Write - Up - 2014 - 15 - Pages - 104-130
Write - Up - 2014 - 15 - Pages - 104-130
Write - Up - 2014 - 15 - Pages - 104-130
4.2 In the 11th Plan, the expenditure was incurred ` 1865.56 Cr. The
12th Plan outlay for irrigation is ` 4935.64 Cr. During 12th plan, irrigation
potential of 660 thousand hectares is likely to be restored and new potential of
300 thousand hectares will be created. An expenditure of ` 418.47 Cr was
incurred during 2012-13. Against an outlay of `1103.52 Cr, an expenditure of
` 276.11 Cr was incurred during 2013-14. An outlay of ` 1283.77 Cr for irrigation
and flood control sector is provided in the Annual Plan 2014-15. The Irrigation
potential likely to be created shall be 45 thousand hectares in the Annual Plan
2014-15.
Ongoing Schemes
CSS –Flagship Schemes
4.1.1 Kandi Canal Stage-II Project from Hoshiarpur to Balachaur i.e from
104
RD 59.500 km to RD 130 km is an extension of Kandi Canal Stage-I, which has
already been constructed. The total cost of this project was ` 147.13 Cr (at 5/97
price level) and was cleared by the Technical Advisory Committee of CWC,
Ministry of Water Resources, in August 1999. The expenditure incurred during
9 th Plan was ` 13.36 Cr. This project has been undertaken under Accelerated
Irrigation Benefit Programme (AIBP) since 2001-2002. The sharing pattern of
this scheme was 67:33 between Government of India and State Government
as central loan assistance. The funding pattern under AIBP has been changed to
25:75 between GoI and state government form 2008-09. The revised project
cost of Kandi Canal Stage-II is ` 346.62 Cr on the basis of January 2008 price
level. The latest revised cost of this project is ` 540.24 Cr. The total length of
Kandi canal phase-II project is 70 km, out of which 56 km length has already
been completed. The remaining 14 km length would be completed in
2014-15.The work in remaining length of canals is in progress. With the
completion of this project, irrigation facilities shall be provided to 29,527 hac.
area of 218 villages.
4.1.3 The Shahpur Kandi Project is a sister concern project of Ranjit Sagar
Dam Project (which stands completed). The construction of Shahpur Kandi Dam
Project is essential to get the optimum benefits of power and irrigation
potential created by Ranjit Sagar Dam Project. Shahpurkandi Dam Project is
being constructed on river Ravi to provide a balancing reservoir to have uniform
water releases for Upper Bari Doab Canal, Kashmir canal off taking from
Madhopur head works and high level Ravi canal (J&K) which will off take from
right side of Shahpurkandi Dam Project. It will ensure optimum power
105
generation during peak hours from Ranjit Sagar Dam Project. Since 2001-02
this project has been covered under AIBP. Cumulative expenditure of ` 240.00 Cr
has already been incurred upto March, 2014 on acquisition of land, preliminary
design, investigation, development of infrastructural works, excavation of main
dam, benches, left side head regulator, hydel channel and concreting of left side
head regulator.
4.1.5 First Patiala Feeder and Kotla branch of Sirhind Canal system (off
taking from Ropar head works) are unlined canals, which runs in heavy filling
reaches through sandy tract zone in Punjab. First Patiala Feeder is presently
capable to carry 3600 cs supply against its authorize discharge of 4010 cs. After
rehabilitation, the carrying capacity of First Patiala Feeder shall be 4914 cs.
Similarly Kotla Branch is presently capable to carry 2550 cs against authorized
discharge of 3018 cs. After rehabilitation, the carrying capacity of Kotla Branch
shall be 3304 cs. GoP has decided to rehabilitate both these canals with 20%
enhanced capacity so that adequate irrigation supply may be provided to the
cotton belt area of districts of Patiala, Sangrur and Mansa. T h e l a t e s t
r e v i s e d t otal cost of project is ` 1 9 9 . 3 9 Cr and physical target is 154 kms.
