Chapter 3-062430234606290.75316323
Chapter 3-062430234606290.75316323
Chapter 3-062430234606290.75316323
Implementation
Chapter 3: Implementation
18
Malda Irrigation Division, Mahananda Embankment Division, Coochbehar Irrigation
Division, Canals Division, Hooghly Irrigation Division, Jalpaiguri Irrigation Division and
Alipurduar Irrigation Division.
19
Coochbehar Irrigation Division, Canals Division, Hooghly Irrigation Division, Jalpaiguri
Irrigation Division and Alipurduar Irrigation Division.
20
Howrah Irrigation Division, Malda Irrigation Division, Mahananda Embankment Division,
Jalpaiguri Irrigation Division and Alipurduar Irrigation Division.
21
Mahananda Embankment Division, Canals Division, Hooghly Irrigation Division, Jalpaiguri
Irrigation Division and Alipurduar Irrigation Division.
22
Howrah Irrigation Division and Jalpaiguri Irrigation Division.
15
Performance Audit of Implementation of Flood Control Measures in West Bengal
help in quick execution. Only one work was completed within the scheduled
date of completion, another work was completed with a delay of 54 days and
the remaining work was on-going as of May 2018 even after the scheduled date
of completion in April 2018.
Thus, irrespective of the time taken in approval process, there were delays in
execution of works under Flood Control Programme.
3.2 Execution of Projects
I&WD executed (1) embankment protection, (2) anti-river erosion, (3) drainage
improvement works for flood control during the years 2013-18. It also
included two major projects namely Kandi Master Plan (KMP) and Kaliaghai-
Kapaleswari-Baghai (KKB) under Flood Management Programme (FMP) with
shared funding by the Centre and the State. As per Para 4.2 of the “Revised
guidelines for providing Central Assistance to State Governments for the
Schemes/Proposals of Flood Control and River Management Works under FMP
(2007-12)”, Central and State share was to be in the ratio of 75:25. The DPRs of
both KMP23 and KKB24 were stated to have been prepared as per the guidelines
of GFCC/CWC and relevant IS codes.
3.2.1 Kandi Master Plan
An area of about 510 sq. km.25 in Murshidabad district is critically prone to
perpetual flooding and drainage congestion and remains totally cut-off for
several days at a time during floods. Most of the embankments, constructed
decades ago, are in dilapidated condition. I&WD prepared (June 2012) the
Detailed Project Report (DPR) for the Kandi Master Plan to ameliorate the
flood situation. The project primarily comprised of structural measures like :
(i) raising/strengthening of a total of 223 km embankments of five different
rivers26,
(ii) protection work of different river embankments of a total length of
38.72 km,
(iii) resuscitation of four khals27,
(iv) renovation of 57 existing sluices,
(v) creation of additional capacity of waterways by renovating 12 existing
rail/road bridges and culverts and
(vi) construction of three double lane River Bridges.
Investment clearance of ` 438.94 crore was accorded by the erstwhile Planning
Commission, GoI in June 2012 under Flood Management Programme (FMP)
with target date of completion by March 2017.
23
Page 7 of Chapter 7 of DPR for Improvement of embankment and ancillary works in Kandi
and other adjoining areas of district of Murshidabad.
24
Page IV-16, X-2, X-10, XI-8 and XIII-1 of Final Report Volume-I and Page 2 of Supplementary
Volume-II (Revised) of Master Plan and DPR for Kaliaghai-Kapaleswari-Baghai Drainage Basin.
25
Consisting of entire Bharatpur-I, parts of Khargram, Burwan and Kandi blocks.
26
Mayurakshi, Bele, Dwarka, Kuye-Babla and Kana Mayurakshi.
27
Small drainage channels namely Jibanti Khal, Jhumjhum Khali Khal, Banki Khal and Swarup
Khali Khal.
