01 MS - POT Bearing
01 MS - POT Bearing
01 MS - POT Bearing
Page 1 of 13
CLIENT: DELHI METRO RAIL CORPORATION LTD.
CONTRACTOR: ITD – ITD Cem JV
Contract Package: BC-21
PROJECT NAME: PART DESIGN AND CONSTRUCTION OF VIADUCT AND STRUCTURAL WORK
OF 5 ELEVATED STATIONS (GARDEN ESTATE, SIKANDERPUR, DT CITY CENTRE, IFFCO
CHOWK AND SUSHANTA LOK) ON QUTUB MINAR - GURGAON CORRIDOR OF DELHI MRTS
PROJECT
Revision: R1
Method Statement Of POT/PTFE Bearing Installation
CONTENTS
i. Preamble
1. Responsibilities and Authorities
2. Safety
3. Risk Hazard
4. Precaution to be taken before Installation
5. Material
6. Finishing of Material
7. Marking of Bearing
8. Installation of Bearing
9. Tests on bearings
10. Bedding for Bearing
11. List of Enclosures
Page 2 of 13
CLIENT: DELHI METRO RAIL CORPORATION LTD.
CONTRACTOR: ITD – ITD Cem JV
Contract Package: BC-21
PROJECT NAME: PART DESIGN AND CONSTRUCTION OF VIADUCT AND STRUCTURAL WORK
OF 5 ELEVATED STATIONS (GARDEN ESTATE, SIKANDERPUR, DT CITY CENTRE, IFFCO
CHOWK AND SUSHANTA LOK) ON QUTUB MINAR - GURGAON CORRIDOR OF DELHI MRTS
PROJECT
Revision: R1
Method Statement Of POT/PTFE Bearing Installation
PREAMBLE
Construction package BC 21 for DMRC is consisting of construction of
elevated viaduct for Phase-II of Delhi MRTS Project on Qutub Minar-
Gurgaon corridor from Delhi border to Sushant Lok. This includes five
elevated station buildings and viaduct.
This method statement illustrates the different activities included in the fixing
of POT/PTFE bearing for three track structure (Pier P204 to pier P218).
Page 3 of 13
CLIENT: DELHI METRO RAIL CORPORATION LTD.
CONTRACTOR: ITD – ITD Cem JV
Contract Package: BC-21
PROJECT NAME: PART DESIGN AND CONSTRUCTION OF VIADUCT AND STRUCTURAL WORK
OF 5 ELEVATED STATIONS (GARDEN ESTATE, SIKANDERPUR, DT CITY CENTRE, IFFCO
CHOWK AND SUSHANTA LOK) ON QUTUB MINAR - GURGAON CORRIDOR OF DELHI MRTS
PROJECT
Revision: R1
Method Statement Of POT/PTFE Bearing Installation
2. SAFETY
During the execution of the work, area will be properly covered with
barricading / plastic tape with suitable supports. It will be maintained
throughout the construction activity. A suitable access by ladders will be
maintained. All persons working in this activity area will wear safety helmet
and will take all necessary safety precautions. Every day ITD-ITD CEM JV site
engineer will inspect the scaffoldings, working platforms, and ladders. etc., for
ensuring safety and record his observations in Form No. ITD/QA/20.
3. RISK HAZARD
An assessment on risk hazard has been done; the copy of same is enclosed with
this method statement. All listed precautions therein shall be taken during work
to minimize the risk
Page 4 of 13
CLIENT: DELHI METRO RAIL CORPORATION LTD.
CONTRACTOR: ITD – ITD Cem JV
Contract Package: BC-21
PROJECT NAME: PART DESIGN AND CONSTRUCTION OF VIADUCT AND STRUCTURAL WORK
OF 5 ELEVATED STATIONS (GARDEN ESTATE, SIKANDERPUR, DT CITY CENTRE, IFFCO
CHOWK AND SUSHANTA LOK) ON QUTUB MINAR - GURGAON CORRIDOR OF DELHI MRTS
PROJECT
Revision: R1
Method Statement Of POT/PTFE Bearing Installation
2. In order that moving surfaces are not contaminated, bearings should not
normally be dismantled after leaving the factory premises, but if for any
reason they are, then this should only be done under expert supervision.
