Shop DWG Checklist
Shop DWG Checklist
Shop DWG Checklist
1. Exact location of all devices should be coordinated with ID, and the dimension should
be taken from walls or columns.
2. Contractor should provide typical installation details in separate plans indicating all
installation, connection and wiring as per the manufacturer recommendations.
3. Each fire fighter telephone should have its own control module.
4. Contractor to submit voltage drop calculation for DC lines.
5. End of line devices should be installed as directed by the manufacturer to electrically
supervise all wiring (DC/Audio lines and telephone lines)
6. Contractor to ensure that all monitor and control modules needed for HVAC and fire
fighting system and any other interfaces are provided and its location is coordinated
with electrical / mechanical drawings.
7. Fault isolator modules shall be installed every 15 devices maximum
8. Contractor to provide earthing conductor for all trunking.
9. Contractor to guarantee enough separation from other service trades for proper
installation and to interferences.
10. Contractor to submit detailed riser diagram showing all system component and the
interface with all other trades.
11. All material used should be according to last approved submittal.
- Exact location of all devices should be coordinated with ID, and the dimension should
be taken from walls or columns.
- Provide earthing conductor for all trunking
- All splitters, tap off, multi-switches to be installed in perforated metal boxes.
- RF and IF TV signal level at each outlets to be indicated.
- Connection to the dish farms to be indicated.
- Location of TV outlets to be coordinated with the advertising outlets.
- Contractor to provide filling ration calculation for the trunk / conduit used.
- Pull boxes should be provided each 15 metres and each two bends and junction
boxes to be used where ever needed.
- Contractor to submit detailed riser diagram.
- Contractor should provide typical installation details for all devices.
- All material used should be according to last approved submittal, and part number of
cable and equipment to be indicated.