JPH1193600A - Construction method for underground structure - Google Patents
Construction method for underground structureInfo
- Publication number
- JPH1193600A JPH1193600A JP9296107A JP29610797A JPH1193600A JP H1193600 A JPH1193600 A JP H1193600A JP 9296107 A JP9296107 A JP 9296107A JP 29610797 A JP29610797 A JP 29610797A JP H1193600 A JPH1193600 A JP H1193600A
- Authority
- JP
- Japan
- Prior art keywords
- hole
- excavated
- segments
- divided
- reinforcing
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Excavating Of Shafts Or Tunnels (AREA)
- Lining And Supports For Tunnels (AREA)
Abstract
Description
【0001】[0001]
【発明の属する技術分野】本発明は、地下構造物、特
に、中空構造物の構築工法に関する。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for constructing an underground structure, in particular, a hollow structure.
【0002】[0002]
【従来の技術】従来、例えば、地下鉄の駅等を構成する
ためのボックス状の地下構造物は、地上より掘削を行う
オープンカット工法が公知である。2. Description of the Related Art Conventionally, for a box-shaped underground structure for forming a subway station or the like, for example, an open cut method for excavating from the ground is known.
【0003】[0003]
【発明が解決しようとする課題】ところが、従来のオー
プンカット工法は、繁華街等で施工すると、交通の渋
滞、騒音や粉塵による公害の発生という問題があり、主
に夜間作業にならざるを得ないという欠点がある。ま
た、電力線やガス供給管等の土中埋設物の保護を考慮し
なければならない。更に、構築のために必要な範囲を越
える部分にわたる掘削や、埋戻しを行わなければなら
ず、コスト面でも問題がある。However, the conventional open cut method, when constructed in a downtown area or the like, has problems such as traffic congestion and the occurrence of pollution due to noise and dust. There is a disadvantage that there is no. In addition, protection of underground objects such as power lines and gas supply pipes must be considered. In addition, excavation and backfilling beyond the necessary range for construction must be performed, which is problematic in terms of cost.
【0004】[0004]
【課題を解決するための手段】本発明は、前記課題を解
決した地下構造物の構築工法を提供するものであり、本
発明によれば、土中に設置したシールド掘進機を前進さ
せることにより掘削形成される横穴の内周壁に沿って分
割された複数個のセグメントを周設することにより地下
構造物を構築するものであるから、従来のオープンカッ
ト工法に見られるような問題を悉く解決することができ
る。SUMMARY OF THE INVENTION The present invention provides a method of constructing an underground structure which solves the above-mentioned problems. According to the present invention, a shield excavator installed in soil is advanced by moving it forward. The underground structure is constructed by laying a plurality of segments divided along the inner peripheral wall of the excavated horizontal hole, so it solves all the problems seen in the conventional open cut method be able to.
【0005】ところで、地下鉄の駅等のような地下構造
物を構築する場合、シールド掘進機により、予め、大規
模で複雑な形状の横穴を一挙に掘削することは至難であ
り、しかも、土砂の崩落による危険がある。この点につ
いて、本発明によれば、中土を残存せしめたまま掘削を
予定された横穴の輪郭線上で複数セグメントの何れかに
対応する分割穴を掘削すると共に、該分割穴に当該セグ
メントを組込む分割作業を構成し、このような分割作業
を同時に又は前後して行うことにより、掘削を予定され
た横穴の輪郭全周にわたり全てのセグメントを周設する
ことにより構造物を組立てるものであるから、大規模で
複雑な形状の構造物を容易に構築することができる。し
かも、個々の分割穴を掘削する構成であるから、掘削時
に土砂の崩落等を生じる虞れがなく、安全に作業を行う
ことができる。[0005] When constructing an underground structure such as a subway station, it is extremely difficult to excavate large-scale and complicated-shaped side holes at once using a shield excavator. There is a danger of collapse. Regarding this point, according to the present invention, a divided hole corresponding to any one of the plurality of segments is excavated on the outline of the horizontal hole to be excavated while the soil remains, and the segment is incorporated into the divided hole. By constructing the division work and performing such division work at the same time or before and after, the structure is assembled by laying all the segments around the entire circumference of the contour of the horizontal hole scheduled to be excavated, A large-scale structure having a complicated shape can be easily constructed. In addition, since each divided hole is excavated, there is no danger of earth and sand collapse during excavation, and the operation can be performed safely.
【0006】そして、全てのセグメントにより構造物を
土中で構築した後、該構造物により囲繞された中土を掘
削し除去することにより横穴を完成し、構造物の全貌を
完成せしめる構成であるから、掘削中の中土が謂わば構
造物をシェルとして囲繞された状態にあり土砂崩落の危
険が小さく、この点においても安全に作業を行うことが
できる。[0006] Then, after a structure is constructed in the soil with all the segments, the inner soil surrounded by the structure is excavated and removed to complete the lateral hole, thereby completing the entire structure of the structure. Therefore, the excavated middle soil is surrounded by a so-called structure as a shell, so that the risk of landslide is small, and work can be performed safely in this respect as well.
