TIME & ACTION CALENDAR

STYLE ALLOCATION DT TO FTY


ATTN DT CREATED
FROM DT ACCPTD
SEASON CREATED BY UPDATIONS ON
STYLE ACCPTD BY
QTY TODAYS DATE 10-Nov-19
2 DAY PRIOR ALERT 12-Nov-19
5 DAY PRIOR ALERT 15-Nov-19

SAMPLING
ACTIVITIES ACTIVITY PERSON
SPECIFICATION RESP
REQUIRE PLAN +/- ACTUAL OVERSHOOT COMMENTS
PROTO SPEC RECEIPT SIZE MESUREMENTS AS PER MODEL 1-Apr-20 1-Apr-20 0
PROTO PATTERN RECEIPT PATTERNS AND MESURMENT DETAILS 6-Apr-20 6-Apr-20 0
PROTO FABRIC & TRIMS RECEIPT LIST OF TRIM GARMENT 7-Apr-20 7-Apr-20 0
PROTO EXIT SENT TO BUYER 10-Apr-20 10-Apr-20 0
ORDER CONFIRMATION DATE 15-Apr-20 15-Apr-20 0
PROTO / 1ST FIT COMMENTS 25-Apr-20 25-Apr-20 0
2nd FIT EXIT 26-Apr-19 26-Apr-19 0
2nd FIT COMMENTS CHNAGES IN PATTRENS 29-Apr-19 29-Apr-19 0
3rd FIT EXIT 30-Apr-20 30-Apr-20 0
3rd FIT COMMENTS CHANGES IN MESUREMENTS 1-May-20 1-May-20 0
4th FIT EXIT 2-May-20 2-May-20 0
4th FIT / FINAL APPROVAL COMMENTS 6-May-20 6-May-20 0
0 Gain/coverup 0 Days gained-/ Days to coverup+

PLAN PLAN ACTUAL


FABRIC COMMIT RECPT DATE 15-Apr-20 15-Apr-20 0
FABRIC ORDER DATE (PO) 15-Apr-20 15-Apr-20 0
FABRIC PI 16-Apr-20 16-Apr-20 0
FABRIC LC 18-Apr-20 18-Apr-20 0
PILOT YARDAGE X MILL 25-Apr-20 25-Apr-20 0
PILOT YARDAGE IN HOUSE DT 25-Apr-20 25-Apr-20 0
FABRIC TEST REPORT RECEIPT FROM MILL 26-Apr-20 26-Apr-20 0
FABRIC INSPECTION REPORT RECPT FROM MILL 6-Jul-20 6-Jul-20 0
SHADE BAND RECPT FROM THE MILL 9-Jul-20 9-Jul-20 0
FABRIC EX MILL 9-Jul-20 9-Jul-20 0
FABRIC IN HSE 9-Jul-20 9-Jul-20 0
FABRIC INSPECTION FROM FTY 11-Jul-20 11-Jul-20 0
SHADE BAND FROM FTY 14-Jul-20 14-Jul-20 0
FABRIC SHRINKAGE TEST RESULT 28-Apr-20 28-Apr-20 0
GARMENT PURCHASE ORDER RECP DT 10-Apr-20 10-Apr-20 0
TRIM ORDERING START 16-Apr-20 16-Apr-20 0
MAIN LABEL ORDER DT 16-Apr-20 16-Apr-20 0
CARE LABEL ORDER DT 16-Apr-20 16-Apr-20 0
BUTTON ORDER DT 16-Apr-20 16-Apr-20 0
SWATCH FR THREAD PANEL 17-Apr-20 17-Apr-20 0
THREAD PANEL FR APPVL 17-Apr-20 17-Apr-20 0
THREAD PANEL APVL & ORDER DT 21-Apr-20 21-Apr-20 0
TRIM IN-HOUSE 27-Apr-20 27-Apr-20 0
TRIM TEST REPORTS 30-Apr-20 30-Apr-20 0
TRIM CARD APPROVAL 5-May-20 5-May-20 0
POLYBAG STICKERS IN HSE DT 22-Apr-20 22-Apr-20 0
POLYBAG IN HSE DT 22-Apr-20 22-Apr-20 0
GPT SPL EXIT 8-May-20 8-May-20 0
GPT TEST REPORT 10-May-20 10-May-20 0
Tight/loose: 0 Gain/coverup 0 Days gained-/ Days to coverup+
Total till now 0 Total till now 0 Days gained-/ Days to coverup+

PLAN PLAN ACTUAL


PRE SIZE SET START 10-May-20 10-May-20 0
PRE SIZE SET APPROVAL 13-May-20 13-May-20 0
SIZE SET + PP SAMPLE START 14-May-20 14-May-20 0
SIZE SET+ PP SAMPLE APPROVAL 18-May-20 18-May-20 0
PRE-PRODUCTION MEETING MEETING REGURDDING IINE SET UP AND AVALIBLITY 20-May-20 20-May-20 0
PILOT START DATE TO CHECK THE QUALITY AND LINE SET UP 21-May-20 21-May-20 0
PILOT RUN APPROVAL 23-May-20 23-May-20 0
PCD PATTRENS 25-May-20 25-May-20 0
SEWING START 1-Jun-20 1-Jun-20 0
PRS EXIT 10-Jul-20 6-Jul-20 -4
Tight/loose: -4 Gain/coverup 0 Days gained-/ Days to coverup+
Total till now -4 Total till now 0 Days gained-/ Days to coverup+
DELIVERY PLAN
REQUIRE PLAN ACTUAL
GMT LC 1-Oct-20 44105
X - FTY 15-Jul-20 44105
SHIP VIA SHIPPPING VIA SEA 22-Jul-20 44027
PORT OF LADING SAN FRANSISCO 1-Aug-20 44034
VESSEL DATE 15-Apr-20 44044

REVIEWED & CONFIRMED BY MERCHANT

COMMENTS

ASSUMPTIONS WORKING OF T&A


1 STYLE IS NON WASH & NON EMBROIDERED. 1 FIT CYCLE, PRE SIZE SET, SIZE SET & PP SAMPLE DATES WORKED FORWARDS
2 TRIM & FABRIC LEAD TIMES, FIT CYCLES. FROM ORDER CONFIRMATION DATE.
2 BALANCE PRODUCTION ACTIVITIES WORKED BACKWARDS FROM X-FTY DATES.
3 HENCE WHILE MAKING T&A NEED TO BALANCE THE PRE-PRODUCTION & PRODUCTION ACTIVITIES
4 TO KEEP A CHECK ON THE SAME ALL ACTIVITIES PRIOR TO PCD HAVE BEN FORMATTED AS BELOW --
IF DATE OF ANY ACTIVITY IS SAME OR BEYOND PCD THEN THE CELL I S HIGHLIGHTED IN RED

KSA Technopak
10-Feb-05
11-Jan-05
26-Jan-05