JP4565494B2 - Design and management support system for buried pipe work and civil engineering work - Google Patents
Design and management support system for buried pipe work and civil engineering work Download PDFInfo
- Publication number
- JP4565494B2 JP4565494B2 JP2004240179A JP2004240179A JP4565494B2 JP 4565494 B2 JP4565494 B2 JP 4565494B2 JP 2004240179 A JP2004240179 A JP 2004240179A JP 2004240179 A JP2004240179 A JP 2004240179A JP 4565494 B2 JP4565494 B2 JP 4565494B2
- Authority
- JP
- Japan
- Prior art keywords
- design
- data
- work
- construction
- volume
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 238000013461 design Methods 0.000 title claims description 101
- 238000010276 construction Methods 0.000 claims description 114
- 238000000034 method Methods 0.000 claims description 38
- 238000010586 diagram Methods 0.000 claims description 37
- 230000001186 cumulative effect Effects 0.000 claims description 19
- 230000008569 process Effects 0.000 claims description 17
- 238000009825 accumulation Methods 0.000 claims description 12
- 238000003860 storage Methods 0.000 claims description 12
- 238000012545 processing Methods 0.000 claims description 10
- 230000008859 change Effects 0.000 claims description 8
- 238000004040 coloring Methods 0.000 claims description 3
- 238000007726 management method Methods 0.000 description 60
- 230000010354 integration Effects 0.000 description 15
- 238000012423 maintenance Methods 0.000 description 9
- 238000009430 construction management Methods 0.000 description 8
- 239000000463 material Substances 0.000 description 8
- 238000011960 computer-aided design Methods 0.000 description 6
- 230000008439 repair process Effects 0.000 description 5
- 238000005259 measurement Methods 0.000 description 4
- 238000012360 testing method Methods 0.000 description 4
- 230000006870 function Effects 0.000 description 3
- 238000009434 installation Methods 0.000 description 3
- 238000009412 basement excavation Methods 0.000 description 2
- 238000011161 development Methods 0.000 description 2
- 238000005516 engineering process Methods 0.000 description 2
- 238000003754 machining Methods 0.000 description 2
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 2
- 238000007796 conventional method Methods 0.000 description 1
- 238000005520 cutting process Methods 0.000 description 1
- 230000008676 import Effects 0.000 description 1
- 230000007246 mechanism Effects 0.000 description 1
- 238000002360 preparation method Methods 0.000 description 1
- 230000000750 progressive effect Effects 0.000 description 1
- 239000004576 sand Substances 0.000 description 1
- 239000010865 sewage Substances 0.000 description 1
- 239000002689 soil Substances 0.000 description 1
Landscapes
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Description
本発明は、埋設管工事・土木工事において、設計作業並びに工事完成後の維持管理を支援するシステムに関し、より具体的にはGISを用いて、設計図面と設計諸元を関連付けると共に独自の管理モデルを採用した埋設管工事・土木工事の支援システムに関する。
なお、本出願において埋設管工事とは、公共下水道事業、集落排水事業、上水道事業、農業用埋設管事業等を指し、土木工事とは、道路事業、水路事業、溜池事業等を指すものとする。
The present invention relates to a system for supporting design work and maintenance after completion of construction in buried pipe work and civil engineering work. More specifically, the present invention relates to a design model and design specifications and a unique management model using GIS. This is related to a support system for buried pipe work and civil engineering work that employs
In this application, buried pipe work refers to public sewerage business, village drainage business, waterworks business, agricultural buried pipe business, etc., and civil engineering work refers to road business, waterway business, pond project, etc. .
従来の埋設管工事・土木工事における支援システムの代表例としては、CAD(Computer-Aided Design)があげられる。CADはコンピュータ援用設計ともいい、土木設計・埋設管設計、建築設計や機械設計、回路設計などで、設計図 などの作成作業をコンピュータを利用して効率よく行う手段として広く認識されている。例えばグラフィックス機能に優れたコンピュータ上でCADソフトウェアを動作させ、高解像度のディスプレイ画面を設計図面にみなして図形の作成・修正・映像化を行うことにより、従来の紙ベースの設計に比べ大幅な効率化を実現することができる。 CAD (Computer-Aided Design) is a typical example of a conventional support system for buried pipe work and civil engineering work. CAD is also known as computer-aided design, and is widely recognized as a means of efficiently creating design drawings using computers in civil engineering design, buried pipe design, architectural design, mechanical design, circuit design, and so on. For example, by operating CAD software on a computer with excellent graphics functions, and creating, modifying, and visualizing figures with a high-resolution display screen regarded as a design drawing, it is significantly more than conventional paper-based designs. Efficiency can be realized.
一方、近年では、ディジタル化された地図をコンピュータ上で参照・操作・分析等するための地理情報システム(Geographical Information System;GIS)が、コンピュータ技術及びネットワーク技術の進展と共に発達している。地理情報システムの導入により、地理情報と各種設計情報の関連づけを行うことが可能となった。
一般に、GISはその目的や利用方法に応じて個別に構築され運用されるものである。例えば、各部署や各事業所毎で個別に地理情報システムが構築する場合、自らの管理外の地理情報が必要となる場合等もある。このような場合、各地理情報システムが何の連携もなく分散している状況下では、どこに必要な地理情報が存在するのか把握しにくく、分散された地理情報システムを効率的に利用することができないという問題があった。
そこで、分散された異なる種類の地理情報システムを相互利用できるようにした地理情報システムが提言されている(特許文献1、特許文献2)。
On the other hand, in recent years, a geographic information system (GIS) for referencing, manipulating, and analyzing a digitized map on a computer has been developed with the progress of computer technology and network technology. With the introduction of the geographic information system, it has become possible to associate geographic information with various design information.
Generally, GIS is constructed and operated individually according to its purpose and usage. For example, when a geographical information system is individually constructed for each department or each business office, geographical information outside its own management may be required. In such a case, in a situation where each geographic information system is distributed without any cooperation, it is difficult to grasp where the necessary geographic information exists, and it is possible to efficiently use the distributed geographic information system. There was a problem that I could not.
