Nothing Special   »   [go: up one dir, main page]

JPH08333813A - Building method of building unit for vertical and horizontal conveying - Google Patents

Building method of building unit for vertical and horizontal conveying

Info

Publication number
JPH08333813A
JPH08333813A JP14091795A JP14091795A JPH08333813A JP H08333813 A JPH08333813 A JP H08333813A JP 14091795 A JP14091795 A JP 14091795A JP 14091795 A JP14091795 A JP 14091795A JP H08333813 A JPH08333813 A JP H08333813A
Authority
JP
Japan
Prior art keywords
building
building block
horizontally
horizontal slide
horizontal
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP14091795A
Other languages
Japanese (ja)
Inventor
Toshiharu Urano
敏晴 浦野
Toshiaki Yamamoto
俊明 山本
Kunio Aoyama
邦男 青山
Mitsuo Asano
三男 浅野
Takumi Fujii
卓美 藤井
Jitsuo Yamada
実男 山田
Makoto Nakajima
眞 中島
Kanta Miyaguchi
幹太 宮口
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Takenaka Komuten Co Ltd
Original Assignee
Takenaka Komuten Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Takenaka Komuten Co Ltd filed Critical Takenaka Komuten Co Ltd
Priority to JP14091795A priority Critical patent/JPH08333813A/en
Publication of JPH08333813A publication Critical patent/JPH08333813A/en
Pending legal-status Critical Current

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

PURPOSE: To enhance workability by loading a building unit on a horizontal slide rack on a lift rack and moving horizontally the horizontal slide rack and setting up the building unit on a lower story area. CONSTITUTION: Two lower story areas 3 of a twin tower are assembled on the rooftop of a building 1 with a tower crane as two layers. A lift rack 4 whose height shares the first story layer, is installed at the middle part of the twin tower. Then, a building block 6 is loaded on a horizontal side rack 5 set up on the top of the lift rack 4 and then the lift rack 4 is adapted to rise up to the elevation of the third story floor. After the horizontal slide rack 5 is horizontally moved, the building block 6 is layered on the lower story area 3. The horizontal slide rack 5 is horizontally moved to the original position while the lift rack 4 is arranged to fall down and then, a subsequent building block 6 is loaded on the lift rack 6. The building units 6 are piled up one after another by repeating a similar process.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】この発明は、例えばスレンダーな
高層ツインタワー型建物を大型タワークレーンを使用せ
ずに建築する建築工法であって、更に言えば、建物を少
なくとも一層分の単位で分割した建物ブロックを基準階
レベルで地組みし、同建物ブロックを垂直、水平運搬し
て順次積み重ねることにより建物を建築する工法に関す
る。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a construction method for constructing, for example, a slender high-rise twin tower type building without using a large tower crane, and more specifically, the building is divided into units of at least one layer. The present invention relates to a construction method in which a building block is erected at a standard floor level, the building block is vertically and horizontally transported, and sequentially stacked to build a building.

【0002】[0002]

【従来の技術】 従来一般の高層建物の建築工法は、大型タワークレ
ーン(仮設揚重機)を設置して鉄骨建方や内装材、外装
材の取付けなど行なっている。 最近になって、移動式屋根部を先行して上昇させ、
同屋根部の直下の位置で建物躯体の構築を進める全天候
型の建築工法も開発され実用化されている(例えば特開
平7−4049号公報に記載された工法参照)。 更に、特開平6−50000号公報には、組立て作
業ヤードに走行台車を用意し、この走行台車上にパレッ
トを載置し、同パレットの上に鉄骨柱、梁、床版等で組
み立てた1スパン分の鉄骨ユニットを載せ、次に走行台
車を揚重位置へ水平移動させ、前記鉄骨ユニットは走行
台車を組立てヤードレベルに残しパレットと共に同パレ
ットが備えた昇降機構で組立て階まで上昇させ、組立て
階では同建物の組立て階に予め用意した天井クレーンな
どで揚重し水平運搬して建て込みを行う自動組立て施工
方法が開示されている。
2. Description of the Related Art Conventionally, a general construction method for a high-rise building is to install a large-scale tower crane (temporary hoisting machine) to construct a steel frame, install interior materials and exterior materials. Recently, the movable roof has been raised first,
An all-weather construction method has also been developed and put into practical use, in which a building frame is constructed immediately below the roof (see, for example, the method described in JP-A-7-4049). Further, in Japanese Unexamined Patent Publication No. 6-50000, a traveling carriage is prepared in an assembly work yard, a pallet is placed on the traveling carriage, and steel columns, beams, floor slabs, etc. are assembled on the pallet. The steel frame unit for the span is placed, then the traveling carriage is horizontally moved to the lifting position, and the steel frame unit is left at the yard level for assembling the traveling carriage, and the pallet together with the lifting mechanism provided for the pallet are raised to the assembly floor to assemble. On the floor, there is disclosed an automatic assembly construction method in which the building is lifted by an overhead crane or the like prepared in advance on the assembly floor of the building and horizontally transported to build.

【0003】[0003]

【本発明が解決しようとする課題】上記の一般的な建
築工法は、タワークレーンを地震等の水平力に対して安
全に支持するため、本設鉄骨に加えて仮設補強がかなり
大掛かりな作業になり、仮設作業の時間及びコストが必
要である。また、タワークレーンが建築工程の鉄骨最終
節まで残るため、クレーン回りの残工事に追われ、仕上
げ工期の確保を圧迫する。更に、高所での作業が多くな
るため、安全性に問題のある作業が増え、安全面で好ま
しくない。従って、タワークレーンを使用せずに実施で
きる建築工法の開発が望まれる。
In the general construction method described above, since the tower crane is safely supported against horizontal forces such as earthquakes, temporary reinforcement is required in addition to the main steel frame. Therefore, temporary construction work requires time and cost. In addition, since the tower crane remains up to the final section of the steel frame in the construction process, the remaining work around the crane is pressed and the securing of the finishing work period is under pressure. Further, since the work at a high place increases, the work having a safety problem increases, which is not preferable in terms of safety. Therefore, it is desired to develop a construction method that can be implemented without using a tower crane.

【0004】この点、上記及びの工法は、大型タワ
ークレーンを使用しないので、一歩進んでいる。しか
し、上記の全天候型建築工法は、建築資材をバラバラ
の状態で屋根部直下の組立て階にまで揚重し、組立て階
において一つ一つ組立て作業を行う内容なので、施工の
省力化、効率化、及び工期の短縮などの面ではまだまだ
改善すべき点が残されている。
In this respect, the above-mentioned construction methods and (1) and (2) are one step ahead because a large tower crane is not used. However, the above-mentioned all-weather construction method involves the construction materials being lifted up to the assembly floor directly under the roof in a disjointed state, and the assembly work is done one by one on the assembly floor, so labor saving and efficiency of construction are improved. In terms of shortening the construction period, etc., there are still points to be improved.