16
Chapter 3: Implementation
First instalment of the Central Fund was released in March 2014. Approval of
State Planning Board was accorded in May 2014. Administrative Approval was
given by I&WD to Chief Engineer (North) in December 2014 and the project
work commenced in January 2015. As per the approved DPR, the project was
to be completed by March 2017, but it was executed in different phases and
only six out of 12 phases were completed as on March 2018. I&WD proposed
(October 2017) to complete the project by March 2019, which was yet to be
approved by GoI (December 2018).
17
Performance Audit of Implementation of Flood Control Measures in West Bengal
18
Chapter 3: Implementation
30
Page 48, Chapter 5 of DPR for Improvement of embankment and ancillary works in Kandi and
other adjoining areas of district of Murshidabad.
31
A line of 4H:1V (for clayey soil) from High Flood Level (HFL) to the country side indicates the
line of seepage through the embankments.
32
A horizontal shelf built into the embankment to strengthen its stability or to catch and arrest
slide material.
19
Performance Audit of Implementation of Flood Control Measures in West Bengal
20
Chapter 3: Implementation
21
Performance Audit of Implementation of Flood Control Measures in West Bengal
3.2.1.5
Non-compliance to Indian Standards Code and GFCC/
Technical Expert Committee recommendations
(a) Non-execution of sand cushion layer38
Para 3.7 of the IS Code 14262:1995 provided 150 mm thick sand layer over
the filter fabric to prevent mechanical rupture of the fabric by revetment stones.
Therefore, a cushion of 100-150 mm of locally available river bed materials/
sand was to be provided over Geo-textile filter.39
Boulder revetment work with Geo-textile filter for 25.11 km embankments of
rivers Mayurakshi, Bele and Dwarka were taken up under Phase-II and III of
KMP after May 2016. Sand layer over Geo-textile filter as recommended in IS
code was, however, not included in the DPR and hence not executed. While
conducting monitoring visit in May 2016, GFCC also observed that during
boulder revetment works40 on slope of embankment non-laying of sand cushion
layer, may lead to puncture of the filter.
Therefore, non-execution of sand cushion layer compromised the quality of
works executed at a cost of ` 21.81 crore upto March 2018 and may also lead to
failure of the protection work on the embankments.
Accepting the audit observation, I&WD stated that there were some difficulties
in bearing the extra expenditure within the tender provision. Extra care had,
however, been taken during execution of works to minimise the possibility of
puncture of Geo-textile filter.
(b) Non-execution of sausage crate41 in step
As per 5th Technical Expert Committee meeting of I&WD, GoWB on
implementation of river bank erosion in February 2015, in the reaches where
there is no scope to set back the bank line, the required slope is to be generated
by dumping boulder in crates over sand filled bags. GFCC also recommended
(May 2016) that in case of steeper slope towards river side, where there was
land constraint, sausage crate had to be provided i.e. at Sundarpur, Bhatkhanda
or places where necessary over the right bank of Dwarka and left bank of river
Bele.
38
A sand layer over Geo-textile filter.
39
A filter layer made with Geo-jute laid over the earthen embankment in protection work with
boulder pitching to protect the erosion of earthen embankment by river water.
40
Sloping structures with boulders placed on embankment.
41
Wire net filled with boulders, used for embankment protection.
22
Chapter 3: Implementation
42
A launching apron is a flexible stone cover placed on the bed of the river which settles into
the scouring area as scouring takes place and covers the base and side of the scour hole,
preventing it from developing further scouring.
23
Performance Audit of Implementation of Flood Control Measures in West Bengal
depends upon the scour43 depth below High Flood Level (HFL). Average
thickness of launching apron should be 1.5 times of the thickness of boulder
pitching.
It was observed that the average thickness of launching apron was provided
1.88 times of the thickness of boulder pitching (0.45 m) in the estimates instead
of 1.5 times and executed subsequently for 18.14 km embankment protection
works on the rivers of Dwarka and Bele under Phase-II and Phase-III of
KMP. Thus, due to execution of excess thickness of launching apron, extra
expenditure of ` 3.53 crore was incurred by I&WD which could have been
avoided.