Therefore, a geographical information system that allows different types of distributed geographical information systems to be mutually used has been proposed (Patent Documents 1 and 2).
埋設管工事・土木工事における設計・管理業務の概要は図1に示す通りである。認可設計(計画設計)は、多年度に渡る事業量全体の概略設計であり、年度計画を立てて実施する基本となる設計書(設計図、数量計算書、工事費明細書、設計諸元等)を作成するものである(STEP1)。測量試験費予算要望では、次年度から1〜2年間で施工する区間について、実施設計をするための測量試験費の予算を積算して要望(要求)する(STEP2)。測量試験費補助金交付申請は、予算要望を提出した施工工区について、測量試験費に係る補助金の交付を受けるための手続である(STEP3)。 The outline of the design and management work in buried pipe work and civil engineering work is as shown in Fig. 1. Authorized design (planned design) is a general design of the entire business volume over many years, and the basic design document (design drawing, quantity calculation sheet, construction cost statement, design specifications, etc.) to be established and implemented for the fiscal year ) Is created (STEP 1). In the survey test budget request, the survey test budget for designing the implementation is calculated (requested) for the section to be constructed in the next year or two years (STEP 2). Surveying test cost subsidy grant application is a procedure for receiving subsidies related to survey test cost for construction zones that submitted budget requests (STEP 3).
実施設計では、上記作業を経て当該年度に割り当てられた事業量について、工事を実施するための見積及び施工に必要な実施設計を作成する(STEP4)。なお、工期全体を1年として全体実施設計を行う事業もある。工事費予算要望は、次年度に施工予定の事業についての工事費を積算して要望(要求)する(STEP5)。工事費補助金交付申請は、予算要望を提出した施工工区について、工事費に係る補助金の交付を受けるための手続である(STEP6)。
上記作業で必要な工事費の見積は、施工工期、事業量、及び工事費等について最適な値を得るまで繰り返し試算を行う必要がある。
In the implementation design, for the project amount allocated in the current fiscal year after the above work, an estimate for carrying out the construction and an implementation design necessary for construction are created (STEP 4). There are also projects that carry out overall implementation design with the entire construction period as one year. The construction cost budget is requested (requested) by accumulating the construction cost for the project scheduled for construction in the next fiscal year (STEP 5). Application for subsidy for construction costs is a procedure for receiving subsidies related to construction costs for construction zones that submitted budget requests (STEP 6).
Estimating the construction cost required for the above work needs to be repeated until optimum values are obtained for the construction period, project volume, construction cost, etc.
請負設計は補助金交付申請と実施設計に基づいて、工区を区分し、工事を発注するために必要な設計書を作成する(STEP7)。この際も事業量と工事費の繰り返し試算が必要である。
変更設計は請負率による金額の変更が生じた場合、当初予測できない土質であった場合、その他の要因で工事に変更が生じた場合に行う(STEP8)。通常は2〜3回の変更設計を行う。
請負設計及び変更設計に基づいて「入札」を行い、落札金額と請負設計金額との割合を請負率として、以降の設計金額に請負率を乗した額を変更設計金額として請負契約を締結する。請負工事が完了すると出来高設計を作成する(STEP9)。この際も事業量と工事費の繰り返し試算が必要である。
工事完了後には、工事対象物を補修等し継続的に利用するための維持管理を行う(STEP10)。
以上の設計・管理業務では、次の課題があった。
The contract design is based on the subsidy application and the execution design, and divides the work area and creates a design document necessary for ordering the work (STEP 7). At this time, it is necessary to repeatedly calculate the project volume and construction costs.
The change design is performed when the amount of money changes due to the contract rate, when the soil is unpredictable, or when the construction changes due to other factors (STEP 8). Usually, the change design is performed 2 to 3 times.
A “bidding” is performed based on the contract design and the change design, and the contract is concluded with the ratio between the successful bid amount and the contract design amount as the contract rate, and the subsequent design amount multiplied by the contract rate as the change design amount. When the contract work is completed, a volume design is created (STEP 9). At this time, it is necessary to repeatedly calculate the project volume and construction costs.
After the completion of construction, maintenance work will be carried out so that the construction object can be repaired and used continuously (STEP 10).
The above design and management tasks have the following issues.
(1)工事費積算の作業負荷の問題
従来の工事費積算業務の流れは図2に示す通りである。
まず、積算対象となる事業量を各種図面上で仮設定する(STEP11)。工種、仕様部材等の施行に関する数量データを入力し(STEP12)、これらの情報から工事費を積算する(STEP13)。積算結果をもとに、目標工事費を実現できるかを確認し(STEP14)、OKであれば積算結果を出力する(STEP15)。目標工事費を実現出来ていない場合には、繰り返し試算を行うというものである。しかしながら、通常は1回で目標工事費を達成できることは少なく、繰り返し行う積算作業の作業負荷が問題となっていた。
(1) Problem of workload for construction cost estimation The flow of conventional construction cost estimation work is as shown in FIG.
First, the business volume to be accumulated is provisionally set on various drawings (STEP 11). Enter the quantity data related to the execution of work types, specification members, etc. (STEP 12), and add construction costs from these information (STEP 13). Based on the integration result, it is confirmed whether the target construction cost can be realized (STEP 14). If it is OK, the integration result is output (STEP 15). If the target construction cost is not realized, the trial calculation is repeated. However, it is rare that the target construction cost can be achieved at one time, and the work load of repeated integration work has been a problem.
