DAILY ACTIVITY PT.

EDBERS NUSANTARA
SERVICE, RECONDISI POPPET VALVE & CONTROL VALVE BOILER, COGEN
Hari /Tanggal : Senin, 25 Februari 2024
Jam : 08.00 - 17.00 WIB

PO No : MJK 43159884 - Service, Recondisi Poppet Valve & Control Valve Boiler, Cogen

NO Description Tag No. Location Size Brand Pressure Type Activity Persentase Next Activity Remarks

1 Poppet Valve, S1, DN 50, 18 BarG S1 TK.1 DN 50 - 18 BarG Poppet Vlv Demobilisasi Ke PT. Tjiwikimia Tbk 95% Instal To Line In Progres

2 Poppet Valve, S3, DN 50, 18 BarG S3 TK.1 DN 50 - 18 BarG Poppet Vlv Machining Back Seat, Machining Seat 50% Lapping Seat In Progres

3 Poppet Valve, S14, DN 50, 18 BarG S14 TK.1 DN 50 - 18 BarG Poppet Vlv Machining Seat 40% Continue Machining Seat In Progres

4 Poppet Valve, Spare, DN 50, 18 BarG S13 TK.1 DN 50 - 18 BarG Poppet Vlv N/A 70% Reassembly Valve In Progres

5 Poppet Valve, R26, DN 50, 18 BarG R26 TK.3 DN 50 - 18 BarG Poppet Vlv Dismatnle From Line, Mobilisasi Ke Workshop
PT. Edbers Nusantara 20% Overhaul Valve In Progres

6 Poppet Valve, R27, DN 50, 18 BarG R27 TK.3 DN 50 - 18 BarG Poppet Vlv N/A 0% Dismatnle From Line Menunggu Instruksi Dari User

Dismatnle From Line, Mobilisasi Ke Workshop


7 Poppet Valve, R31, DN 50, 18 BarG R31 TK.3 DN 50 - 18 BarG Poppet Vlv PT. Edbers Nusantara 20% Overhaul Valve In Progres

8 Poppet Valve, W15, DN 50, 18 BarG W15 TK.3 DN 50 - 18 BarG Poppet Vlv N/A 0% Dismatnle From Line Menunggu Instruksi Dari User

9 Poppet Valve, L1, DN 50, 18 BarG L1 TK.4 DN 50 - 18 BarG Poppet Vlv Mobilisasi Ke Workshop PT. Edbers Nusantara 10% Overhaul Valve In Progres

10 Poppet Valve, Spare, DN 50, 18 BarG - TK.4 DN 50 - 18 BarG Poppet Vlv Mobilisasi Ke Workshop PT. Edbers Nusantara 10% Overhaul Valve In Progres

CV-Desuperheater Demobilisasi Ke PT. Tjiwikimia Tbk, Welding Join To


11 Control Valve Desuperheater TK 2
1A TK.2 DN 20 CCI 120 BarG Control Vlv Line, Instal Actuator 90% Kalibrasi Control Valve In Progres

CV-Desuperheater Demobilisasi Ke PT. Tjiwikimia Tbk, Welding Join To


12 Control Valve Desuperheater TK 2
2A TK.2 DN 20 CCI 120 BarG Control Vlv Line, Instal Actuator 90% Kalibrasi Control Valve In Progres

Total Progres 42,08%

N/A : No Activity Contractor Representative Sign :

S/C : Subject Close Hardiman Sihombing


DAILY ACTIVITY PT. EDBERS NUSANTARA
SERVICE, RECONDISI POPPET VALVE & CONTROL VALVE BOILER, COGEN
Hari /Tanggal : Minggu, 24 Februari 2024
Jam : 08.00 - 23.00 WIB

PR. 7100481789 - Service, Recondisi Poppet Valve & Control Valve Boiler, Cogen

NO Description Tag No. Location Size Brand Pressure Type Activity Persentase Next Activity Remarks
Continue Lapping Seat, Colour Test,
1 Poppet Valve, S1, DN 50, 18 BarG S1 TK.1 DN 50 - 18 BarG Poppet Vlv Reassembly Valve, Internal Pressure Test 90% Demobilisasi Ke PT. Tjiwikimia Tbk In Progres

2 Poppet Valve, S3, DN 50, 18 BarG S3 TK.1 DN 50 - 18 BarG Poppet Vlv Welding Back Seat 50% Machining Back Seat In Progres

3 Poppet Valve, S14, DN 50, 18 BarG S14 TK.1 DN 50 - 18 BarG Poppet Vlv N/A 30% Machining Seat In Progres

4 Poppet Valve, Spare, DN 50, 18 BarG S13 TK.1 DN 50 - 18 BarG Poppet Vlv Machining Seat, Lapping Seat, Colour Test 70% Reassembly Valve In Progres

