Quality Control Plan (QCP) For Ammonia Pressure Vessel: Before Manufacturing
Quality Control Plan (QCP) For Ammonia Pressure Vessel: Before Manufacturing
Quality Control Plan (QCP) For Ammonia Pressure Vessel: Before Manufacturing
Inspection
Remar
No Inspection/Examination Reference/Standard Code
k
QC TPI CLient
1 Before Manufacturing
1.1 Pre-Inspection meeting H H H
Review of approved technical
1.2 H RD A
Document & drawing
Material inspection against
plates, pipes, flanges, welding
1.3 CERT./DWG./SPEC. H H/V RD
consumables, etc (Certificate
review+ DT/NDT if required
1.4 W.P.S & P.Q.R ASME SEC IX H RD A
1.5 Welders certificate (W.P.Q) ASME SEC IX H RD A
1.6 NDT procedure & NDT map As per ASME SEC VIII Div.1 H RD A
1.7 Pressure test procedure As per ASME SEC VIII Div.1 H RD A
1.8 Inspection & Test Plan (ITP) AS Per SPEC. RD V A
Sandblasting & Painting
1.9 AS Per SPEC. H RD A
procedure
Shipment, installation &
1.10 AS Per SPEC. H RD A
maintenance procedure
1.10 Welding repair procedure AS Per SPEC. H RD A
2 Inspection of Manufacturing
Marking & Dimensional check As per ASME SEC VIII
2.1 prior to cutting
H RI RI
Div.1+Drawing
Identification marks (stamps & As per ASME SEC VIII Div.1
2.2 Heat No) transfer
H RI RI
UG 94
2.3 Check of edges preparation As per approved drawing H RI RI
Visual & dimensional check of As per ASME SEC VIII
2.4 cutting
H H RI
Div.1+Drawing
Ultrasonic lamination Check for
2.5 head & shell plates
As per ASME SEC V&VIII H H RI
Visual & dimensional check of
2.6 forming
As per approved drawing H RI RI
As per approved
2.8 Fit-Up of longitudinal seams H H RI
drawing+WPS
Page 1 of 3
Manufacturer logo
Quality Control Plan(QCP) Client logo
for Ammonia Pressure Vessel
Inspection
Remar
No Inspection/Examination Reference/Standard Code
k
QC TPI CLient
Page 2 of 3
Manufacturer logo
Quality Control Plan(QCP) Client logo
for Ammonia Pressure Vessel
Inspection
Remar
No Inspection/Examination Reference/Standard Code
k
QC TPI CLient
As per approved
2.27 Fit-Up & Welding of lifting lugs H RI RI
drawing+WPS
Fit-Up & Welding nameplate As per approved
2.28 support
H RI RI
drawing+WPS
Non-destructive examination of As per ASME SEC V &
2.29 welds (except RT) VIII+NDT Procedure
H H RI
Weld repair (if any weld needs AS Per SPEC. & ASME SEC
2.30 repair)
H W RI
V & VIII
Final visual & dimensional
2.31 check of completed vessel
As per approved drawing H V RI
2.32 Hydrostatic test As per ASME SEC VIII Div.1 H H H
2.33 Sandblast AS Per SPEC. & SA 2 1/2 H RI RI
2.34 painting AS Per SPEC H W RI
2.35 Installation of instruments As per approved drawing H RI RI
2.36 Nameplate stamping & fixing As per approved drawing H W
3 Packing & Shipping
Review marking for shipping,
3.1 packing list
H R RI
As per shipment
3.4 Check of shipment condition
procedure
H H H
Abbreviations:
V: Verify RD: Review of Document
H: Hold point RI: Random Inspection point
W: Witness point A: Approval