Jul-19 Progress
No Process name Bobot (%) WEEK I WEEK II WEEK III WEEK IV WEEK V (%)
1 2 3 4 5 8 9 10 11 12 13 15 16 17 18 19 22 23 24 25 26 29 30 31
Baseframe FAbrication
1 FABRIKASI BASEFRAME 9,15% 1,83% 1,83% 1,83% 1,83% 1,83%
General Assy
6 PEMASANGAN Z BAR U BAR 3,27% 3,27%
9 ACCESORIES (PINTU DAN VYNIL DLL) 10,84% 2,71% 2,71% 2,71% 2,71%
12 FABRIKASI SPREADER BAR, LIFTING LUG dan PAINTING 4,63% 1,16% 1,16% 1,16% 1,16%
Total 100,00% `
Per Day 1,83% 1,83% 2,48% 2,48% 3,33% 2,52% 2,52% 4,85% 3,74% 7,09% 5,87% 5,82% 2,55% 3,87% 5,43% 3,44% 6,69% 3,78% 3,16% 4,91% 16,24% 4,24% 1,34%
Progress Plan
Accumulated 1,83% 3,66% 6,14% 8,62% 11,94% 14,46% 16,98% 21,83% 25,57% 32,67% 38,54% 44,36% 46,90% 50,77% 56,20% 59,64% 66,33% 70,11% 73,28% 78,18% 94,43% 98,66% 100,00%
2,25% 3,69% 5,35% 8,54% 9,89% 14,43% 19,59% 23,84% 25,60% 35,35%
Daily Realization
Progress Actual
0,4% 0,0% -0,8% -0,1% -2,1% 0,0% 2,6% 2,0% 0,0% 2,7%
Deviation