5 Poppet Valve, Spare, DN 50, 18 BarG - TK.3 DN 50 - 18 BarG Poppet Vlv N/A 0% Dismatnle From Line Menunggu Instruksi Dari User

6 Poppet Valve, R26, DN 50, 18 BarG R26 TK.3 DN 50 - 18 BarG Poppet Vlv N/A 0% Dismatnle From Line Menunggu Instruksi Dari User

7 Poppet Valve, R31, DN 50, 18 BarG R27 TK.3 DN 50 - 18 BarG Poppet Vlv N/A 0% Dismatnle From Line Menunggu Instruksi Dari User

8 Poppet Valve, W15, DN 50, 18 BarG W15 TK.3 DN 50 - 18 BarG Poppet Vlv N/A 0% Dismatnle From Line Menunggu Instruksi Dari User

Mobilisasi Ke Workshop PT. Edbers Menunggu Instruksi Dari User


9 Poppet Valve, L1, DN 50, 18 BarG L1 TK.4 DN 50 - 18 BarG Poppet Vlv N/A 0% Nusantara
Mobilisasi Ke Workshop PT. Edbers Menunggu Instruksi Dari User
10 Poppet Valve, Spare, DN 50, 18 BarG - TK.4 DN 50 - 18 BarG Poppet Vlv N/A 0% Nusantara
CV-Desuperheater Machining Back Seat Body, Fabrikasi Packing PTFE, Reassembly Valve, Demobilisasi Ke PT. Tjiwikimia Tbk,
11 Control Valve Desuperheater TK 2
1A TK.2 DN 20 CCI 120 BarG Control Vlv Low Pressure Test (7 BarG) 80% Instal To Line In Progres

CV-Desuperheater Machining Back Seat Body, Fabrikasi Packing PTFE, Reassembly Valve, Demobilisasi Ke PT. Tjiwikimia Tbk,
12 Control Valve Desuperheater TK 2
2A TK.2 DN 20 CCI 120 BarG Control Vlv Low Pressure Test (7 BarG) 80% Instal To Line
In Progres

Total Progres 33,33%

N/A : No Activity Contractor Representative Sign :

S/C : Subject Close Hardiman Sihombing


DAILY ACTIVITY PT. EDBERS NUSANTARA
SERVICE, RECONDISI POPPET VALVE & CONTROL VALVE BOILER, COGEN
Hari /Tanggal : Sabtu, 24 Februari 2024
Jam : 08.00 - 21.00 WIB

PR. 7100481789 - Service, Recondisi Poppet Valve & Control Valve Boiler, Cogen

NO Description Tag No. Location Size Brand Pressure Type Activity Persentase Next Activity Remarks
Overhaul Valve, Cleaning Part Valve,
1 Poppet Valve, S1, DN 50, 18 BarG S1 TK.1 DN 50 - 18 BarG Poppet Vlv Machining Seat, Lapping Plug, Lapping Seat 55% Continue Lapping Seat In Progres

Overhaul Valve, Cleaning Part Valve,


2 Poppet Valve, S3, DN 50, 18 BarG S3 TK.1 DN 50 - 18 BarG Poppet Vlv Machining Seat 40% Welding Back Seat In Progres

Overhaul Valve, Cleaning Part Valve, Lapping


3 Poppet Valve, S14, DN 50, 18 BarG S14 TK.1 DN 50 - 18 BarG Poppet Vlv Plug 30% Machining Seat In Progres

Overhaul Valve, Cleaning Part Valve, Lapping


4 Poppet Valve, Spare, DN 50, 18 BarG S13 TK.1 DN 50 - 18 BarG Poppet Vlv Plug 30% Machining Seat In Progres

5 Poppet Valve, Spare, DN 50, 18 BarG - TK.3 DN 50 - 18 BarG Poppet Vlv N/A 0% Dismatnle From Line Menunggu Instruksi Dari User

6 Poppet Valve, R26, DN 50, 18 BarG R26 TK.3 DN 50 - 18 BarG Poppet Vlv N/A 0% Dismatnle From Line Menunggu Instruksi Dari User

7 Poppet Valve, R31, DN 50, 18 BarG R27 TK.3 DN 50 - 18 BarG Poppet Vlv N/A 0% Dismatnle From Line Menunggu Instruksi Dari User

8 Poppet Valve, W15, DN 50, 18 BarG W15 TK.3 DN 50 - 18 BarG Poppet Vlv N/A 0% Dismatnle From Line Menunggu Instruksi Dari User

