained its original pressure.
• Boiler:
Here external heat is added to the fluid in order to bring fluid back
to its original temperature. This heat is added through a heat
exchanger called a boiler. Here the pressure of the fluid remains
the same, since it is free to expand in heat exchanger tubes.
Temperature rises and liquid gets transformed to vapour and
regains its original temperature. This completes the
thermodynamic cycle of a thermal power plant, called Rankine
Cycle. This cycle can be repeated and continuous power
production is possible.
39 | P a g e
• Boot Tank:
The partially condensate water from turbine exhaust duct is stored
into the boot tank or drain tank. This water sometimes fed to CST
by some drain boot pumps.
40 | P a g e
Fig: Steam Turbine at NEEPCO AgGBPS
41 | P a g e
6. AIR COOLED CONDENSER (ACC)
The exhaust steam from the STG is cooled & condensed by the
air-cooled condenser & stored in the condensate storage tank. It
consists of a huge duct which is later divide into two, followed by
various small pipes which are connected to the common header to
condensate storage tank. There are many heat exchangers attached
with the small pipes to make the process quicker.
There are 6 huge fans which act as air coolers rotating at a rated
speed of 1500 rpm (each fan) for each of the steam turbine. As
there is no pump given to extract the exhaust gas from STG, hence
a negative pressure is maintained inside ACC duct. This process
is usually done by taking ejector into service. It also extracts all
non-condensable gases from duct. The Air- Cooled Condenser
installed in this project is of A-frame shape. There are a total 12
nos. of ACC fans for two STG unit and the blades of each fan are
set at an angle of 15-17° depending upon the voltage consumed
by fan.
Air Cooled Condenser fans runs on 415 volts. When the ACC fans
rotates it provides the cooling medium (air) in the upward
direction (due to set blade action) which makes the exhaust
present in duct to condensate and later is collected in condensate
tank.
42 | P a g e
Fig: ACC (NEEPCO AgGBPS)
➢ FIELD DETAILS:
43 | P a g e
➢ Condensate Extraction Pump:
The condensate extraction pump extracts the condensed water from
condensate storage tank and delivers it into the ejector. It is also used to
fill up the LP drum during start up if needed through CPH bypass.
NEEPCO has arranged two CEP for each of the steam turbine among
which one is employed for the service and another is kept in the standby.
Ejector:
Steam jet Ejectors are based on the venture ejector principle & operated
by passing motive steam through an expanding nozzle. The nozzle
provides controlled expansion of the motive steam to convert pressure
into velocity which creates a negative pressure or gas are then completely
mixed and then passed through the diffuser, where the gases velocity is
converted into sufficient pressure to meet the predetermined discharge
pressure. The ejector maintains a negative pressure into discharge line,
condensate storage tank. The condensate water from condensate storage
tank is supplied to ejector through condensate extraction pump and then
supplied to gland sealing condensate.
FIELD DETAILS:
44 | P a g e
7. LUBRICATION SYSTEM
45 | P a g e
Fig: Gas Turbine Lube oil system
46 | P a g e
➢ Selection Criteria:
A steam turbine oil’s most important functions are to:
• Lubricate bearings, both journal and thrust. Depending on the
type of installation, this also may include the hydraulic control
system, oil shaft seals, gears and flexible couplings.
• Provide efficient cooling.
• Prevent sludge, rust and corrosion while in service.
• Maintenance professionals need to evaluate and monitor
several integral properties of their steam turbine oil to achieve
these optimal performance characteristics. Some of these
attributes include viscosity, viscosity index, foam resistance,
rust and corrosion prevention and oxidation stability.
➢ Uses:
• Lubrication and cooling of turbine and generator bearings
• Metallic debris flush out from bearings.
• Supply of Control Oil to Governing and Protection System
• Supply of Control Oil to LP Bypass Governing.
47 | P a g e
8. ELECTRICAL SYSTEMS
• Generator:
In electricity generation, a generator is a device that converts
motive power (mechanical energy) into electric power for use in
an external circuit. Sources of mechanical energy include steam
turbines, gas turbines, water turbines, internal combustion
engines, wind turbines and even hand cranks.