The implementation of this project shall provide better irrigation facilities to
about 2.65 lac ha area and bring additional area of 68624 ha falling in Patiala,
Sangrur, and Mansa districts under canal command. An outlay of `123.30 Cr
was provided under this scheme in the 11th Plan against which an expenditure
of ` 120.91 Cr has been incurred. An outlay of ` 2.93 Cr and ` 20.00 Cr has
been provided in the 12th Plan 2012-17 and Annual Plan 2012-13 respectively. An
outlay of ` 40.00 Cr was provided in the Annual Plan 2013-14. No expenditure
was incurred during 2012-13 & 2013-14. An outlay of ` 20.00 Cr out of which
` 5.00 Cr as central share and ` 15.00 Cr as state share is provided for Annual
Plan 2014-15. The cumulative expenditure upto March, 2014 is ` 120.00 Cr. The
physical progress of the project is 89%. The project is targeted to be completed
by March 2015.
Outlay - ` 4.00 Cr
4.1.6 Govt. of India has recently sanctioned new project for extension
Renovation and Modernization of Canals being Fed from River Sutlej amounting
107
to ` 734.56 Cr under AIBP assistance. Project is likely to be completed by March,
2016. The details of 4 canals are as under:-
4.1.7 Bist Doab Canal off takes from the right bank of river Sutluj upstream
of Ropar head works with full supply discharge of 1452 Cs. The Bist Doab Canal
System serves for Gross Culturable Area of 6.36 lac acres and Culturable
Command Area of 4.90 lac acres of Nawanshahar, Hoshiarpur, Jalandhar and
Kapurthala Districts. The authorized full supply discharge of this system is 1452
cusecs but at present, the system carries only 1000 cusecs and irrigates about
30240 hectares land. The Bist Doab Canal System is not capable to carry
additional water as per demand of the area. The estimated cost of project is
` 210.90 Cr. After the implementation of this project, Bist Doab System shall be
able to carry 1832 cusecs discharge and existing area of 39860 hectares shall be
restored and an additional area of about 8100 hectares shall be brought under
irrigation. An outlay of ` 53.28 Cr was provided under this scheme in the 11th
Plan. However, no expenditure was incurred during 11 th plan. No outlay has
been provided in the 12th Plan 2012-17 and an outlay of ` 15.00 Cr has been
provided in the Annual Plan 2012-13. An outlay of ` 0.01 Cr was provided during
2013-14. An outlay of ` 1.00 Cr out of which ` 0.25 Cr as central share and ` 0.75
Cr as state share is provided in Annual Plan 2014-15.
` 20.00 Cr was provided under this scheme in the 11th Plan. No expenditure
was incurred during 11th plan. No outlay has been provided in the 12th Plan
108
2012-17 and an outlay of ` 15.00 Cr has been provided in the Annual Plan 2012-
13. An outlay of ` 0.01 Cr was provided during 2013-14. An outlay of ` 1.00 Cr
out of which ` 0.25 Cr as central share and ` 0.75 Cr as state share is provided in
Annual Plan 2014-15.
4.1.9 A project for the rehabilitation of Sidhwan branch has been prepared
to ensure full utilization of or share in Sidhwan branch off-takes from tail
RD194444/R of Sirhind Canal at Manpur Head. The authorized discharge of
Sidhwan Branch is 1751 cusecs and it supplies water for irrigation to the
districts of Ludhiana, Moga and Ferozepur. The Gross Culturable Area (GCA) of
the system is 1.71 lac hectares and Culturable Command Area (CCA) is 1.59 lac
hectares. The existing area under irrigation of this canal is about 94638
hectares. The carrying capacity of the canal is not required to be increased. Only
the sidelining of both sides of the canal is proposed. With the implementation
of the project irrigation potential of about 32500 hectares shall be restored and
an additional area of about 6000 hectares shall also be brought under
irrigation. The outlay approved for Annual Plan 2009-10 is ` 3.50 Cr for
implementation of Hon’ble High Court order for cleaning of canal against which
an expenditure of ` 2.95 Cr was incurred. An outlay of ` 10.00 Cr was provided
An outlay of ` 20.00 Cr was provided under this scheme in the 11th Plan. No
expenditure was incurred during 11 th plan. No outlay has been provided in the
12th Plan 2012-17 and an outlay of ` 15.00 Cr has been provided in the Annual
Plan 2012-13. An outlay of ` 0.01 Cr was provided during 2013-14. An outlay of
` 1.00 Cr out of which ` 0.25 Cr as central share and ` 0.75 Cr as state share is
provided in Annual Plan 2014-15.
