INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE & QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. ACTIVITY CODE PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO
Welding Procedure
1.1 Specifications/Welding Procedure SAIC-W-2075 RH1 RH1
Qualification Record (WPS/WPQR)
Welder & Welding Operator
1.2 SAIC-W-2035 RH1 R1
Certifications (and Issuance of JCC)
Method Statement & WPS for Weld
1.3 SAIC-W-2076 RH1 RH1
Repair
Receiving Inspection and Verification of S. Aramco shall verify and inspect the first batch of
2.1 Welding Consumables-(Properties, Type, SAIC-W-2081 SAIC-W-2081 H1 W2 delivered consumables, then random inspection
approve source, storage, etc.) thereafter.
SAIC-W-2082
Welding Equipment Calibration Random witnessing by S. Aramco at each calibration
2.2 SAIC-W-2082 SATR-W-2009 H1 W2
Verification cycle.
SATR-W-2011
Positive Material Identification of Low SAIC-L-2010 Refer to Note 1 of the General Notes for S.Aramco
2.3 Alloy, Stainless Steel, Nickel & Copper SAIC-L-2010 SATR-L-2012 H1 W2 Inspection responsibility, afterwhich pre-arranged
Based Materials (If Required) SATR-L-2013 witnessing shall be agreed upon.
3.0 INSTALLATION
Welding of Overlays & Clad Materials
3.1 See SATIP No: W-014-01
(If Required)
Page 1 of 4
SAUDI ARAMCO ID/PID - REV 1 - 5/18/05 (Standards Cutoff - August 2004)
SATIP No. APPROVED DATE DISCIPLINE:
SAUDI ARAMCO TYPICAL INSPECTION PLAN
WELDING OF API TANKS SATIP-W-017-01 25-May-05 MECHANICAL
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR
INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE & QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. ACTIVITY CODE PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO
SAIC-W-2088
3.15 Selection of Weld Joints for NDE (Tanks) SAIC-W-2088 H1 R1 S. Aramco reviews on weekly basis.
SATR-W-2007
Page 2 of 4
SAUDI ARAMCO ID/PID - REV 1 - 5/18/05 (Standards Cutoff - August 2004)
SATIP No. APPROVED DATE DISCIPLINE:
SAUDI ARAMCO TYPICAL INSPECTION PLAN
WELDING OF API TANKS SATIP-W-017-01 25-May-05 MECHANICAL
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR
INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE & QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. ACTIVITY CODE PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO
4.0 PRE-COMMISSIONING
Final Welding Inspection & Document Refer to Note 1 of the General Notes for S.Aramco
SATR-W-2008
4.1 Verification (Welding Summary Report/ H1 R1 Inspection responsibility, afterwhich pre-arranged or
(or equiv)
Record & Weld Map) random Review shall be agreed upon.
GENERAL NOTES
The first three incidents of each Inspection or testing activity listed require 100 % participation by Saudi Aramco Site Inspection Personnel. After this period, Saudi Aramco Inspection may adjust the
1 levels of Saudi Aramco participation based upon the Contractor’s performance.
Witness: QA/QC organization shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as scheduled if the QA/QC organization
3 representative is not present.
4 Hold: QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC organization representative in attendance.
Page 3 of 4
SAUDI ARAMCO ID/PID - REV 1 - 5/18/05 (Standards Cutoff - August 2004)
SATIP No. APPROVED DATE DISCIPLINE:
SAUDI ARAMCO TYPICAL INSPECTION PLAN
WELDING OF API TANKS SATIP-W-017-01 25-May-05 MECHANICAL
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR
INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE & QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. ACTIVITY CODE PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO
5 If the Main Contractor delegates the assigned responsibility to the Subcontractor, then the Main Contractor will have the same degree of responsibility as assigned to Saudi Aramco.
LEGEND
W1 100% Witness Inspection/Test H2 Sample Hold Point for QC Inspection or Test RH1 100% Review and Approval of Documents
W2 Sample Witness Inspection/Test R1 100% Review of Documents RH2 Sample Review and Approval of Documents
H1 100% Hold Point for QC Inspection or Test R2 Sample Review of Documents S Surveillance
Page 4 of 4