Nothing Special   »   [go: up one dir, main page]

Me24-Id-V432-Gypsum-R00 - 260624

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

QUOTATION

MEL ENA Technical Services Date : 26-Jun-24

LLC Quotation No.: ME24-ID-V432-R00


(INTERIOR FIT OUT & OUTDOOR) Project Name: GYPSUM CEILING
Mirdif, Dubai , UAE Project Location WADI AL ARMADI,DUBAI

Client
Contact Person
1 PROJECT : VILLA 432 - TYPE A Name
Mr Mohummad Ziad

Location Plot : WADI AL ARMADI, DUBAI Contact Person No.:

DEAR SIR,
We are Thank you very much for your enquiryand are please to submit our most competitive offer for the same as follow.

Item No. Item Description Qty Unit Unit price Total Amount
SCOPE OF WORKS
CEILING BOARD REGULAR - Supply & Installation of 12.5 mm Thk. Regular Gypsum Board
G.1 23328 Sq.m 68.00 1,586,304.00
Gyproc with suspension and joints tape only
CEILING BOARD MOISTURE - Supply & Installation of 12.5 mm Thk. Moisture Resistant
G.2 11016 Sq.m 75.00 826,200.00
Gypsum Board Gypoc with Suspension and joint tape only
GYPSUM BOARD BULKHEAD-REGULAR- Supply & Installation of 12.5 mm Thk. Regular
G.3 2378 L.m 65.00 154,570.00
Gypsum Board Bulkhead 890mm high with Suspension and joint tape
GYPSUM BOARD BULKHEAD-REGULAR- Supply & Installation of 12.5 mm Thk. Regular
G.4 12744 L.m 55.00 700,920.00
Gypsum Board Bulkhead 530mm high with Suspension and joint tape
G.5 CURTAIN BOX- Supply & Installation of Gypsum Curtain Box 20cm/20cm 11664 L.m 58.00 676,512.00
VINYL TILE CEILING- Supply & Installation of 60 X 60cm Gypsum Vinyl Tiles Ceiling for Kitchen
G.6 13824 Sq.m 58.00 801,792.00
& Wash Room Area
CALCIUM SILICATE- Supply & Installation of 12mm Board for Balcony Area - Approx 8m2 per
G.7 3456 Sq.m 145.00 501,120.00
Villa
G.8 SHADOW GAP-REGULAR- Supply & Installation of Shadow Gap profile 10 x 10 1 R/M 29.00 Rate only

MATERIAL SPECIFICATION
1 All steel structure are using Ceiling Suspension form GTI UAE. Brand
2 12.5 mm Thick Regular $ MR Gypsum Board From KNAUF Brand
3 Stucco from GYPROC Brand
4 60x60 Ceiling Tile to be t-24 grid Suspension type GTI BRAND
5 All Area only joint tape
6 Not Include Access Panel
Any Extra will be charge as a variation cost
PAYMENT DETAILS
50% ADVANCE IN CASH MATERIAL PURCHASING & CUTTING

30% 2nd PAYMENT IN CASH AFTER 50% COMPLETION AT SITE

15% 3rd PAYMENT IN CASH AFTER 75% COMPLETION AT SITE

5% final PAYMENT IN CASH AFTER INSTALLATION COMPLETE

NO retantion & no back to bak payment


VAT WILL BE INCLUDE AFTER CONFIRMATION VAT
TOTAL AMOUNT Five Million Two Hundred and Forty Seven Thousand Four Hundred and Eighteen & 00/100 Dirhams Only 5,247,418.00
ALL THE AUTHORITY AND PERMISSION WORK PERMIT ALL NECESSARY PAPERS TO WORK AT THE SITE
TO BE PROVIDED BY CLIENT
NOTE
1 - All Quantities are base on the client requirement as per drawing
2 - This Quotation Validity 20 days
3 - Any additional or variation which is not included in our above quotatian will be charge separately
4 - Works will be taken in hand only after receiving written confirmation & advance payment in CASH
5 - NO refund after receiving the payment for purchasing material
6 - Relevant submission fees and other fees/fines/Special approval fees payable to the authorities not included
7 - Job time will be depend upon the site
8 - Site visit require for Final measurement befor start manufacture
9 - We are not responsible for any damage/broken of Third Party's Civil works during our job

CHIEF DESIGN PARTNER CUSTOMER SIGNATURE


WANURA DATE
MEL ENA TECHNICAL SERVICES LLC

ME24-ID-V432-GYPSUM-R00 - 260624 Page No 1/1

You might also like