Outlay - ` 100.00 Cr
Ongoing Schemes
State Funded Schemes
4.2.1 Banur Canal is a non-perennial canal being fed from Ghagger river
by construction of katcha earthen bundh for the period from November to
June. This project envisages of a pucca weir across for river Ghaggar to feed
Banur canal with an assured supply of water throughout the year in S.A.S.
111
Nagar and Patiala districts. The total cost of the project is ` 58.15 Cr out of
which NABARD share is ` 45.56 Cr and state share is ` 12.59 Cr . The updated
revised cost of the project is ` 87.14 Cr. With the completion of this project,
36022 acres of agricultural area of 60 villages, falling in Derabassi, Rajpura and
Ghanur blocks of District Patiala shall be benefited. New area of 3000 acres
shall also be brought under the command of Banur Canal system. The Project
is likely to be completed by March, 2015. An outlay of ` 50.00 Cr was provided
MI-02 Tubewells and other schemes for Deep Tubewells in Kandi Area-RIDF-
X (95:5) Completed
Outlay - ` 2.00 Cr
4.2.3 The project for installation of 280 No. Deep tubewells in Kandi area
of Punjab State for irrigation purposes costing ` 130.06 Cr has been sanctioned
by NABARD under RIDF-XV on 27/10/2009 against which an amount of ` 123.56
Cr is to be financed by NABARD as a loan during 3 years of its implementation
w.e.f.1/4/2009. An expenditure of `33.79 Cr has been incurred during 11 t h
plan. No outlay has been provided in the 12th Plan 2012-17 and an outlay of
` 30.00 Cr has been provided in the Annual Plan 2012-13. An expenditure of
` 18.79 Cr was incurred during 2012-13.Against an outlay of ` 30.00 Cr, an
expenditure of ` 16.93 Cr was incurred during 2013-14. An outlay of ` 64.00 Cr is
112
provided for Annual Plan 2014-15. The target planned to drill 93 tubewells is
Kandi Area.
113
various purposes. The revised cost of the project is ` 60.67 Cr. The main
objective of the project is to improve the institutional and organizational
arrangements, technical capabilities and physical facilities available for
measurements, validation, collection, analysis, transfer and dissemination of
hydrological, hydro metrological and water quality data which is basic for water
resources evaluation and help in the development of the improved water
resources and environmental planning and management. The project is to be
implemented over a period of six years. The project has been declared effective
w.e.f. 5/4/2006 with the completion date 31/3/2015. An outlay of ` 44.50 Cr
was provided under this scheme in the 11th Plan against which an expenditure
of ` 16.23 Cr has been incurred. An outlay of ` 46.43 Cr and ` 30.00 Cr has
been provided in the 12th Plan 2012-17 and Annual Plan 2012-13 respectively. An
expenditure of ` 7.50 Cr was incurred during 2012-13. Against an outlay of
` 20.00 Cr, an expenditure of ` 4.99 Cr was incurred during 2013-14. An outlay of
` 21.00 Cr is provided for Annual Plan 2014-15.
MI-08/MI-12: Remodeling/Constructionofdistributaries/minors:
4.2.7 The position of meager releases of funds for works component for
the remodeling of canals has been going on since last several years. The
condition of all the canal systems has deteriorated to such an extent that the
114
channels are incapable to carry their authorized discharge whereas the
eagerness of the department as per policy of the Govt. is to run channels with
20% extra discharge. Therefore, remodeling of the existing canal system to cater
for enhanced carrying capacity is required to be undertaken being a long term
project.