【0007】そこで、本発明が第一の手段として構成し
たところは、土中で掘削形成される横穴の内周壁に沿っ
て分割された複数個のセグメントを周設することにより
地下構造物を構築する方法において、中土を残存せしめ
たまま掘削を予定された横穴の輪郭線上で複数セグメン
トの何れかに対応する分割穴を掘削すると共に、該分割
穴に当該セグメントを組込む分割作業工程と、前記分割
作業工程を同時に又は前後して行うことにより、掘削を
予定された横穴の輪郭全周にわたり全てのセグメントを
周設することにより構造物を組立てる組立工程と、前記
構造物により囲繞された中土を掘削し除去することによ
り横穴を完成する横穴完成工程とから成る点にある。Therefore, the present invention is configured as a first means to construct an underground structure by laying a plurality of segments divided along the inner peripheral wall of a lateral hole formed by excavation in the soil. In the method, while excavating a divided hole corresponding to any of the plurality of segments on the outline of the horizontal hole scheduled to be excavated while leaving the middle soil, a dividing operation step of incorporating the segment into the divided hole, An assembling step of assembling a structure by performing all the segments around the entire periphery of the side hole to be excavated by performing the division work step simultaneously or before and after; and a soil surrounded by the structure. Excavating and removing the hole to complete the side hole.
【0008】また、本発明が第二の手段として構成した
ところは、前記横穴完成工程と同時に又は前記横穴完成
工程の後に、前記構造物を補強する補強柱等の補強構造
物を形成する補強工程を構成して成る点にある。Further, the present invention is constituted as a second means, in a reinforcing step of forming a reinforcing structure such as a reinforcing column for reinforcing the structure simultaneously with the horizontal hole completing step or after the horizontal hole completing step. It consists in comprising.
【0009】[0009]
【発明の実施の形態】以下、図面に基づいて発明の実施
形態を詳述する。Embodiments of the present invention will be described below in detail with reference to the drawings.
【0010】図1は、本発明の工法により構築した地下
構造物50を示しており、地山51の内部で掘削形成さ
れた横穴52の内周壁に沿って分割された複数個のセグ
メントを周設することにより組立てられている。図例の
場合、セグメントは、一対の断面同形の側壁セグメント
53a、53bと、一対の断面同形の上壁セグメント5
4a、54bと、一対の断面同形の底壁セグメント55
a、55bと、前記一対の上壁セグメント54a、54
bの間と一対の底壁セグメント55a、55bの間にそ
れぞれ介装される一対の断面ほぼ対称形の中央壁セグメ
ント56a、56bと、上壁セグメント54a、54b
と側壁セグメント53a、53bのそれぞれの間におけ
るコーナー部分に配置される一対の断面対称形の上コー
ナーセグメント57a、57bと、底壁55a、55b
と側壁セグメント53a、53bのそれぞれの間におけ
るコーナー部分に配置される一対の断面対称形の下コー
ナーセグメント58a、58bとから成る合計12個の
セグメントを構成する。尚、セグメントの個数や形状
は、構築すべき構造物の規模や形状に応じて適宜変更す
れば良い。また、これらのセグメントは、鉄筋コンクリ
ート製とする他、鉄鋼製としても良く、目的に応じて材
質、形状を選択することができる。FIG. 1 shows an underground structure 50 constructed according to the method of the present invention. A plurality of segments divided along an inner peripheral wall of a lateral hole 52 excavated and formed inside a ground 51 are shown. It is assembled by installing. In the illustrated example, the segments are a pair of side wall segments 53a and 53b having the same cross section and a pair of upper wall segments 5 having the same cross section.
4a, 54b and a pair of bottom wall segments 55 having the same cross section
a, 55b and said pair of upper wall segments 54a, 54
b and a pair of bottom wall segments 55a and 55b, respectively, and a pair of substantially symmetrical central wall segments 56a and 56b and upper wall segments 54a and 54b.
And a pair of symmetrical upper corner segments 57a, 57b disposed at a corner portion between each of the side walls 53a, 53b, and bottom walls 55a, 55b.
And a pair of symmetrical lower corner segments 58a, 58b disposed at the corners between the side wall segments 53a, 53b, respectively, to form a total of 12 segments. The number and shape of the segments may be appropriately changed according to the scale and shape of the structure to be constructed. These segments may be made of reinforced concrete or steel, and the material and shape can be selected according to the purpose.