In reply, I&WD stated that considering the criteria laid down in clause 5.6.2 of
Indian Standard 10751:1994 (design of Guide banks), such thickness was
provided for launching apron. The fact, however, is that this code is applicable
for designing Guide banks44 and not for embankment protection.
Thus, the intended benefits of the KMP project could not be assured only
by the raising and strengthening of embankments of different rivers,
without creating additional waterways by renovating the existing bridges
and culverts. The already executed improvement works of different
embankments were also not in conformity with the approved DPR or
guidelines of GFCC.
The inundation maps below show the comparison between the water available in
the catchment area of KMP and the floods that had taken place in the catchment
area in the years 2011 (before the commencement of the project), 2015 and
2017.
Flood Report of 2017 reflects that all the four blocks (Bharatpur-I, Khargram,
Burwan and Kandi) included under KMP were inundated by flood water in
July 2017. The flood protection measures taken by I&WD may, therefore, not
have been adequate.
Figure 3.7: Inundation map of Kandi Basin Figure 3.8: Inundation map of Kandi Basin
on 16.08.2011 in dry season
43
‘Scouring’ is the name given to the removal of the bed or bank of a water course by the action
of flowing.
44
Guide Bank is defined as the site of a barrage to guide the river flow through the confined
waterway without causing damage to the structure and its approaches.
24
Chapter 3: Implementation
Figure 3.9: Inundation map of Kandi Basin Figure 3.10: Inundation map of Kandi
on 07.08.2015 Basin during 23-25.08.2016
I&WD stated that though the blocks were inundated, the extent of inundation
was less compared to previous years.
3.2.2 Kaliaghai-Kapaleswari-Baghai Project
The entire KKB (Kaliaghai-Kapaleswari-Baghai) basin covers an area of
2145 sq. km. spread over the districts of Paschim and Purba Midnapore. The
southern portion of the basin, having low lying terrain, historically suffers from
flood and tidal inundation.
The project primarily comprised of structural measures like:
(i) Excavation/re-sectioning of a total of 186 km embankments of five rivers/
tributaries45,
(ii) Realignment of the flood protective embankments of Kaliaghai,
Kapaleswari and Baghai and construction of embankments as per standard
specification,
(iii) Construction of Rubber dam type regulator on river Kaliaghai at Chabukia
downstream of outfall of Kapaleswari,
(iv) Construction of three bridges across river Chandia at Sridharpur, Ejmali
Chak and Chandipur etc.
25
Performance Audit of Implementation of Flood Control Measures in West Bengal
The KKB Drainage Scheme was initiated to provide relief to seven flood prone
blocks in Paschim and Purba Medinipur districts. The scheme was envisaged to
benefit a total area of 621 sq. km. with population of four lakh.
Investment clearance of ` 650.38 crore for KKB project was accorded by the
Planning Commission, GoI in March 2010 with target date of completion by
March 2015. The project was included under FMP with a funding ratio of
75:25 (Central:State) in July 2010. The project was commenced in March
2011 and ` 347.78 crore (Central Share ` 165.73 crore and State Share
` 182.05 crore) was released against which expenditure of ` 340.24 crore was
incurred up to March 2018. Release of Central Share was 36.46 per cent46 less
as the project could not be completed within the stipulated time. Meanwhile,
the State Government released funds in anticipation of receipt of Central fund.
I&WD proposed (August 2017) to complete the project by March 2019 which
was yet to be approved by GoI. The project was still (December 2018) ongoing.
The project could not be completed within stipulated period mainly due to delay
in land acquisition. Only 35 per cent of the estimated land was acquired up to
March 2018. The main rivers were excavated with reduced design bed width
due to non-availability of required land. The length of the rivers/channels were
resuscitated only on the available Government land (i.e. river course) and to
the extent of land acquired for the purpose. Besides, resuscitation works were
executed in khals not in the original scope of the DPR.
