UPDATED PROGRAMME - TWO WEEK LOOKAHEAD


Activity ID Activity Name Early Start Early Finish Late Start Late Finish Total 2024 2025
Float
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
09-Dec-23 08-Nov-24 11-Nov-23 28-Dec-24 41 08-Nov-24, G+1P+14
G+1P+14 Residential Building on Plot 6820156, One-Hebiah, Dubai. - REV 01
09-Dec-23 08-Nov-24 27-Jan-24 28-Dec-24 49 08-Nov-24, General
General
GENERAL-COM-1040 Prelimns - Running 09-Dec-23 08-Nov-24 27-Jan-24 28-Dec-24 49 Prelimns - Running
09-Dec-23 13-Dec-23 13-Nov-23 17-Nov-23 -21 13-Dec-23, Mobilization
Mobilization
GEN-MOB-1030 Site Fencing / Sign Boards / Site Offices / Worker Welfare
09-Dec-23 13-Dec-23 13-Nov-23 17-Nov-23 -21 Site Fencing / Sign Boards / Site Offices / Worker Welfare
09-Dec-23 13-Jan-24 05-Jan-24 14-Feb-24 27 13-Jan-24, Tower Cranes / Hoist / Placing Boom
Tower Cranes / Hoist / Placing Boom
GEN-EQP-1000 Erection of Tower Crane Incl Foundation - TC 01 09-Dec-23 14-Dec-23 05-Jan-24 11-Jan-24 23 Erection of Tower Crane Incl Foundation - TC 01
GEN-EQP-1010 Erection of Tower Crane Incl Foundation - TC 02 09-Dec-23 13-Jan-24 11-Jan-24 14-Feb-24 27 Erection of Tower Crane Incl Foundation - TC 02
09-Dec-23 12-Jun-24 11-Nov-23 28-Oct-24 113 12-Jun-24, Engineering & Procurement
Engineering & Procurement
Provisional Sum Items 09-Dec-23 03-Jan-24 01-Dec-23 16-Feb-24 38 03-Jan-24, Provisional Sum Items
Aluminium & Glazing Works 09-Dec-23 03-Jan-24 01-Dec-23 27-Dec-23 -6 03-Jan-24, Aluminium & Glazing Works
Nomination & Award 09-Dec-23 03-Jan-24 01-Dec-23 27-Dec-23 -6 03-Jan-24, Nomination & Award
PRV-ALU-1010 Evaluate & Award Contract 09-Dec-23 03-Jan-24 01-Dec-23 27-Dec-23 -6 Evaluate & Award Contract
Carpentry & Joinery Works 09-Dec-23 03-Jan-24 29-Dec-23 23-Jan-24 17 03-Jan-24, Carpentry & Joinery Works
Nomination & Award 09-Dec-23 03-Jan-24 29-Dec-23 23-Jan-24 17 03-Jan-24, Nomination & Award
PRV-JOI-1010 Evaluate & Award Contract 09-Dec-23 03-Jan-24 29-Dec-23 23-Jan-24 17 Evaluate & Award Contract
Swimming Pool & Water Fountain 09-Dec-23 03-Jan-24 22-Dec-23 17-Jan-24 11 03-Jan-24, Swimming Pool & Water Fountain
Nomination & Award 09-Dec-23 03-Jan-24 22-Dec-23 17-Jan-24 11 03-Jan-24, Nomination & Award
PRV-SWP-1010 Evaluate & Award Contract 09-Dec-23 03-Jan-24 22-Dec-23 17-Jan-24 11 Evaluate & Award Contract
Facade Lighting 09-Dec-23 03-Jan-24 24-Jan-24 16-Feb-24 38 03-Jan-24, Facade Lighting
Nomination & Award 09-Dec-23 03-Jan-24 24-Jan-24 16-Feb-24 38 03-Jan-24, Nomination & Award
PRV-FCL-1010 Evaluate & Award Contract 09-Dec-23 03-Jan-24 24-Jan-24 16-Feb-24 38 Evaluate & Award Contract
Landscape Works 09-Dec-23 02-Jan-24 11-Jan-24 02-Feb-24 27 02-Jan-24, Landscape Works
Nomination & Award 09-Dec-23 02-Jan-24 11-Jan-24 02-Feb-24 27 02-Jan-24, Nomination & Award
PRV-LNC-1010 Evaluate & Award Contract 09-Dec-23 02-Jan-24 11-Jan-24 02-Feb-24 27 Evaluate & Award Contract
