Pressure Vessel Inspection and Test Plan Sample
Pressure Vessel Inspection and Test Plan Sample
Pressure Vessel Inspection and Test Plan Sample
com
Pressure Vessel Inspection and Test Plan Sample
Activity By Remark
No. Inspection and Test Plan Reference Document Acceptance Criteria Verifying Document
Manuf. TPI Client
Before Manufacturing
DWG, Design, DWG,
2 ASME, Spec ASME, Spec H R A -
Calculation Document Calculation book
3 WPS&PQR ASME ASME IX Welding Book H R A -
Welder Qualification
4 ASME ASME IX Certificates H R - -
Certificates
Materials
Original Material
10 Material Certificates ASME ASME II H R - -
Certificates
Storage of raw material
11 ASME ASME - H W - -
and Welding
1
www.inspection-for-industry.com
During Manufacturing
Transferring of marking
13 ASME VIII ASME VIII Report H SW - -
Material
2
www.inspection-for-industry.com
ASME/NDT map/NDT
26 PT, UT (Nozzle) ASME VIII Report
Procedure
Fit-Up, Welding (Pad of
27 WPS/DWG WPS/DWG - H SW - -
shell)
Final Inspection
Packing
3
www.inspection-for-industry.com
Marking Control &
40 - Spec. MOM H H - -
Release Note
Shipping Document
42 Procedure Spec. Packing List H R - -
Control
Abbreviations:
H: Hold Point = Hold on the production till TPI Inspector performs inspection and supervise the required test
W: Witness Point = Manufacture shall notify client and TPI Inspector but there is no hold on the production;
Client can waive this inspection based on his discretion and informs TPI Inspector accordingly.
R: Document Review = Review means Review document, which includes of material test certificates, WPS, PQR, NDT Procedures and etc.
A: Approval
SW: Spot Witness = for items with spot witness manufacture shall notify TPI inspector as fulfilling the monitoring;
For example one random visit for whole UT tests or one or two visits for whole surface preparation works for painting.