(2)図面管理の問題
施工管理においては、多数の図面を作成することとなるが、これらを突き合わせて施工管理することは多くの労力を要する作業である。例えば、平面図、縦断図、横断図、標準図、構造図等の図面は数枚ずつあり、この中から各図面の測点とか、構造物の名称番号等の属性から必要な図面及びデータを探して施工管理をしなくてはならなかった。
GISにCADで作成した図面データやスキャナーで取り込んだイメージデータ等をそのまま取り込むことも考えられるが、紙ベースの情報をそのまま電子化しても複数図面を突き合わせる必要性はなくならず、大幅な改善は望めなかった。
(3)維持管理の問題
工事完了後には、工事対象物を補修等するために、図面管理の仕組みが必要である。従来からGISによる図面管理は行われていたが、管理図面のデータを出来高設計後に作成していたため、二度手間となっていた。
また、補修費用の積算においても、上記同様に工事費の繰り返し試算が必要という問題がある。
(2) Problem of drawing management In construction management, a large number of drawings are created. However, it is a work requiring a lot of labor to manage construction by matching these drawings. For example, there are several drawings such as plan, vertical, cross-sectional, standard, and structural drawings. From these, the necessary drawings and data can be obtained from the measurement points of each drawing and attributes such as the structure name number. I had to find and manage the construction.
Although it is conceivable to directly import drawing data created by CAD or image data captured by a scanner into GIS, there is no need to match multiple drawings even if paper-based information is digitized as it is. Couldn't hope.
(3) Maintenance problems After construction is complete, a drawing management mechanism is required to repair the construction object. Conventionally, drawing management by GIS has been performed, but it has been troublesome twice because the data of the management drawing was created after the volume design.
In addition, there is a problem in that it is necessary to repeatedly estimate the construction cost in the same manner as described above in the estimation of repair costs.
本発明は、このような事情を鑑みてなされたものであって、GISにおいて設計管理・施工管理・維持管理作業に必要な管理情報付き制御図を表示すると共に出来高管理モデルなる新たな概念を採用することで、埋設管工事・土木工事の設計・管理作業を支援するシステムを提供することを目的とする。 The present invention has been made in view of such circumstances, and displays a control diagram with management information necessary for design management, construction management, and maintenance work in GIS and adopts a new concept of a volume management model. The purpose is to provide a system that supports the design and management of buried pipe work and civil engineering work.
第1の発明は、入力手段と、表示手段と、平面図を含む図面データ、構造物の出来高を2以上に分類したモデルを含む出来高管理モデルデータ、管種、管径、土工タイプ及び土留タイプを含む設計諸元データ、工種別及び部材名称を含む数量データ、並びに、部材名称の単位数量当たりの金額を含む積算データが登録された記憶手段とを備えるGISを用いた埋設管工事・土木工事の設計・管理支援システムであって、記憶手段から図面データ、出来高管理モデルデータ、設計諸元データ及び数量データを読み出し、これらの関連付けがなされた設計諸元データ付き平面図である制御図をGISの機能を用いて作成し、作成した制御図データを記憶手段に記憶する手段と、記憶手段から制御図データを読み出し、表示手段に制御図を表示させる手段と、表示手段により表示された制御図において入力手段により区間・ヶ所を選択可能とする選択手段と、表示手段により表示された制御図において選択された区間・ヶ所を着色して表示させる手段と、選択された区間・ヶ所に基づき、記憶手段から設計諸元データ、数量データ及び積算データを読み出し、累加事業量及び累加事業費を自動積算する積算手段と、自動積算した累加事業量及び累加工事費を表示手段に表示させる手段と、を有する設計・管理支援システムである。
第2の発明は、第1の発明において、前記選択手段は、(A)入力手段により起点、方向及び目標工事費を入力することにより、目標工事費に到達するまでヶ所・区間を自動指定する手段、(B)入力手段により起点及び終点を入力することにより、起点から終点までを自動指定する手段、(C)入力手段により中間点を含む起点及び中間点を含む終点を入力することにより、中間点を含む起点から中間点を含む終点までを自動指定する手段を含むことを特徴とする。
第3の発明は、第2の発明において、前記(A)の自動指定は、区間とヶ所の荷重平均又は按分計算により行うことを特徴とする。 The first invention includes input means, display means, drawing data including a plan view, volume management model data including a model in which the volume of a structure is classified into two or more, pipe type, pipe diameter, earthwork type, and earth retaining type Construction data including design specifications, quantity data including type of work and member name, and storage means in which accumulated data including the amount per unit quantity of the member name is registered. Design / management support system, which reads out drawing data, volume management model data, design specification data, and quantity data from storage means, and displays a control diagram that is a plan view with design specification data associated with these GIS prepared using the functions, means for storing the control view data created in the storage means, reads the control view data from the storage means, and means for displaying the control view on the display means Selection means for a selectable period, locations by the input means in the control diagram displayed by the display means, and means for displaying by color the selected section-locations in the control diagram displayed by the display means is selected was based on the section-places, design specifications based on data from the storage means, read the quantity data and integrated data, display and integrated means for automatically integrating the cumulative business volume and cumulative project costs, cumulative business volume was automatically accumulated and the cumulative construction costs A design / management support system having means for displaying on the means .
In a second aspect based on the first aspect, the selecting means automatically designates a location / section until the target construction cost is reached by inputting the starting point, direction and target construction cost by the input means (A). Means, (B) means for automatically specifying from the start point to the end point by inputting the start point and end point by the input means, and (C) by inputting the start point including the intermediate point and the end point including the intermediate point by the input means, A means for automatically designating from the starting point including the intermediate point to the ending point including the intermediate point is included.
The third invention is characterized in that, in the second invention, the automatic designation of (A) is performed by load average or proportional calculation of sections and locations.
第4の発明は、第1ないし3のいずれかの発明において、更に予め定められた様式の帳票を表示手段に表示させる手段を有することを特徴とする。 According to a fourth invention, in any of the first to third, and having a means for displaying the document further to a predetermined manner on the display means.
第5の発明は、第4の発明において、前記帳票は予算要望書、補助金交付申請書、委託設計書、請負設計書、変更設計書、及び/又は出来高設計書であることを特徴とする。 According to a fifth invention, in the fourth invention, the form is a budget request, a subsidy grant application, a consignment design, a contract design, a change design, and / or a volume design. .
