Activity ID Activity Name Duration Start Finish 2024 2025 2026

Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul

Southlinks Estate - Site Development Works 703 06-Dec-23 30-Jun-26

Project Milestone 703 06-Dec-23 30-Jun-26

Major Milestone 703 06-Dec-23 30-Jun-26


MM100 Limited Notice to Proceed (LNTP) 0 06-Dec-23 Limited Notice to Proceed (LNTP), , 06-Dec-23
MM110 Notice to Proceed (NTP) 0 07-Dec-23* Notice to Proceed (NTP), , 07-Dec-23*
MM120 Commencement Date of NTP 0 07-Dec-23 Commencement Date of NTP, , 07-Dec-23
MM130 Start of Site Grading at North Side 0 01-Jun-24 Start of Site Grading at N orth Side, , 01-Jun-24
MM140 Start of Site Grading at South Side 0 24-Jun-24 Start of Site Grading at South Side, , 24-Jun-24
MM150 Start of Tunneling across Southvale Drive 0 18-Dec-24 Start of Tunneling across Southvale Drive, , 18-Dec-24
MM151 Start of Road Works 0 06-Nov-24 Start of Road Works, , 06-Nov-24
MM160 Ground Breaking Ceremony 0 09-May-24* Ground Breaking Ceremony, , 09-May-24*
MM170 Energization of Meralco 0 02-Feb-26* Energization of Meralco, , 02-Feb-26*
MM180 Completion of Works 0 30-Jun-26 Completion of Works, 30-Ju

