Zhu et al., 2022 - Google Patents
Protection of Ground Buildings (Structures) and Treatment Technologies of Underground ObstaclesZhu et al., 2022
- Document ID
- 17288668165694873281
- Author
- Zhu W
- Ju S
- Wang H
- Publication year
- Publication venue
- Shield Tunneling Technology in Mixed Face Ground Conditions
External Links
Snippet
Tunnel construction in urban areas will inevitably pass under or sideways through some buildings (structures), such as ground houses, existing tunnels, railways, bridges. There is a risk of shield construction disturbing the surrounding rock and pile foundation (wood piles …
- 238000010276 construction 0 abstract description 44
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21B—EARTH DRILLING, e.g. DEEP DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
- E21B7/00—Special methods or apparatus for drilling
- E21B7/20—Driving or forcing casings or pipes into boreholes, e.g. sinking; Simultaneously drilling and casing boreholes
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D7/00—Methods or apparatus for placing sheet pile bulkheads, piles, mouldpipes, or other moulds
- E02D7/26—Placing by using several means simultaneously
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21B—EARTH DRILLING, e.g. DEEP DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
- E21B7/00—Special methods or apparatus for drilling
- E21B7/04—Directional drilling
- E21B7/046—Directional drilling horizontal drilling
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21C—MINING OR QUARRYING
- E21C41/00—Methods of underground or surface mining; Lay-outs therefor
- E21C41/16—Methods of underground mining; Layouts therefor
- E21C41/18—Methods of underground mining; Layouts therefor for brown or hard coal
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D9/00—Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
- E21D9/06—Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02F—DREDGING; SOIL-SHIFTING
- E02F9/00—Component parts of dredgers or soil-shifting machines, not restricted to one of the kinds covered by groups E02F3/00 - E02F7/00
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/045—Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D1/00—Sinking shafts
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D23/00—Caissons; Construction or placing of caissons
- E02D23/08—Lowering or sinking caissons
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D13/00—Large underground chambers; Methods or apparatus for making them
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21C—MINING OR QUARRYING
- E21C41/00—Methods of underground or surface mining; Lay-outs therefor
- E21C41/26—Methods of surface mining; Layouts therefor
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21F—SAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105804758B (en) | Across constructing metro tunnel method on the rectangular top pipe of the shallow small spacing of earthing big cross section | |
CN110821503B (en) | Construction method for main body of ultra-deep shield section air shaft after tunnel advance | |
CN102418531B (en) | Tunneling construction method for directly removing overpass group piles by using shield machine | |
CN111236957B (en) | Mechanical pipe jacking construction process | |
CN106978807A (en) | Existing bridge pile pulling device and construction method are passed through by a kind of weak soil shield driving area | |
CN106437737B (en) | Pipe jacking type coal mine small-section roadway tunneling method | |
CN103835661A (en) | Local excavation pre-supporting raise boring technology | |
CN106545007A (en) | The method of pile in stratum of the bottom for hard rock stratum | |
CN109812271B (en) | Construction method for shield-crossing limited box culvert | |
CN105714769A (en) | Construction method for anti-sliding cast-in-place pile | |
Phadke et al. | Construction of tunnels, by new austrian tunneling method (NATM) and by tunnel boring machine (TBM) | |
CN112942399A (en) | Open caisson mechanical construction device and method for penetrating rock stratum | |
Zhang et al. | A shield tunneling method for enlarging the diameter of existing tunnels: Experimental investigations | |
Mangushev et al. | Modern technologies of foundation building in the conditions of weak soils of St. Petersburg | |
Zhu et al. | Protection of Ground Buildings (Structures) and Treatment Technologies of Underground Obstacles | |
CN206570811U (en) | Existing bridge pile pulling device is passed through in weak soil shield driving area | |
CN113266362B (en) | A construction method of pipe jacking and cover excavation crossing existing dense anchor cable area | |
CN113684838A (en) | Grooving construction method for rock-socketed ultra-deep underground diaphragm wall | |
Hansen | The history of TBM tunnelling in Norway | |
CN114165242B (en) | Mechanized construction method for hard rock small-section cable tunnel | |
Chen et al. | Conventional Cutterhead and Tool-Changing Under Normal Pressure Technology | |
Schmäh | Vertical shaft machines. State of the art and vision | |
Kinnear et al. | Cross passage construction on the Crossrail C310 Thames Tunnel | |
Chen et al. | TBM Construction in Special Stratum | |
Zou et al. | Mechanical Underground Excavation in Rock |