48 | P a g e
• Switch Yard:
Before electricity is consumed, three steps are followed:
production, transmission and distribution. In the first, the
generator produces the electricity from a primary energy source.
The transmission step consists of moving the electricity produces
at generating stations to consumption locations. Thereafter, the
electricity must be distributed to each house, factory or business.
Electricity generated by the generators flows to transformers that
step up the voltage in preparation for travel over long distances.
The most powerful generating stations are more than one thousand
kilometers from major consumption centers. Electricity travels
more easily at high voltage because there are fewer energy losses.
49 | P a g e
• Transformer:
A transformer is a static electrical device that transfers energy by
inductive coupling between its winding circuits. A varying
current in the primary winding creates a varying magnetic flux in
the transformers core and thus a varying magnetic flux through
the secondary winding. This varying magnetic flux induces a
varying electromotive force (EMF) or voltage in the secondary
winding. Transformers are essential for the transmission,
distribution and utilization of electrical. As an essential element
of all nuclear, thermal or hydraulic power stations. generator
transformers are step-up transformers with delta connected LV
windings energized by the generator
50 | P a g e
Fig: Transformer of AgGBPS
• Bus Duct:
In electrical power distribution, a bus duct is sheet metal duct
containing either copper or aluminium busbar for the purpose of
containing a substantial current of electricity. It is an alternative
means of conducting electricity to power cables or cables bus
• Isolator:
Isolator is a manually operated mechanical switch which separates
a part of the Electrical power. Its main purpose is to isolate one
portion of the circuit from the other and is not intended to be
opened while current is flowing in the line. Isolator are generally
used on both ends of the breaker so that repair or replacement of
circuit breaker can be done without any danger.
52 | P a g e
• Current Transformer (CT):
Current transformers are basically used to take the readings of the
currents entering the substation. This transformer steps down the
current from 800 amps to 1 amp. This is done because we have no
instrument for measuring of such a large current. The main use of
this transformer is
1. Distance Protection
2. Backup Protection
3. Measurement
• Potential Transformer:
There are two Potential Transformers (PT) used in the bus
connected both side of the bus The potential transformer uses a
bus isolator to protect itself. The main use of this transformer is to
measure the voltage through the bus. This is done so as to get the
detail information of the voltage passing through the bus to the
instrument. There are two main parts in it
1. Measurement
2. Protection
• Bus Bar:
The bus is a line in which the incoming feeders come into and get
into the instruments for further step up or step down. The first bus
is cd for putting the incoming feeders in la single line. There may
be double line in the bus so that if any fault occurs in the one the
other can still have the current and the supply will not stop. The
two Lines in the bus are separated by a little distance by a
conductor having a connector between them. This is so that one
can work at a time and the other works only if the first is having
any fault.
53 | P a g e
Specification of Different Machineries
GENERATORS:
MVA 28.9
Gen volt: 11 KV; PF: 0.8
1 Gas Turbine Generator No. of poles: 02 04 nos.
Ratted speed: 3000 rpm
Make: Alstom
Model: T-600
Site rating: 21 MW
Make: TDPS, standard .IS4712
2001
MVA Rating: 32.5 MVA
2 Steam Turbine Generator No. of poles: 4 02 nos.
Speed: 1500 rpm
MECHANICAL RATINGS:
1 Gas Turbine Model: G 5371 (PA)
No of shafts:1 04 nos.
Shaft Rotation: Counter
Clockwise
Make: GE
54 | P a g e
55 | P a g e
9. CONCLUSION
• Vision:
• Mission:
To harness the huge power potential of the country, from
conventional and non- conventional sources, with minimal
impact on the environment through a planned development
of power generation projects by an integrated approach
covering all aspects of investigation, planning, design
construction, operation and maintenance of power projects,
which in turn would effectively promote the development
of the nation as a whole.
56 | P a g e
10. SAFETY PRECAUTIONS
57 | P a g e
11. REFERENCES
58 | P a g e