Outlay – ` 15.97 Cr
Outlay - ` 463.35 Cr
115
in 1974. Since 2008-09 the Government of India decided to carry out the work
of field channels under AIBP on 50:50 basis with sharing pattern of 50:40:10
between GoI, GoP and beneficiary farmers. Out of the total 1,20,000 km of
watercourses in Punjab, 84000 km (70%) are to be lined. 47760 km of water
courses has been lined under the different schemes upto March 2014, 36702 km
of katcha watercourses are yet to be lined. The work for lining of water courses
on five no. projects i.e Eastern Canal System, Kotla Branch, UBC Sirhind Feeder
part-11 and Bathinda Branch Part-11 was taken up during 11th plan, out of
which eastern canal system and Kotla Branch have been completed on
31/10/2007 and 31/3/2008 respectively & remaining three are ongoing. During
2007-10 the expenditure incurred was ` 227.21 Cr. An expenditure of ` 123.85
Cr was incurred against the approved outlay of `100.00 Cr during 2010-11. An
outlay of ` 200.00 Cr was provided under this Sub-head “CAD” in the 11th Plan
against which an expenditure of ` 510.45 Cr has been incurred. An outlay of
` 1183.07 Cr and ` 300.00 Cr has been provided in the 12th Plan 2012-17 and
Annual Plan 2012-13 respectively. An expenditure of ` 123.86 Cr was incurred
during 2012-13. Against an outlay of ` 310.00 Cr, an expenditure of ` 124.90 Cr
was incurred during 2013-14. The work of Sirhind Feeder Part-II, Bathinda Branch
Part-II and Kotla Branch Part-II will be executed under Command Area
Development and water Management Programme (CADWM) for which the
proposed target planned is to execute 3584 KMs length of water courses with the
cost of ` 652.52 Cr and 45878 hectares potential will be created for utilization. An
outlay of ` 463.35 Cr is provided for Annual Plan 2014-15.The priority will be:
(1) Where the area is water logged and underground water is not fit for
irrigation;
(2) Where the underground water is brackish i.e Kharamajha area; and
(3) Sweet water zone.
Ongoing Schemes
CSS- Flagship Schemes
116
Command Area Development Agency (CAD) wing of MoWR, GoI and stands
sanctioned vide dated 24/2/2004. The total cost of the project is ` 358.57 Cr
which is revised @ `15000/- per ha w.e.f. 1/4/2009. On physical side the target
is 184861 ha. The c o m p l e t i o n date is 31/3/2015. An outlay of ` 36.80 Cr was
provided under this scheme in the 11th Plan against which an expenditure of
` 37.58 Cr has been incurred. An outlay of ` 263.62 Cr and ` 30.00 Cr has been
provided in the 12th Plan 2012-17 and Annual Plan 2012-13 respectively. An
expenditure of ` 5.04 Cr was incurred during 2012-13. Against an outlay of
` 10.00 Cr, no expenditure was incurred during 2013-14. An outlay of ` 8.15 Cr is
provided for Annual Plan 2014-15. Project is likely to be completed by 31/3/2015.
Outlay - ` 100.00 Cr
Outlay –` 50.00 Cr
117
sanctioned on 6/5/2008. The total cost of the project is ` 366.10 Cr which is
revised @ ` 15000/- per ha w.e.f 1/4/2009.State share of this project of ` 70 Cr
has already been sanctioned by NABARD vide dated 21/4/2008 under RIDF-XIII.
On physical side the target is 181707 ha. The expenditure incurred during 2008-
09 was ` 38.25 Cr. The completion date is 31/3/2015. An outlay of ` 40.00 Cr
th
was provided under this scheme in the 11 Plan against which an expenditure of
` 131.57 Cr has been incurred. An outlay of ` 152.45 Cr and ` 50.00 Cr has
been provided in the 12th Plan 2012-17 and Annual Plan 2012-13 respectively. An
expenditure of ` 14.61 Cr was incurred during 2012-13. Against an outlay of
` 50.00 Cr, an expenditure of `15.85 Cr was incurred and length of water courses
lived is 64.57 Km during 2013-14. An outlay of ` 50.00 Cr out of which ` 25.00 Cr
as central share and ` 25.00 Cr as state share is provided for Annual Plan
2014-15.