【0005】また、上記の自動組立て施工方法は、地
組み作業を多くした点を評価できるが、組立て階に用意
する天井クレーンは依然として仮設揚重機であり、建物
の組立てに先行して盛り替えをしなければならず、その
盛り替え作業の手間とコストが掛かるほか、盛替え作業
が結局は高所作業となって安全性の面でも問題を残して
いる。
In addition, although the above-mentioned automatic assembly construction method can be evaluated in terms of increasing the amount of ground work, the overhead cranes provided on the assembly floor are still temporary hoisting machines, and the reassembling must be performed prior to building assembly. It is necessary to do this, and it takes time and cost for the refilling work, and the refilling work eventually becomes a high place work, and there is a problem in terms of safety.

【0006】従って、本発明の目的は、タワークレーン
等の仮設揚重機を一切必要とせず、仮設作業及びクレー
ン回りの工事が殆ど発生せず、また、建物を分割した建
物ブロックは地上レベル等(基準階レベル)の作業ヤー
ドで地組みされて高所作業が少なく、施工の安全性が高
い建築工法を提供することである。
Therefore, the object of the present invention is to eliminate the need for a temporary lifting machine such as a tower crane, almost no temporary work and construction around the crane, and a building block obtained by dividing a building into a ground level or the like ( It is to provide a construction method in which construction work is performed at a standard yard (work floor) with less work in high places and high construction safety.

【0007】[0007]

【課題を解決するための手段】上述の課題を解決するた
めの手段として、請求項1に記載した垂直、水平運搬す
る建物ブロックによる建物の建築工法は、先行して構築
した建物の下層階部分の中央に位置し同下層階部分の本
設柱を利用して垂直に昇降する昇降架台を、建物ブロッ
クの組立て作業ヤードレベルにおいて組立て、更に該昇
降架台の上面部を水平移動する横スライド架台を設置す
る段階と、前記横スライド架台の上に、作業ヤードで地
組みした少なくとも一層分の建物ブロックを載せる段階
と、前記昇降架台を当該建物ブロックの取付け階の高さ
位置まで上昇させ、次いで取付け位置までは横スライド
架台を利用して水平移動させる段階と、水平移動させた
建物ブロックを既設の下層階部分の上に積み重ねてセッ
トする段階と、前記横スライド架台を昇降架台上へ戻
し、昇降架台は当初の作業ヤードレベルまで下降させ、
作業ヤードで地組みした次の建物ブロックを前記横スラ
イド架台上へ載せ、以下同様の工程を繰り返して建物の
建築を進めることを特徴とする。
[Means for Solving the Problems] As a means for solving the above-mentioned problems, the construction method of a building by vertically and horizontally carrying building blocks according to claim 1 is a lower floor part of a building constructed in advance. At the center of the building, a vertical elevating pedestal using the main pillars of the lower floor is vertically assembled at the building block assembly work yard level, and a horizontal slide pedestal that horizontally moves the upper surface of the elevating pedestal is installed. Installing, mounting at least one layer of building block grounded in a working yard on the horizontal slide base, raising the elevating base to a height position of the installation floor of the building block, and then mounting To the position, move horizontally using a horizontal slide stand, and set the horizontally moved building blocks by stacking them on the existing lower floors. Return the horizontal slide frame on the lifting frame, the lifting frame is lowered to the original work yard level,
The next building block grounded in the working yard is placed on the horizontal slide stand, and the same steps are repeated thereafter to proceed with building construction.

【0008】前記請求項1に記載した昇降架台は、ツイ
ンタワーの中間部、又は吹抜け、中庭を持つような建物
のセンターコアホールを昇降させる。前記請求項1に記
載した建物ブロックは、少なくとも四隅の位置に本設の
鉄骨柱を備え、鉄骨建方及び内装、外装仕上げの大部分
を完成してあり、下層階部分に対するセットは上下の本
設柱の継ぎ足し接合によって行う。
The elevator platform according to the first aspect elevates and lowers the center part of the twin tower, or the center core hall of a building having an atrium or a courtyard. The building block according to claim 1 is provided with steel columns that are permanently installed at least at the four corners, and most of the steel frame construction, interior and exterior finishes are completed, and the set for the lower floor part is the upper and lower books. This is done by adding and joining the columns.

【0009】前記請求項1又は3に記載した建物ブロッ
クは、予めその上部に次上位の建物ブロックを水平運搬
するための横行レールを具備しており、使用済となった
横行レールはその後撤去して利用する。
The building block according to claim 1 or 3 is provided with a traverse rail for horizontally transporting the next higher building block in the upper portion in advance, and the traverse rail that has been used is then removed. To use.

【0010】[0010]

【作用】建物ブロックの組立て作業ヤードは、地上レベ
ル又は建物の屋上部分であってツインタワーの最下部
(足元)のレベル(基準階レベル)に設定され、この作
業ヤードで建物ブロックは約90%以上の完成度、例え
ば積み重ねたセット部分の仕上げを残すぐらいの完成度
に地組みされる。
[Operation] The building block assembly work yard is set at the ground level or the rooftop part of the building at the lowest level (foot level) of the twin tower (standard floor level), and the building block is approximately 90% in this work yard. It is grounded to the above-mentioned degree of perfection, for example, the degree of perfection that leaves the finishing of the stacked set parts.

【0011】昇降架台は、その上面部のスライド架台上
に載せた建物ブロックを、その組立て作業ヤードレベル
から取付け階まで既設の下層階部分の本設柱を反力支柱
に利用して垂直運搬する。取付け階のレベルでは、横ス
ライド架台が水平移動して建物ブロックをその取付け位
置へ水平運搬する。横スライド架台が昇降架台上から出
て取付け位置まで水平移動するための横行レールは予め
直下階の建物ブロックに付設される。横スライド架台
は、建物ブロックにおける鉄骨柱の下部を側方から支持
しており、取付け位置に到達した建物ブロックは下層階
部分の上に本設の鉄骨柱同士を継ぎ足す形に積み重ね、
上下の鉄骨柱の接合によってセットが行われる。横スラ
イド架台は当該建物ブロックとの連結を解いて昇降架台
の上に戻される。その後、昇降架台は組立て作業ヤード
レベルまで下降し、その間に地組みされた次の建物ブロ
ックが横スライド架台の上へ載せられる。以下、同様の
工程をくり返すことにより、所望高さの高層建物が建物
ブロックを順次積み重ねる積み木細工の要領で構築され
るのである。
The elevator platform vertically transports the building block placed on the slide platform on the upper surface of the building block from the assembly work yard level to the installation floor by utilizing the existing main column of the lower floor as the reaction column. . At the level of the mounting floor, the horizontal slide cradle moves horizontally to horizontally transport the building block to its mounting position. A traverse rail for the horizontal slide stand to move out of the elevating stand and move horizontally to the mounting position is attached to the building block on the floor directly below. The horizontal slide frame supports the lower part of the steel column in the building block from the side, and the building block reaching the mounting position is stacked on top of the lower floor part in such a way that the steel columns of the main building are added together,
The setting is done by joining the upper and lower steel columns. The horizontal slide base is released from the connection with the building block and returned to the elevator base. After that, the elevating platform is lowered to the level of the assembly work yard, during which the next building block erected in the ground is placed on the lateral slide platform. Hereinafter, by repeating the same steps, a high-rise building having a desired height is constructed in the manner of building blocks in which building blocks are sequentially stacked.

