GP 32-45
GP 32-45
GP 32-45
GP 32-45
Applicability Group
Date 26 December 2005
GP 32-45
Foreword
This is the first issue of Engineering Technical Practice (ETP) BP GP 32-45. This Guidance on
Practice (GP) is based on parts of heritage documents from the merged BP companies as follows:
British Petroleum
RP 32-4 Inspection & Testing of In-Service Civil and Mechanical Plant -
Technical Guidance – Section B2 - Steam Boilers and Section B8 - Fired
Heaters.
BPOUS RPs
RP 20-4-5 In-Plant Inspection of Existing Boilers.
RP 20-4-6 In-Plant Inspection of Existing Fired Heaters.
RP 20-4-7 In-Plant Inspection of Refractories.
DO NOT COPY
Copyright © 2005, BP Group. All rights reserved. The information contained in this
document is subject to the terms and conditions of the agreement or contract under which
the document was supplied to the recipient’s organisation. None of the information
contained in this document shall be disclosed outside the recipient’s own organisation
without the prior written permission of Director of Engineering, BP Group, unless the
terms of such agreement or contract expressly allow.
Page 2 of 13
26 December 2005 GP 32-45
Guidance on Practice for In Service Inspection and Testing of Fired Boilers and Heaters
Table of Contents
Page
1. Scope........................................................................................................................................4
2. Normative references ...............................................................................................................4
3. Symbols and abbreviations.......................................................................................................5
4. Terms and definitions ...............................................................................................................5
5. Site Technical Practices, inspection plans and procedures......................................................5
5.1. General..........................................................................................................................5
5.2. Site Technical Practices ................................................................................................5
5.3. Inspection plans and procedures...................................................................................5
5.4. External inspection ........................................................................................................6
5.5. Internal inspection .........................................................................................................8
5.6. Refractory ....................................................................................................................11
5.7. Final inspection............................................................................................................13
6. Inspection frequency...............................................................................................................14
7. Operational surveillance .........................................................................................................15
8. Safety devices ........................................................................................................................16
9. Pressure testing......................................................................................................................16
10. Repairs and alterations...........................................................................................................17
11. Records and documentation...................................................................................................17
11.1. General........................................................................................................................17
11.2. Construction and design information ...........................................................................17
11.3. Inspection history.........................................................................................................17
11.4. Repairs and modifications ...........................................................................................17
Bibliography .....................................................................................................................................18
DO NOT COPY
Page 3 of 13
26 December 2005 GP 32-45
Guidance on Practice for In Service Inspection and Testing of Fired Boilers and Heaters
1. Scope
a. This GP provides specific guidance for in service inspection and testing of direct fired
steam boilers and process heaters.
b. This GP applies to:
1. Direct fired steam boilers and process heaters, including essential ancillary
equipment, such as damper servo mechanisms, flue gas uptakes, and ducting up to
and including stack or isolating spade.
2. Waste heat boilers or generators using heat of flue gases.
3. Direct fired incinerators.
c. Outside scope of this GP are:
1. Waste heat boilers designed to pressure vessel and heat exchanger codes and using
heat of process fluids (refer to GP 32-41 and GP 32-48).
2. Non integral chimney stacks (refer to GP 32-46).
3. Deaerators and blowdown vessels (refer to GP 32-41).
4. Mechanical protective devices (refer to GP 32-47).
5. Flare tips and appurtenances (refer to GP 32-49).
6. Selective catalytic reduction equipment.
2. Normative references
The following normative documents contain requirements that, through reference in this text,
constitute requirements of this technical practice. For dated references, subsequent amendments to, or
revisions of, any of these publications do not apply. However, parties to agreements based on this
technical practice are encouraged to investigate the possibility of applying the most recent editions of
the normative documents indicated below. For undated references, the latest edition of the normative
document referred to applies.
BP
GP 32-30 Guidance on Practice for In Service Inspection and Testing of
Equipment - Management Principles.
GP 32-40 Guidance on Practice for In Service Inspection and Testing of
Equipment - Common Requirements.
GP 32-41 Guidance on Practice for In Service Inspection of Unfired Pressure
DO NOT COPY
Vessels.
GP 32-46 Guidance on Practice for In Service Inspection and Testing of
Equipment - Onshore Civils and Structures.
GP 32-47 Guidance on Practice for In Service Inspection and Testing of
Equipment - Mechanical Protective Devices.
GP 32-48 Guidance on Practice for In Service Inspection and Testing of Heat
Exchangers.
GP 32-49 Guidance on Practice for In Service Inspection and Testing of Special and
Other Equipment.
Page 4 of 13
26 December 2005 GP 32-45
Guidance on Practice for In Service Inspection and Testing of Fired Boilers and Heaters
For the purpose of this GP, the following symbols and abbreviations apply:
For the purposes of this GP, the following terms and definitions apply:
External Inspection
Visual inspection of external parts of equipment while in or out of service.
Internal Inspection
Combination of visual, non destructive examination (NDE), and testing of internal parts of equipment
while out of service and entry to fire box, convection section, breaching, and stack are possible.