Mobilisasi Ke Workshop PT. Edbers Menunggu Instruksi Dari User


9 Poppet Valve, L1, DN 50, 18 BarG L1 TK.4 DN 50 - 18 BarG Poppet Vlv N/A 0% Nusantara
Mobilisasi Ke Workshop PT. Edbers Menunggu Instruksi Dari User
10 Poppet Valve, Spare, DN 50, 18 BarG - TK.4 DN 50 - 18 BarG Poppet Vlv N/A 0% Nusantara
CV-Desuperheater Cleaning Part Valve, Polish Cage, Lapping Plug, Lapping Seat, Colour
11 Control Valve Desuperheater TK 2
1A TK.2 DN 20 CCI 120 BarG Control Vlv Test 40% Machining Back Seat Body In Progres

CV-Desuperheater Cleaning Part Valve, Polish Cage, Lapping Plug, Lapping Seat, Colour
12 Control Valve Desuperheater TK 2
2A TK.2 DN 20 CCI 120 BarG Control Vlv Test, Machining Back Seat Body 50% Continue Machining Back Seat Body In Progres

Total Progres 20,41%

N/A : No Activity Contractor Representative Sign :

S/C : Subject Close Hardiman Sihombing


DAILY ACTIVITY PT. EDBERS NUSANTARA
SERVICE, RECONDISI POPPET VALVE & CONTROL VALVE BOILER, COGEN
Hari /Tanggal : Jumat, 23 Februari 2024
Jam : 08.00 - 17.00 WIB

PR. 7100481789 - Service, Recondisi Poppet Valve & Control Valve Boiler, Cogen

NO Description Tag No. Location Size Brand Pressure Type Activity Persentase Next Activity Remarks

1 Poppet Valve, S1, DN 50, 18 BarG S1 TK.1 DN 50 - 18 BarG Poppet Vlv Mobilisasi Ke Workshop PT. Edbers Nusantara 10% Overhaul Valve In Progres

2 Poppet Valve, S3, DN 50, 18 BarG S3 TK.1 DN 50 - 18 BarG Poppet Vlv Mobilisasi Ke Workshop PT. Edbers Nusantara 10% Overhaul Valve In Progres

3 Poppet Valve, S14, DN 50, 18 BarG S14 TK.1 DN 50 - 18 BarG Poppet Vlv Mobilisasi Ke Workshop PT. Edbers Nusantara 10% Overhaul Valve In Progres

4 Poppet Valve, Spare, DN 50, 18 BarG S13 TK.1 DN 50 - 18 BarG Poppet Vlv Mobilisasi Ke Workshop PT. Edbers Nusantara 10% Overhaul Valve In Progres

5 Poppet Valve, Spare, DN 50, 18 BarG - TK.3 DN 50 - 18 BarG Poppet Vlv N/A 0% Dismatnle From Line Menunggu Instruksi Dari User

6 Poppet Valve, R26, DN 50, 18 BarG R26 TK.3 DN 50 - 18 BarG Poppet Vlv N/A 0% Dismatnle From Line Menunggu Instruksi Dari User

7 Poppet Valve, R31, DN 50, 18 BarG R27 TK.3 DN 50 - 18 BarG Poppet Vlv N/A 0% Dismatnle From Line Menunggu Instruksi Dari User

8 Poppet Valve, W15, DN 50, 18 BarG W15 TK.3 DN 50 - 18 BarG Poppet Vlv N/A 0% Dismatnle From Line Menunggu Instruksi Dari User

Mobilisasi Ke Workshop PT. Edbers Menunggu Instruksi Dari User


9 Poppet Valve, L1, DN 50, 18 BarG L1 TK.4 DN 50 - 18 BarG Poppet Vlv N/A 0%
Nusantara
Mobilisasi Ke Workshop PT. Edbers Menunggu Instruksi Dari User
10 Poppet Valve, Spare, DN 50, 18 BarG - TK.4 DN 50 - 18 BarG Poppet Vlv N/A 0%
Nusantara
CV-Desuperheater Overhaul Valve, Pemotongan Valve dari Line,
11 Control Valve Desuperheater TK 2
1A TK.2 DN 20 - 120 BarG Control Vlv
Mobilisasi Ke Workshop PT. Edbers Nusantara
20% Cleaning Part Valve In Progres

CV-Desuperheater Overhaul Valve, Pemotongan Valve dari Line,


12 Control Valve Desuperheater TK 2
2A TK.2 DN 20 - 120 BarG Control Vlv
Mobilisasi Ke Workshop PT. Edbers Nusantara
20% Cleaning Part Valve In Progres

Total Progres 6,66%

N/A : No Activity Contractor Representative Sign :

S/C : Subject Close Hardiman Sihombing