Physical progress under different components of KKB is shown in Table 3.2.
Table 3.2: Physical progress of different components of the KKB project
Sl. No. Name of the Unit Estimated Completed upto Progress in
Component quantity March 2018 Percentage
1. Land Acquisition Ha 500.00 173 35
2. Resuscitation of main Km 141.00 128.85 91
rivers
3. Resuscitation of small Km 170.00 170.46 100
drainage channels
4. Earth work Lakh 484.47 414.12 85
Cum
5. Concrete work Cum 6000.37 5490.00 91
(Source: Divisional records)
46
` 165.73 crore against ` 260.84 crore (75 percent of ` 347.78 crore).
26
Chapter 3: Implementation
47
Horizontal width of river bed.
48
Page 3, Chapter VIII of Master Plan and DPR for Kaliaghai-Kapaleswari-Baghai Drainage
Basin (Final Report-Volume I).
49
From Poktapol (46 km) to Dheubhanga (109 km) i.e. 63 km was included for re-sectioning
work in the DPR.
50
Excavation for de-siltation.
51
Page 2, Chapter VIII of Master Plan and DPR for Kaliaghai-Kapaleswari-Baghai Drainage
Basin (Final Report-Volume I).
52
Barriers with polythene sheets in flowing rivers for fishing.
27
Performance Audit of Implementation of Flood Control Measures in West Bengal
reduce the velocity of river flow as well as augment silt deposition. Therefore,
the DPR proposed for removal of fishing barriers across main rivers.
53
Page 2, 3 and 6, Chapter XI of Master Plan and DPR for Kaliaghai-Kapaleswari-Baghai
Drainage Basin (Final Report-Volume I).
54
Haorar Khea (at Ch. 55.00 km of River Kaliaghai), at Ch.42.70 km of River Kaliaghai,
Chabukia (at Ch.49.20 km of River Kaliaghai).
28
Chapter 3: Implementation
55
Khal means a narrow water channel.
56
Page 14 and 15, Table 10.4B, 10.4C, 10.4D of Kaliaghai-Kapaleswari-Baghai Drainage
Basin Scheme – Gradient Statement.
29
Performance Audit of Implementation of Flood Control Measures in West Bengal
The executing Divisions replied that resuscitation of rivers was carried out
only on available Government land (river course) as the required land was not
acquired. Due to non-resuscitation of rivers up to the design bed width specified
in the DPR, the problem of frequent flooding and drainage congestion in the
basin remained unresolved.
• Construction of Rubber Dam yet to be taken up
In the DPR57 of KKB Project, non-monsoon tidal ingress was identified as one
of the major causes of faster siltation of the river beds. Accordingly, it was
planned to construct a regulator structure58 having one-way flow system at the
confluence of river Kapaleswari with river Kaliaghai. Provision for construction
of the regulating structure on river Kaliaghai was also made to store upstream
water for irrigation purposes during non-monsoon period. In order to construct
the regulating structure over river Kaliaghai, a cost effective Rubber Dam was
incorporated (2010) in the DPR59 with a stipulation to complete the work within
three years of commencement, i.e., by 2012-13.
I&WD, however, failed to construct the regulator at the designated site. Scrutiny
of related records revealed that revised target was set by I&WD to complete
the same by March 2019. I&WD was still (December 2018) in the process
of preparation of modified Expression of Interest (EoI) for this work. On the
issue of revised expected date of completion, the Department stated (January
2019) that due to complexity of technical know-how, no positive response was
received from bidders in the past.
30
Chapter 3: Implementation
31
Performance Audit of Implementation of Flood Control Measures in West Bengal
It was observed that during 2012-13 to 2016-17, four works65 were executed at
a cost of ` 8.68 crore without obtaining technical sanction from the competent
authority and was also not vetted by the GFCC as per stipulation. Violation of
provisions of WBFR not only rendered the execution of works unauthorised
but also led to a risk that the works did not adhere to the prescribed technical
standards.