PC Rate items 09-Dec-23 09-Jan-24 17-Jan-24 23-May-24 113 09-Jan-24, PC Rate items
Light Fittings Supply 09-Dec-23 06-Jan-24 13-Apr-24 11-May-24 105 06-Jan-24, Light Fittings Supply
PCR-LIG-S-1000 Source & Submit Quotation & Materials 09-Dec-23 02-Jan-24 13-Apr-24 06-May-24 105 Source & Submit Quotation & Materials
PCR-LIG-S-1010 Review & Approve PC rate / Supplier & Material by20-Dec-23
Engineer 06-Jan-24 25-Apr-24 11-May-24 105 Review & Approve PC rate / Supplier & Material by Engineer
Porcelain Wall tile for Lift Lobby 09-Dec-23 06-Jan-24 25-Apr-24 23-May-24 115 06-Jan-24, Porcelain Wall tile for Lift Lobby
PCR-TL3T-S-1010 Source & Submit Quotation & Materials 09-Dec-23 02-Jan-24 25-Apr-24 17-May-24 115 Source & Submit Quotation & Materials
PCR-TL3T-A-1010 Review & Approve PC rate / Supplier & Material by20-Dec-23
Engineer 06-Jan-24 07-May-24 23-May-24 115 Review & Approve PC rate / Supplier & Material by Engineer
Marble / Engineered Stone 16-Dec-23 09-Jan-24 17-Jan-24 08-Feb-24 26 09-Jan-24, Marble / Engineered Stone
PCR-STN-S-1010 Source & Submit Quotation & Materials 16-Dec-23 09-Jan-24 17-Jan-24 08-Feb-24 26 Source & Submit Quotation & Materials
Porcelain Tiles 16-Dec-23 09-Jan-24 25-Apr-24 17-May-24 109 09-Jan-24, Porcelain Tiles
PCRT-TL1-S-1010 Source & Submit Quotation & Materials 16-Dec-23 09-Jan-24 25-Apr-24 17-May-24 109 Source & Submit Quotation & Materials
Ceramic Wall & Floor Tiles - Apartment Wet areas 09-Dec-23 06-Jan-24 20-Feb-24 19-Mar-24 61 06-Jan-24, Ceramic Wall & Flo or Tiles - Apartment Wet areas
PCR-TL4-S-1010 Source & Submit Quotation & Materials 09-Dec-23 02-Jan-24 20-Feb-24 13-Mar-24 61 Source & Submit Quotation & Materials
PCR-TL4-A-1010 Review & Approve PC rate / Supplier & Material by20-Dec-23
Engineer 06-Jan-24 01-Mar-24 19-Mar-24 61 Review & Approve PC rate / Supplier & Material by Engineer
Ceramic Floor Tiles - Apartment Dry Areas 16-Dec-23 09-Jan-24 08-Feb-24 01-Mar-24 46 09-Jan-24, Ceramic Floor Tiles - Apartment Dry Areas
PCRT-TL2-S-1010 Source & Submit Quotation & Materials 16-Dec-23 09-Jan-24 08-Feb-24 01-Mar-24 46 Source & Submit Quotation & Materials
Sanitaryware & Accessories 09-Dec-23 02-Jan-24 23-Apr-24 15-May-24 112 02-Jan-24, Sanitaryware & Accessories
PCR-PRO91 Source & Submit Quotation & Materials 09-Dec-23 02-Jan-24 23-Apr-24 15-May-24 112 Source & Submit Quotation & Materials
Subcontractor/Supplier Procurement for Contractor's Direct Items 09-Dec-23 12-Dec-23 06-Mar-24 09-Mar-24 75 12-Dec-23, Subcontractor/Supplier Procurement for Contractor's Direct Items
Lifts 09-Dec-23 12-Dec-23 06-Mar-24 09-Mar-24 75 12-Dec-23, Lifts
PRO-SC-LIF-A-1000 Review & Approve Subcontractor/Supplier by Engineer
09-Dec-23 12-Dec-23 06-Mar-24 09-Mar-24 75 Review & Approve Subcontractor/Supplier by Engineer

Actual Level of Effort Actual Work Critical Remaining Work Page 1 of 3 TASK filter: 2 Weeks Ahead.