Page 5 of 13
CLIENT: DELHI METRO RAIL CORPORATION LTD.
CONTRACTOR: ITD – ITD Cem JV
Contract Package: BC-21
PROJECT NAME: PART DESIGN AND CONSTRUCTION OF VIADUCT AND STRUCTURAL WORK
OF 5 ELEVATED STATIONS (GARDEN ESTATE, SIKANDERPUR, DT CITY CENTRE, IFFCO
CHOWK AND SUSHANTA LOK) ON QUTUB MINAR - GURGAON CORRIDOR OF DELHI MRTS
PROJECT
Revision: R1
Method Statement Of POT/PTFE Bearing Installation
5. MATERIAL
1. Top plate, Piston and POT/bottom plate will be made up of cast steel grade
280-520W of IS: 1030. Anchor bolts shall confirm to IS: 1364.
2. The material such as PTFE lubrication, confined elastomer, stainless steel
and internal seal will be as per IRC: 83 (part III)-2000
3. Stainless Steel will confirm to AISI: 316L with the sliding surface finished
smooth.
Page 6 of 13
CLIENT: DELHI METRO RAIL CORPORATION LTD.
CONTRACTOR: ITD – ITD Cem JV
Contract Package: BC-21
PROJECT NAME: PART DESIGN AND CONSTRUCTION OF VIADUCT AND STRUCTURAL WORK
OF 5 ELEVATED STATIONS (GARDEN ESTATE, SIKANDERPUR, DT CITY CENTRE, IFFCO
CHOWK AND SUSHANTA LOK) ON QUTUB MINAR - GURGAON CORRIDOR OF DELHI MRTS
PROJECT
Revision: R1
Method Statement Of POT/PTFE Bearing Installation
Page 7 of 13
CLIENT: DELHI METRO RAIL CORPORATION LTD.
CONTRACTOR: ITD – ITD Cem JV
Contract Package: BC-21
PROJECT NAME: PART DESIGN AND CONSTRUCTION OF VIADUCT AND STRUCTURAL WORK
OF 5 ELEVATED STATIONS (GARDEN ESTATE, SIKANDERPUR, DT CITY CENTRE, IFFCO
CHOWK AND SUSHANTA LOK) ON QUTUB MINAR - GURGAON CORRIDOR OF DELHI MRTS
PROJECT
Revision: R1
Method Statement Of POT/PTFE Bearing Installation
13. The outside diameter of the piston shall not be more then 1 mm less the
inside diameter of the pot at the interface level of the piston and
Elastomeric rotational element.
14. The dimensional tolerance of confined PTFE will be as per CL.927.1.3
IRC: 83 (part III) – 2000.
15. Manufacture tolerance will be as per CL.927.1.1 IRC: 83 (part- III)-2000.
6. FINISHING OF MATERIAL
1. All non working surfaces will be coated with Two coats of Epoxy Primer
and or more coats each of high built Epoxy paint reinforced with MIO
(Micaceous Iron Oxide) and finish paint after shot blasting to SA 2 ½
quality as per IS: 9954 and total dry film thickness of protective coating
should not be less than 160 microns. All the finishing material i.e. Epoxy
primer, epoxy paint and finishing paint will be of Berger or Asian paints.
2. Bearing component to be embedded in concrete surface or surface of any
component to be in contact with concrete surface will be given a coat of
epoxy primer.
3. Anchor sleeves will be Hot Dip Galvanized coated @ 300 gm/m 2 before
dispatch.
4. The mating surface of the cylinder of the POT and that of the piston shall
be Metallurgical Hardened to a valve not less than 350 BHN.
5. The Silicon Grease will be applied at PTFE stainless steel interface after
testing.
Page 8 of 13
CLIENT: DELHI METRO RAIL CORPORATION LTD.