【0011】図示実施形態において、構造物50には補
強柱59等の補強構造物60が設けられており、更に
は、鉄骨その他の種々の補強手段を設けても良い。In the illustrated embodiment, the structure 50 is provided with a reinforcing structure 60 such as a reinforcing column 59, and may be provided with a steel frame or other various reinforcing means.
【0012】前記セグメントの組立てによる構造物50
を構築するに際しては、中土を残存せしめたまま掘削を
予定された横穴の輪郭線上で複数セグメント(53a、
53b、54a、54b、55a、55b、56a、5
6b、57a、57b、58a、58b)の何れかに対
応する分割穴(63a、63b、64a、64b、65
a、65b、66a、66b、67a、67b、68
a、68b)を掘削すると共に、該分割穴に当該のセグ
メントを組込む分割作業工程が実施され、このような分
割作業工程を順次に繰返して行うことにより、掘削を予
定された横穴の輪郭全周にわたり全てのセグメントを周
設することにより構造物50を組立てる組立工程が実施
される。その後、中土を掘削し除去することにより横穴
52を完成する横穴完成工程が実施され、その際、前記
補強構造物60を形成する補強工程か実施される。Structure 50 by assembling the segments
When constructing a multi-segment (53a, 53a,
53b, 54a, 54b, 55a, 55b, 56a, 5
6b, 57a, 57b, 58a, 58b) corresponding to any of the divided holes (63a, 63b, 64a, 64b, 65).
a, 65b, 66a, 66b, 67a, 67b, 68
a, 68b) is excavated, and a division operation step of incorporating the relevant segment into the division hole is performed. By repeating such division operation steps sequentially, the entire circumference of the contour of the side hole for which excavation is to be performed is performed. The assembly process of assembling the structure 50 is performed by surrounding all the segments. Thereafter, a horizontal hole completing step of excavating and removing the inner soil to complete the horizontal hole 52 is performed. At this time, a reinforcing step of forming the reinforcing structure 60 is performed.
【0013】前述した分割作業工程において、分割穴を
掘削するためには、図3に示すような筒状のシールド本
体2の前部にカッターヘッド3を有するシールド掘進機
1が使用される。In the above-described division work step, a shield excavator 1 having a cutter head 3 at the front of a cylindrical shield body 2 as shown in FIG.
【0014】前記カッターヘッド3は、シールド本体2
の先端近傍に配置されると共に、大小複数の枠状フレー
ム4をほぼ同一面内で間隔をおいて組合わせ且つ連結材
により連結することによりフレーム4、4間に開口部を
形成した掘削部6を有し、各フレーム4の前面に多数の
カッター歯群41から成る掘削手段17を突設せしめて
いる。この掘削部6は、シールド本体2の内部に配置せ
しめられたヘッド支持部7に対して連結アーム8を介し
て連結され、該ヘッド支持部7は、中心から後方に向け
て延設される筒状軸体9を有する。尚、カッター歯群4
1から成る掘削手段17の全体形状は、前述した分割穴
(63a、63b、64a、64b、65a、65b、
66a、66b、67a、67b、68a、68b)の
何れかに対応しており、カッター歯41は、掘削すべき
地山の土質に応じたものとされている。The cutter head 3 includes a shield body 2
Excavation part 6 which is arranged near the front end of the frame 4 and which has a plurality of large and small frame-shaped frames 4 combined at intervals in substantially the same plane and connected by a connecting member to form an opening between the frames 4 The excavating means 17 comprising a large number of cutter teeth 41 is provided on the front surface of each frame 4. The excavation part 6 is connected via a connecting arm 8 to a head support part 7 disposed inside the shield main body 2, and the head support part 7 is a tube extending rearward from the center. The shaft 9 is provided. In addition, cutter tooth group 4
The excavating means 17 composed of the first and second excavating means 17 has the above-mentioned divided holes (63a, 63b, 64a, 64b, 65a, 65b,
66a, 66b, 67a, 67b, 68a, 68b), and the cutter teeth 41 are adapted to the soil quality of the ground to be excavated.
【0015】前記シールド本体2は、前部近傍に隔壁1
0を設け、該隔壁10を貫通して固着された筒状支持体
11を有し、該筒状支持体11に前記カッターヘッド3
の筒状軸体9を軸受部材12を介して摺動自在に挿通せ
しめている。尚、筒状支持体11と筒状軸体9との間に
は、シール材22が配置されている。従って、カッター
ヘッド3は、シールド本体2の軸心に沿って前後方向に
出退自在であり、この出退駆動を可能とするための油圧
ブレーカー装置等から成る出退駆動装置13がシールド
本体2内に設けられている。The shield body 2 is provided with a partition 1 near the front.
0, and has a cylindrical support 11 fixedly penetrating through the partition 10. The cylindrical support 11 has the cutter head 3 attached thereto.