In reply, I&WD stated that all works were duly sanctioned by the competent
authority as per departmental norms. Reply of I&WD was, however, not specific
to the four cases pointed out by Audit.
(e)
Non-compliance of recommendation of the Independent Agency
engaged by I&WD
Clause 5.8 of FMP Guidelines (2009) required performance evaluation of the
project by independent professional agencies having expertise in related field.
Accordingly, Indian Institute of Technology (IIT), Kharagpur was nominated
by I&WD for performance evaluation of the project. IIT Kharagpur in its
report recommended (April 2014) that proper maintenance of the channels be
undertaken once in a year to maintain its geometry, otherwise problem may
reappear due to siltation. GFCC in the Monitoring Report of January 2018 also
recommended for periodical maintenance of the channels to assure the safety of
the excavated channels.
32
Chapter 3: Implementation
66
Chabukia (at Ch.49.35 km of River Kaliaghai), Haorar Khea (at Ch.55.00 km of River
Kaliaghai), Dheubhanga (at Ch.62.50 km of River Kaliaghai), Chandibenia (at Ch.22.00 km of
River Chandia), Asnan Ghat (at Ch.24.00 km of River Chandia), Dheubhanga (at Ch.6.80 km of
Moyna New Cut Channel), at Ch.42.70 km of River Kaliaghai and outfall of river Kapaleswari,
Chabukia at Ch.49.20 km of River Kaliaghai, Birjiban (at Ch.2.00 km of Kapaleswari).
67
House, shops, cattle sheds, clubs, primary school, machine sheds, party offices, etc.
68
River Kapaleswari left embankment (2.00 kmp to 14.70 kmp), Kalimondop Khal left
embankment (0.142 kmp to 0.950 kmp, 2.00 kmp to 2.50 kmp, 5.40 kmp to 6.60 kmp),
Kalimondop Khal right embankment (4.60 kmp to 6.80 kmp), Kalimondop Khal both left and
right at Mohanbazar, River Kaliaghai (13 kmp to 34 kmp), Ganapatkhal, Banskona khal and
Amrakhali khal.
33
Performance Audit of Implementation of Flood Control Measures in West Bengal
The Annual Flood Report of 2017 of I&WD reflected that all the seven blocks69
included under KKB were inundated in 2017. The flood protection measures
taken by I&WD may, therefore, not have been adequate.
3.2.3
Implementation of other Embankment protection and
anti-river erosion works
Apart from the two FMP projects as discussed above, I&WD executed
embankment protection as well as anti-erosion of river bank works under State
Plan, Rural Infrastructure Development Fund (RIDF), Common Border Rivers
Fund, One Time Additional Central Assistance (OTACA) etc. In eight test
checked Divisions70 (other than project Divisions of KKB and KMP), 145 out
of 357 tenders having estimated cost more than ` one crore each, which were
executed during 2013-14 to 2017-18 under flood control measures, were selected
for detailed examination.
Scrutiny of selected embankment protection and anti-erosion works revealed
the following deviations which would have an adverse impact on the flood
control measures:
3.2.3.1 Work done without obtaining clearance from the Forest
Department
As per Forest Conservation Act, 1980, clearance from Forest Department is
required for construction of embankment on forest land. Alipurduar Irrigation
Division took up (December 2016) the work of ‘Extension of Subhasini
embankment along the left bank of river Torsa’ at a cost of ` 5.78 crore without
obtaining forest clearance. Subsequently, the work was proposed for termination
by the Chief Engineer, I&WD in April 2018 due to objection raised by the
Forest Department for not obtaining clearance; no reply was received from the
Department in this regard.
Thus, commencement of work without obtaining forest clearance made the partially
executed work worth ` 0.70 crore (only earth work without protection) wasteful.
3.2.3.2 Required thickness of graded filter not provided in the revetment
Para 3.7 of IS code-14262:1995 as well as Para 4.5.4 of CWC Guidelines-
2012 stipulate that graded filter of size 150 mm to 300 mm thickness should be
provided below the revetment71 to prevent water from removing the underlying
soil of embankments through voids in the boulder pitching.
