Brace Cut
Brace Cut
Brace Cut
Introduction
• Deep excavations with vertical sides require
lateral supports to prevent cave in of the
earth and to protect the adjacent areas
against ground subsidence and lateral
movement of the subsoil.
• When excavations are shallow and ample
space is available, the sides of the excavation
can be sloped at a safe angle to ensure
stability.
• However, in deep excavation, especially in
built up areas there may not be adequate
space for providing safe slopes.
• Moreover it becomes uneconomical to
provide safe slope because of large
quantities of earth involved.
1
27/12/2020
Introduction
• Excavations which are laterally supported are
Braced.
• The vertical sides of the excavations are
supported by a sheeting and bracing system.
• It consists of relatively flexible sheeting placed
against excavations walls. The lateral thrust on
the sheeting is resisted by the horizontal
members in compression (struts).
• Bracing is provided as the excavation proceeds
and the face of the sheeting becomes exposed.
So, various types of the Bracing systems is
adopted to make the excavation stable.
• Sheet piling is used primarily as a bulkhead to
hold or restrict the lateral movement behind it.
Introduction
• A Gravity Retaining wall is a Permanent Structure, used, when an
excavation is permanent.
• But when excavation is temporary i.e. excavation for buildings or
subway, the excavation is filled with a structure which then permanently
retain surrounding soil/earth. If the temporary excavation is made in
sand, the walls of the excavation must be supported during construction
of the building by a system of bracing.
• Example of constructions - Laying underground pipeline, construction of
bridge abutment, construction of basement, metro railway construction,
construction of subway tunnel.
2
27/12/2020
Introduction
• Types of braced cut systems:
• Vertical Timber Sheeting
• Steel Sheet Piles
• Soldier Beams
• Tie Backs
3
27/12/2020
4
27/12/2020
10
5
27/12/2020
11
Soldier Beams
• Soldier beams are H-piles which are driven at suitable spacing of 1.5 to
2.5 m. around the boundary of the proposed excavation.
• As the excavation proceeds, horizontal timber planks called lagging are
placed between the soldier beams.
• When the excavation advances to the suitable depth, Wales and the
struts are inserted. The lagging is properly wedged between piles
flanges or behind thee back flange.
12
6
27/12/2020
13
Tie Backs
• In this method, no bracing in the form of struts or inclined rakes is
provided. Therefore, there is no hindrance to the construction activity to
be carried out inside the excavated area. The tie back is a rod or a cable
connected to the sheeting or lagging on one side and anchored into the
soil or rock out side of the excavation area. Inclined holes are drilled in
to the soil Or Rock, and the tensile reinforcement (tendon) is then
inserted and the hole is concreted.
• An enlargement or bell is usually formed at the end of the hole. Each tie
back is generally prestressed before the depth of excavation is increased
further to cope with the increased tension.
14
7
27/12/2020
15
16
8
27/12/2020
17
18
9
27/12/2020
Example
19
Example
20
10
27/12/2020
Example
21
Example
22
11
27/12/2020
Example
23
12