【0012】[0012]

【実施例】次に、図示した本発明の実施例を説明する。
図1〜図5は本発明の建築工法が実施される場合の枢要
な工程図であり、図6は完成したツインタワーの立面図
を示している。これらの実施例は建物1の屋上に更にツ
インタワー2,2を構築する場合について示している
が、この例の限りではなく、地上レベルから直接ツイン
タワーを建築する場合でも全く同様に施工が進められ
る。更に云えば、ツインタワーの建築に限らず、昇降架
台が垂直に昇降可能な規模のセンターコアホール等を持
つ例えば吹抜け、中庭がある建物の建築にも全く同様に
実施される。
EXAMPLE An example of the present invention shown in the drawings will be described below.
1 to 5 are essential process diagrams when the construction method of the present invention is carried out, and FIG. 6 is an elevation view of a completed twin tower. These examples show the case where the twin towers 2 and 2 are further built on the roof of the building 1, but the present invention is not limited to this example, and even when the twin towers are directly built from the ground level, the construction proceeds in exactly the same manner. To be Furthermore, the present invention is not limited to the construction of a twin tower, and is similarly applied to the construction of a building having a center core hall or the like having a scale capable of vertically moving up and down, such as a building with a colonnade or a courtyard.

【0013】図1は建物1の屋上に、ツインタワーの下
層階部分3として2層分ぐらいを組立てると共に、同ツ
インタワーの中間部に1層分の高さをもつ昇降架台4を
組立て、同昇降架台4の上面部に設置した横スライド架
台5の上に建物ブロック6を載せた段階を示している。
前記下層階部分3の組立て、昇降架台4の組立て、及び
建物ブロック6の組立て、並びに建物ブロック6を横ス
ライド架台5の上へ吊り込む作業は、図示例では建物1
の建築に使用したタワークレーン7を便宜上使用して行
う記載になっている。しかし、組立て作業ヤードが地上
レベルであるときはトラッククレーン、クローラクレー
ンなどが便利に使用される。いずれにしてもツインタワ
ーの構築に伴い盛り替えられて上昇する仮設揚重機は一
切使用しない。建物ブロック6は、前記建物1の屋上に
用意された作業ヤードで、前記タワークレーン7を便宜
的に使用して地組みが行われる。建物ブロック6は、少
なくともツインタワーの1層分を1ブロックとし(図
7、図8参照)、その鉄骨組立て,及び必要によっては
床版の取付け、内装材、外装材などの取付けを行い、9
0%以上の完成度とし、例えばセット時に取合い部の仕
上げを残す程度の完成度とされる。
FIG. 1 shows that two layers of lower floors 3 of a twin tower are assembled on the roof of a building 1, and an elevator platform 4 having a height of one layer is assembled in the middle of the twin tower. The stage in which the building block 6 is placed on the horizontal slide mount 5 installed on the upper surface of the elevating mount 4 is shown.
Assembling the lower floor portion 3, assembling the elevating mount 4, assembling the building block 6, and suspending the building block 6 on the horizontal slide mount 5 are performed in the illustrated example in the building 1
It is described that the tower crane 7 used for the construction is used for convenience. However, truck cranes, crawler cranes, etc. are conveniently used when the assembly work yard is at ground level. In any case, we will not use any temporary lifting machine that will be refilled and raised as the twin tower is constructed. The building block 6 is a working yard prepared on the roof of the building 1, and the tower crane 7 is used for convenience to assemble the building. The building block 6 has at least one layer of the twin tower as one block (see FIG. 7 and FIG. 8), and assembles its steel frame and, if necessary, installs floor slabs, interior materials, exterior materials, etc.
The degree of perfection is 0% or more, and for example, the degree of perfection is such that the finish of the mating portion is left when setting.

【0014】図2は昇降架台4を、その上に載せた建物
ブロック6の取付け階(3階)の高さ位置(3階)まで
上昇させた段階を示している。図3は建物ブロック6を
横スライド架台5と共に水平移動させ、取付け位置へ積
み重ねてセットした段階を示している。昇降架台4は、
既設の下層階鉄骨柱を反力支柱として油圧昇降装置によ
り昇降する構成とされている。具体的には図7、図9、
図10に示したように、上部フレーム4a(作業ステー
ジ)及び下部フレーム4bを垂直なガイドポスト4cと
剛結して階高相当の版状の主要骨格が形成されている。
下部フレーム4bに油圧ジャッキ8が垂直上向きに固定
され、その出力軸8aの先端部は、前記ガイドポスト4
cに沿って昇降する昇降フレーム9と連結されている。
FIG. 2 shows a stage in which the lifting platform 4 is raised to the height position (3rd floor) of the floor (3rd floor) where the building block 6 placed on it is mounted. FIG. 3 shows a stage in which the building blocks 6 are horizontally moved together with the horizontal slide frame 5 and stacked and set at the mounting position. The lifting platform 4
The existing lower-floor steel frame columns are used as reaction columns to be lifted and lowered by a hydraulic lifting device. Specifically, FIG. 7, FIG.
As shown in FIG. 10, the upper frame 4a (work stage) and the lower frame 4b are rigidly connected to the vertical guide posts 4c to form a plate-shaped main skeleton corresponding to the floor height.
The hydraulic jack 8 is fixed vertically upward to the lower frame 4b, and the tip of the output shaft 8a of the hydraulic jack 8 is fixed to the guide post 4
It is connected to an elevating frame 9 which ascends and descends along c.