Outlay - ` 200.00 Cr
4.3.5 This is a new project is being implemented under Command Area
Outlay –` 40.00 Cr
Outlay - ` 20.00 Cr
4.3.9 The NABARD has approved the project for lining of 1790 kms.
length of watercourses on Bhakhra Main Branch Canal System amounting to
119
expenditure of ` 17.16 Cr was incurred during 2012-13. Against an outlay of
` 50.00 Cr, an expenditure of ` 22.58 Cr was incurred during 2013-14. An outlay
of ` 20.00 Cr is provided for Annual Plan 2014-15.
New Schemes
4.3.10 This is a new project and is being implemented under state plan
scheme. The total cost of this project is ` 6.71 Cr. Out of this ` 6.04 Cr is state
share and ` 0.67 Cr is beneficiaries share. The State Share amounting to ` 4.98
Cr has been financed by the NABARD under RIDF XIX. Under this project 54.516
Kms length of watercourses will be lined and 3257 Ha. area will be covered. The
date of completion is 31-3-2016. An outlay of ` 6.71 Cr is provided for Annual
Plan 2014-15.
Outlay – ` 8.49 Cr
4.3.11 This is a new project and is being implemented under state plan
scheme. The total cost of this project is ` 8.48 Cr. Out of this ` 7.63 Cr is state
share and ` 0.85 Cr is beneficiaries share. The state share amounting to ` 6.29 Cr
has been financed by the NABARD under RIDF XIX. Under this project 75 Kms
length of watercourses will be lined and 5566 Ha. area will be covered. The date
of completion is 31-3-2016. An outlay of ` 8.49 Cr is provided for Annual Plan
2014-15.
Ongoing Schemes
State Funded Schemes
120
district SAS Nagar and Patiala, 40 Km is in district Sangrur and the remaining
23 Km is in district Mansa. The aim to save the agricultural land and village
abadis of the area of district Sangrur adjoining river Ghaggar from flood
damages during every rainy season. The total cost of the project is `137.43 Cr
out of which NABARD assistance is ` 67.49 Cr and State share is ` 69.94 Cr
which includes the land compensation of ` 48.12 Cr (` 69.94 - ` 21.82 = ` 48.12
Cr ). An outlay of ` 66.61 Cr was provided under this scheme in the 11th plan
against which an expenditure of ` 91.88 Cr has been incurred and the area
benefited is 24246 acres. An outlay of ` 5.00 Cr and ` 1.00 Cr has been
provided in the 12th Plan 2012-17 and Annual Plan 2012-13 respectively. An
expenditure of ` 2.93 Cr was incurred during 2012-13. Against an outlay of ` 1.00
Cr, an expenditure of ` 3.00 Cr was incurred during 2013-14. An outlay of ` 7.68
Cr is provided for Annual Plan 2014-15. The area benefited is 24246 acres.
4.4.3 165 schemes of flood protection works on rivers Sutlej, Ravi & Beas
121
in Punjab State NABARD RIDF-XVII during the year 2011-12 amounting to ` 79.74
Cr. Out of these funds for ` 15.15 Cr has been released by NABARD. The detail is
as under:-
4.4.4 An outlay of ` 5.00 Cr and ` 5.00 Cr has been provided in the 12th
Plan 2012-17 and Annual Plan 2012-13 respectively. An expenditure of ` 30.30 Cr
was incurred during 2012-13. Against an outlay of ` 10.00 Cr , an expenditure of
`11.17 Cr was incurred during 2013-14. An outlay of ` 5.00 Cr is provided for
Annual Plan 2014-15.
New Schemes
Outlay – ` 20.00 Cr
4.4.5 The main reasons of water logging are that the topography of the
entire area falling in Sri Muktsar Sahib, Lambi, Malout, Balluana, Abohar & Fazilka
constituency, being of saucer shape, impedes surface drainage. The ground
water in this tract is saline and brackish which cannot be utilized for irrigation,
drinking and industrial purpose unlike other areas in Punjab, where the ground
water is sweet and is being over-exploited. The constant seepage from the twin
canals flow of intensive canal irrigation, non-existence of surface drainage
system both natural and artificial absence of proper outfalls and insufficient
drawn by pumping in the area and up in water logging in the area.
4.4.6 The high powered state Technical Committee after through study has
listed out the various reasons of devastation deficiencies in the drainage system
and its remedial measures. Keeping in view the short comings listed and the
suggestions made by the committee, the present drainage system needs to be
122
revamped to cater with the rains of present days, which is very high in nature.