Pre-Construction 699 07-Dec-23 25-Jun-26

Permit and Clearances 95 07-Dec-23 12-Apr-24


Employer 0 12-Apr-24 12-Apr-24
PC100 ECC - South Side 0 12-Apr-24* ECC - South Side, , 12-Apr-24*
Contractor 47 07-Dec-23 08-Feb-24
PC110 Building Permit 15 07-Dec-23 02-Jan-24
PC120 Demolition Permit 6 07-Dec-23 14-Dec-23
PC130 Excavation Permit 47 07-Dec-23 08-Feb-24
PC140 Fencing Permit 31 20-Dec-23 01-Feb-24
Engineering 199 05-Feb-24 23-Oct-24
Issuance of Detailed Design 67 05-Feb-24 30-Apr-24
ENG100 Prelim inary Detailed Design 0 05-Feb-24* Prelim inary Detailed Design, , 05-Feb-24*
ENG110 Final Detail ed Design 0 30-Apr-24* Final Detail ed Design, , 30-Apr-24*
Request for Information 42 30-Apr-24 22-Jun-24
ENG119 Plan Review 30 30-Apr-24 05-Jun-24
ENG120 Preparation & Submission of RFI 30 30-Apr-24 05-Jun-24
ENG130 Review / Response of DCI & AMH 30 15-May-24 22-Jun-24
Request for Approval 132 30-Apr-24 23-Oct-24
ENG140 Method Statement Approval 120 30-Apr-24 08-Oct-24
ENG150 Shop Drawing Approval 120 15-May-24 23-Oct-24
Procurement 174 15-May-24 08-Jan-25
Material Submittal 70 15-May-24 16-Aug-24
PRO100 Gathering of Brochures/ Samples 35 15-May-24 29-Jun-24
PRO110 Preparation and Submission to DCI & AMH 35 23-May-24 09-Jul-24
PRO120 Review/ Response of DCI & AMH 35 10-Jun-24 29-Jul-24
PRO130 Receipt of Approval from DCI & AMH 35 01-Jul-24 16-Aug-24
Procurement 42 11-Jul-24 07-Sep-24
PRO140 Procurement for PVC Pipes for Sewer Lines 42 11-Jul-24 07-Sep-24
PRO150 Procurement for PVC Pipes for Electrical Lines 42 11-Jul-24 07-Sep-24
PRO160 Procurement for RC Pipes for Drainage Lines 42 11-Jul-24 07-Sep-24
PRO170 Procurement for PVC Pipes & CI Fittings for Water Lines 42 11-Jul-24 07-Sep-24
PRO180 Procurement for Miscellaneous Steels (Manhole cover, gratings, ladder42
rungs) 11-Jul-24 07-Sep-24
PRO190 Procurement for CHB - Load Bearing 42 11-Jul-24 07-Sep-24
PRO200 Procurement for Street Light Post & Fixtures 42 11-Jul-24 07-Sep-24
PRO210 Procurement for Rebar 7 11-Jul-24 19-Jul-24
PRO220 Procurement for Ready Mix Concrete 30 11-Jul-24 19-Aug-24
PRO230 Procurementfor Formworks 21 11-Jul-24 06-Aug-24
Fabrication / Manufacturing / Delivery 125 20-Jul-24 08-Jan-25
PRO240 Fabrication /Manufacturing /Delivery of PVC Pipes for Sewer Lines 90 09-Sep-24 08-Jan-25
PRO250 Fabrication /Manufacturing /Delivery of PVC Pipes for Electrical Lines 90 09-Sep-24 08-Jan-25
PRO260 Fabrication /Manufacturing /Delivery of RC Pipes for Drainage Lines 90 09-Sep-24 08-Jan-25
PRO270 Fabrication /Manufacturing /Delivery of PVC Pipes & CI Fittings for Water
90Lines 09-Sep-24 08-Jan-25
PRO280 Fabrication /Manufacturing /Delivery of Miscellaneous Steels (Manhole90
cover, gratings,
09-Sep-24 ladder
08-Jan-25
rungs)
PRO290 Fabrication /Manufacturing /Delivery of Street Light Post & Fixtures 90 09-Sep-24 08-Jan-25
PRO300 Fabrication /Manufacturing /Delivery of CHB - Load Bearing 90 09-Sep-24 08-Jan-25
PRO310 Fabrication /Manufacturing /Delivery of Rebar 90 20-Jul-24 18-Nov-24
PRO320 Fabrication /Manufacturing /Delivery of Ready Mix Concrete 90 20-Aug-24 16-Dec-24
PRO330 Fabrication /Manufacturing /Delivery of Formworks 90 08-Aug-24 05-Dec-24
Mobilization and Early Works 699 07-Dec-23 25-Jun-26
Mobilization 164 07-Dec-23 09-Jul-24
MEW100 Manpower 150 07-Dec-23 19-Jun-24
MEW110 Equipment 150 02-Jan-24 09-Jul-24
Early Works 544 08-Jan-24 23-Dec-25
MEW120 Employer Site Office 58 08-Jan-24 15-Mar-24
MEW130 Contractor's Site Office 51 26-Feb-24 30-Apr-24
MEW140 Worker's Camp and Accomodation 41 08-Jan-24 24-Feb-24
MEW150 Establishment of Temporary Works 68 05-Feb-24 30-Apr-24
MEW200 Relocation of Employer's Site Office 60 01-Sep-25 15-Nov-25

Critical Remaining Work Remaining Work Date Revision Checked Approved


Page 1 of 2 Southlinks Estate - Site Development Works 23-Apr-24 Rev.06 CGP
Milestone
INDICATIVE SCHEDULE 12-Apr-24 Rev.05 CGP
Summary
SUBJECT FOR DISCUSSION 20-Feb-24 Rev.04 CGP
Activity ID Activity Name Duration Start Finish 2024 2025 2026
Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
MEW210 Relocation of Contractor's Site office 60 10-Oct-25 23-Dec-25
MEW220 Relocation of Worker's Camp and Accomodation 60 09-Sep-25 24-Nov-25
Survey Works 656 05-Feb-24 25-Jun-26
MEW160 Prelim inary Site Survey Works 68 05-Feb-24 30-Apr-24
MEW170 Setting-out and Staking Works 588 02-May-24 25-Jun-26
Tree Cutting Works (by Others) 93 29-Jan-24 30-Apr-24
MEW180 Tree Cutting Works at North Side 93 29-Jan-24* 30-Apr-24
MEW190 Tree Cutting Works at South Side 35 27-Mar-24* 30-Apr-24
Construction 688 02-Jan-24 30-Jun-26