【0015】既設の下層階鉄骨柱を反力支柱として利用
するため、昇降架台4と対面する鉄骨柱10の側面に
は、その全長にわたり、図9に示したように、上下方向
に例えば800mm位のピッチPで反力ブラケット11が
設けられている。反力ブラケットの高さ寸法は170mm
ぐらいである。この反力ブラケット11は厚鋼板をT字
形に溶接した構成で、図11のように、鉄骨柱10の側
面に300mmぐらいの間隔をあけて平行に並べた2個を
一組とし、各々のT脚部が溶接で鉄骨柱へ取付けられて
いる。一方、昇降架台4において前記鉄骨柱10との取
合い部分は、上部フレーム4a及び下部フレーム4bに
関してそれぞれ共通な構成とされ、それは図11に示し
たように、鉄骨柱10の外側面を伝い走る振れ止めロー
ラ12、及び前記2個の反力ブラケット11,11の内
外を垂直方向に通過する3個を一組とするずれ止めブラ
ケット13を設けた構成とされている。更に図12に示
したように鉄骨柱10の直角2側面を伝って走行する2
個を一組とするガイドローラ14,14が設けられてい
る。次に昇降フレーム9と鉄骨柱10との取合い部分
は、図13に示したように、反力ブラケット11,11
の内外を垂直方向に通過する3個を一組とするずれ止め
ブラケット13が設けられ、更にガイドポスト4cの直
角3側面を伝って走行する3個のガイドローラ15が設
けられている。同じ昇降フレーム9の下面側であって前
記油圧ジャッキ8の位置とはガイドポストを間に挾んで
正反対側の位置には、図9に示したように、反力受けロ
ーラ16が設けられている。
Since the existing lower-floor steel-framed columns are used as reaction columns, the side face of the steel-framed column 10 facing the elevating stand 4 has its entire length, and as shown in FIG. The reaction force brackets 11 are provided at the pitch P of. Height of reaction bracket is 170mm
It's about. The reaction force bracket 11 is composed of thick steel plates welded into a T shape. As shown in FIG. 11, a pair of two steel plates are arranged in parallel on the side surface of the steel frame column 10 at intervals of about 300 mm. The legs are welded to the steel column. On the other hand, the portion of the elevating frame 4 that engages with the steel column 10 has a common structure for the upper frame 4a and the lower frame 4b, and as shown in FIG. The stopper roller 12 and the anti-slip bracket 13 that is a set of three rollers that vertically pass through the inside and the outside of the two reaction force brackets 11 and 11 are provided. Further, as shown in FIG. 12, the steel frame column 10 travels along two side faces at right angles 2
Guide rollers 14, 14 are provided as a set. Next, as shown in FIG. 13, the mating portion between the elevating frame 9 and the steel column 10 has reaction force brackets 11, 11
A pair of shift stopper brackets 13 that vertically pass through the inside and the outside of the guide post 13 are provided, and further three guide rollers 15 that travel along the three right side surfaces of the guide post 4c are provided. As shown in FIG. 9, a reaction force receiving roller 16 is provided at the position on the lower surface side of the same lifting frame 9 and on the side opposite to the position of the hydraulic jack 8 with the guide post in between. .

【0016】次に、昇降架台4が前記油圧ジャッキ8の
働きにより、前記鉄骨柱10の反力ブラケット11を利
用して昇降するための手段として、図9に示したように
前記昇降フレーム9において油圧ジャッキの出力軸8a
が連結された位置、及び前記下部フレーム4bにおいて
油圧ジャッキ8の本体の取付け位置の直下に、前記反力
ブラケット11の上に乗り降りする反力レバー17,1
8が設置されている。各反力レバー17,18は、水平
な取付けピン19を中心として水平姿勢を回転限度(突
き当り限度位置)として垂直方向の下方へ約60°ぐら
い回動可能に設置され、各々空圧ジャッキ20により回
動されるようになっている。反力レバー17,18の取
付け配置は、図14に示したように、鉄骨柱10の前記
2個を一組とする反力ブラケット11,11の真上に平
行な配置で乗り降りする2個を一組の構成とされてい
る。
Next, as shown in FIG. 9, in the elevating frame 9, as a means for elevating the elevating base 4 by the action of the hydraulic jack 8 using the reaction force bracket 11 of the steel column 10. Output shaft 8a of hydraulic jack
Of the reaction levers 17 and 1 for getting on and off the reaction force bracket 11 immediately below the position where the main body of the hydraulic jack 8 is attached to the lower frame 4b.
8 are installed. The respective reaction levers 17 and 18 are installed so as to be rotatable about a horizontal position about a rotation limit (abutting limit position) about 60 ° in the vertical direction about a horizontal mounting pin 19, and each of them is driven by a pneumatic jack 20. It is designed to be rotated. As shown in FIG. 14, the reaction levers 17 and 18 are mounted so that the two reaction brackets 11 and 11 are mounted in parallel with each other in parallel with the reaction brackets 11 and 11, which are a set of the two steel pillars 10. It is composed of a set.

【0017】昇降架台4の昇降は、図15〜図17にそ
れぞれ示した要領と手順で行われる。図15Aでは下部
フレーム4b側の反力レバー18が反力ブラケット11
の上に乗り反力をとった状態で、油圧ジャッキ8の出力
軸8aが伸長動作を開始し、昇降フレーム9側の反力レ
バー17は上方の反力ブラケット11を通過するのに支
障ない位置まで斜め下向きの姿勢に回動されている。図
15Bでは油圧ジャッキ8の出力軸8aの伸長ストロー
クが次上位の反力ブラケット11の位置を少し超え、昇
降フレーム9側の反力レバー17を水平な反力受け姿勢
に戻した状態を示している。図16Aでは出力軸8aを
少し下降させ、昇降フレーム9側の反力レバー17を次
上位の反力ブラケット11の上に乗せて反力をとる状態
になったことを示している。図16Bは昇降フレーム9
側の反力レバー17が次上位の反力ブラケット11に反
力をとって油圧ジャッキ8が少し収縮動作をし、下部フ
レーム4b側の反力レバー18が反力ブラケット11か
ら浮上し荷重の盛り替えが行われ、同反力レバー18は
次上位の反力ブラケットを通過するのに支障ない位置ま
で斜め下向きに回動された状態を示している。図17A
は下部フレーム4b側の反力レバー18が次上位の反力
ブラケット11の位置を少し超えるまで油圧ジャッキ8
の収縮動作が進み、同反力レバー18は水平な反力受け
姿勢に戻された状態を示している。図17Bは油圧ジャ
ッキ8を少し伸長動作させて下部フレーム4b側の反力
レバー18が次上位の反力ブラケット11の上に乗り、
反力をとり得る状態になったことを示している。この状
態から油圧ジャッキ8の出力軸8aを伸長動作させる
と、昇降フレーム9側の反力レバー17が反力ブラケッ
ト11から浮上して荷重の盛り替えが行われ、図15A
の状態に回帰し、昇降架台4は1ピッチの上昇サイクル
を遂行したことになる。以下、同様な工程をくり返して
所謂イモ虫の如き動作で昇降架台4は上昇動作する。逆
に、下降する動作は、正反対の手順と工程で行われる。
The raising and lowering of the raising and lowering stand 4 is performed by the procedure and procedure shown in FIGS. 15 to 17, respectively. In FIG. 15A, the reaction force lever 18 on the lower frame 4b side is the reaction force bracket 11
At a position where the output shaft 8a of the hydraulic jack 8 starts to extend and the reaction lever 17 on the elevating frame 9 side passes through the reaction bracket 11 on the upper side while the reaction force is riding on It has been rotated diagonally downward. FIG. 15B shows a state in which the extension stroke of the output shaft 8a of the hydraulic jack 8 slightly exceeds the position of the next upper reaction force bracket 11, and the reaction force lever 17 on the lifting frame 9 side is returned to the horizontal reaction force receiving posture. There is. FIG. 16A shows that the output shaft 8a is slightly lowered and the reaction lever 17 on the elevating frame 9 side is placed on the next upper reaction force bracket 11 to take a reaction force. FIG. 16B shows the lifting frame 9
Side reaction lever 17 takes a reaction force to the next upper reaction force bracket 11, the hydraulic jack 8 contracts a little, and the reaction force lever 18 on the lower frame 4b side floats up from the reaction force bracket 11 to balance the load. After the replacement, the reaction force lever 18 is in a state of being rotated obliquely downward to a position where it does not hinder the passage of the next higher reaction force bracket. FIG. 17A
Is the hydraulic jack 8 until the reaction lever 18 on the lower frame 4b side slightly exceeds the position of the next upper reaction force bracket 11.
The contraction operation of 1 is advanced, and the reaction lever 18 is returned to the horizontal reaction force receiving posture. In FIG. 17B, the hydraulic jack 8 is slightly extended so that the reaction lever 18 on the lower frame 4b side rides on the next upper reaction bracket 11.
It shows that the reaction force is ready. When the output shaft 8a of the hydraulic jack 8 is extended from this state, the reaction force lever 17 on the elevating frame 9 side levitates from the reaction force bracket 11 and the load is rescaled.
Returning to the above condition, the elevating platform 4 has executed the ascending cycle of 1 pitch. After that, the same steps are repeated, and the elevating platform 4 moves up by an operation like a so-called caterpillar. On the contrary, the descending operation is performed by the opposite procedure and process.