Is slidably inserted through a bearing member 12. Note that a seal member 22 is disposed between the cylindrical support 11 and the cylindrical shaft 9. Therefore, the cutter head 3 can move back and forth along the axis of the shield main body 2 in the front-rear direction, and a retracting drive device 13 including a hydraulic breaker device or the like for enabling the retracting drive is provided. It is provided within.
【0016】図例において、前記出退駆動装置13は、
油圧等の流体圧式のシリンダー装置14により構成さ
れ、該シリンダー装置14は、前記筒状軸体9の内部に
向けて配置され、シリンダーロッド部15の先端を筒状
軸体9の底部に枢結すると共に、該シリンダー装置14
の尾端をシールド本体2の後部近傍に固設したガーダ部
16に枢結している。従って、シリンダー装置14を伸
縮せしめることにより、図3に鎖線で示すように、カッ
ターヘッド3をシールド本体2の先端において出退駆動
することができる。In the example shown in FIG.
It is constituted by a hydraulic cylinder device 14 of a hydraulic pressure or the like. The cylinder device 14 is arranged toward the inside of the cylindrical shaft 9, and pivotally connects the tip of the cylinder rod portion 15 to the bottom of the cylindrical shaft 9. And the cylinder device 14
Is connected to a girder portion 16 fixed near the rear portion of the shield main body 2. Therefore, by extending and contracting the cylinder device 14, the cutter head 3 can be driven to move back and forth at the tip of the shield main body 2 as shown by a chain line in FIG. 3.
【0017】前記カッターヘッド3は、掘削部6とヘッ
ド支持部7との間の空間部により土砂取込室40を形成
しており、該土砂取込室40の内部に開口せしめられた
送泥管18及び排泥管19を、ヘッド支持部7に相対的
に摺動自在に挿通せしめると共に、隔壁10に挿着して
おり、該隔壁10の後方位置において、バルブを介して
送泥管18及び排泥管19を後方に延長してガーダ部1
6を挿通せしめ、シールド本体2の後方に導出せしめて
いる。前記送泥管18は、土砂取込室40に泥水を供給
するためのものであり、前記排泥管19は、土砂取込室
40内でスラリー化された土砂を排出するためのもので
ある。The cutter head 3 has a sediment intake chamber 40 formed by a space between the excavation part 6 and the head support part 7, and a mud pump that is opened inside the sediment intake chamber 40. The pipe 18 and the sludge pipe 19 are slidably inserted into the head support portion 7 and slidably inserted into the partition wall 10. At the rear position of the partition wall 10, the mud pipe 18 is inserted through a valve. And the sludge pipe 19 is extended rearward to make the girder 1
6 is inserted and led out behind the shield body 2. The mud pipe 18 is for supplying muddy water to the sediment intake chamber 40, and the drain pipe 19 is for discharging sediment slurried in the sediment intake chamber 40. .
【0018】尚、図3において、23は、シールド掘進
機1内の後部に配置されたシールドジャッキ、24は、
同じく後部に配置されたセグメントのエレクタ装置であ
り、25は、バイブレータ(振動発生装置)である。In FIG. 3, reference numeral 23 denotes a shield jack arranged at the rear of the shield machine 1;
Similarly, a segmental erector device is disposed at the rear, and 25 is a vibrator (vibration generator).
【0019】(本発明工法の実施形態)図1に示した構
造物50の実施形態の場合、合計12個のセグメント
(53a、53b、54a、54b、55a、55b、
56a、56b、57a、57b、58a、58b)か
ら構築されているため、各セグメントに対応する合計1
2の分割穴(63a、63b、64a、64b、65
a、65b、66a、66b、67a、67b、68
a、68b)を掘削するための12台のシールド掘進機
1が使用される。(Embodiment of the Construction Method of the Present Invention) In the case of the embodiment of the structure 50 shown in FIG. 1, a total of 12 segments (53a, 53b, 54a, 54b, 55a, 55b, 55b,
56a, 56b, 57a, 57b, 58a, 58b), so that a total of 1
2 divided holes (63a, 63b, 64a, 64b, 65
a, 65b, 66a, 66b, 67a, 67b, 68
Twelve shield machines 1 are used for excavating a, 68b).
【0020】(縦穴形成工程)図示省略しているが、地
面の所定個所において、地下構造物を構築すべきレベル
に至る深さの縦穴を掘削し、該縦穴内に前述した12台
のシールド掘進機1を設置する。このような縦穴は、従
来周知の方法により、例えばバックホー等により掘削さ
れるが、シールド掘進機1を設置するために必要十分な
大きさの穴であれば良い。(Vertical hole forming step) Although not shown in the figure, a vertical hole having a depth to a level at which an underground structure is to be constructed is excavated at a predetermined location on the ground, and the above-mentioned 12 shield excavations are drilled in the vertical hole. Machine 1 is installed. Such a vertical hole is excavated by a conventionally known method, for example, by a backhoe or the like, but may be a hole having a size sufficient and necessary for installing the shield machine 1.
