Subject : LINDEN HOUSE MODEL CONSTRUCTION MONITORING

FA = 40.00sqm, CIP Wall System, 2BR, 1TB, LA = 80.00sqm


Location : Orchard Place Residences, Brgy. Pinagbarilan, Baliwag Bulacan MODULAR ACCOMPLISHMENT BASED ON NTP
Owner : Prominence Properties Inc.
Contractor: : ABB BUILDERS NTP NO: 21 NO OF UNIT: 4
Date: : December 22, 2021

AT 100%
1.0 2.0 3.0 4.0
ACCOMPLISHMENT
MODULE
PAY ITEMS B18L02 B18L04 B18L06 B18L08
NO. DUPLEX UNIT
DUPLEX UNIT DUPLEX UNIT DUPLEX UNIT DUPLEX UNIT
Module I SUB - STRUCTURE 9.80% 9.80% 9.80% 9.80% 9.80%
1.01 Layout, Batterboards & Excavation 0.56% 0.56% 0.56% 0.56% 0.56%
1.02 2500psi RC Wall Footing 2.54% 2.54% 2.54% 2.54% 2.54%
1.03 Wooden Zucallo Forms,600x2400mm 0.75% 0.75% 0.75% 0.75% 0.75%
1.04 2500psi RC Zucallo Wall 2.05% 2.05% 2.05% 2.05% 2.05%
1.05 Septic Vault,1200x2800x1600mm 3.90% 3.90% 3.90% 3.90% 3.90%
Module II GROUND FLOOR RC WALL 9.49% 9.49% 9.49% 9.49% 9.49%
2.01 Wires & Conduits 0.86% 0.86% 0.86% 0.86% 0.86%
2.02 PVC Pipes & Fittings 0.67% 0.67% 0.67% 0.67% 0.67%
2.03 GF Wall Concreting 7.95% 7.95% 7.95% 7.95% 7.95%
Module III SECOND FLOOR SUSPENDED SLAB 7.18% 7.18% 7.18% 7.18% 7.18%
3.01 2F Slab Concreting 7.18% 7.18% 7.18% 7.18% 7.18%
Module IV SECOND FLOOR RC WALL 0.00% 0.00% 0.00% 0.00% 10.93%
Module VA STEEL FRAMING WORKS 0.00% 0.00% 0.00% 0.00% 3.92%
Module VB ROOFING & ACCESSORIES 0.00% 0.00% 0.00% 0.00% 4.68%
Module VC MISCELLANEOUS CONCRETE 0.00% 0.00% 0.00% 0.00% 2.97%
Module VD MASONRY FINISHES 0.00% 0.00% 0.00% 0.00% 11.50%
Module VI SLAB-ON-FILL 0.00% 0.00% 0.00% 0.00% 5.66%
Module VII CARPENTRY 0.00% 0.00% 0.00% 0.00% 12.57%
Module VIIIA FINISHING WORKS 0.00% 0.00% 0.00% 0.00% 12.22%
Module VIIIB MOVE-IN-WORKS 0.00% 0.00% 0.00% 0.00% 9.09%
TOTAL 26.47% 26.47% 26.47% 26.47% 100.00%

1.00 % Weight TOTAL ACCOMPLISHMENT 26.47% 26.47% 26.47% 26.47%


2.00 % Weight PREVIOUS ACCOMPLISHMENT 26.47% 26.47% 19.29% 19.29%
3.00 % Weight BILLABLE THIS PERIOD 0.00% 0.00% 7.18% 7.18%
4.00 % Weight BALANCE AFTER THIS PERIOD 73.53% 73.53% 73.53% 73.53%
Target date of Completion 5-Apr-22 5-Apr-22 5-Apr-22 5-Mar-22
No of days remaining/ delays 104.00 104.00 104.00 73.00

Prepared by: Verified by: Checked by: Noted by:

__________________ ___________________ _____________________ ________________


ROBERTO NOLLORA JR. AR JASON HERNANDEZ JOHN PAUL T. DY
OPR-SE A&E - Engineer A&E -Architect President