Integrated Approach To Water/ Wastewater Treatment at Zero Liquid Discharge, Combined Cycle Power Plants
Integrated Approach To Water/ Wastewater Treatment at Zero Liquid Discharge, Combined Cycle Power Plants
Integrated Approach To Water/ Wastewater Treatment at Zero Liquid Discharge, Combined Cycle Power Plants
Paper
Find a contact near you by visiting www.ge.com/water and clicking on “Contact Us”.
* Trademark of General Electric Company; may be registered in one or more countries.
©2011, General Electric Company. All rights reserved.
TP1043EN.doc Feb-11
Case One: tion after a preliminary evaluation. EPC and plant
Southwest Power Plant representatives visited operating ZLD plants to
assess the overall reliability and operating histories,
The Texas Independent Energy (TIE) Guadalupe then selected a system which included a raw
Power Plant in Marion, Texas is a 1000 MW com- water softener/clarifier unit (SCU), brine concentra-
bined-cycle plant with two power blocks (2 x 1 con- tor (BC), calandria crystallizer, and an electrodeioni-
figuration, 500 MW each) using General Electric 7F zation (EDI) unit with a mixed bed ion exchange (MB
gas turbines. The plant was designed with supple- IX) polisher. The overall plant water balance and
mental duct firing during peak power demand peri- treatment subsystems are depicted in Figure 1.
ods. The plant started up in 2000 and went
commercial in 2001.
The nearby Guadalupe River supplies the make-up
water to the plant. The design make-up water
chemistry is given in Table 1. The design range
specified is a function of seasonal variations. A raw
water clarifier was required to accommodate
increased suspended solids (TSS) loads during
the rainy season.
Page 2 TP1043EN
after the contract was awarded. Typically, similar
systems require 18 to 24 months from award to
mechanical completion.
Conclusions
TP1043EN Page 3
Case Two: for the overall plant water balance and selected
Northeast Power Plant subsystems.
The AES Ironwood facility in Lebanon, Pennsylvania This integrated system utilized a more aggressive
is a 700 MW combined cycle plant with a 2 x 1 con- cooling tower chemical program to increase the
figuration using Siemens Westinghouse 501G gas cycles (about 15x at peak design conditions) with
turbines. The plant is primarily designed to operate the blowdown going directly to a BC. The selected
on natural gas, but originally had provisions to cooling tower chemical program required a scale
accommodate oil firing, if required. The plant inhibitor, corrosion inhibitor, dispersant, and bio-
started up in 2001 and went commercial in 2002. cide. This eliminated the need for a lime sof-
tener/clarifier and wastewater RO, thereby
The Ironwood plant has two sources of make-up minimizing the number of unit operations required.
water; secondary treated effluent from the nearby The MVR BC operating at 97% recovery, blows
publicly owned treatment works (POTW) and quarry down to a small steam driven crystallizer (Figure 6).
water from the adjacent quarry. The design The solids produced in the crystallizer are dewa-
make-up feed to the power plant is a 60% quarry - tered in a pressure filter and are sent to a landfill for
40% POTW blend. See Table 2 for compositions. disposal.
Table 2: Make-up Water Composition (mg/l as ion) AES
Ironwood Power Plant
Page 4 TP1043EN
with polyaluminum chloride (PAC) addition was ret-
rofitted to the water treatment plant. The primary
cause of the high SDI was traced back to a sand
filter installed at the POTW that wasn’t performing
as expected. The other main issue discovered dur-
ing start-up was higher than expected total organic
carbon (TOC) in the demineralized water. The com-
bination of treatment additives and high cycles in
the cooling tower produced a build up of volatile
inorganic components, which resulted in a higher
TOC level in the BC distillate, above a level that
could be effectively removed in the EDI. Granular
activated carbon (GAC) canisters were installed on
the BC distillate, which removed enough of the TOC
to meet the plant demineralized water specification
(< 300 ppb).
The distillate is fed to the electrodeionization (EDI) The integrated system installed at the Ironwood
units to produce the required 10 megaohm-cm power plant provided the following benefits:
boiler feedwater. During the normal, gas-fired • Optimized recirculating cooling tower treatment
mode, the distillate flow is sufficient to meet the program.
EDI/demineralizer feedwater demand. The original
• Elimination of the lime softener/clarifier mini-
design allowed for operation in an oil fired mode,
mized addition of bulk chemicals and reduced
during which time the demineralized water
off-site sludge disposal requirements by up
demand for the plant was designed to be nearly ten
to 40%.
times higher due to the NOx reduction
requirements in the combustion turbines. Because • Simplified treatment system with fewer unit
there was not sufficient BC distillate to satisfy the operations, yet flexible enough to accommodate
EDI/demin demand under all conditions, another chemistry variations in the make-up water.
source of EDI feed was required. A two-stage, two- • Shorter contract schedule and more efficient
pass RO unit (Figure 7) was included to supple- supplier management by utilization of a single-
ment the BC distillate. The RO is only required dur- source supplier for the entire plant
ing periods of high demineralized water demand. water/wastewater treatment system.
• Common, integrated control system interface
for all the plant water and wastewater treat-
ment functions allowing for streamlined opera-
tion and fewer operators.
Summary
An integrated approach to water and wastewater
treatment can yield a number of advantages to ZLD
power plants when compared to conventional, seg-
regated methods. The unit operations for the cool-
Figure 7: Reverse Osmosis ing tower, ZLD system, and demineralizer are based
on fundamentally similar principles and combining
During start-up of the plant, it was discovered that the responsibility for the design makes good engi-
the make-up water blend silt-density index (SDI) neering and contracting sense. The performance of
was out-of-spec high. To reduce the SDI to an each operation is often dependent on the other, so
acceptable level, a multi-media filter (MMF) system having one supplier responsible for all the water
TP1043EN Page 5
treatment is the preferred solution to eliminate con-
flicts. When designed properly, the plant benefits
with streamlined processes and simpler, easier-to-
operate treatment systems.
Other recently commissioned power plants such as
La Paloma Generating near Bakersfield, California
and Hays Energy near San Marcos, Texas have used
the same integrated approach. Both installations
included reverse osmosis pre-concentration stages
in the ZLD train to reduce the system’s overall
power consumption.
References
Prato, T., Muller, R., Alvarez, F., “EDI Application:
Evaporator Product Polishing”, Ultrapure Water,
April 2001.
Heimbigner, B., “Integrated Water and Wastewater
treatment including ZLD”, PowerGen Latin America,
August 2002.
Solomon, R., Schooley, K., Griffin, S., “The Advan-
tages of Mixed Salt Crystallizers in ZLD Wastewater
Treatment Systems”, International Water Confer-
ence, October 1998.
Bostjancic, J., Ludlum, R., “Getting to Zero Discharge:
How to Recycle that Last Bit of Really Bad Waste-
water”, International Water Conference,
October 1997.
Page 6 TP1043EN