【0021】(分割作業工程)縦穴から横に向けてシー
ルド掘進機1を前進させることにより、各セグメントに
対応した分割穴が掘削形成される。(Division work step) By moving the shield machine 1 forward from the vertical hole to the side, the division hole corresponding to each segment is excavated.
【0022】即ち、シールド掘進機1は、バイブレータ
25により振動を与えながらシリンダー装置14のシリ
ンダーロッド部15を駆動することにより、カッターヘ
ッド3を出退駆動しつつ地山に所定形状の分割穴を掘削
しながら前進する。掘削された土砂は、送泥管18から
供給された泥水によりスラリー化され、排泥管19によ
り外部に排出される。このように、シールド掘進機1
は、カッターヘッドを回転させながら穴を掘削するもの
に比して、掘削穴の断面形状に制約がなく、カッター歯
群41から成る掘削手段17の全体形状を上述した各セ
グメントの断面形状に対応せしめることにより、当該セ
グメントに対応した断面形状の分割穴を掘削形成するこ
とができる。従って、12台のシールド掘進機1を使用
することにより、図2(A)ないし(D)に示すよう
に、それぞれの分割穴63a、63b、64a、64
b、65a、65b、66a、66b、67a、67
b、68a、68bを掘削形成することができる。That is, the shield machine 1 drives the cylinder rod portion 15 of the cylinder device 14 while giving vibrations by the vibrator 25, thereby driving the cutter head 3 out and back, and forming a predetermined divided hole in the ground. Go forward while digging. The excavated earth and sand is slurried by muddy water supplied from a mud feeding pipe 18 and discharged to the outside by a mud discharging pipe 19. Thus, shield machine 1
Does not limit the cross-sectional shape of the drilling hole as compared with the one in which the hole is drilled while rotating the cutter head, and the entire shape of the drilling means 17 composed of the cutter teeth 41 corresponds to the cross-sectional shape of each segment described above. By doing so, a divided hole having a cross-sectional shape corresponding to the segment can be formed by excavation. Therefore, by using the twelve shield excavators 1, as shown in FIGS. 2A to 2D, each of the divided holes 63a, 63b, 64a, 64
b, 65a, 65b, 66a, 66b, 67a, 67
b, 68a, 68b can be excavated.
【0023】図2(A)は、掘削を予定された横穴の輪
郭線L上で、側壁セグメント53a、53bのための分
割穴63a、63bと、上壁セグメント54a、54b
のための分割穴64a、64bと、底壁セグメント55
a、55bのための分割穴65a、65bを掘削し形成
している状態を示している。これらの6個の分割穴は、
6台のシールド掘進機により掘削形成され、このため、
各シールド掘進機におけるカッターヘッド3の掘削手段
17は、当該分割穴に応じた形状のものとされている。FIG. 2 (A) is a view showing a division hole 63a, 63b for the side wall segments 53a, 53b and upper wall segments 54a, 54b on the contour line L of the horizontal hole to be excavated.
Holes 64a, 64b for the bottom wall segment 55
The state which excavates and forms the division | segmentation hole 65a, 65b for a, 55b is shown. These six split holes are
Excavated and formed by six shield excavators,
The excavating means 17 of the cutter head 3 in each shield excavator has a shape corresponding to the divided hole.
【0024】図2(B)は、掘削を予定された横穴の輪
郭線L上で、上コーナーセグメント57a、57bのた
めの分割穴67a、67bを掘削し形成している状態を
示している。これらの2個の分割穴67a、67bは、
2台のシールド掘進機により掘削形成され、このため、
各シールド掘進機におけるカッターヘッド3の掘削手段
17は、それぞれ分割穴67a、67bの断面形状に応
じた形状のものとされている。FIG. 2B shows a state in which division holes 67a and 67b for the upper corner segments 57a and 57b are excavated and formed on the contour line L of the horizontal hole to be excavated. These two divided holes 67a, 67b
Excavation is formed by two shield excavators,
The excavating means 17 of the cutter head 3 in each shield excavator has a shape corresponding to the sectional shape of the divided holes 67a and 67b.
【0025】図2(C)は、掘削を予定された横穴の輪
郭線L上で、中央壁セグメント56a、56bのための
分割穴66a、66bを掘削し形成している状態を示し
ている。これらの2個の分割穴66a、66bは、2台
のシールド掘進機により掘削形成され、このため、各シ
ールド掘進機におけるカッターヘッド3の掘削手段17
は、それぞれ分割穴66a、66bの断面形状に応じた
形状のものとされている。FIG. 2C shows a state in which division holes 66a and 66b for the center wall segments 56a and 56b are excavated and formed on the contour line L of the horizontal hole to be excavated. These two divided holes 66a and 66b are formed by excavation by two shield excavators. Therefore, the excavation means 17 of the cutter head 3 in each shield excavator is formed.
