DORMITORY BUILDING CONSTRUCTION

DETAIL TIME PROGRAM_DB_FMIL


Activity ID Activity Name Planned Planned Start Planned Finish Total Float
Duration

DORMITORY BUILDING CONSTRUCTION 230d 02-May-23 27-Dec-23 0d

CONSTRUCTION 230d 02-May-23 27-Dec-23 0d

SUB-STRUCTURE 44d 02-May-23 14-Jun-23 0d


FOUNDATIONS WORKS 16d 02-May-23 17-May-23 0d
PADESTRAL & GRADE BEAM 33d 13-May-23 14-Jun-23 0d
SUPER STRUCTURE 115d 15-Jun-23 17-Oct-23 0d
GROUND FLOOR 26d 15-Jun-23 20-Jul-23 0d
FIRST FLOOR 26d 21-Jul-23 15-Aug-23 0d
SECOND FLOOR 26d 16-Aug-23 10-Sep-23 0d
THIRD FLOOR 26d 11-Sep-23 06-Oct-23 0d
ROOF & STAIR TOP 11d 07-Oct-23 17-Oct-23 0d
MASIONARY WORKS 109d 09-Aug-23 25-Nov-23 32d
GROUND FLOOR 27d 09-Aug-23 04-Sep-23 77d
FIRST FLOOR 31d 04-Sep-23 04-Oct-23 84d
SECOND FLOOR 28d 30-Sep-23 27-Oct-23 61d
THIRD FLOOR 31d 26-Oct-23 25-Nov-23 32d
ROOF & STAIR TOP 11d 06-Nov-23 16-Nov-23 0d
FINISHING WORKS 109d 10-Sep-23 27-Dec-23 0d
INTERNAL FINISHING WORKS 96d 10-Sep-23 14-Dec-23 13d
GROUND FLOOR 19d 10-Sep-23 28-Sep-23 90d
FIRST FLOOR 19d 10-Oct-23 28-Oct-23 60d
SECOND FLOOR 19d 02-Nov-23 20-Nov-23 37d
THIRD FLOOR 19d 26-Nov-23 14-Dec-23 13d
ROOF & STAIR TOP 4d 24-Nov-23 27-Nov-23 17d
FINAL FINISHING WORKS 46d 12-Nov-23 27-Dec-23 0d
EXTERNAL FINISHING WORKS 46d 12-Nov-23 27-Dec-23 0d
FINAL WORKS 14d 11-Dec-23 24-Dec-23 2d

EXTERNAL GROUND WORK 30d 01-Sep-23 30-Sep-23 87d

SEPTIC TANK 30d 01-Sep-23 30-Sep-23 87d