Sumsdghdhgdjfgnbbv Uhhhhhvhg
Sumsdghdhgdjfgnbbv Uhhhhhvhg
Sumsdghdhgdjfgnbbv Uhhhhhvhg
PRACTICALS
1. A company uses 1200 unit per month of an electric component each costing Rs.2. placing each
order cost Rs. 50 and carrying cost is 6% per year of the average inventory. 1. Find EOQ. 2. If the
company gets 5% discount if it place single order, should they accept the discount order?
2. An auto industry purchases spark plugs at the rate of Rs. 25 per piece. The annual consumption of
spark plug is 18,000 nos. if the ordering cost is Rs. 250 per order and carrying cost 25% pa. what
would be EOQ? If the supplier offers a discount of 5% for order quantity of 3000 no per order, do you
accept the offer?
3. For a given item, there is constant demand rate. Annual demand is 60,000 nos. the price per item is
Rs. 30. The ordering cost is estimated as Rs. 300 per order and carrying cost is 30% per annum. What
should be the optimal ordering quantity? If 2000 unit is purchased at time, a discount of 5% on unit
price is given , is offer accepted?
4. A company uses every month 1500 units of a component costing Rs. 1.20 each. Each purchase
order cost Rs. 50 and inventory carrying cost is 6% per yr of the average inventory. A] Find EOQ. B]
if 5% discount is given for a single order placement, is it worth?
EOQ METHOD:
Formulae
Maximum Level = (ROL + ROQ) – (Minimum Usage x Minimum Re Order
Period) or Maximum Level = Safety Stock + EOQ
Book A B C D E F
Printing 30 120 50 20 90 110
time (hrs.)
Binding 80 100 90 60 30 10
time (hrs.)
Q.2. Find the sequence that minimize the total Elapsed time required to complete the following jobs
on 2 machines:
Job 1 2 3 4 5 6 7 8 9
Machine A 12 15 14 19 16 18 17 15 14
Machine B 16 18 17 14 13 19 13 18 21
Q.3. Processing times of 7 jobs on three machines I,II,III are given. The order of processing is I-II-III.
Determine the sequence that minimizes the total elapsed time required to complete the jobs. Also
evaluate the idle time of machines.
Jobs I II III
A 30 40 60
B 80 30 70
C 70 20 50
D 40 50 110
E 90 10 50
F 80 40 60
G 70 30 120
Q.4. Six task must go through 3 machines A,B,C in the order ABC process time in days are given in the
following table:
Determine the sequence for the five jobs that minimize the elapsed time.
Job J1 J2 J3 J4 J5 J6
Machine A 8 3 7 2 5 1
Machine B 3 4 5 2 1 6
Machine C 8 7 6 9 10 9
Activity 1-2 1-6 2-3 2-4 3-5 4-5 6-7 5-8 7-8
Time 8 4 14 7 13 8 10 5 20
A 1-2 7 12 13
B 1-3 7 10 12
C 2-5 8 13 15
D 3-5 10 12 22
E 5-6 10 14 18
A - 2
B A 3
C B 4
D - 5
E D 2
F C,E 5
4. Determined critical path for the following project. Find EFT,LFT and FLOAT TIME
Job Time
1-2 2
1-3 5
2-4 4
3-4 3
3-5 5
4-6 6
5-7 2
6-7 4
5. Time estimates and predecessors of each activity in a project are given below
⮚ Draw a CPM network diagram
Activity A B C D E F G H
Time 2 4 8 3 2 3 4 8
6. Construct the project network and find optimal project duration by crashing activities.
Consider Indirect cost = Rs. 200 per week.
Activity Time (weeks) NormalCost (RS) Crash Time(week) Crash cost (Rs.)
1
step 4 Deeide Chashing Aeffoiy find Crash linait slope
minimum
Gashing linit Sopen
CHkeal Pth (Cikeal Aefoiliy LCost
|-2-5-4 I-2 4-4 =(3) 2 50
9-5 225
5-4
|-4 8-5- 3 200
4-6 7-5-(2)1 125
350
Iterahion Repea all
Stp 1 Draw olagam Airad Criheal Palk
Path Tie Taleen
|-2-5-+
(6) 12
2
5 5 |-3-6 -+ 14
I 4-6-+
I-4-6-+ -4 200
4-6 125
3SO
2
Tterabion 3
Arnd cp
Step 1 Drao Nelawok Fathhe laln
2-2-54 CP
|-3-5-+
5
l3- 6-7 14
6
1-4-6- I6 cP
CP
5-4
-4-6 + |4 3 200
4-6
350
I teration 4
3
stp 2 Find Total ost of Pojet oith t6 days.
lost
10tal Cost = FewiousTotal Cost + Diret ost - Ihdiret
025 + (50+ 20D)+ 200
= l0,
l00 R.