第6の発明は、第1ないし5のいずれかの発明において、更に構造物の図面、事業量及び工事費を表示手段に同時に表示させる手段を有することを特徴とする。 According to a sixth aspect, in any one invention of the first to fifth, drawing further the structure, characterized by having a means for simultaneously displaying on the display means the business volume and construction costs.
第7の発明は、第1ないし6のいずれかの発明において、前記図面データは、制御図に、平面図に中心線を引き、中心線に直角に交わる複数の横断方向線を引き、各横断方向線間に設定した一意の中心区間コードを表示手段に表示させることを可能とする情報を含むことを特徴とする。 According to a seventh invention, in any of the first to sixth, wherein the drawing data, the control view, draw a center line in plan view, draw plurality of transverse lines intersecting at right angles to the center line, each cross It includes information that makes it possible to display a unique central section code set between the direction lines on the display means .
第8の発明は、第7の発明において、前記選択手段は、前記中心線を指定することで中心線区間に存在する全ての構造物を指定する手段を有することを特徴とする。 Advantageously, in the invention of the seventh, the selection means may have a means for specifying all the structures present in the center line section by specifying the center line.
本発明に係る設計・管理支援システムを使用することで、認可設計・実施設計から抜粋して、設計書を作ること、工事費から事業量を求めること、事業量から工事費を求めること、また区間を決めて事業費を求めること等の作業をするに際し、自動積算の機能を使って、迅速に作業をすることが出来る。
また、本発明に係る制御図を使用することで、埋設管工事・土木工事の施工管理・維持管理作業において多くの図面を見比べながら使用することなく、工事内容を容易、かつ迅速に把握することができる。例えば、平面図に加え縦断図を見なくても、設計諸元付き平面図を見ることで設計管理・施工管理を行うことが可能となる。
By using the design / management support system according to the present invention, excerpts from the authorized design / implementation design, making a design document, obtaining the business amount from the construction cost, obtaining the construction cost from the business amount, When performing work such as determining the section and obtaining the project cost, it is possible to work quickly by using the automatic accumulation function.
In addition, by using the control diagram according to the present invention, it is possible to grasp the construction contents easily and quickly without using it while comparing many drawings in construction management and maintenance management work for buried pipe work and civil engineering work. Can do. For example, it is possible to perform design management and construction management by looking at a plan view with design specifications without looking at a longitudinal view in addition to the plan view.
また、GIS上で予算要望・補助金交付申請に伴う積算、請負設計・変更設計・出来高設計等の作業を行うことが可能となり、試算のために紙ベースの資料をくり返し作成する業務が無くなり、高度な技術者の労力を大幅に節減することができる。 In addition, it is possible to perform work such as budgeting / subsidy grant application, contract design / change design / volume design etc. on GIS, eliminating the need to repeatedly create paper-based materials for trial calculation, The labor of advanced engineers can be greatly reduced.
さらに、本発明の設計・管理支援システムでは、請負設計、設計管理業務、施工管理業務、及び維持管理業務において個別に管理していたデータを、全ての作業を通して一括管理することができる。
さらにまた、維持管理のために改めて設計図面を作成する必要が生じるという問題を解決することができ、更には人事異動が生じても後任者が容易に作成データの編集を行うことができる。
Furthermore, in the design / management support system of the present invention, data individually managed in contract design, design management work, construction management work, and maintenance management work can be collectively managed through all work.
Furthermore, it is possible to solve the problem that it is necessary to create a design drawing anew for maintenance management. Furthermore, even if personnel changes occur, the successor can easily edit the created data.
本発明を実施するための最良の形態を、以下に説明する。
(システム構成)
図3は、本発明のシステム構成図である。本発明に係るシステムは、入力装置1と出力装置3に接続されたパーソナルコンピュータ2から構成される。入力装置1は、デジタイザやスキャナ等の図面データ等の入力機器である。出力装置3は、ドットプリンタ、レーザープリンタ及びインクジェットプロッタ等の出力機器である。パーソナルコンピュータ2は、GIS21とデータベースソフト23、CADソフト24、表計算ソフト25及び測量ソフト26を連携するための設計・管理支援プログラム22とから構成される。設計・管理支援プログラム22は、Microsoft社のVisualBasic(登録商標)等の汎用的な開発言語で作成されたプログラムである。また、それ以外のソフト21,23〜26は市販の汎用的なソフトウェアである。
CADソフト24及び測量ソフト26は、初期データを編集するために用いるものであり、本発明の必須の構成要素ではない。
また、ネットワークや電子記憶媒体等によるデータのやり取りが可能である場合には、入力装置1及び出力装置3の双方がなくとも本発明は成立する。
The best mode for carrying out the present invention will be described below.
(System configuration)
FIG. 3 is a system configuration diagram of the present invention. The system according to the present invention includes a personal computer 2 connected to an input device 1 and an output device 3. The input device 1 is an input device such as drawing data such as a digitizer or a scanner. The output device 3 is an output device such as a dot printer, a laser printer, or an inkjet plotter. The personal computer 2 includes a design / management support program 22 for linking the GIS 21 with database software 23, CAD software 24, spreadsheet software 25, and surveying software 26. The design / management support program 22 is a program created in a general-purpose development language such as Microsoft's VisualBasic (registered trademark). The other softwares 21, 23 to 26 are commercially available general-purpose software.
The CAD software 24 and the survey software 26 are used for editing the initial data and are not essential components of the present invention.
In addition, when data can be exchanged via a network, an electronic storage medium, or the like, the present invention can be realized without both the input device 1 and the output device 3.