【0018】以上に述べた油圧昇降装置の働きで昇降架
台4を昇降動作させるために、昇降架台4には、図9に
示したように、油圧ジャッキ用の電動油圧ポンプ21と
バルブユニット22、反力レバー回動用の空圧ジャッキ
20のためのエアコンプレッサー23とバルブユニット
24、並び前記各要素の操作盤25が各々搭載されてい
る。そして、前記各要素の運転状態を計測し管理するモ
ニター装置26が作業ヤードに設置されている。原則的
に昇降架台4の昇降動作時には人は乗らず、昇降架台4
の昇降はモニター装置26を通じて遠隔制御する。
In order to raise and lower the lifting platform 4 by the action of the hydraulic lifting device described above, the lifting platform 4 has an electric hydraulic pump 21 for a hydraulic jack and a valve unit 22, as shown in FIG. An air compressor 23 and a valve unit 24 for the pneumatic jack 20 for rotating the reaction lever, and an operation panel 25 for each of the above elements are mounted. A monitor device 26 that measures and manages the operating state of each element is installed in the work yard. As a general rule, no person rides during the lifting operation of the lifting platform 4,
Lifting and lowering is controlled remotely through the monitor device 26.

【0019】なお、昇降架台4に前記の油圧昇降装置を
採用した理由は、油圧制御により昇降架台4の水平度、
高さ位置(昇降量)の調整(精度出し)が容易である
し、油圧ジャッキ8に油圧センサーを付設することによ
って負荷の大きさの確認、そして、過大な荷重に対して
安全装置を働かせる措置が容易だからである。従って、
同様な調整と安全装置の働きを確保できるときは、公
知、周知のラックピニオン機構その他の昇降装置を採用
し実施することができる。
The reason why the above-mentioned hydraulic lifting device is adopted for the lift base 4 is that the level of the lift base 4 is controlled by hydraulic control.
It is easy to adjust the height position (up and down amount) (accuracy), and to attach a hydraulic sensor to the hydraulic jack 8 to check the size of the load and to activate the safety device against an excessive load. Is easy. Therefore,
When the same adjustment and the function of the safety device can be ensured, a well-known and well-known rack and pinion mechanism or other lifting device can be adopted and implemented.

【0020】次に、横スライド架台5について述べる。
図7で概略構造を理解できるように、横スライド架台5
は、上述した昇降架台4の上面部に水平な横行レール3
0を敷設し、該横行レール30の上面を転がるローラ
(ヒルマンローラ)31によって水平移動するように構
成されている。更に詳細な構造は図10に示したよう
に、横スライド架台5を構成する鉄骨5aのフランジ下
面部にローラ31が取付けられ、直下の横行レール3
0’の上面を転がるものとされている。鉄骨5aのフラ
ンジ下面部にはまた、横行レール30’の上フランジを
両側から抱える形状の浮き上り防止板32,32が左右
対称な配置に設けられ、更に上フランジの両外縁に当る
横ずれ防止ローラ33,33も設けられている。
Next, the horizontal slide mount 5 will be described.
In order to understand the schematic structure in FIG.
Is a horizontal traverse rail 3 which is horizontal to the upper surface of the above-mentioned lifting platform 4.
0 is laid, and is horizontally moved by a roller (Hillman roller) 31 rolling on the upper surface of the traverse rail 30. As for a more detailed structure, as shown in FIG. 10, the roller 31 is attached to the lower surface of the flange of the steel frame 5a constituting the horizontal slide base 5, and the traverse rail 3 immediately below is mounted.
It is supposed to roll on the upper surface of 0 '. On the lower surface of the flange of the steel frame 5a, lift preventing plates 32 and 32 having a shape holding the upper flange of the traverse rail 30 'from both sides are provided in a symmetrical arrangement, and a lateral deviation preventing roller that contacts both outer edges of the upper flange. 33, 33 are also provided.

【0021】当該横スライド架台5の上に載せる建物ブ
ロック6は、少なくとも四隅の本設の鉄骨柱10の下部
に、下層階3の鉄骨柱10との継ぎ足し(ボルト接合)
用として用意されたガゼットプレート34の一つを、前
記鉄骨5aから斜め上向きに外方へ突き出る形状に設け
た支持プレート35と当て板36を介してボルト接合し
た状態で支持される。そして、建物ブロック6を取付け
階の取付け位置まで横スライド架台5で水平移動させ積
み重ねるセッティング処理は、やはり図10に示してい
るように、まず既設の下層階部分3の鉄骨柱10の上に
当該建物ブロック6の鉄骨柱10を継ぎ足す形に積み重
ねる。その前提として、建物ブロック6の鉄骨柱10の
下端面は、下層階の鉄骨柱の上端面とほぼ一致する(実
際には建物ブロック6の鉄骨柱10の下面は、2〜3mm
程度高い)程度の水平レベル精度を確保した水平移動が
行われるように、横行レール30,30’の取付け、及
び横スライド架台5の水平レベル出しが行われている。
従って、必要に応じてジャッキアップ装置なども採用さ
れる。下層階部分3の鉄骨柱10の天端には水平な受け
プレート37が設けられており、該受けプレート37上
へ建物ブロック6の鉄骨柱10の下端が同心配置に載せ
られ継ぎ足される。その後ガゼットプレート34と前記
支持プレート35との接合を解き、横スライド架台5は
速やかに昇降架台4の上面位置まで戻す。また、上下の
鉄骨柱10,10は各々のガゼットプレート34,34
間に当板38を添えハイテンションボルトを締付けて接
合しセッティングが行われる。
The building block 6 placed on the lateral slide base 5 is added (bolted) to the steel columns 10 of the lower floor 3 at least at the lower portions of the main steel columns 10 at the four corners.
One of the gusset plates 34 prepared for use is supported in a bolted state via a support plate 35 and a contact plate 36 which are provided in a shape protruding obliquely upward from the steel frame 5a. Then, as shown in FIG. 10, the setting process of horizontally moving the building blocks 6 to the mounting position on the mounting floor by the horizontal slide base 5 and stacking them is first performed on the steel column 10 of the existing lower floor portion 3. The steel columns 10 of the building block 6 are piled up in such a form that they are added together. As a premise, the lower end surface of the steel column 10 of the building block 6 substantially coincides with the upper end surface of the steel column of the lower floor (actually, the lower surface of the steel column 10 of the building block 6 is 2 to 3 mm.
The horizontal rails 30 and 30 ′ are attached and the horizontal level of the horizontal slide base 5 is set so that the horizontal movement can be performed while ensuring the horizontal level accuracy of a high level.
Therefore, a jack-up device or the like is also adopted as needed. A horizontal receiving plate 37 is provided at the top end of the steel frame column 10 of the lower floor portion 3, and the lower end of the steel frame column 10 of the building block 6 is placed on the receiving plate 37 in a concentric arrangement and added thereto. After that, the joint between the gusset plate 34 and the support plate 35 is released, and the horizontal slide base 5 is quickly returned to the upper surface position of the elevating base 4. In addition, the upper and lower steel frame columns 10, 10 are respectively provided with the gusset plates 34, 34.
A plate 38 is attached between them, and high tension bolts are tightened to join them for setting.