North Side 688 02-Jan-24 30-Jun-26


Priority Area 318 02-Jan-24 20-Feb-25
Site Preparation 117 02-Jan-24 24-May-24
Earthworks 30 01-Jun-24 13-Jul-24
Road Works 81 06-Nov-24 20-Feb-25
Area 1 375 26-Apr-24 12-Sep-25
Site Preparation 48 26-Apr-24 26-Jun-24
Earthworks 35 15-Jul-24 02-Sep-24
Road Works 99 29-Apr-25 12-Sep-25
Area 2 415 18-Apr-24 24-Oct-25
Site Preparation 43 18-Apr-24 08-Jun-24
Earthworks 35 03-Sep-24 16-Oct-24
Road Works 214 15-Jan-25 24-Oct-25
Area 3 470 18-Apr-24 09-Jan-26
Site Preparation 52 18-Apr-24 22-Jun-24
Earthworks 30 18-Oct-24 25-Nov-24
Road Works 88 13-Sep-25 09-Jan-26
Area 4 495 26-Apr-24 16-Feb-26
Site Preparation 54 26-Apr-24 05-Jul-24
Earthworks 30 26-Nov-24 09-Jan-25
Road Works 60 28-Nov-25 16-Feb-26
Area 4.A 12 02-Jan-26 15-Jan-26
Site Preparation 6 02-Jan-26 08-Jan-26
Earthworks 6 09-Jan-26 15-Jan-26
Area 9 595 26-Apr-24 30-Jun-26
Site Preparation 480 26-Apr-24 29-Jan-26
Earthworks 15 30-Jan-26 16-Feb-26
Road Works 100 18-Feb-26 30-Jun-26
South Side 313 02-Apr-24 21-May-25
Area 5 193 02-Apr-24 12-Dec-24
Site Preparation 37 02-Apr-24 17-May-24
Earthworks 35 24-Jun-24 09-Aug-24
Road Works 30 06-Nov-24 12-Dec-24
Area 6 215 13-Apr-24 25-Jan-25
Site Preparation 44 13-Apr-24 05-Jun-24
Earthworks 35 10-Aug-24 28-Sep-24
Road Works 30 13-Dec-24 25-Jan-25
Area 7 252 23-Apr-24 21-Mar-25
Site Preparation 42 23-Apr-24 13-Jun-24
Earthworks 35 30-Sep-24 12-Nov-24
Road Works 45 27-Jan-25 21-Mar-25
Area 8 282 11-May-24 21-May-25
Site Preparation 33 11-May-24 22-Jun-24
Earthworks 35 14-Nov-24 03-Jan-25
Road Works 45 22-Mar-25 21-May-25
Southvale Drive 210 18-Dec-24 30-Sep-25
From South Side 210 18-Dec-24 30-Sep-25
SD-TW100 Earthworks 45 18-Dec-24 18-Feb-25
SD-TW110 Portal Works 165 19-Feb-25 30-Sep-25
SD-TW120 Tunneling Works 120 16-Apr-25 30-Sep-25
Exluded Activities 231 23-May-25 27-Mar-26
EXA100 Construction of Perim eter Fence 0 18-Feb-26 Construction of Perimeter Fence, , 18-Feb-26
EXA110 Construction of Perim eter Lightings 0 18-Feb-26 Construction of Perimeter Lightings, , 18-Feb-26
EXA120 Construction of Guard Post 0 27-Mar-26 Construction of Guard Post, , 27-Mar-26
EXA130 Installation of CCTV 0 27-Mar-26 Installation of CCTV, , 27-Mar-26
EXA140 Installation of Gates 0 27-Mar-26 Installation of Gates, , 27-Mar-26
EXA150 Construction of MRF 0 23-May-25 Construction of MRF, , 23-May-25
EXA160 Construction of STP 0 23-May-25 Construction of STP, , 23-May-25

Post-Construction 421 13-Dec-24 30-Jun-26

Commissioning Works 421 13-Dec-24 30-Jun-26


North Side 401 15-Jan-25 30-Jun-26
Flushing / Cleaning Works 401 15-Jan-25 30-Jun-26
South Side 120 13-Dec-24 21-May-25
Flushing / Cleaning Works 120 13-Dec-24 21-May-25

Critical Remaining Work Remaining Work Date Revision Checked Approved


Page 2 of 2 Southlinks Estate - Site Development Works 23-Apr-24 Rev.06 CGP
Milestone
INDICATIVE SCHEDULE 12-Apr-24 Rev.05 CGP
Summary
SUBJECT FOR DISCUSSION 20-Feb-24 Rev.04 CGP