Benefits
1. Reduce the period of evacuation of storm from the fields and enhance
fertility of land.
2. Improve the drainage of the area and reclaim the water logged fertile area
for agriculture production.
3. Improve the economy of state as well as the nation by increasing the
agriculture production.
4. Reduce the seepage of rain and flood waters into the saline ground water
regime due to improved drainage of the area.
5. Improve the environment of the area and check the health hazards.
6. Provide quick evacuation of excess storm water without creating stagnant
pools near out fall and in low lying pockets.
Outlay –` 15.00 Cr
Outlay- ` 50.00 Cr
4.4.9 The project has been sanctioned as per the report of “High Level
Expert Committee” headed by Dr. Mihir Shah, member Planning Commission,
Ministry of Water Resources, GOI, submitted to Planning Commission, GOI, New
Delhi so as to address the waterlogging problem in South-Western districts of
Punjab.
4.4.10 During the year 2011-12 in the month of September, there was
unprecedented rainfall in the area due to which the crops got completely
damaged in South-Western districts of Punjab. Life and property was badly
affected. Low lying pockets remained inundated for long time causing misery in
the area. The farmers faced great hardships to retrieve the normal life. The
menace of water logging which caused devastation in the area shocked the
central teams during their visits in the state. To tackle the problem in South-
Western districts of Punjab, this project proposal envisages the following:-
124
BG(FC)-05/FC-10 Measures to address the Problem of Water Logging in the
State -13th Finance Commission
Outlay – ` 50.00 Cr
4.4.12 The water table is rising in south-western districts of the State due
to limited or non-extraction of groundwater due to its blackish/saline quality
which makes it unfit for domestic, irrigation and other purposes mainly in the
Muktsar, Malout and Abohar tracts level. After the construction of twin canals
i.e. Rajasthan Canal feeder and Sirhind canal feeder, in addition to Abohar
Branch and Bikaner canals, the sub- soil water level started rising at the rate of
0.2 metre to 1.0 metre annually. The area has witnessed a rise in water level
upto 22 metre in the last 25 years. The main reason of water logging is non-
extraction of underground water, which is blackish/saline.
4.4.13 Due to water-logging in these areas about 1.04 lac hectare area out
of 2.16 lac hectare area of Muktsar has become critically water logged, the land
stands submerged and is totally unfit for cultivation, the rising water table is
making the land saline and unfit for productivity when ground water reaches
the root zone area of crops. It has resulted in reduced agriculture production &
soil quality deterioration, more inputs by farmers, thereby raising input costs
and decreasing returns due to low productivity of crops.
125
4.4.15 13th Finance Commission has recommended a grant of ` 200.00 Cr
four years i.e. 2011-2015 for anti water logging measures for Punjab State out
of which ` 50.00 Cr are provided during 2011-12. No expenditure was incurred
during 11th plan. An outlay of ` 200.00 Cr and ` 50.00 Cr has been provided in
the 12th Plan 2012-17 and Annual Plan 2012-13 respectively. An expenditure of
` 50.00 Cr was incurred during 2012-13. Against an outlay of ` 50.00 Cr, an
expenditure of ` 39.22 Cr was incurred during 2013-14. An outlay of ` 50.00 Cr as
100% central share is provided for Annual Plan 2014-15.
Ongoing Schemes
CSS- Flagship Schemes
126
FC-12 Construction of Flood Protection Works along left side and right sides
of River Beas in District Gurdaspur, Hoshiarpur and Kapurthala
(75:25)(AIBP)
Outlay – ` 10.00 Cr
4.4.19 This project have been prepared by the Drainage Administration for
the safety of c-land and village abadies along indo-Pak Border on River Ravi to be
funded under BADP. The site inspection has been done by CWC Team. The
project has been cleared by State Technical Advisory Committee. Administrative
approval stands issued by the State Government. It required to be granted
technical clearance. The case is under process in the office of Director CWC, GOI,
Chandigarh. Under the scheme token outlay of ` 0.01 Cr has been provided for
the Annual Plan 2013-14. Against an outlay of ` 0.01 Cr, no expenditure was
incurred during 2013-14. An outlay of ` 20.00 Cr as central share is provided for
Annual Plan 2014-15.