Final Inspection
Inspection of work to ensure completeness and adequacy of repair and to verify equipment cleanliness
prior to closing.
5.1. General
This GP shall be read in conjunction with GP 32-30 and GP 32-40.
DO NOT COPY
5.3.
b. The STP shall be approved by the Site Engineering Authority and form the basis for the
development of equipment specific inspection plans and procedures.
Page 5 of 13
26 December 2005 GP 32-45
Guidance on Practice for In Service Inspection and Testing of Fired Boilers and Heaters
DO NOT COPY 7.
g)
h)
i)
Flame impingement.
Tube supports for sagging, breaking, or bending.
Tube counterweight systems for deterioration.
Burners for proper operation and flame impingement onto internal parts.
8. Soot blowers for packing leaks and warping.
9. Breaching, ducts, and internally lined steel stacks for leaks, oxidation, buckling, and
cracked weld seams.
10. Externally insulated and fireproofed stacks for CUI or CUF.
11. Air preheaters for evidence of fouling or dewpoint corrosion.
Page 6 of 13
26 December 2005 GP 32-45
Guidance on Practice for In Service Inspection and Testing of Fired Boilers and Heaters
12. Forced and induced draft fans for evidence of excessive vibration or noise.
13. Stack or flue gas dampers for correct operation as viewed externally.
14. Compatible local and control room steam drum pressure and level indication for
boilers only.
15. Stack anchor bolts for corrosion or looseness.
16. Elevated flanged joints for corrosion due to escaping flue gases.
DO NOT COPY
or failure.
e. Supports and support connections shall be examined for cracking, oxidation, corrosion,
distortion, and bowing.
f. Refractory and insulation shall be examined for spalling, cracking, or other deterioration.
Refer to 5.6.1.
g. Breaching, duct, and stack linings shall be examined for deterioration.
h. Stack dampers shall be examined for deterioration from corrosion, wear, and excessive
heat.
i. Damper operation shall be checked to ensure free movement throughout full range.
Page 7 of 13
26 December 2005 GP 32-45
Guidance on Practice for In Service Inspection and Testing of Fired Boilers and Heaters
j. Air register dampers shall be checked internally for damage and to ensure correct
operation.
k. Stack integrity
1. Thickness survey of steel stacks shall be performed to determine structural integrity.
2. Minimum allowable thickness at which repairs will be made shall be established.
3. Areas of missing refractory, identified by either thermography or internal inspection,
shall be inspected for corrosion.
4. Concrete stacks shall be inspected in accordance with GP 32-46.
5.5.2. Boilers
Site specific inspection procedures for boilers shall address known areas of vulnerability.
Typical inspection procedures for direct fired utility boiler shall include the following as
appropriate:
a. Forced draft fan structural inspection, air ducting, burner box and air preheater integrity,
and functional examination.
b. Flue gas ducting and induced draft fan structural inspection.
c. External pressure parts, headers, and downcomers.
d. Soot blowers.
e. Steam drum and internals.
f. Water drum.
g. Furnace tubes, including pre clean inspection to define level of cleaning required to ensure
damage mechanisms are exposed. Refer to 5.5.1 for inspection requirements.
h. Superheater tubes and headers. Refer to 5.5.1 for inspection requirements.
i. Convection and economiser tubes. Refer to 5.5.1 for inspection requirements. Water side
scaling caused by salts shall also be checked.
j. Refractory. Refer to 5.6.1 for inspection requirements.
k. Burners and burner tiles.
l. Manholes and peepholes.
m. Safety valve overhaul (refer to GP 32-47).
n. Bellows and expansion joints.
o. Gauge glass connections.
p. Dampers and controls.
DO NOT COPY
q.
r.
s.
t.
Pressure test (refer to 9).
Safety valve float.
Isolation valves.
Blowdowns and associated equipment.
u. Protective instrumentation.
Page 8 of 13
26 December 2005 GP 32-45
Guidance on Practice for In Service Inspection and Testing of Fired Boilers and Heaters
5.6. Refractory
5.6.1. Inspection
a. Visual examination of refractory shall be performed to confirm suitability for continued
service.
b. Refractory lined equipment shall be inspected for:
1. Excessive cracking.
2. Cast refractory and anchor erosion.
3. Blanket type refractory anchoring failure.
4. Excessive fluxing (melting).
5. Bulging.
6. Spalling.
7. Fallout.
8. Voids.
c. If erosion, spalling, or fallout has occurred, measurement shall be made of depth or
thickness of remaining refractory.
d. Hammer test may be performed by striking lining with a non metallic mallet at 300 mm
(1 ft) intervals.
5.6.2. Repairs
a. Refractory areas requiring repair shall be field marked using contrasting colour spray paint.
Boundaries of repair area shall be accurately defined and painted.
b. Unless specified otherwise by Inspection Authority, refractory linings shall be repaired or
replaced under the following circumstances:
1. Steerhorn or Vee anchors are exposed to hot face.
2. For erosion resistant linings, areas of hexmesh have pulled away from wall.
3. For erosion resistant linings, hexmesh and refractory cupping exceeds:
a) 6 mm (1/4 in) depth for 19 mm (3/4 in) hexmesh.
b) 9,5 mm (3/8 in) for 25 mm (1 in) hexmesh.
