Ariisto Goregaon Addendum 1
Ariisto Goregaon Addendum 1
Ariisto Goregaon Addendum 1
Wastage in
Sr.No. Description Unit Basic Rate
%
Employer will supply RMC, Steel and major finishing items along with MEP materials on a star rate basis as mentioned
above. Employer shall give all VAT bill to Contractor and it shall be consignee name in form of bid. Any increase or
decrease on the star rate will be in Employer’s account adjusted from RA Bill. Variation in the wastage is agreed by
Ariisto and bider. Employer will be liable to supply the fixed quantity according to the project and if any additional
1 quantity will be required to be procured by bidder for any reasons attributable to bidder and or on account of additional
wastage or for any other reasons it will be at the sole cost of bidder.
Above mentioned basic price of materials are the landed cost of materials at Project site including all taxes, duties,
cesses including VAT, Central & Local taxes, Loading, Transportation etc. complete. The unloading shall be factored in
the overall item rate.
Contractor should submit the Reconcilation Statement along with Running Account Bill (RA Bill). Contractor should take
2 all necessary care to see that wastage should not be exceeded % mentioned . If wastage exceeds by below mentioned
wastage %, cost of the extra wastage shall be recovered at 10% higher than supply rate and shall be deducted from
Running Bill. For Rolling Margin, Testing shall be done from every lot of steel of all diameter received at site and
wastage shall be calculated based on rolling margin
Bidder will submit list of materials with specifications as to quality and quantity as required on site at least one month in
3 advance to Employer. Such specifications shall be submitted along with the Price list and the vendor list. Employer
shall at its sole discretion either supply below or at par with the purchase rate or give consent to bidder for the
The Contractor, before procuring any item with base rate shall provide all documentary justification (three quotes) for
5
the base rate of materials. Final decision on supplier will be by Employer.