Outlay – ` 5.00 Cr
4.4.20 Punjab being a riparian State has to suffer and face devastation
due to floods in three rivers i.e. Ravi, Sutluj and Beas whereas non-riparian
127
States Rajasthan and Haryana remain immune to adverse action of floods. The
State Government has submitted projects (20 no. schemes) of ` 330.00 Cr for
flood protection works to Central Water Commission (CWC) for approval. The
CWC, GoI has sanctioned following three projects with a cost of ` 30.99 Cr
(75% GoI Grant and 25% state share) under Flood Management Programme for
district Nawanshehar and Hoshiarpur:-
(ii) Plugging and stg. breaches and bringing to design section of 11.27
FPE along choes in district Hoshiarpur(Part-I)
(iii) Plugging and strengthening breaches and bringing to 8.05
design section of FPE along Mechagerwal choe, Arniala choe
and Gambowal choe in district Hoshiarpur(Part-I)
Total: 30.99
4.4.22 The project has been cleared by Planning Commission Govt of India
vide letter dated 4-8-2011. An outlay of ` 5.00 Cr and ` 5.00 Cr has been
provided in the 12th Plan 2012-17 and Annual Plan 2012-13 respectively. An
expenditure of ` 2.00 Cr was incurred during 2012-13. Against an outlay of ` 6.00
128
Cr, an expenditure of ` 3.12 Cr was incurred during 2013-14. An outlay of ` 4.00
Cr out of which ` 3.00 Cr as central share and ` 1.00 Cr as state share is provided
for Annual Plan 2014-15.
in the 11th Plan against which an expenditure of ` 0.79 Cr has been incurred.
An outlay of ` 2.56 Cr and ` 51.20 lac has been provided in the 12th Plan 2012-17
and Annual Plan 2012-13 respectively. An expenditure of ` 9.44 lac was incurred
during 2012-13. Against an outlay of `0.30 Cr, no expenditure was incurred
during 2013-14. An outlay of ` 0.40 Cr is provided for Annual Plan 2014-15.
4.4.24 This scheme was started during the year 1983-84. Under this
scheme the funds are provided for the execution of emergent flood protection
works along international border to divert the flow of river Sutluj away from
Indian side. This scheme is approved by the Ministry of Water Resources,
Government of India. As per practice in vogue the Remedial Committee
constituted by Central Water Commission proposes the funds after visiting the
site. The 31st Remedial Committee has already visited the site during January
2011 and has recommended 16 No. emergent works costing ` 5.97 Cr. Works
will be started after receipt of funds. N o funds were released by Government of
India. An outlay of ` 50.00 Cr was provided under this scheme in the 11th Plan
129
against which an expenditure of ` 7.02 Cr has been incurred. An outlay of
` 37.50 Cr and ` 7.50 Cr has been provided in the 12th Plan 2012-17 and Annual
Plan 2012-13 respectively. No expenditure was incurred during 2012-13 &
2013-14. An outlay of ` 7.50 Cr is provided for Annual Plan 2014-15.
4.4.25 This scheme was started during the year 1997-98. Under this
scheme funds are provided by Government of India for emergent flood protection
works along international border for defense security purposes. This scheme is
approved by Ministry of Home Affairs, Government of India. As per practice in
vogue the Remedial Committee (Constituted by Ministry of Home Affairs)
proposes funds after field visits at sites. The 31st Remedial Committee has
already visited the site during January 2011 and has recommended 25 No.
emergent works costing ` 18.27 Cr. Works will be started after receipt of
funds. No funds were released by Government of India. An outlay of `50.00 Cr
was provided under this scheme in the 11th Plan against which an expenditure
of ` 3.95 Cr has been incurred. An outlay of ` 50.00 Cr and ` 7.50 Cr has been
provided in the 12th Plan 2012-17 and Annual Plan 2012-13 respectively. No
expenditure was incurred during 2012-13 & 2013-14. An outlay of ` 7.50 Cr is
provided for Annual Plan 2014-15.
130