Primary Baseline Remaining Work Milestone © Oracle Corporation
EMPLOYER ENGINEER Vista - Proposed G 1P 14 Storey Residential Building CONTRACTOR
on Plot No. 6820156, One Hebiah,
Dubai, UAE.

UPDATED PROGRAMME - TWO WEEK LOOKAHEAD


Activity ID Activity Name Early Start Early Finish Late Start Late Finish Total 2024 2025
Float
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
Materials Submittals & Approvals 09-Dec-23 07-Feb-24 18-Nov-23 12-Aug-24 152 07-Feb-24, Materials Submittals & Approvals
Waterprooofing & Thermal Insulation 09-Dec-23 25-Jan-24 22-Nov-23 27-May-24 102 25-Jan-24, Waterprooofing & Thermal Insulation
MT-TMP-S-1010 Prepare & Submit Materials - Internal et Area WP 09-Dec-23 02-Jan-24 11-Apr-24 03-May-24 102 Prepare & Submit Materials - Internal et Area WP
MT-TMP-S-1000 Prepare & Submit Materials - Substructure WP 09-Dec-23 14-Dec-23 22-Nov-23 27-Nov-23 -14 Prepare & Submit Materials - Substructure WP
MT-TMP-A-1000 Review & Approve Materials by Engineer - Substructure
14-Dec-23
WP 20-Dec-23 28-Nov-23 04-Dec-23 -14 Review & Approve Materials by Engineer - Substructure WP
MT-TMP-A-1010 Review & Approve Materials by Engineer - Internal et
20-Dec-23
Area WP 25-Jan-24 23-Apr-24 27-May-24 102 Review & Approve Materials by Engineer - Internal et Area WP
Lifts 12-Dec-23 20-Jan-24 09-Mar-24 20-Apr-24 75 20-Jan-24, Lifts
MT-LIF-S-1000 Prepare & Submit Materials 12-Dec-23 16-Jan-24 09-Mar-24 15-Apr-24 75 Prepare & Submit Materials
MT-LIF-A-1000 Review & Approve Materials by Engineer 23-Dec-23 20-Jan-24 20-Mar-24 20-Apr-24 75 Review & Approve Materials by Engineer
Structural Steel Works - Sheer plates & Canopy frame 09-Dec-23 25-Jan-24 18-Nov-23 04-Apr-24 60 25-Jan-24, Structural Steel Works - Sheer plates & Canopy frame
MT-STR-S-1000 Prepare & Submit Materials - Sheer plates 09-Dec-23 20-Dec-23 18-Nov-23 29-Nov-23 -17 Prepare & Submit Materials - Sheer plates
MT-STR-S-1010 Prepare & Submit Materials - Canopy Steel Frame 09-Dec-23 02-Jan-24 26-Dec-23 18-Jan-24 15 Prepare & Submit Materials - Canopy Steel Frame
MT-STR-A-1000 Review & Approve Materials by Engineer- Sheer plates
20-Dec-23 26-Dec-23 04-Dec-23 09-Dec-23 -14 Review & Approve Materials by Engineer- Sheer plates
MT-STR-A-1010 Review & Approve Materials by Engineer - Canopy 20-Dec-23
Steel Frame 25-Jan-24 29-Feb-24 04-Apr-24 60 Review & Approve Materials by Engineer - Canopy Steel Frame
Expansion Joint / Construction Joints 09-Dec-23 26-Dec-23 26-Dec-23 13-Jan-24 15 26-Dec-23, Expansion Joint / Construction Joints
MT-EXJ-S-1000 Prepare & Submit Materials 09-Dec-23 20-Dec-23 26-Dec-23 08-Jan-24 15 Prepare & Submit Materials
MT-EXJ-A-1000 Review & Approve Materials by Engineer 20-Dec-23 26-Dec-23 08-Jan-24 13-Jan-24 15 Review & Approve Materials by Engineer
Post Tension Works Subcontractor 09-Dec-23 06-Jan-24 12-Dec-23 10-Jan-24 3 06-Jan-24, Post Tensio n Works Subcontractor
