Pip-001 Rev. A6
Pip-001 Rev. A6
Pip-001 Rev. A6
Method Statement
Document Title:
A6
ARCC/EE/ ISSUE STATUS
TABLE OF CONTENTS
Page
1 PURPOSE 3
2 SCOPE 3
3 REFERENCES 3
4 EQUIPMENT 3
5 MANPOWER 3
8 SAFETY CONSIDERATIONS 7
9 ATTACHMENTS 8
Notes:
1.0 The latest revised documents shall always be used.
2.0 Any conflict between this method statement and the CPL procedure, the CPL procedure
shall be followed
1.0 PURPOSE
This method statement will serve as a minimum guideline to carry out and complete the pipe
installation works at pipe racks.
2.0 SCOPE
This procedure will cover the random pipes & pipe spools installation at piperack.
3.0 REFERENCES
3.1 00-P-0036 Specification For Field Fabrication And Erection
3.2 00-P-0034 Specification for Acceptance Criteria - Flange Face
3.3 00-P-0031 Specification for Piping Traceability and Certification
3.4 00-W-0001 General Welding / NDE Specification for Pressure
Retaining Components
3.5 00-W-0003 General Welding / NDE Specifications for Piping,
Shop/Field Fabrication
3.6 00-Z-0004 Specification for Shop Preparation of Equipment and
Materials for Shipment
3.7 10-Z-0104 Positive Material Identification (PMI) Procedure (by
CPL)
3.8 ASME B 31.3 Process Piping
3.9 A008-ITP-P001 Inspection and Test Plan for
Installation of ASME B31.1 / B31.3 Piping (Site)
3.10 Relevant Project WPS
A6 3.11 A008-MS-PIP-011 Method Statement for Pressure Testing
4.0 EQUIPMENT
4.1 Mobile Cranes
4.2 Air Compressors
4.3 Welding Machines
4.4 Pneumatic Winch
4.5 Manlifts
4.6 Lifting Accessories
4.7 Rubber Lined Rollers
4.8 Hand Tools and Fixtures as required
5.0 MANPOWER
5.1 Field Superintendent
5.2 Field Supervisor
7.15.2 The weld joint, bevel angle, root opening and alignment is in accordance
with Spec. no. 00-W-0001 Sect. 2.5.2 and approved WPS.
7.15.3 The flange face free from damage and scratches. Refer to Table 1 of Spec.
00-P-0034 for the acceptance criteria.
7.15.4 The weld seam is staggered as per Spec. No. 00-P-0036 Sect. 10.5
7.15.5 The 6mm vent hole in reinforcing pad is provided as per Spec. No. 00-P-
0036 Sect. 9.3.3 para. (c).
7.15.6 The gap for socket welding is in accordance with the Spec. No. 00-P-0036
Sect. 10.6
7.15.7 The welding consumables to be used is in accordance with the approved
WPS and Spec. No. 00-W-0001 Sect. 2.4.1 & 2.4.2.
7.14 Submit request for inspection of the fitted spool / pipe.
7.15 When the fit-up is accepted proceed full welding of the pipe / spool. Welding process
used shall be as per approved WPS and the welder is qualified for the said WPS and
documents such as WPS and WPQR should be made available as per Spec. No. 00-
W-0001 Sect. 2.2 and 2.3 and hanged on the work area.
7.16 During the welding process the in-process inspection will be done verifying the following
items;
7.16.1 The Welding consumables used is in accordance with the approved WPS and
Spec. No. 00-W-0001 Sect. 2.4.1. & 2.4.2.
7.16.2 The required pre-heating / inter-pass temperature requirements is done as per
approved WPS and Spec. No. 00-P-0036 Sect. 9.1.3.
7.16.3 Purged requirement, as applicable, is being maintained as per approved WPS
and Spec. No. 00-W-0001 Sect. 2.5.8 para. 2.5.8.2 (b).
7.17 When the welding is completed visual inspection will be done checking the following
items, as applicable;
7.17.1 Inside surface of orifice flanges welded joints is ground or machined smooth as
per Spec. No. 00-P-0036 Sect. 10.4.
7.17.2 Threaded joints checked for fit and roundness as per Spec. No. 00-P-0036
Sect. 10.7
7.17.3 Weld surface reinforcement in accordance with ASME B31.3 Table 341.3.2
7.17.4 Dimension of fillet weld in accordance with ASME B31.3 Figure 328.5.2B and
328.5.4D.