(データ設定)
本発明に係るシステムを利用するためには、事前に以下のデータを入力し、データ間の関連づけを行う必要がある。
(1)表示出力用の図面データ
平面図(現況を背景図とした図)、縦断図(工事の対象となる構造物等を縦断方向に切って高低距離等を示した図)、横断図(工事の対象となる構造物等を横断方向に切って土工等を示した図)、標準図(どの地区にも当てはまる一般的な構造を示した図)、構造図(一般的な組み立て方を示した図)、平面図の計画データ(工事の対象となる中心線、測点、構造物等を平面上に投影した図)をイメージデータ又はCADデータで取得する。
(2)設計諸元データ
土工データ、マンホールデータ、公共桝データ等のデータである。
本発明で取り扱う設計諸元データの例は、図4のとおりである。なお、従来の手法においては、このうち1〜7のデータしか平面図上に表されていなかった。
(3)数量データ
工種別、区間、ヶ所毎部材名称の延長、面積、体積データである。
下水道工事における工種別としては、管渠工、マンホール工、汚水桝、取付管工などがある。管渠工における部材名称としては、ゴム輪受口片受直管、マンホール可とう継手、土留工、砂埋戻、埋設標識シート、土工などがある。
(4)単価データ
単価データは、部材名称の単位数量当りの金額で、積算歩掛×労務資材単価、数量必要資料、見積資料、積算資料を登録する。
以上のデータ設定を行うことにより、設計諸元付き平面図(制御図)を出力することが可能となる。図5の右側に下水道事業における例を、図18に道路工事における例を示す。
(Data setting)
In order to use the system according to the present invention, it is necessary to input the following data in advance and associate the data.
(1) Drawing data for display output Plan (plan with the current situation as a background), longitudinal view (drawing the structure to be constructed in the longitudinal direction, etc., showing high and low distances, etc.), cross-sectional view ( Figure showing earthwork etc. by cutting the structure etc. that is the object of construction in the transverse direction, standard figure (figure showing general structure applicable to any district), structure figure (showing general assembly method) Plan data), and plan data (projected centerline, measurement points, structures, etc. on the plane) are acquired as image data or CAD data.
(2) Design specification data These are data such as earthwork data, manhole data, and public fence data.
An example of design specification data handled in the present invention is as shown in FIG. In the conventional method, only 1 to 7 of these data are represented on the plan view.
(3) Quantity data These are data of extension, area, and volume data for construction type, section, and part name.
The types of sewerage work include pipe works, manhole works, sewage works, and installation pipe works. The member names in pipe construction include rubber ring receiving piece straight pipe, manhole flexible joint, earth retaining work, sand backfill, buried sign sheet, and earthwork.
(4) Unit Price Data Unit price data is the amount per unit quantity of the member name, and registers accumulated yield × labor material unit price, quantity required material, estimate material, and accumulated material.
By performing the above data setting, it is possible to output a plan view (control diagram) with design specifications. An example in the sewer business is shown on the right side of FIG. 5, and an example in road construction is shown in FIG.
(出来高管理モデル)
本発明においては、施工管理情報手段として、「出来高管理モデル」なる新たな概念を採用している。出来高管理モデルとは、従来工程毎に作成していた設計図面において、年度をまたがって施工が可能な仕上がりの形状、構造物(土工を含む)を予め工程毎に数種のモデルに分類し、工事費の積算や進捗管理を容易に行うことを可能とするための手段である。
図6は、i)下水道工事、ii)道路工事、iii)水路工事、iv)橋工事、v)ポンプ場とポンプ工事、の5つの工事における出来高管理モデルである。
図6においては、制御図に中心線を有する工事と有しない工事がある。前者には、i)〜iv)が該当し、後者にはv)が該当する。
i)下水道工事においては、M1は掘削・管布設・埋戻・舗装を、M2は掘削・管布設・埋戻を、M3は舗装を表している。ii)道路工事においては、M40は側壁を、M41は擁壁を、M45は舗装を、M46は土工を表している。iii)水路工事においては、M41は擁壁を、M45は舗装を、M100は水路を表している。iv)橋工事においては、M201は橋台を、M202は橋脚を、M203は上部工を、「H,m」は出来高の高さを表している。v)ポンプ場とポンプ工事においては、M301は建屋を、M302はポンプ場設備を表している。
以下では、i)下水道工事のモデルを例にあげて出来高管理モデルを説明する。
(Volume management model)
In the present invention, a new concept of “volume management model” is adopted as the construction management information means. The volume management model is a design drawing created for each process in the past. The finished shape and structure (including earthwork) that can be constructed across years are classified into several models for each process in advance. It is a means for making it possible to easily estimate construction costs and manage progress.
Fig. 6 shows the volume management model for five works: i) sewerage work, ii) road work, iii) waterway work, iv) bridge work, and v) pump station and pump work.
In FIG. 6, there is a construction having a center line and a construction having no center line in the control diagram. The former corresponds to i) to iv), and the latter corresponds to v).
i) In sewerage works, M1 represents excavation / pipe installation / backfill / pavement, M2 represents excavation / pipe installation / backfill, and M3 represents pavement. ii) In road construction, M40 represents a side wall, M41 represents a retaining wall, M45 represents a pavement, and M46 represents an earthwork. iii) In waterway construction, M41 represents a retaining wall, M45 represents pavement, and M100 represents a waterway. iv) In the bridge construction, M201 represents the abutment, M202 represents the pier, M203 represents the superstructure, and “H, m” represents the height of the work piece. v) In the pump station and pump construction, M301 represents the building and M302 represents the pump station equipment.
In the following, the volume management model is explained by taking i) sewerage model as an example.
従来の下水道工事においては、標準断面(通常は、横断線で切った図面)のような図面で工事の管理が行われていたが、本件事案ではこれをM1乃至3の3つのモデルに分類している。このように分類することでM1乃至3のいずれのモデルに該当する工程における工事費用の積算が容易になり、また工事着工に際しても、工程毎に図面を新たに作成することなく、工事管理を行うことができる。
図6の各工事を見ると分かるように、モデルの分類は、2乃至4程度の範囲で行われている。モデルの分類は当業者であれば、容易にその見極めを行うことができると考えられるが、工事管理を行う上で当事者に都合の良い2以上の数であれば、その分類の仕方に制限はない。しかし、理想的には、埋設管工事・土木工事の各種工事について官業間で標準化モデルを作成することが好ましい。
In the conventional sewerage work, the work was managed with a drawing like a standard cross section (usually a drawing cut by a crossing line). In this case, this is classified into three models M1 to M3. ing. By classifying in this way, the construction costs in the processes corresponding to any of the models M1 to M3 can be easily integrated, and the construction management can be performed without creating a new drawing for each process. be able to.