MT-PTW-S-1000 Prepare & Submit Materials 09-Dec-23 02-Jan-24 12-Dec-23 04-Jan-24 3 Prepare & Submit Materials
MT-PTW-A-1000 Review & Approve Materials by Engineer 20-Dec-23 06-Jan-24 23-Dec-23 10-Jan-24 3 Review & Approve Materials by Engineer
MEP Works 09-Dec-23 07-Feb-24 05-Dec-23 12-Aug-24 152 07-Feb-24, MEP Works
MEP Early Fix items - Sleeves / Pipes / Conduites/ Enclosures 09-Dec-23 03-Jan-24 05-Dec-23 28-Dec-23 -4 03-Jan-24, MEP Early Fix items - Sleeves / Pipes / Conduites/ Enclosures
MT-MEP-S-S-1100 Prepare & Submit Materials 09-Dec-23 29-Dec-23 05-Dec-23 25-Dec-23 -4 Prepare & Submit Materials
MT-MEP-A-1100 Review & Approve Materials by Engineer 13-Dec-23 03-Jan-24 08-Dec-23 28-Dec-23 -4 Review & Approve Materials by Engineer
Electrical 09-Dec-23 07-Feb-24 04-Mar-24 06-May-24 72 07-Feb-24, Electrical
Cables / Enclosures / Wires 09-Dec-23 07-Feb-24 04-Mar-24 06-May-24 72 07-Feb-24, Cables / Enclosures / Wires
MT-MEP-S-1120 Prepare & Submit Materials 09-Dec-23 31-Jan-24 04-Mar-24 29-Apr-24 72 Prepare & Submit Materials
MT-MEP-A-1120 Review & Approve Materials by Engineer 23-Dec-23 07-Feb-24 18-Mar-24 06-May-24 72 Review & Approve Materials by Engineer
Fire Fighting 14-Dec-23 25-Jan-24 29-Jun-24 12-Aug-24 163 25-Jan-24, Fire Fighting
Fire Extingushers 14-Dec-23 25-Jan-24 29-Jun-24 12-Aug-24 163 25-Jan-24, Fire Extingushers
MT-MEP-S-1280 Prepare & Submit Materials 14-Dec-23 25-Jan-24 29-Jun-24 12-Aug-24 163 Prepare & Submit Materials
Shop Drawings Submittals & Approvals 09-Dec-23 30-Mar-24 16-Nov-23 28-Oct-24 173 30-Mar-24, Shop Drawings Submittals & Approvals
Structure Concrete Works 09-Dec-23 02-Jan-24 06-Jan-24 27-Jun-24 147 02-Jan-24, Structure Concrete Works
SD-CON-S-1020 Prepare & Submit Shop Drawings - Columns & Corewalls
09-Dec-23
up to Podium
26-Dec-23 06-Jan-24 23-Jan-24 23 Prepare & Submit Shop Drawings - Columns & Corewalls up to Podium
SD-CON-A-1020 Review & Approve Shop Drawings - Columns & Corewalls
20-Dec-23up to 02-Jan-24
Podium by Engineer
13-Jun-24 27-Jun-24 147 Review & Approve Shop Drawings - Columns & Corewalls up to Podium by Engineer
Structural Steel Works 09-Dec-23 28-Dec-23 18-Nov-23 09-Dec-23 -17 28-Dec-23, Structural Steel Works
SD-STR-S-1000 Prepare & Submit Shop drawings - Sheer Plates 09-Dec-23 22-Dec-23 18-Nov-23 04-Dec-23 -17 Prepare & Submit Shop drawings - Sheer Plates
SD-STR-A-1000 Review & Approve Shop drawings - Sheer Plates by23-Dec-23
Engineer 28-Dec-23 04-Dec-23 09-Dec-23 -17 Review & Approve Shop drawings - Sheer Plates by Engineer
Masonry Supply 09-Dec-23 02-Jan-24 08-Mar-24 30-Mar-24 76 02-Jan-24, Masonry Supply
SD-MAS-S-1000 Prepare & Submit Blockwork Layout -Ground Floor 09-Dec-23 02-Jan-24 08-Mar-24 30-Mar-24 76 Prepare & Submit Blockwork Layout -Ground Floor
Post Tension Works Subcontractor 09-Dec-23 06-Jan-24 16-Nov-23 26-Dec-23 -9 06-Jan-24, Post Tensio n Works Subcontractor