7.17.5 The root pass in accordance with ASME B31.3 Table 341.3.2 and Spec. No.
00-P-0036 Sect. 10.8
7.17.6 Arc strikes in areas in areas not covered by the finished weld is ground as per
Spec. No. 00-W-0001 Sect. 2.5.5 para. 2.5.5.4.
7.17.7 Temporary materials used are already removed as per Spec. No. 00-W-0001
Section 2.5.5 para. 2.5.5.4.
7.17.8 Cleanliness of pipe shall be maintained as per Spec. No. 00-W-0001 Sect.
2.7.1 para. 2.7.1.2. The weld spatter, slag, flux, and other foreign materials
are removed.
7.18 The welder’s ID, weld no., and line no. will be marked with metal marker on the pipe
next to the weld. In addition the heat no. will be marked with low stress die stamp.
A6 7.19 For Golden joint, welding shall be as per A008-MS-PIP-011, Method Statement for
Pressure Testing.
7.20 The completed weld will be subjected to the required NDE as per Spec. No. 00-W-0003
Sect. 2.4. PMI as required shall be conducted in accordance with Spec. No. 10-Z-0104
Section 5.0, 5.2 and Table 1,2,& 3. “AV” shall be marked on the longitudinal surface of
the pipe 75mm away from the weld joints to denotes PMI acceptance. Hardness test as
required on some joints shall also be conducted and in accordance with Spec. No. 00-
W-0001 Sect. 2.6 and Spec. No. 00-P-0036 Sect. Sect. 11.7. Note that hardness test on
some joints requiring PWHT shall be done after the completion of PWHT.
7.21 Rejected weld will be repaired and will again undergo visual inspection as per item 7.17
above and required NDE as per item 7.19 above.
7.22 PWHT as required on some weld will be done after the weld pass the NDE
requirements.
7.23 Tightening of bolts shall be done in sequence to produce even compression and
uniform bolt loads as required in Spec. No. 00-P-0036 Sect. 10.3.2. Torque wrench use
shall be calibrated daily as required in Spec. No. 00-P-0036 Sect. 10.3.4. When using
stud tensioner the manufacturer procedure must be followed as specified in Spec. No.
00-P-0036 Sect. 10.3.6. The bolt used shall be checked for conformance with the
specifications.
7.24 For pipelines with shoes, saddles, others; these attachments will be tacked welded to
the pipe after being rigged to position. Shoes and saddle shall be positioned such that it
will align and rest properly at beams or supports. Prior to full welding the alignment,
location, and orientation must be checked and verified with the IFC drawings. The
supports used should be in accordance with the IFC drawing. PMI, if required, for
supports directly weld to alloy pipes shall also be conducted.
7.25 Pipe stoppers and guides will be full welded and painted while still accessible.
7.26 At interconnecting pipe racks, the same roller system will be utilized where new steel
works is installed and when there are no obstructions. Other areas will utilize cranes or
manual rigging method (sticking-out method) to directly install the spools and straight
lengths into position (see attached drawing for reference).
7.27 Prior to closure of piping sections, full compliance with cleanliness inspections and
documentation shall be insured in accordance with Spec. No. 00-P0036 Section 12
para. 12.2 and 12.3.
8 SAFETY PRECAUTIONS
8.1 Obtain the approval of the work permit from the concerned CPL/JUPC Department
before starting any work.
8.2 Fire Watcher with Fire Extinguisher shall be at work area whenever there is hot work.
8.3 All electrical tools shall be checked and color coded.
8.4 Continuous monitoring and inspection shall be implemented to detect and correct unsafe
practices while performing the work activities.
8.5 Provide warning sign and sufficient barricade on working area and only assigned
personnel will be allowed in the area.
8.6 Welding location shall be enclosed with wind barrier and provided with non-asbestos fire
blanket to prevent spread of any welding sparks.
8.7 Safety Officer shall monitor the work activities to help and to protect all assigned workers
against exposure to safety hazards. He shall ensure that Personnel Protection
Equipment (PPE’s) are supplied and used and comply with CPL/JUPC applicable
general instruction and standards.
8.8 Safety harness with double lanyards shall be used all the time when working at elevated
temporary platforms.
8.9 Manlift users shall be trained and certified to operate and use the equipment.
9 ATTACHMENTS