As can be seen from the constructions in FIG. 6, the classification of the models is performed in the range of about 2 to 4. A person skilled in the art can easily determine the classification of a model. However, if the number is two or more, which is convenient for the parties in the construction management, there is no limitation on the classification. Absent. However, ideally, it is preferable to create a standardized model between the public sector for various construction works such as buried pipe work and civil engineering work.
図7は、出来高管理モデルの編集作業手順を示したものである。
出来高管理モデルを利用するためには、まず出来高モデルコードの設定を行う必要がある(STEP21)。出来高モデルコードとは、図6に記載のMから始まるコードであり、例えば下水道工事においてはM1乃至M3の3つのコードを設定する必要がある。出来高モデルコードは、出来高モデル毎に一意のコードを設定する必要がある。これにより出来高管理モデルを利用する準備が完了する。
次に、本発明に係る出来高管理モデルを利用するためには、各構造物がどの中心線区間に属するか、関連する図面はどれかを設定する必要がある。そこで、平面図において横断方向線をひき、中心区間コードを決定する(STEP22)。中心区間が決まったら、構造物毎に中心区間コードを設定設定し(STEP23)、関連する各種図面のリンクを設定する(STEP24)。全ての構造物にこれらの作業を行うことで、出来高管理モデルの編集作業は終了する。
これらの作業を行うことにより、出来高管理モデルにより構造物が示された平面図(制御図)を作成することが可能となる。
なお、構造物とは、埋設管工事では、管渠・ボックス等、土木工事では、擁壁・排水路構造等を指すがの一般的であるが、本発明においては土木・仮設工等の工事対象となる全てのものを指すものとする。
FIG. 7 shows a procedure for editing the volume management model.
In order to use the volume management model, it is first necessary to set the volume model code (STEP 21). The volume model code is a code starting from M shown in FIG. 6. For example, three codes M1 to M3 need to be set in sewerage work. For the volume model code, it is necessary to set a unique code for each volume model. This completes preparations for using the volume management model.
Next, in order to use the volume management model according to the present invention, it is necessary to set which centerline section each structure belongs to and which drawing is related. Therefore, the central section code is determined by drawing the transverse direction line in the plan view (STEP 22). When the central section is determined, the central section code is set and set for each structure (STEP 23), and links of various related drawings are set (STEP 24). By performing these operations on all the structures, the editing operation of the volume management model is completed.
By performing these operations, it is possible to create a plan view (control diagram) in which the structure is shown by the volume management model.
In addition, a structure means a pipe wall / box, etc., for buried pipe work, and a retaining wall / drainage structure, etc., for civil engineering work, but in general, construction work for civil engineering / temporary construction, etc. It shall refer to all objects.
出来高管理モデルを用いた設計作業は図8の要領で行われる。図8の左側には従来の設計作業の流れ図が記載されている。本発明においては、従来作業に加え、出来高管理モデルの作成、出来高管理モデルコード(Mコード)、記号の決定作業が新たに発生するが(図6参照)、これらの作業を行うことにより、年度実施設計における工事費積算業務の労力を大幅に削減することが可能となる。 The design work using the volume management model is performed as shown in FIG. On the left side of FIG. 8, a flowchart of conventional design work is shown. In the present invention, in addition to the conventional work, a work volume management model creation, a work volume management model code (M code), and a symbol determination work are newly generated (see FIG. 6). It is possible to greatly reduce the labor of construction cost estimation work in the implementation design.
図9は、埋設管工事における制御図と土木工事における制御図を出来高管理モデルにより表示した例である。
図9に示すとおり、上段が埋設管工事の出来高管理モデルにおける構造物管理コードの記載例であり、下段が土木工事の出来高管理モデルにおける構造物管理コードの記載例である。
例えば、構造物に「32・33・41」との番号が付されていた場合、その構造物は中心から離れた構造物であり、中心線区間共有構造物である擁壁であることを意味する。
FIG. 9 is an example in which a control diagram in buried pipe construction and a control diagram in civil engineering work are displayed by a volume management model.
As shown in FIG. 9, the upper part is a description example of the structure management code in the volume management model of the buried pipe work, and the lower part is a description example of the structure management code in the work volume management model of the civil engineering work.
For example, if the structure is numbered “32/33/41”, it means that the structure is a structure away from the center and a retaining wall that is a shared structure of the center line section. To do.
(工事費の自動積算)
GISの画面上に表示された制御図において、ユーザーは「1.ヶ所・区間指定」、「2.起点・方向指定」、「3.起点・終点指定」「4.中間点を含む起点指定・中間点を含む終点指定」の4通りの手段により、工事費の自動積算を行うことができる。本発明に係る工事費積算の流れを図10を用いて説明する。
まず、ユーザーは、先に述べた4通りの工事費積算手段から一の手段を選択する(STEP31)。「1.ヶ所・区間指定」を選択した場合、画面上に対応する制御図が出力されるので、工事費積算の対象となるヶ所及び区間をクリックして指定すると、(STEP32a)、選択した部分が着色される(STEP33a)。
「2.起点・方向指定」を選択した場合においては、画面上に対応する制御図が出力されるので、ユーザーが工事費積算の対象となる起点、方向及び目標工事費を入力すると(STEP32b)、目標工事費に到達するまでヶ所・区間が着色される(STEP33b)。
「3.起点・終点指定」を選択した場合においては、画面上に対応する制御図が出力されるので、ユーザーが工事費積算の対象となる起点及び終点を入力すると(STEP32c)、起点から終点までのヶ所・区間が着色される(STEP33c)。
「4.中間点を含む起点指定・中間点を含む終点指定」を選択した場合においては、画面上に対応する制御図が出力されるので、ユ−ザ−が工事費積算の対象となる中間点を含む起点指定及び終点を入力すると(STEP32d)、中間点を含む起点から中間点を含む終点までのヶ所・区間が着色される(STEP33d)。
全ての選択が終了して累加事業量及び工事費の算出を実行すると(STEP34)、算出された累加事業量及び工事費が表示される(STEP35)。累加事業量及び工事費の算出は、図11の要領で行われる。他の方法による追加指定が必要な場合には、STEP31に戻り作業を繰り返す(STEP36)。
(Automatic calculation of construction costs)
In the control diagram displayed on the GIS screen, the user can specify “1. Location / section specification”, “2. Start / direction specification”, “3. Start / end specification”, “4. The construction cost can be automatically accumulated by four means of “designating the end point including the intermediate point”. A construction cost accumulation flow according to the present invention will be described with reference to FIG.