It was noticed that in 28 estimates prepared by three test checked Divisions72
valuing ` 61.83 crore, provision for only 100 mm thick filter layer of shingles
under the slope pitching was made and executed in violation of the existing
norms. Thus, construction of embankments with less thickness of filter layer
made them vulnerable to erosion.
69
Narayangar, Datan-I, Sabong, Pingla, Bhagabanpur-I, Patashpur-I and Moyna.
70
Howrah Irrigation Division, Malda Irrigation Division, Mahananda Embankment Division,
Coochbehar Irrigation Division, Canals Division, Hooghly Irrigation Division, Jalpaiguri
Irrigation Division and Alipurduar Irrigation Division.
71
Embankment protection work with boulders placed along the slope of the embankments.
72
Coochbehar Irrigation Division, Jalpaiguri Irrigation Division and Alipurduar Irrigation
Division.
34
Chapter 3: Implementation
In reply, I&WD stated that 100 mm thickness shingles filter is normally provided
where discharge is less than 4500 cumec73.
The reply was, however, not in consonance with the fact that neither the IS code
nor the CWC guidelines recommend graded filter layer of 100 mm thickness.
3.2.3.3 Non-execution of sand cushion layer in embankment
Para 3.7 of Indian Standards code-14262:1995 stipulates that a 150 mm thick
sand cushion layer should be provided over the filter fabric to prevent mechanical
rupture of the fabric by revetment stones.
Mahananda Embankment Division executed nine embankment protection and
anti-erosion works valuing ` 58.36 crore where boulder pitching on top and
slope was executed over Geo-textile filter. It was, however, observed that laying
of sand cushion was not envisaged in the estimates and works were executed
without providing such layer.
As a result, possibility of rupture of filter layer and failure of the protection
works could not be ruled out. In reply, the concerned Division stated (June
2018) that in future sand cushion layer will be included in this type of work.
3.2.3.4 Delay in execution of works
Clause-2 of standard tender agreement stipulates that time is the essence of
the contract. NIT clause further stipulates that time extension may be granted
only on the ground of non-receipt of departmental materials, land injunction or
public interference, etc.
It was observed that completion of 42 works taken up by the six test checked
Divisions74 were delayed by nearly four months to four years. Further, scrutiny
revealed that time extension was granted by the competent authority on grounds
other than those specified in the contract agreements in all cases. This resulted
in delay in achievement of the intended benefits from the projects. Moreover,
delay in execution of works kept the river embankments in vulnerable condition.
3.2.3.5 Use of lower specification Galvanised Iron wires in boulder
crates for construction of embankment
Para 3.6 of Indian Standard 14262:1995 on Planning and Design of Revetment
stipulates that Galvanised Iron (GI) wire of minimum four mm diameter should
be used for crates in revetment in the area where velocity of river is high. It
was observed that in five test checked Divisions75 crated boulder with GI wire
of less than four mm diameter (ø) was used in all 48 test checked embankment
protection/anti-erosion works valuing ` 219.79 crore during 2013-18 in violation
of the norms. The works remained vulnerable due to use of below specification
GI wire for boulder crates in embankment and anti-erosion works. During joint
site visit (April 2018) of left bank of river Mahananda in Adampur Block of
Malda District it was also noticed that the crates used in protection works were
in broken condition.
73
Cubic metre per second.
74
Howrah Irrigation Division, Malda Irrigation Division, Mahananda Embankment Division,
Hooghly Irrigation Division, Jalpaiguri Irrigation Division and Alipurduar Irrigation Division.
75
Malda Irrigation Division, Mahananda Embankment Division, Coochbehar Irrigation
Division, Jalpaiguri Irrigation Division and Alipurduar Irrigation Division.
35
Performance Audit of Implementation of Flood Control Measures in West Bengal
36