Podium Slab 09-Dec-23 06-Jan-24 16-Nov-23 26-Dec-23 -9 06-Jan-24, Podium Slab
SD-P1-FLR-S-1000 Prepare & Submit Flooring Layout - Podium 09-Dec-23 22-Dec-23 16-Nov-23 30-Nov-23 -19 Prepare & Submit Flooring Layout - Podium
SD-P1-FLR-A-1000 Review & Approve Flooring Layout - Podium 23-Dec-23 29-Dec-23 13-Dec-23 19-Dec-23 -9 Review & Approve Flooring Layout - Podium
SD-P1-FBW-S-1000 Prepare & Submit Co-ordinated MEP drawings for Slab
23-Dec-23
opening/Sleeves
06-Jan-24
- Podium
13-Dec-23 26-Dec-23 -9 Prepare & Submit Co-ordinated MEP drawings for Slab opening/Sleeves - Podium
Level 1 Slab 23-Dec-23 06-Jan-24 30-Nov-23 15-Dec-23 -19 06-Jan-24, Level 1 Slab
SD-L1-FLR-S-1000 Prepare & Submit Flooring Layout - Level 1 23-Dec-23 06-Jan-24 30-Nov-23 15-Dec-23 -19 Prepare & Submit Flooring Layout - Level 1
Lift Subcontractor 12-Dec-23 17-Jan-24 23-Sep-24 28-Oct-24 237 17-Jan-24, Lift Subcontractor

Actual Level of Effort Actual Work Critical Remaining Work Page 2 of 3 TASK filter: 2 Weeks Ahead.
Primary Baseline Remaining Work Milestone © Oracle Corporation
EMPLOYER ENGINEER Vista - Proposed G 1P 14 Storey Residential Building CONTRACTOR
on Plot No. 6820156, One Hebiah,
Dubai, UAE.

UPDATED PROGRAMME - TWO WEEK LOOKAHEAD


Activity ID Activity Name Early Start Early Finish Late Start Late Finish Total 2024 2025
Float
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
SD-LIF-S-1000 Prepare & Submit Shop drawings for Lift works 12-Dec-23 17-Jan-24 23-Sep-24 28-Oct-24 237 Prepare & Submit Shop drawings for Lift works
MEP Subcontractor 09-Dec-23 30-Mar-24 10-Feb-24 04-Jun-24 53 30-Mar-24, MEP Subcontractor
SD-MEP-S-1000 Prepare & Submit MEP Shop Drawings 09-Dec-23 16-Mar-24 10-Feb-24 21-May-24 53 Prepare & Submit MEP Shop Drawings
SD-MEP-A-1000 Review & Approve MEP Shop Drawings by Engineer
09-Dec-23 30-Mar-24 10-Feb-24 04-Jun-24 53 Review & Approve MEP Shop Drawings by Engineer
Formwork System 09-Dec-23 26-Dec-23 24-Nov-23 27-Dec-23 0 26-Dec-23, Formwork System
SD-FMW-S-1000 Prepare & Submit Shop drawings for Formwork - Corewalls
09-Dec-23 26-Dec-23 24-Nov-23 13-Dec-23 -12 Prepare & Submit Shop drawings for Formwork - Corewalls
SD-FMW-S-1010 Prepare & Submit Shop drawings for Formwork - Slabs
09-Dec-23 26-Dec-23 09-Dec-23 27-Dec-23 0 Prepare & Submit Shop drawings for Formwork - Slabs
Material Procurement 09-Dec-23 12-Jun-24 11-Nov-23 07-Jun-24 -4 12-Jun-24, Material Procurement
Steel Reinforcement Supplier 09-Dec-23 14-Dec-23 15-Dec-23 21-Dec-23 6 14-Dec-23, Steel Reinforcement Supplier
PR-SRF-S-1010 Procure & deliver Materials - Substructure 09-Dec-23 14-Dec-23 15-Dec-23 21-Dec-23 6 Procure & deliver Materials - Substructure
Anti-termite 09-Dec-23 12-Dec-23 11-Nov-23 14-Nov-23 -23 12-Dec-23, Anti-termite
PR-ANT-S-1000 Procure & deliver Materials 09-Dec-23 12-Dec-23 11-Nov-23 14-Nov-23 -23 Procure & deliver Materials