【0022】なお、図10中の横行レール30’は、横
スライド架台5を昇降架台4上の位置から取付け位置ま
で水平移動させるために既設の下層階部分3の鉄骨柱1
0(従って、各建物ブロック6の鉄骨柱10)の上部に
予め地組み作業の一つとして取付けておいた延長用レー
ルであり、取付け階の高さ位置まで上昇した昇降架台4
の上面部の横行レール30と必ず同一レベルとなるよう
に考慮してその延長線上の位置に設けられている。該延
長用の横行レール30’は、下層階部分の鉄骨柱10へ
溶接で固定したブラケット39へ横向きの支持腕40を
突き合せ、当て板41を介してボルト接合することによ
り取付けられている。従って、建物ブロック6のセッテ
ィングを終り、横スライド架台5が昇降架台4上の位置
に戻され、用済みとなった横行レール30’は、前記ブ
ラケット39と支持腕40との接合を解いて撤去され、
必要に応じて次の建物ブロックに利用される。
The traverse rail 30 'shown in FIG. 10 is a steel column 1 of the existing lower floor portion 3 in order to horizontally move the lateral slide mount 5 from the position on the elevating mount 4 to the mounting position.
0 (hence, the steel pillars 10 of each building block 6) is an extension rail that has been installed in advance as one of the groundwork operations, and has been lifted to the height of the installation floor.
It is provided at a position on the extension line in consideration of being always at the same level as that of the traverse rail 30 on the upper surface portion. The transverse rail 30 'for extension is attached by abutting a lateral support arm 40 on a bracket 39 fixed to the steel column 10 of the lower floor by welding, and by bolting it through a contact plate 41. Therefore, after the setting of the building block 6 is completed, the horizontal slide base 5 is returned to the position on the elevating base 4, and the used horizontal rail 30 ′ is removed by unbonding the bracket 39 and the support arm 40. Is
It will be used for the next building block as required.

【0023】建物ブロック6を載せた横スライド架台5
の水平移動に際しては、図8に示したように、横スライ
ド架台5の移動方向に水平な引きワイヤ42と押えワイ
ヤ43とを前後に連結し、引きワイヤ42をウインチ等
により引いて横スライド架台5を前進させる。他方、押
えワイヤ43には適度な張力を付与して建物ブロック6
がオーバーランを生じないように注意深く移動させる。
横スライド架台5の水平移動は、前記引きワイヤ42等
を利用した機構のほか、電動式、油圧又は空圧式、ある
いは手動式等々が適宜採用される。
A horizontal slide stand 5 on which a building block 6 is placed
When moving horizontally, as shown in FIG. 8, the pulling wire 42 and the presser wire 43, which are horizontal in the moving direction of the horizontal slide base 5, are connected back and forth, and the pulling wire 42 is pulled by a winch or the like to pull out the horizontal slide base. Move 5 forward. On the other hand, a proper tension is applied to the presser wire 43 so that the building block 6
Move carefully to avoid overruns.
For horizontal movement of the horizontal slide base 5, in addition to the mechanism using the pulling wire 42 and the like, an electric type, a hydraulic or pneumatic type, or a manual type is appropriately adopted.

【0024】図7及び図8で明らかなように、地組みし
た建物ブロック6には、上記の横行レール30’が付設
されるほか、上下の鉄骨柱の接合作業、その他の取合い
部分の仕上げ作業の安全を期すため、外周部分に作業足
場44が付設されている。図7と図8の例では、建物ブ
ロック6の平面形状の大きさは桁行方向が約12m、梁
間方向が約6.4mぐらいとされている。
As is apparent from FIGS. 7 and 8, the above-mentioned traverse rail 30 'is attached to the grounded building block 6, and the joining work of the upper and lower steel frame columns and the finishing work of other connecting parts are performed. For the sake of safety, a work scaffold 44 is attached to the outer peripheral portion. In the example of FIGS. 7 and 8, the planar shape of the building block 6 is about 12 m in the column direction and about 6.4 m in the beam-to-beam direction.

【0025】かくして、本発明の建築工法は、組立て作
業ヤードレベルで地組みした完成度の高い建物ブロック
6を昇降架台4の横スライド架台5上に載せ(図4)、
同昇降架台4により取付け階まで垂直運搬し(図5)、
取付け階においては横スライド架台5を利用して取付け
位置まで水平移動させ、取付け位置に到達した建物ブロ
ックは直下の下層階部分の上に各本設柱(鉄骨柱10)
を継ぎ足す形に積み重ね、鉄骨柱10,10同士を接合
しセットする作業をくり返して所望の高さまで建築を進
める。図6に示した完成状態は、前記昇降架台4を最終
的にツインタワー2,2の間の屋上2階部分の構築に躯
体の一部として転用し、タワークレーンを解体した状態
を示している。
Thus, according to the construction method of the present invention, the building block 6 having a high degree of completion assembled at the assembly work yard level is placed on the horizontal slide mount 5 of the elevating mount 4 (FIG. 4),
It is vertically transported to the installation floor by the lifting platform 4 (Fig. 5).
On the installation floor, the horizontal slide pedestal 5 is used to horizontally move to the installation position, and the building block that has reached the installation position is the main pillars (steel pillars 10) on the lower floors directly below.
Are piled up in the form of replenishment, and the work of joining and setting the steel frame columns 10 and 10 is repeated to proceed with the construction to the desired height. The completed state shown in FIG. 6 shows a state in which the elevator cradle 4 is finally diverted as a part of the skeleton to construct the rooftop second floor portion between the twin towers 2 and 2, and the tower crane is disassembled. .

【0026】[0026]

【本発明が奏する効果】本発明の建築工法は、仮設揚重
機としてのタワークレーン等を一切使用しないから、タ
ワークレーンのマストを最上階まで伸ばす必要がなく、
クレーン取合い部の構造補強の必要がない。また、クレ
ーンを最上階まで伸ばすと、クレーンの解体時期が遅
れ、その結果クレーン廻りの残工事が多数発生し、仕上
げ工程が遅れる等々の問題も一挙に解決する。
EFFECTS OF THE INVENTION Since the construction method of the present invention does not use any tower crane or the like as a temporary lifting machine, it is not necessary to extend the mast of the tower crane to the top floor,
There is no need to reinforce the crane interface. Moreover, when the crane is extended to the top floor, the dismantling time of the crane is delayed, and as a result, a lot of residual work around the crane occurs, and the finishing process is delayed.

