Nothing Special   »   [go: up one dir, main page]

Reuse Pipeline Modification For Flow Improvement

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 2

SUCCESS STORY

Overview
Effluent Pond is the final point in the Plant
Waste Water System. By term ‘Effluent’, it means
water that is no longer needed or suitable for its most
recent use, but can be returned to the water cycle with
minimal environmental issues. The effluent pond is the
central monitoring basin of the effluent water for final
discharge to reuse for aquaculture or agriculture.
The Reuse Pump is the transport machine
utilized to distribute water for re-use from the Effluent
Pond to its end users, in particular the Boiler Area, FA
Handling System, Coal Shelter Dust Supp. System, Coal
Jetty Dust Supp. System, Ash Runoff Sump, and the
major customer, Aquaculture Ponds. There are two (2) units at
100% capacity each.

The Dilemma
During the first quarter of 2018, Effluent Pond level has
become one of the major areas of concern that the Operations
team has always been monitoring because of its recurrent
critical level status which may pose environmental issues
(overflowing). After a series of tests and monitoring by the
Performance Team on May 2018, it was found out that the
non-operational of the end users other than Aqua pond have restricted
(to about 66 m3/hr) the existing system in discharging the water from effluent pond at a rate the Reuse Pump is originally
designed to deliver (87 m3/hr).

The Solution
Increasing the Reuse Pump flow capacity thru
implementing modifications to the current piping system will
give permanent and long-term solution. After a series of
engineering analysis and consolidation of gathered data by
the Performance Team, a set of potential solutions were
presented on August 2018 and evaluated based on the
resulting improvement in flow and the corresponding
estimated first costs and operational costs. Major comparison
points are shown in the following table and figure.

POWER PLANT PROJECT SITE: Barangay Kamanga, Maasim, Sarangani Province


Telephone No.: (083) 263-1002 / (02) 823-7225 loc. 1901
HEAD OFFICE: 4th Floor Alphaland Southgate Tower 2258 Chino Roces Avenue corner EDSA, Makati City 1232
Telephone Nos.: (02) 823-7225
SUCCESS STORY

It was agreed together with other O&M sections to select


Option 2 as the best option. The Booster Pump is an auxiliary Options Comparison
equipment in the Effluent Water system that can be utilized to 1 2 3A 3B 4
further reduce system resistance whenever higher flow to Aqua pond
is desired – in fact this results to the highest gain of flow with up to 40 373.20
35 m3/hr variance from the current set-up. 35
On December 2018, the capex budget on the pipeline 30 35
modification compatible to option 2 was finally approved. Quotation 25
price is at P1.118M and contractor is Metallic Pisces Engineering 26
20
Works (already contracted some projects with SEC before). 15
103.36 116.00
10 14
12
5 10
Benefits 0
 Significant flow improvement, with fairly low additional power -5
QUICK FACTS
-45.23
requirements. The Booster Pump can be operated anytime to -10 -60.11
further reduce system resistance whenever higher flow to Aqua
Flow Improvement, m3/hr Ave. Daily Energy Variance, kWhr
pond is desired. Improved flow can reach up to 35 m3/hr gain. Plant Sarangani Energy Corporation Unit
 Allows flexibility for the operations team to maximize the 1
quantity of water going into the pond as needed. Operation April 2016
 Induces operational savings to some extent in the long run - Start
payback period is about 5 years w/ annual savings of about Industry Power and Energy Industry
Php200K (combined coal & Diesel fuel converted to monetary
Asset Process Equipment
values).
 Operating Costs variance may reach up to Php2M in 10 years due Application
to savings versus original. Strategy Performance Evaluation
 No need to stop operation during additional line tapping since the Specific Performance Monitoring and Data
source line going to the Booster Pump has an isolation valve. Methods Gathering, Pump Performance
 The problem of critical monitoring of Effluent Pond level and Curves, Friction Loss and Pump
immediate hauling assistance from MTH will be totally Calculations
eliminated.

POWER PLANT PROJECT SITE: Barangay Kamanga, Maasim, Sarangani Province


Telephone No.: (083) 263-1002 / (02) 823-7225 loc. 1901
HEAD OFFICE: 4th Floor Alphaland Southgate Tower 2258 Chino Roces Avenue corner EDSA, Makati City 1232
Telephone Nos.: (02) 823-7225

You might also like