Has a shape corresponding to the cross-sectional shape of each of the divided holes 66a and 66b.
【0026】図2(D)は、掘削を予定された横穴の輪
郭線L上で、下コーナーセグメント58a、58bのた
めの分割穴68a、68bを掘削し形成している状態を
示している。これらの2個の分割穴68a、68bは、
2台のシールド掘進機により掘削形成され、このため、
各シールド掘進機におけるカッターヘッド3の掘削手段
17は、それぞれ分割穴68a、68bの断面形状に応
じた形状のものとされている。FIG. 2D shows a state in which divided holes 68a and 68b for the lower corner segments 58a and 58b are excavated and formed on the contour line L of the horizontal hole to be excavated. These two divided holes 68a, 68b
Excavation is formed by two shield excavators,
The excavating means 17 of the cutter head 3 in each shield excavator has a shape corresponding to the sectional shape of the divided holes 68a and 68b.
【0027】(組立工程)そこで、以上のようにして掘
削形成した合計12個の分割穴63a、63b、64
a、64b、65a、65b、66a、66b、67
a、67b、68a、68bには、それぞれのセグメン
ト53a、53b、54a、54b、55a、55b、
56a、56b、57a、57b、58a、58bが組
込まれ(組立工程)、これにより、図2(E)に示すよ
うに、掘削を予定された横穴の輪郭線Lの全周にわたり
全てのセグメントが周設された構造物50が構築され
る。この際、各セグメントに、図1に示すようなガイド
付きシェル70を用いれば、構造物50の仕上がりにズ
レ等を生じることが防止される。(Assembling process) Therefore, a total of twelve divided holes 63a, 63b, 64 excavated and formed as described above.
a, 64b, 65a, 65b, 66a, 66b, 67
a, 67b, 68a, 68b have respective segments 53a, 53b, 54a, 54b, 55a, 55b,
56a, 56b, 57a, 57b, 58a, and 58b are assembled (assembly process), whereby all the segments are formed over the entire circumference of the outline L of the horizontal hole to be excavated as shown in FIG. The surrounding structure 50 is constructed. At this time, if a shell 70 with a guide as shown in FIG. 1 is used for each segment, it is possible to prevent a deviation or the like from occurring in the finish of the structure 50.
【0028】ところで、合計12個の分割穴の全てが掘
り終えられたときは、全ての分割穴が連通状態にあるの
で、そこで12個のセグメントを接続しながら組立てる
ことができる。一方、全ての分割穴が掘り終えられるま
で待つことなく、一部の分割穴が掘り終えられた時、そ
の都度、当該分割穴に対応するセグメントを組込むこと
により作業を進めても良く、最終的に全ての分割穴の掘
削と全てのセグメントの組込みが終了した時点で、セグ
メント相互を接続することにより構造物50を完成せし
めるように構成しても良い。By the way, when all the twelve divided holes have been dug, all the divided holes are in communication with each other, so that the twelve segments can be connected and assembled. On the other hand, instead of waiting until all the divided holes have been dug, when some of the divided holes have been dug, the work may be proceeded by incorporating the segment corresponding to the divided hole each time. When the excavation of all the divided holes and the incorporation of all the segments are completed, the structure 50 may be completed by connecting the segments.
【0029】(横穴完成工程)而して、組立てられた構
造物50により囲繞された内部空間には、中土69が残
存せしめられているので、該中土69を掘削し除去する
ことにより横穴52を完成する(横穴完成工程)。これ
により、図2(F)に示すように構造物50の全貌が完
成することになる。中土69の掘削除去は、前記と同様
のシールド掘進機1により行っても良く、或いは、その
他の掘削手段により行っても良い。(Side Hole Completion Process) Since the inner soil 69 is left in the internal space surrounded by the assembled structure 50, the inner hole 69 is excavated and removed to remove the inner hole. 52 is completed (horizontal hole completing step). Thus, the entire structure 50 is completed as shown in FIG. Excavation and removal of the inner soil 69 may be performed by the same shield excavator 1 as described above, or may be performed by other excavation means.
【0030】(補強工程)前記横穴完成工程と同時に又
は前記横穴完成工程の後、上述した補強柱59等の補強
構造物60が形成される。このような補強構造物60
は、所定の設計に基づくサイズ及び間隔の下で、随時、
型枠及び配筋を行った後、生コンを打設することにより
形成される。(Reinforcing Step) Simultaneously with or after the horizontal hole completing step, a reinforcing structure 60 such as the above-described reinforcing column 59 is formed. Such a reinforcing structure 60
At any time, under the size and spacing based on the predetermined design,
It is formed by placing a ready-mixed concrete after performing the formwork and the arrangement of reinforcing bars.