【0027】次に、地上その他の基準階レベルに設定し
た組立て作業ヤードで建物ブロックの完成度の高い地組
みを行い、これを垂直、水平運搬して順次積み重ねてセ
ットする工程をくり返すだけであるから、高所での作業
が大幅に低減し、安全性の向上に極めて有利となる。ま
た、外周足場を全面に架ける必要がなくなるため仮設作
業、仮設資材の使用量が大幅に減る利点も大きい。
Then, the building blocks with a high degree of perfection are constructed in an assembly work yard set on the ground or other standard floor level, and the steps of vertically and horizontally transporting and sequentially stacking and setting the building blocks are repeated. Therefore, work at a high place is significantly reduced, which is extremely advantageous for improving safety. Further, since it is not necessary to span the outer peripheral scaffold, the temporary work and the amount of temporary materials used can be greatly reduced.

【0028】従って、本発明の工法を採用することによ
り工期の大幅な短縮が図れる。
Therefore, the construction period can be greatly shortened by adopting the construction method of the present invention.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明の建築工法を建物屋上のツインタワーの
建築に実施する初期段階を簡単に示した立面図である。
FIG. 1 is an elevational view briefly showing an initial stage of implementing the building method of the present invention for building a twin tower on a rooftop of a building.

【図2】3層目の建物ブロックを取付け階まで垂直運搬
した状態の立面図である。
FIG. 2 is an elevational view showing a state where a third-layer building block is vertically transported to an installation floor.

【図3】3層目の建物ブロックを取付け位置へ水平運搬
した状態の立面図である。
FIG. 3 is an elevational view showing a state where a third-layer building block is horizontally transported to a mounting position.

【図4】8層目の建物ブロックを昇降架台へ載せた状態
の立面図である。
FIG. 4 is an elevational view showing a state in which an 8th-layer building block is placed on an elevator platform.

【図5】8層目の建物ブロックを取付け階において取付
け位置へ水平移動した状態の立面図である。
FIG. 5 is an elevational view showing a state where the eighth-layer building block is horizontally moved to the installation position on the installation floor.

【図6】完成したツインタワーの立面図である。FIG. 6 is an elevation view of the completed twin tower.

【図7】建物ブロックを取付け階まで垂直運搬した後、
取付け位置まで水平運搬する要領を具体的に示した立面
図である。
[Fig. 7] After the building blocks are vertically transported to the installation floor,
FIG. 7 is an elevational view specifically showing a procedure for horizontally transporting to a mounting position.

【図8】図7の平面図である。FIG. 8 is a plan view of FIG.

【図9】昇降架台と鉄骨柱との取合い部分を詳示した立
面図である。
FIG. 9 is an elevational view showing in detail the connecting portion between the lifting platform and the steel frame column.

【図10】横スライド架台と横行レール及び鉄骨柱の取
合い部分の構造を詳示した立面図である。
FIG. 10 is an elevational view showing in detail the structure of the connecting portion of the horizontal slide mount, the transverse rail, and the steel frame column.

【図11】図9のA矢視図である。11 is a view on arrow A in FIG. 9. FIG.

【図12】図9のB矢視図である。FIG. 12 is a view on arrow B of FIG. 9.

【図13】図9のC矢視図である。FIG. 13 is a view on arrow C of FIG. 9.

【図14】図9のD矢視図である。14 is a view on arrow D in FIG. 9. FIG.

【図15】A,Bは油圧ジャッキが伸長する昇降フレー
ムの上昇工程を示した立面図である。
15A and 15B are elevation views showing a lifting process of the lifting frame in which the hydraulic jack extends.

【図16】A,Bは昇降フレームの反力レバーが反力ブ
ラケットに乗って反力をとり、下部フレームの反力カバ
ーが浮上して荷重が盛り替えられる段階を示した立面図
である。
16A and 16B are elevation views showing a stage in which the reaction force lever of the elevating frame rides on the reaction force bracket to take a reaction force, and the reaction force cover of the lower frame floats to rebalance the load. .

【図17】A,Bは下部フレームの反力レバーが反力ブ
ラケットに乗って反力をとるまでの段階を示した立面図
である。
17A and 17B are elevation views showing a stage in which the reaction force lever of the lower frame rides on the reaction force bracket and takes a reaction force.

【符号の説明】[Explanation of symbols]

3 下層階部分 10 本設柱(鉄骨柱) 4 昇降動作 6 建物ブロック 30 横行レール 5 横スライド架台 30’ 横行レール 3 Lower floor part 10 Permanent pillar (steel frame pillar) 4 Lifting operation 6 Building block 30 Traverse rail 5 Traverse slide stand 30 'Traverse rail

───────────────────────────────────────────────────── フロントページの続き (72)発明者 浅野 三男 名古屋市中区錦一丁目18番22号 株式会社 竹中工務店名古屋支店内 (72)発明者 藤井 卓美 千葉県印旛郡印西町大塚一丁目5番 株式 会社竹中工務店技術研究所内 (72)発明者 山田 実男 名古屋市中区錦一丁目18番22号 株式会社 竹中工務店名古屋支店内 (72)発明者 中島 眞 名古屋市中区錦一丁目18番22号 株式会社 竹中工務店名古屋支店内 (72)発明者 宮口 幹太 名古屋市中区錦一丁目18番22号 株式会社 竹中工務店名古屋支店内 ─────────────────────────────────────────────────── ─── Continued Front Page (72) Inventor Mitsuo Asano 1-18-22 Nishiki, Naka-ku, Nagoya City Takenaka Corporation Nagoya Branch (72) Inventor Takumi Fujii 1-5 Otsuka, Inzai-cho, Inba-gun, Chiba Prefecture No. 18 Incorporated Takenaka Corporation Technical Research Institute (72) Inventor Mio Yamada 1-18-22 Nishiki, Naka-ku, Nagoya City Takenaka Corporation Nagoya Branch (72) Inventor Makoto Nakajima Nishiki 1-chome, Naka-ku, Nagoya 18-22 No. 22 Takenaka Corporation Nagoya Branch (72) Inventor Mitsuta Miyaguchi 1-18-22 Nishiki, Naka-ku, Nagoya City Takenaka Corporation Nagoya Branch

Claims (4)