Waterprooofing & Thermal Insulation 20-Dec-23 26-Dec-23 04-Dec-23 09-Dec-23 -14 26-Dec-23, Waterprooofin g & Thermal Insulation
PR-TMP-S-1010 Procure & deliver Materials - Substructure WP 20-Dec-23 26-Dec-23 04-Dec-23 09-Dec-23 -14 Procure & deliver Materials - Substructure WP
Masonry 09-Dec-23 02-Jan-24 05-Apr-24 01-May-24 100 02-Jan-24, Masonry
PR-MAS-S-1005 Procure & deliver Materials 09-Dec-23 02-Jan-24 05-Apr-24 01-May-24 100 Procure & deliver Materials
Masonry Supply 09-Dec-23 02-Jan-24 13-Apr-24 06-May-24 104 02-Jan-24, Masonry Supply
PR-MAS-S-1000 Procure & deliver Materials 09-Dec-23 02-Jan-24 13-Apr-24 06-May-24 104 Procure & deliver Materials
MEP Works 16-Dec-23 12-Jun-24 12-Dec-23 07-Jun-24 -4 12-Jun-24, MEP Works
MEP Early Fix items - Sleeves / Pipes / Conduites/ Enclosures 16-Dec-23 12-Jun-24 12-Dec-23 07-Jun-24 -4 12-Jun-24, MEP Early Fix items - Sleeves / Pipes / Condui
PR-MEP-S-1100 Procure / Fabricate & deliver Materials - sleeves / Pipes/
16-Dec-23
Conduites/Enclosures
12-Jun-24 12-Dec-23 07-Jun-24 -4 Procure / Fabricate & deliver Materials - sleeves / Pipes/ Co
09-Dec-23 11-Jan-24 13-Nov-23 06-Jan-24 -5 11-Jan-24, Construction
Construction
Sub Structure 09-Dec-23 11-Jan-24 13-Nov-23 06-Jan-24 -5 11-Jan-24, Sub Structure
Zone 1 - Foundation @ +0.15 M (22.90 m DMD) - GRID 13 to 5 28-Dec-23 11-Jan-24 22-Dec-23 06-Jan-24 -5 11-Jan-24, Zone 1 - Foundation @ +0.15 M (22.90 m DMD) - GRID 13 to 5
SUB-FD-Z01-1050 Reinforcement & MEP Embedded items Raft @0.15
28-Dec-23
m 11-Jan-24 22-Dec-23 06-Jan-24 -5 Reinforcement & MEP Embedded items Raft @0.15 m
Zone 4 - Raft Below Water Tank @ -2.95 m (19.80 m DMD) & Water Tank 15-Dec-23 25-Dec-23 01-Dec-23 12-Dec-23 -10 25-Dec-23, Zone 4 - Raft Below Water Tank @ -2.95 m (19.80 m DMD) & Water Tank
SUB-FD-Z04-1010 Excavation to Foundation level 15-Dec-23 16-Dec-23 01-Dec-23 04-Dec-23 -10 Excavation to Foundation level
SUB-FD-Z04-1020 Filling in 250 mm layers, Compaction & Antitermite16-Dec-23 21-Dec-23 04-Dec-23 09-Dec-23 -10 Filling in 250 mm layers, Compaction & Antitermite
SUB-FD-Z04-1030 Blinding Below Raft 21-Dec-23 25-Dec-23 09-Dec-23 12-Dec-23 -10 Blinding Below Raft
Zone 2 - Foundation @ +0.15 M (22.90 m DMD) - GRID 1- 5 / D-H 09-Dec-23 29-Dec-23 13-Nov-23 01-Dec-23 -23 29-Dec-23, Zone 2 - Foundation @ +0.15 M (22.90 m DMD) - GRID 1- 5 / D-H
SUB-FD-Z02-1000 Excavation to raft level @ 0.15m Grid 1-5 09-Dec-23 11-Dec-23 13-Nov-23 14-Nov-23 -21 Excavation to raft level @ 0.15m Grid 1-5
SUB-FD-Z02-1010 Filling in 250 mm layers, Compaction up to 22.90 m12-Dec-23
DMD & Antitermite
21-Dec-23 14-Nov-23 23-Nov-23 -23 Filling in 250 mm layers, Compaction up to 22.90 m DMD & Antitermite
SUB-FD-Z02-1020 Blinding below raft Grid 1-5 21-Dec-23 29-Dec-23 23-Nov-23 01-Dec-23 -23 Blinding below raft Grid 1-5

Actual Level of Effort Actual Work Critical Remaining Work Page 3 of 3 TASK filter: 2 Weeks Ahead.
Primary Baseline Remaining Work Milestone © Oracle Corporation