CONTRACTOR: ITD – ITD Cem JV
Contract Package: BC-21
PROJECT NAME: PART DESIGN AND CONSTRUCTION OF VIADUCT AND STRUCTURAL WORK
OF 5 ELEVATED STATIONS (GARDEN ESTATE, SIKANDERPUR, DT CITY CENTRE, IFFCO
CHOWK AND SUSHANTA LOK) ON QUTUB MINAR - GURGAON CORRIDOR OF DELHI MRTS
PROJECT
Revision: R1
Method Statement Of POT/PTFE Bearing Installation
6. At the time of fabrication all the steel surface expose to atmosphere, except
stainless steel and metal surface to be welded, will be shop painted. Prior
to painting, the exposed steel surface shall be cleaned.
7. MARKING OF BEARING
8. INSTALLATION OF BEARING
Page 9 of 13
CLIENT: DELHI METRO RAIL CORPORATION LTD.
CONTRACTOR: ITD – ITD Cem JV
Contract Package: BC-21
PROJECT NAME: PART DESIGN AND CONSTRUCTION OF VIADUCT AND STRUCTURAL WORK
OF 5 ELEVATED STATIONS (GARDEN ESTATE, SIKANDERPUR, DT CITY CENTRE, IFFCO
CHOWK AND SUSHANTA LOK) ON QUTUB MINAR - GURGAON CORRIDOR OF DELHI MRTS
PROJECT
Revision: R1
Method Statement Of POT/PTFE Bearing Installation
9. TESTS ON BEARINGS
Page 10 of 13
CLIENT: DELHI METRO RAIL CORPORATION LTD.
CONTRACTOR: ITD – ITD Cem JV
Contract Package: BC-21
PROJECT NAME: PART DESIGN AND CONSTRUCTION OF VIADUCT AND STRUCTURAL WORK
OF 5 ELEVATED STATIONS (GARDEN ESTATE, SIKANDERPUR, DT CITY CENTRE, IFFCO
CHOWK AND SUSHANTA LOK) ON QUTUB MINAR - GURGAON CORRIDOR OF DELHI MRTS
PROJECT
Revision: R1
Method Statement Of POT/PTFE Bearing Installation
2. FRICTION TEST
A pair of sliding bearing selected at random shall undergo friction test.
Friction test for sliding shall be performed at constant vertical design load.
The horizontal load shall then be applied till sliding occurs. The co-
efficient of friction shall be determined on the basis of applied vertical load
and horizontal load. The measured sliding coefficient of friction shall not
exceed 3%. The value of co-efficient of friction shall not exceed 2/3 rd of
the value specified in CI. 926.2.4.2 of IRC: 83(part – III) – 2002
depending on the actual average pressure on PTFE due to applied vertical
load.
3. ROTATION TEST
Rotation test for bearing shall be performed at constant vertical load equal
to design load and design rotation. The load shall be removed and bearing
shall be dismantled and examined.
Page 11 of 13
CLIENT: DELHI METRO RAIL CORPORATION LTD.
CONTRACTOR: ITD – ITD Cem JV
Contract Package: BC-21
PROJECT NAME: PART DESIGN AND CONSTRUCTION OF VIADUCT AND STRUCTURAL WORK
OF 5 ELEVATED STATIONS (GARDEN ESTATE, SIKANDERPUR, DT CITY CENTRE, IFFCO
CHOWK AND SUSHANTA LOK) ON QUTUB MINAR - GURGAON CORRIDOR OF DELHI MRTS
PROJECT
Revision: R1
Method Statement Of POT/PTFE Bearing Installation
Page 12 of 13
CLIENT: DELHI METRO RAIL CORPORATION LTD.
CONTRACTOR: ITD – ITD Cem JV
Contract Package: BC-21
PROJECT NAME: PART DESIGN AND CONSTRUCTION OF VIADUCT AND STRUCTURAL WORK
OF 5 ELEVATED STATIONS (GARDEN ESTATE, SIKANDERPUR, DT CITY CENTRE, IFFCO
CHOWK AND SUSHANTA LOK) ON QUTUB MINAR - GURGAON CORRIDOR OF DELHI MRTS
PROJECT
Revision: R1
Method Statement Of POT/PTFE Bearing Installation
Page 13 of 13