4. Bulging or fallout has occurred towards bottom of lining, leaving upper lining
unsupported.
5. Erosion, fallout, or spalling has occurred near pressure parts or structural support
DO NOT COPY
members.
6. Cracking is judged severe and/or is accompanied by fallout. Hairline cracking up to
4 mm (5/32 in) in width is generally acceptable.
7. Cracking has occurred at locations that permit extensive air leakage.
8. Shell or casing hot spots have developed.
9. Hammer testing reveals void or reveals that refractory has separated from metal shell.
c. Refractory repair shall strictly comply with applicable refractory specification and repair
procedures.
d. Inspection of repair shall include:
1. Verification of complete removal of defective refractory.
Page 9 of 13
26 December 2005 GP 32-45
Guidance on Practice for In Service Inspection and Testing of Fired Boilers and Heaters
6. Inspection frequency
DO NOT COPY 2.
3.
4.
5.
Feedstock and feedwater quality control.
Flow control through heater coils.
Firing controls (i.e., avoidance of flame impingement and local overheating).
Fuel quality, particularly sulphur and metals content that can lead to hot corrosion of
uncooled furnace parts, and acid dewpoint corrosion and fouling in heat recovery or
air preheater or economiser sections and in refractory lined ducting and stacks.
6. Process and firebox temperature measurement and control.
7. Steam temperature and drum water level control systems performance.
8. Remaining life of tubes based on measured corrosion rates, age of tubes, and
condition of tube supports.
Page 10 of 13
26 December 2005 GP 32-45
Guidance on Practice for In Service Inspection and Testing of Fired Boilers and Heaters
9. Age of parts operating in creep range and need to perform remaining life assessments.
10. Fatigue assessment based on number of shutdowns or startups compared with Vendor
design specification.
11. Peaking/ crack detection on shell seam welds as described in 5.5.2.e.
12. Specific inspection and maintenance history of equipment.
13. History of temperature, pressure, or other excursions.
d. Guidelines for establishing interval and extent of inspection are in GP 32-30.
7. Operational surveillance
a. During fired heater and boiler operations, the following monitoring shall be performed, as
applicable and the data shall be made available to the Inspection Authority or delegate:
1. Thermocouple readings shall be monitored to assess coking in coil, firing conditions,
and requirements for decoking.
2. Routine operator rounds shall include visual examination of fireboxes to ensure
flames do not impinge upon tubes.
3. Operating boundaries shall be defined for key process variables that affect damage
mechanisms. Associated monitoring requirements shall be established, including:
a) How and if key process variables are to be monitored.
b) When key process variables are to be monitored.
c) Who will monitor key process variables.
d) What action should be taken on excursions of boundaries (e.g., reporting and
evaluation).
b. Operating conditions can change rapidly. Inspection Authority shall be informed of any
changes that could affect safe life predictions.
8. Safety devices
a. If isolation (diverter) valves are fitted upstream of relief valves on boilers, management
practice to ensure that relief valves are protecting equipment from overpressure shall be
audited as part of boiler inspection.
b. Hot float testing of boiler relief valves to check hot setting pressure and blowdown settings
shall be performed after boiler has reached steady operation.
DO NOT COPY
9. Pressure testing
a. If no repairs or renewals are performed and inspections have confirmed integrity, pressure
testing shall be for sole purpose of confirming leak tightness of tubes and joints.
b. If tubing repairs or renewals are made or if mechanical integrity of tubes or pressure
envelope is in doubt, a pressure strength test shall be performed.
c. Pressure testing shall take place above minimum temperature specified by boiler design
code.
d. Pressure tests shall be witnessed and recorded by inspector.
Page 11 of 13
26 December 2005 GP 32-45
Guidance on Practice for In Service Inspection and Testing of Fired Boilers and Heaters
a. Equipment repairs and alterations shall comply with normative references in this GP and
applicable industry codes and standards.
b. Alterations or modifications shall comply with site management of change (MOC)
procedure.
11.1. General
Equipment files shall include information described in 11.2 through 11.4.
DO NOT COPY
Page 12 of 13
26 December 2005 GP 32-45
Guidance on Practice for In Service Inspection and Testing of Fired Boilers and Heaters
Bibliography
BP
[1] GIS 72-002, Guidance on Industry Standard for Refractory Installation.
[3] GN 32-004, Corrosion Under Insulation and Fireproofing (CUI and CUF).
[8] API RP 936, Refractory Installation Quality Control Guidelines - Inspection and Testing Monolithic
Refractory Linings and Materials.
[10] ASME, Boiler and Pressure Vessel Code, Section VI, Recommended Rules for the Care and
Operation of Heating Boilers.
[12] BS 2486, Recommendations for treatment of water for steam boilers and water heaters.
[15] SAFED, Guidelines for the Examination of Boiler Shell-to-Endplate and Furnace-to-Endplate Welded
Joints.
DO NOT COPY
Page 13 of 13