First, the user selects one means from the four construction cost accumulating means described above (STEP 31). When “1. Location / section designation” is selected, the corresponding control diagram is output on the screen. If you click on the location and section for which construction costs are to be accumulated (STEP 32a), the selected part will be displayed. Is colored (STEP33a).
When “2. Start / Direction” is selected, the corresponding control chart is output on the screen, so when the user inputs the start point, direction and target construction cost for which construction costs are to be accumulated (STEP32b) The locations and sections are colored until the target construction cost is reached (STEP 33b).
When "3. Start / end specification" is selected, the corresponding control chart is output on the screen. When the user inputs the start and end points for construction cost accumulation (STEP 32c), the start point to the end point The locations and sections up to are colored (STEP33c).
When “4. Specify start point including intermediate point / Specify end point including intermediate point” is selected, the corresponding control diagram is output on the screen, so the user is the target of construction cost accumulation. When a start point specification including a point and an end point are input (STEP 32d), the location / section from the start point including the intermediate point to the end point including the intermediate point is colored (STEP 33d).
When all the selections are completed and the calculation of the cumulative project amount and construction cost is executed (STEP 34), the calculated cumulative project amount and construction cost are displayed (STEP 35). Calculation of the cumulative amount of work and the construction cost is performed as shown in FIG. If additional designation by another method is required, the process returns to STEP 31 and is repeated (STEP 36).
以上の作業を終了すると、工種毎に事業量及び工事費が算出され、各工種の累計が出力結果として表示される。ユーザーは目標工事費に到達したかの判断を行い、再度積算が必要な場合にはSTEP31に戻り作業を繰り返すこととなる(STEP37)。目標工事費が得られた場合には、工事明細書、数量計算書、積算箇所が着色された各種図面を出力することができる(STEP38)。 When the above work is completed, the business amount and the construction cost are calculated for each work type, and the total of each work type is displayed as an output result. The user determines whether or not the target construction cost has been reached, and if it is necessary to accumulate again, the process returns to STEP 31 and repeats the work (STEP 37). When the target construction cost is obtained, it is possible to output a construction description, a quantity calculation sheet, and various drawings with colored integration points (STEP 38).
下水道事業において、STEP32bを選択した場合の積算処理を、図12を用いて具体的に説明する。
まず、システム内では起点情報が設定され(STEP41)、起点における図形の種類がアーク(管渠工)の場合(STEP43a)、変数FIG$には「アーク」が入力される(STEP44a)。指定された図形に付された間内部番号により、アークDBからマンホール1及びマンホール2の情報を取得し、各変数に値を代入する(STEP45a)。アークDBより間内部番号によりリンクされている図形を着色し(STEP46a)、変数NAME1$とNAME2$により事業量、工事費の演算を行う(STEP47a)。事業量、工事費の演算においては、取得した変数を元に「工種別、区間・ケ所毎部材名称の数量×単価=工事費」とし、各工事費の総和を「累加事業費」とする。
The integration process when STEP32b is selected in the sewer business will be specifically described with reference to FIG.
First, starting point information is set in the system (STEP 41), and when the figure type at the starting point is arc (pipe work) (STEP 43a), "arc" is input to the variable FIG $ (STEP 44a). Information on the manhole 1 and manhole 2 is acquired from the arc DB by the internal number assigned to the designated figure, and a value is substituted for each variable (STEP 45a). The figure linked by the internal number from the arc DB is colored (STEP 46a), and the project amount and the construction cost are calculated by the variables NAME1 $ and NAME2 $ (STEP 47a). In the calculation of the project amount and the construction cost, based on the acquired variables, “quantity of work type, part / section / part name x unit price = construction cost”, and the total of each construction cost as “cumulative project cost”.
起点における図形の種類がポイント(マンホール工)の場合(STEP43b)、変数FIG$には「ポイント」が入力される(STEP44b)。指定された図形に付された内部番号により、ポイントDBからマンホールの情報を取得し、各変数に値を代入する(STEP45b)。ポイントDBより内部番号によりリンクされている図形を着色し(STEP46b)、変数NAME$により事業量、工事費の演算を行う(STEP47b)。
アーク(管渠工)又はポイント(マンホール工)の何れでも無い場合には、積算を終了する(STEP43c)。
When the figure type at the starting point is a point (manhole work) (STEP 43b), “point” is input to the variable FIG $ (STEP 44b). Manhole information is acquired from the point DB by the internal number assigned to the specified figure, and a value is substituted for each variable (STEP 45b). The figure linked by the internal number is colored from the point DB (STEP 46b), and the project amount and the construction cost are calculated by the variable NAME $ (STEP 47b).
If neither the arc (pipe work) nor the point (manhole work) is found, the integration is terminated (STEP 43c).
