75kw Bom Train A - A1, A2 Train-B b1, b2 - Revb1
75kw Bom Train A - A1, A2 Train-B b1, b2 - Revb1
75kw Bom Train A - A1, A2 Train-B b1, b2 - Revb1
INDEX SHEET
SHEET NO. TITLE A1 B1
1 COVER SHEET 13-Mar-23 21-Mar-23
2 INDEX SHEET 13-Mar-23 21-Mar-23
3 REVISION RECORD 13-Mar-23 21-Mar-23
4 VFD DATA SHEET 13-Mar-23 21-Mar-23
TITLE DOCUMENT NO
KEAS -BOM -75kW MOTOR - PUMP A1/A2 TRAIN A, PUMP B1/B2 TRAI 0
PROJECT DESCRIPTION PURCHASE ORDER NUMBER SHEET REV
LS25-1 GAS FIELD DEVELOPMENT PROJECT
MEG REGENERATION AND RECLAMATION PACKAGE - 3 OF 9 B1
LS25-1气田开发项目MEG 再生和回收包
COMPANY REQUISITION No. SPECIFICATION No.
CNOOC CHINA LTD. _HAINAN - -
CONTRACTOR REV No. BY DATE CKD DATE APP. DATE DESCRIPTION
VME PROCESS ASIA PACIFIC PTE LTD A1 AM 13-Mar-23 VI 13-Mar-23 EAE 13-Mar-23 ISSUED FOR APPROVAL
CONTRACTOR B1 AM 21-Mar-23 VI 21-Mar-23 EAE 21-Mar-23 ISSUED FOR APPROVAL
KEAS CONTROL SYSTEM INDIA PVT,LTD.
ORIGINATOR ORIG. DATE
KEAS 13-Mar-23