【0031】(最終工程)構造物を構築した後は、シー
ルド掘進機を土中から引揚げたり、縦穴部分を土砂によ
り埋める等、仕上げのために必要な最終工程が行われ
る。(Final Step) After the construction of the structure, final steps necessary for finishing, such as withdrawing the shield machine from the soil and filling the vertical hole with earth and sand, are performed.
【0032】[0032]
【発明の効果】本発明によれば、土中に設置したシール
ド掘進機を前進させることにより掘削形成される横穴の
内周壁に沿って分割された複数個のセグメントを周設す
ることにより地下構造物を構築するものであるから、従
来のオープンカット工法に見られるような問題を悉く解
決することができる。According to the present invention, an underground structure is formed by laying a plurality of segments divided along the inner peripheral wall of a lateral hole formed by excavating a shield machine installed in the soil. Since the object is constructed, it is possible to solve all the problems seen in the conventional open cut method.
【0033】特に、本発明によれば、中土を残存せしめ
たまま掘削を予定された横穴の輪郭線L上で複数セグメ
ントの何れかに対応する分割穴を掘削すると共に、該分
割穴に当該セグメントを組込む分割作業を構成し、この
ような分割作業を同時に又は前後して行うことにより、
掘削を予定された横穴の輪郭Lの全周にわたり全てのセ
グメントを周設することにより構造物50を組立てる構
成であるから、地下鉄の駅等のような大規模で複雑な形
状の構造物を容易に構築することができる。しかも、個
々の分割穴を掘削する構成であるから、掘削時に土砂の
崩落等を生じる虞れがなく、安全に作業を行うことがで
きる。In particular, according to the present invention, a divided hole corresponding to any one of the plurality of segments is excavated on the contour line L of the horizontal hole which is to be excavated while the soil remains, and the corresponding divided hole is excavated. By configuring the division work that incorporates the segment and performing such division work simultaneously or before and after,
Since the structure 50 is assembled by laying all segments around the entire periphery L of the outline L of the horizontal hole to be excavated, a large-scale complicated structure such as a subway station can be easily formed. Can be built. In addition, since each divided hole is excavated, there is no danger of earth and sand collapse during excavation, and the operation can be performed safely.
【0034】そして、全てのセグメントにより構造物5
0を土中で構築した後、該構造物により囲繞された中土
69を掘削し除去することにより横穴52を完成し、構
造物50の全貌を完成せしめる構成であるから、掘削中
の中土69が謂わば構造物50をシェルとして囲繞され
た状態にあり土砂崩落の危険が小さく、この点において
も安全に作業を行うことができる。The structure 5 is formed by all the segments.
0 is constructed in the soil, and then the inner soil 69 surrounded by the structure is excavated and removed to complete the lateral hole 52 and complete the entire structure of the structure 50. 69 is a state in which the structure 50 is surrounded as a shell, so that the risk of landslide is small, and in this respect, work can be performed safely.
【図1】本発明の工法により構築した地下構造物の1例
を示す断面図である。FIG. 1 is a cross-sectional view showing an example of an underground structure constructed by the method of the present invention.
【図2】本発明の工法の1実施形態を示しており、
(A)(B)(C)(D)はそれぞれ分割作業工程を示
す断面図、(E)は構造物の組立工程を示す断面図、
(F)は横穴完成工程を示す断面図である。FIG. 2 shows an embodiment of the method of the present invention,
(A), (B), (C), and (D) are cross-sectional views each showing a division work process, (E) is a cross-sectional view showing a structure assembling process,
(F) is sectional drawing which shows a side hole completion process.
【図3】本発明の工法における分割穴を掘削形成するた
めに使用するシールド掘進機の1例を示す断面図であ
る。FIG. 3 is a cross-sectional view showing an example of a shield machine used for excavating and forming a division hole in the method of the present invention.
