Newproj Mockup Rooms Newproj Mockup Rooms: 11-Jul-23 15-Sep-23 60 0
Newproj Mockup Rooms Newproj Mockup Rooms: 11-Jul-23 15-Sep-23 60 0
Newproj Mockup Rooms Newproj Mockup Rooms: 11-Jul-23 15-Sep-23 60 0
Start Finish Original Duration Total Float Qtr 3, 2023 Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
NEWPROJ MOCKUP ROOMS 11-Jul-23 15-Sep-23 60 0 15-Sep-23, NEWPROJ MOCKUP ROOMS
NEWPROJ.2 TIME FOR COMPLETION 11-Jul-23 15-Sep-23 60 0 15-Sep-23, NEWPROJ.2 TIME FOR COMPLETION
A1000 Commencement Date 11-Jul-23 0 27 Commencement Date, 11-Jul-23
A1010 Project Completion 15-Sep-23 0 0 Project Completion,
NEWPROJ.4 PRE- CONSTRUCTION 11-Jul-23 11-Jul-23 1 27 11-Jul-23, NEWPROJ.4 PRE- CONSTRUCTION
A1350 Site Visit 11-Jul-23 11-Jul-23 1 27 Site Visit
A1360 Receipt of As-Built Drawings 11-Jul-23 11-Jul-23 1 27 Receipt of As-Built Drawings
NEWPROJ.6 DETAILED DRAWINGS DEVELOPMENT 14-Jul-23 25-Jul-23 10 27 25-Jul-23, NEWPROJ.6 DETAILED DRAWINGS DEVELOPMENT
NEWPROJ.7.1 DESIGN DRAWING SUBMISSION TO CLIENT 14-Jul-23 19-Jul-23 5 52 19-Jul-23, NEWPROJ.7.1 DESIGN DRAWING SUBMISSION TO CLIENT
A1380 Submission of Detailed Design / Coordinated Drawings to WASL/HYATT 14-Jul-23 14-Jul-23 1 33 Submission of Detailed Design / Coordinated Drawings to WASL/HYATT
A1390 Comments / Approval from WASL/ HYATT 15-Jul-23 18-Jul-23 3 52 Comments / Approval from WASL/ HYATT
A1400 Resubmission of Final Drawings to WASL/ HYATT 18-Jul-23 19-Jul-23 1 52 Resubmission of Final Drawings to WASL/ HYATT
NEWPROJ.1 CONTRACTOR SUBMITTALS 13-Jul-23 16-Aug-23 31 27 16-Aug-23, NEWPROJ.1 CONTRACTOR SUBMITTALS
Actual Level of Effort Remaining Work Milestone Page 1 of 2 Mouhajer International Design - Planning Engineer
Actual Work Critical Remaining Work summary © Oracle Corporation
Activity ID Activity Name Start Finish Original Duration Total Float Qtr 3, 2023 Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
NEWPROJ.5.2.2 CONSTRUCTION 11-Jul-23 11-Sep-23 56 4 11-Sep-23, NEWPROJ.5.2.2 CONSTRUCTION
A1260 Demolition works 11-Jul-23 12-Jul-23 2 46 Demolition works
A1270 Existing wood refinishing 19-Jul-23 26-Jul-23 6 46 Existing wood refinishing
A1280 Joinery Installation 19-Aug-23 24-Aug-23 4 0 Joinery Installation
A1290 Ceiling and wall paint 25-Aug-23 31-Aug-23 5 0 Ceiling and wall paint
A1300 Supply and installation of Axminister carpet with underlay 31-Aug-23 06-Sep-23 6 0 Supply and installation of Axminister carpet with underlay
A1310 Supply and installation of electrical final fix items 04-Sep-23 06-Sep-23 3 0 Supply and installation of electrical final fix items
A1320 Furniture delivery & installation 07-Sep-23 11-Sep-23 4 0 Furniture delivery & installation
NEWPROJ.5.2.1 Landlord Final Integrations, Testing & Commissioning 07-Sep-23 12-Sep-23 5 0 12-Sep-23, NEWPROJ.5.2.1 Landlord Final Integrations, Testing & Commissioning
A1340 3rd Party / Landlord FM Team Testing & Commissioning 07-Sep-23 12-Sep-23 5 0 3rd Party / Landlord FM Team Testing & Commissioning
NEWPROJ.3 HANDOVER ( MOCK UP ROOM ) 12-Sep-23 15-Sep-23 3 0 15-Sep-23, NEWPROJ.3 HANDOVER ( MOCK UP ROOM )
A1330 HANDOVER MOCK UP ROOM 12-Sep-23 15-Sep-23 3 0 HANDOVER MOCK UP ROOM
Actual Level of Effort Remaining Work Milestone Page 2 of 2 Mouhajer International Design - Planning Engineer
Actual Work Critical Remaining Work summary © Oracle Corporation