【特許請求の範囲】[Claims] 【請求項1】 先行して構築した建物の下層階部分の中
央に位置し同下層階部分の本設柱を利用して垂直に昇降
する昇降架台を、建物ブロックの組立て作業ヤードレベ
ルにおいて組立て、更に該昇降架台の上面部を水平移動
する横スライド架台を設置する段階と、 前記横スライド架台の上に、作業ヤードで地組みした少
なくとも一層分の建物ブロックを載せる段階と、 前記昇降架台を当該建物ブロックの取付け階の高さ位置
まで上昇させ、次いで取付け位置までは横スライド架台
を利用して水平移動させる段階と、 水平移動させた建物ブロックを既設の下層階部分の上に
積み重ねてセットする段階と、 前記横スライド架台を昇降架台上へ戻し、昇降架台は当
初の作業ヤードレベルまで下降させ、作業ヤードで地組
みした次の建物ブロックを前記横スライド架台上へ載
せ、以下同様の工程を繰り返して建物の建築を進めるこ
とを特徴とする、垂直、水平運搬する建物ブロックによ
る建物の建築工法。
1. An ascending / descending platform which is located in the center of a lower floor portion of a building constructed in advance and which vertically elevates and lowers using a main pillar of the lower floor portion is assembled at a building block assembly work yard level, Further, a step of installing a horizontal slide base that horizontally moves the upper surface of the elevator base, a step of mounting a building block for at least one layer grounded in a working yard on the horizontal slide base, and the elevator base Raise the building block to the height of the installation floor and then move horizontally to the installation position using a horizontal slide stand, and stack the horizontally moved building blocks on top of the existing lower floors. And the horizontal slide base is returned to the elevator base, the elevator base is lowered to the original work yard level, and the next building block grounded in the work yard is removed. Loaded onto Kiyoko slide frame, characterized in that advancing the architecture of the building by repeating the same process following vertical, construction methods the building by the building block for horizontal movement.
【請求項2】 請求項1に記載した昇降架台は、ツイン
タワーの中間部、又は吹抜け、中庭を持つような建物の
センターコアホールを昇降させることを特徴とする、垂
直、水平運搬する建物ブロックによる建物の建築工法。
2. The building block for vertical and horizontal transportation, characterized in that the elevating platform according to claim 1 elevates and lowers a center core hole of a building having a twin tower, a central part of a twin tower, a stairwell, or a courtyard. Building construction method by.
【請求項3】 請求項1に記載した建物ブロックは、少
なくとも四隅の位置に本設の鉄骨柱を備え、鉄骨建方及
び内装、外装仕上げの大部分を完成してあり、下層階部
分に対するセットは上下の本設柱の継ぎ足し接合によっ
て行うことを特徴とする、垂直、水平運搬する建物ブロ
ックによる建物の建築工法。
3. The building block according to claim 1 is provided with main steel columns at least at four corners, and most of the steel frame construction, interior and exterior finishes are completed, and the building block is set for the lower floors. Is a construction method of a building with vertically and horizontally transported building blocks, which is characterized by adding and joining main columns above and below.
【請求項4】 請求項1又は3に記載した建物ブロック
は、予めその上部に次上位の建物ブロックを水平運搬す
るための横行レールを具備しており、使用済となった横
行レールはその後撤去して利用する、垂直、水平運搬す
る建物ブロックによる建物の建築工法。
4. The building block according to claim 1 or 3 is previously provided with a traverse rail for horizontally transporting the next higher building block on the upper part thereof, and the traverse rail that has been used is then removed. The construction method of the building by the building block that is used vertically and horizontally.
JP14091795A 1995-06-07 1995-06-07 Building method of building unit for vertical and horizontal conveying Pending JPH08333813A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP14091795A JPH08333813A (en) 1995-06-07 1995-06-07 Building method of building unit for vertical and horizontal conveying

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP14091795A JPH08333813A (en) 1995-06-07 1995-06-07 Building method of building unit for vertical and horizontal conveying

Publications (1)

Publication Number Publication Date
JPH08333813A true JPH08333813A (en) 1996-12-17

Family

ID=15279829

Family Applications (1)

Application Number Title Priority Date Filing Date
JP14091795A Pending JPH08333813A (en) 1995-06-07 1995-06-07 Building method of building unit for vertical and horizontal conveying

Country Status (1)

Country Link
JP (1) JPH08333813A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007131453A (en) * 2005-11-11 2007-05-31 Industrial Leasing Corp Climbing crane
CN107288352A (en) * 2016-03-31 2017-10-24 中国二十冶集团有限公司 The transport of the closed shed dormer roof boarding of overlarge area and installation method
JP2018199933A (en) * 2017-05-26 2018-12-20 株式会社巴コーポレーション Structure body and construction method of structure constructed on top of tower-like building
JP2021088883A (en) * 2019-12-05 2021-06-10 株式会社巴コーポレーション Column base portion structure in structure, and column base portion fixing method
CN115506588A (en) * 2022-10-25 2022-12-23 四川路桥桥梁工程有限责任公司 Intelligent integrated lifting support

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007131453A (en) * 2005-11-11 2007-05-31 Industrial Leasing Corp Climbing crane
CN107288352A (en) * 2016-03-31 2017-10-24 中国二十冶集团有限公司 The transport of the closed shed dormer roof boarding of overlarge area and installation method
CN107288352B (en) * 2016-03-31 2019-07-30 中国二十冶集团有限公司 The transport of the closed shed dormer roof boarding of overlarge area and installation method
JP2018199933A (en) * 2017-05-26 2018-12-20 株式会社巴コーポレーション Structure body and construction method of structure constructed on top of tower-like building
JP2021088883A (en) * 2019-12-05 2021-06-10 株式会社巴コーポレーション Column base portion structure in structure, and column base portion fixing method
CN115506588A (en) * 2022-10-25 2022-12-23 四川路桥桥梁工程有限责任公司 Intelligent integrated lifting support
CN115506588B (en) * 2022-10-25 2024-05-28 四川路桥桥梁工程有限责任公司 Intelligent integrated lifting support

Similar Documents

Publication Publication Date Title
CN109538238B (en) Tunnel arch prefabricated segment construction device and control method
CN107013038A (en) A kind of steel structure slipping of building roof lighting Zhongting changes column construction method
JP5769961B2 (en) Construction method and removal method of structure
JP2859163B2 (en) Rotary erection method for bridges with high piers
JPH08333813A (en) Building method of building unit for vertical and horizontal conveying
JPH08333898A (en) Trestle for vertically and horizontally conveying building blocks
CN110700418B (en) Construction process for mounting laminated slab by matching laminated slab mounting trolley with tower crane
CN108643941A (en) Gantry type arch installs trolley
JPH0483060A (en) Building construction
JP2001213584A (en) Large-scale elevation stage and lifting method and reversely driving technique using the same
KR102242485B1 (en) Method for vertical transportation of a heavy module using of a module lifting system inculding of a strand jack
CN113175222A (en) Installation method of embedded prefabricated external wall panel component
JPH059981A (en) Construction of building
KR200200364Y1 (en) High building construction apparatus
JPH05113026A (en) Temporary scaffold structure
CN109056741B (en) Method for dismantling lower steel support in multi-layer steel support
CN113863684B (en) Construction method of stepped double-layer steel truss
JPH10245994A (en) Temporary curing body
JPH0733688B2 (en) Push-up method
JPH05133129A (en) Method for installing plural layer type underground parking equipment and carrying device used therefor
JPH05133128A (en) Method for installing plural layer type underground parking equipment and installation working vehicle used for the installation method
RU2276244C2 (en) Movable form with mechanized set for floor structure erection
JPH08326323A (en) Constructing device for multistoried building
JP2934567B2 (en) Work gondola for multi-story parking lot construction
JP2000145127A (en) Transferable scaffold