1 シールド掘進機 17 掘削手段 52 横穴 53a、53b 側壁セグメント 54a、54b 上壁セグメント 55a、55b 底壁セグメント 56a、56b 中央壁セグメント 57a、57b 上コーナーセグメント 58a、58b 下コーナーセグメント 59 補強柱 60 補強構造物 63a、63b 側壁セグメント用の分割穴 64a、64b 上壁セグメント用の分割穴 65a、65b 底壁セグメント用の分割穴 66a、66b 中央壁セグメント用の分割穴 67a、67b 上コーナーセグメント用の分割穴 68a、68b 下コーナーセグメント用の分割穴 69 中土 L 掘削を予定された横穴の輪郭線 DESCRIPTION OF SYMBOLS 1 Shield machine 17 Excavation means 52 Side hole 53a, 53b Side wall segment 54a, 54b Top wall segment 55a, 55b Bottom wall segment 56a, 56b Central wall segment 57a, 57b Upper corner segment 58a, 58b Lower corner segment 59 Reinforcement column 60 Reinforcement structure Objects 63a, 63b Dividing holes for side wall segments 64a, 64b Dividing holes for upper wall segments 65a, 65b Dividing holes for bottom wall segments 66a, 66b Dividing holes for central wall segments 67a, 67b Dividing holes for upper corner segments 68a, 68b Divided hole for lower corner segment 69 Middle soil L Outline of horizontal hole to be excavated
Claims (2)
って分割された複数個のセグメントを周設することによ
り地下構造物を構築する方法において、 中土を残存せしめたまま掘削を予定された横穴の輪郭線
上で複数セグメントの何れかに対応する分割穴を掘削す
ると共に、該分割穴に当該セグメントを組込む分割作業
工程と、 前記分割作業工程を同時に又は前後して行うことによ
り、掘削を予定された横穴の輪郭全周にわたり全てのセ
グメントを周設することにより構造物を組立てる組立工
程と、 前記構造物により囲繞された中土を掘削し除去すること
により横穴を完成する横穴完成工程とから成ることを特
徴とする地下構造物の構築工法。1. A method of constructing an underground structure by circulating a plurality of segments divided along an inner peripheral wall of a lateral hole excavated and formed in soil, wherein the excavation is performed while the soil remains. By digging a division hole corresponding to any of the plurality of segments on the outline of the planned horizontal hole, a division work step of incorporating the segment into the division hole, and performing the division work step simultaneously or before and after, An assembling step of assembling a structure by laying all segments around the entire contour of a side hole to be excavated; and completing a side hole by excavating and removing the inner soil surrounded by the structure A method for constructing an underground structure, comprising:
完成工程の後に、前記構造物を補強する補強柱等の補強
構造物を形成する補強工程を構成して成ることを特徴と
する請求項1に記載の地下構造物の構築工法。2. A reinforcing step for forming a reinforcing structure such as a reinforcing column for reinforcing the structure at the same time as or after the horizontal hole completing step. Construction method of underground structure described in 4.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP9296107A JPH1193600A (en) | 1997-09-22 | 1997-09-22 | Construction method for underground structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP9296107A JPH1193600A (en) | 1997-09-22 | 1997-09-22 | Construction method for underground structure |
Publications (1)
Publication Number | Publication Date |
---|---|
JPH1193600A true JPH1193600A (en) | 1999-04-06 |
Family
ID=17829234
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP9296107A Pending JPH1193600A (en) | 1997-09-22 | 1997-09-22 | Construction method for underground structure |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPH1193600A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2006161544A (en) * | 2004-11-10 | 2006-06-22 | Zenitaka Corp | Steel shell joining device, steel shell, outer shell and outer shell preceding tunnel construction method |
-
1997
- 1997-09-22 JP JP9296107A patent/JPH1193600A/en active Pending
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2006161544A (en) * | 2004-11-10 | 2006-06-22 | Zenitaka Corp | Steel shell joining device, steel shell, outer shell and outer shell preceding tunnel construction method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP6862237B2 (en) | Outer skeleton construction method and outer skeleton | |
JP2003155889A (en) | Master and slave shield machine and its boring method | |
JPH1193600A (en) | Construction method for underground structure | |
JP6765566B1 (en) | Construction method of the skeleton and the skeleton | |
JP3135188B2 (en) | Construction method of underground cavity | |
JP2019094697A (en) | Construction method of large cross section tunnel and excavation device for large cross section tunnel | |
JP2007332720A (en) | Construction method for underground structure | |
JP2668109B2 (en) | Construction method for underground structures | |
JP2648051B2 (en) | Construction method of arch shell in tunnel precedent | |
JP2006046061A (en) | Pipe jacking method of shielding machine and shielding machine | |
JP4038533B2 (en) | Variable section shield lining structure | |
JP6756892B1 (en) | Underground skeleton and how to build an underground skeleton | |
JPH04309692A (en) | Underground space construction method | |
JP6730540B2 (en) | Outer shell structure and outer shell structure construction method | |
JP2617418B2 (en) | Construction method of underground large space structure | |
JP4343748B2 (en) | Tunnel excavation method | |
JP4514220B2 (en) | Composite shield method and composite shield machine and segment therefor | |
JP4180347B2 (en) | Construction method of underground continuous wall and underground continuous wall | |
JPH05287983A (en) | Construction of underground space having long and large diametral dimension | |
JPH0821190A (en) | Shield machine, excavating method, vertical/horizontal excavator, tunnel and shaft | |
JP2860373B2 (en) | Construction method of an attached tunnel | |
JP2005330760A (en) | Shield machine, and construction method of underground space using the same | |
JP6740156B2 (en) | Construction method of underground structure and underground structure | |
JPH0378917B2 (en) | ||
JP3137902B2 (en) | Drilling rig for underground diaphragm wall construction |