2.8 Lifting Works Supervision
2.8 Lifting Works Supervision
2.8 Lifting Works Supervision
中国京冶工程技术有限公司(新加坡分公司)
CHINA JINGYE ENGINEERING CORPORATION LIMITED (SINGAPORE BRANCH)
Address: 21 Bukit Batok Crescent, #19-77 WCEGA Tower, Singapore 658065
Reg. No.: T06FC6884E Tel: 65 67666883 Fax: 65 67666779
E-mail: info@mccsingapore.com.sg Website: www.mccsingapore.com.sg
CONTRACT CR101
• Lifting works supervision with toppling zone more than 6m away from
outermost edge of road structure shall be a qualified lifting supervisor
• Lifting works supervision with toppling zone less than 6m away from
outermost edge of road structure shall be a professional engineer or an
assignee appointed on his behalf
中国京冶工程技术有限公司(新加坡分公司)
CHINA JINGYE ENGINEERING CORPORATION LIMITED (SINGAPORE BRANCH)
Address: 21 Bukit Batok Crescent, #19-77 WCEGA Tower, Singapore 658065
Reg. No.: T06FC6884E Tel: 65 67666883 Fax: 65 67666779
E-mail: info@mccsingapore.com.sg Website: www.mccsingapore.com.sg
CONTRACT CR101
Lifting Supervisor
中国京冶工程技术有限公司(新加坡分公司)
CHINA JINGYE ENGINEERING CORPORATION LIMITED (SINGAPORE BRANCH)
Address: 21 Bukit Batok Crescent, #19-77 WCEGA Tower, Singapore 658065
Reg. No.: T06FC6884E Tel: 65 67666883 Fax: 65 67666779
E-mail: info@mccsingapore.com.sg Website: www.mccsingapore.com.sg
g Supervisor
ty CoursE"
LIALITY SAf- E
A C A D ~ l\ii C"
RA~ ID HARUN OR
ID No : O 64313851
Coutsto Date : 6-25 December 1016
Co urse Venue ; 10S Enterpri"-e Road
Singapore 627676
Validity Date : NA
i/ik,,eshw~r •n
,;, -
~J•
--------
Bu<um
Pnnc1p.,I Tr no,
...,ung 0111:~on lra1n1r.9 Oi111~iun
1• uo l1ty Safe Acade-mic Pte Ltd ls ..an Accredited Lear~ing.
!:> erv,ce Prov1d,~ by_Sing.a pore Accredit1on Council for the
Sa ld course over Feat.
This card Is the property of Quality Safe Academic Pte Ltd and
must be returned upon request. ,
PE & PE Assignee
中国京冶工程技术有限公司(新加坡分公司)
CHINA JINGYE ENGINEERING CORPORATION LIMITED (SINGAPORE BRANCH)
Address: 21 Bukit Batok Crescent, #19-77 WCEGA Tower, Singapore 658065
Reg. No.: T06FC6884E Tel: 65 67666883 Fax: 65 67666779
E-mail: info@mccsingapore.com.sg Website: www.mccsingapore.com.sg
FORM LTA DBC RSSZ-SUPV-R2
Manager
Instructions
Rail and Road Structure Protection
a. This form must be duly completed and submitted to the
Development and Building Control
Authority together with the application for permit to
Land Transport Authority
commence work.
251 North Bridge Road
b. * Delete as appropriate.
Singapore 179102
Dong Weibin
(1) I _________________________, 3885
PE No.______________________; am the appointed qualified person to
provide full time standing supervision of movement and operation of any crane, whether fixed or mobile,
hoist, ladder, drilling or piling equipment, excavator or any other mechanical equipment or vehicle within the
road structure safety zone;
(2) I undertake to fully discharge the duties stipulated in appendix of this form; and
(3) I will take reasonable steps and exercise due diligence to ensure that works are carried out in accordance with
the approved plans/details and in compliance with the Guide to carrying out Engineering Works within Road
Structure Safety Zone and Engineering Activity on Land adjoining Public Streets.
In carrying out his duty of ensuring the safety of the road structures against the movement and operation of
any crane, drilling or piling equipment, excavator or any other mechanical equipment or vehicle, a qualified
person shall:
1. Be responsible to ensure that works carried out within the road structures safety zones are safe and that
they do not infringe the requirements of the Guide to carrying out Engineering Works within Road
Structure Safety Zone and Engineering Activity on Land adjoining Public Streets as amended from time
to time.
2. Notify the Authority and seek approval at least two weeks in advance of commencement of work within
the road structures safety zones;
3. Ensure that working platforms for supporting the cranes, piling machines or any other mechanical plant
are stable before use and during the times they are in use and as work progresses. Should there be
changes in the site conditions that may affect the safe operation of these plant, he shall assess the
situation and certify whether the working platforms are safe before allowing the operation of the crane,
piling machines, etc. to continue;
4. Check and look out for potential hazards during such works and ensure that adequate precautionary and
safety measures are taken by the contractor, plant and machine operators before allowing them to
proceed;
5. Be in attendance on site at all times during the period when such works and activities are carried out;
6. Inspect and check that safety measures implemented on site such as provision of physical barriers or
demarcation to prevent encroachment of crane or similar plants are maintained and protected from
inadvertent removal or damage;
7. Keep a record of test certificates of all cranes, lifting gears and appliances employed at site and also the
certification by a Professional Engineer (Mechanical) of mechanical plants used at site;
8. Keep a daily register of all the names of site lifting supervisors and crane operators and record them
against each works and activities in which they are responsible. The register and a complete set of the
certificates of competency of these personnel shall be maintained at site and shall be available for
inspection by the Authority's staff;
9. Keep and maintain a site diary that states the details of activities carried out within the road structures
safety zones. The dairy shall record the following:
10. Conduct daily check together with the safety officer, lifting supervisors and crane operators of all
mechanical plant and equipment including any lifting gears and appliances to confirm that they are in
good working condition before work starts;
11. Ensure that site agents, site supervisors, foremen, crane operators and lifting supervisors are briefed and
well versed with the requirements and conditions of the Authority for works in the vicinity of the road
structures; and
12. Ensure that any operation which is likely to endanger the operational safety of the road structures such as
unsafe lifting operation, etc. are immediately stopped and reported to the Authority.
IS HEREBY ACCREDITED AS A
RESIDENT ENGINEER