次に、目標金額が累加事業費を超えているか否かの判断を行う(STEP48)。既に目標金額に達している場合は、超えた金額を除いた事業量を算出する。すなわち、変数NAME$がアークの場合には、事業費とLINEから荷重平均又は按分演算で目標金額を満足する管渠工の延長を算出し(STEP59)、その範囲内において当該図形の着色を行う(STEP60)。変数NAME$がアークでない場合には、累加事業費から最後に指定されたマンホール工の工事費を引いたものを積算結果とする(STEP61)。
目標金額が累加事業費を超えていない場合には、継続して積算処理を行う。変数FIG$がアークの場合で、取付管DBより変数NAME1$とマンホール1が一致する場合は(STEP62)、取付管DBより変数NAME3$に取付管番号を代入する(STEP63)。取付管DBにおいて、内部番号によりリンクされている図形を着色し(STEP64)、変数NAME3$により事業量、工事費の演算を行う(STEP65)。
再度、目標金額が累加事業費を超えているか否かの判断を行い(STEP66)、目標金額を超えてない場合にはSTEP62に戻り、目標金額を超えている場合には、取付管の工事費を引いたものを積算結果とする(STEP61)。
変数FIG$がアークであり、且つ取付管DBより変数NAME1$とマンホール1が一致しない場合には、ポイントDBよりNAME2$と一致する内部番号のマンホールを取得し、各変数に値を代入する(STEP56)。接続DBにおいて、変数NAME$と始点マンホールが一致し、且つ変数ROS$と路線(−1レコード)が一致する場合には、STEP55に進み、そうでない場合には、STEP46bに進む。
Next, it is determined whether or not the target amount exceeds the cumulative project cost (STEP 48). If the target amount has already been reached, the business amount excluding the excess amount is calculated. In other words, when the variable NAME $ is arc, the extension of the pipework that satisfies the target amount is calculated from the project cost and LINE by the load average or proportional calculation (STEP 59), and the figure is colored within that range. (STEP60). If the variable NAME $ is not an arc, the cumulative result is the result of subtracting the last designated manhole construction cost (STEP 61).
If the target amount does not exceed the cumulative project cost, the integration process is continued. If the variable FIG $ is an arc and the variable NAME1 $ matches the manhole 1 from the attachment pipe DB (STEP 62), the attachment pipe number is substituted into the variable NAME3 $ from the attachment pipe DB (STEP 63). In the mounting pipe DB, the figure linked by the internal number is colored (STEP 64), and the project amount and the construction cost are calculated by the variable NAME3 $ (STEP 65).
Again, it is determined whether the target amount exceeds the cumulative project cost (STEP 66) .If the target amount is not exceeded, the process returns to STEP 62. The result of subtracting is used as the integration result (STEP 61).
If the variable FIG $ is an arc and the variable NAME1 $ and manhole 1 do not match from the mounting pipe DB, the manhole of the internal number that matches NAME2 $ is acquired from the point DB, and a value is substituted for each variable ( STEP56). In the connection DB, if the variable NAME $ matches the starting point manhole, and if the variable ROS $ matches the route (−1 record), the process proceeds to STEP55; otherwise, the process proceeds to STEP46b.
変数FIG$がアークで無い場合には、接続DBにおいて、変数NAME$と始点マンホールが一致し、且つ変数ROS$と路線が一致するかを確認する(STEP50)。STEP50の条件を満たさない場合には、STEP55に進む。STEP50の条件を満たす場合には、接続DBから一致する行番号を取得し、変数NO2に代入する(STEP51)。変数NO2の値を1増加し(STEP52)、接続DBよりNO2行の始点マンホールを取得し、変数NAME$に値を代入する(STEP53)。ポイントDBよりNAME$と一致する内部番号のマンホールを取得し、各変数に値を代入し、STEP46bに戻る(STEP54)。
STEP50の条件を満たさない場合には、アークDBより変数NAME$と一致する内部番号のマンホールを取得し、各変数に値を代入し、STEP46aに戻る(STEP55)。
If the variable FIG $ is not an arc, it is confirmed in the connection DB whether the variable NAME $ matches the starting point manhole and the variable ROS $ matches the route (STEP 50). If the conditions of STEP50 are not satisfied, go to STEP55. When the condition of STEP50 is satisfied, a matching line number is acquired from the connection DB and substituted into the variable NO2 (STEP51). The value of the variable NO2 is incremented by 1 (STEP 52), the starting point manhole of the NO2 line is acquired from the connection DB, and the value is substituted into the variable NAME $ (STEP 53). A manhole with an internal number matching NAME $ is acquired from the point DB, a value is assigned to each variable, and the process returns to STEP 46b (STEP 54).
If the condition of STEP50 is not satisfied, the manhole of the internal number that matches the variable NAME $ is acquired from the arc DB, the value is assigned to each variable, and the process returns to STEP46a (STEP55).
積算処理で用いる公共下水道事業における内部データの例を図13に示す。
工事費の積算処理では、アークDB、ポイントDB、ポリゴンDB、接続DB、取付管DBの5つのデータが利用される。
アークDBは管渠工におけるデータを管理し、路線(路線番号)は合流毎に打つ番号を、延長はマンホール間の管渠長を、マンホール1,2は管渠両端のマンホール番号をそれぞれ格納する。ポイントDBはマンホール工で必要な路線とマンホール番号の対応を管理している。ポリゴンDBは行番号と制御盤(センターと関係ない構造物)の対応を管理している。接続DBは路線番号と、始点・終点マンホールにより路線の接続データを管理している。取付管DBは、取付管公共桝のデータを管理し、始点マンホール名と、始点マンホール名より順に番号を付して管理している。
これらのDBに振られる間内部番号、内部番号、及び行番号はGIS上で一意に管理される。
An example of internal data in the public sewer business used in the integration process is shown in FIG.
In the construction cost accumulation process, five data of an arc DB, a point DB, a polygon DB, a connection DB, and a mounting pipe DB are used.
The arc DB manages data in pipework, the route (route number) stores the number to be hit at each merge, the extension stores the pipe length between manholes, and the manholes 1 and 2 store the manhole numbers at both ends of the pipework. . The point DB manages the correspondence between routes and manhole numbers required for manhole work. The polygon DB manages the correspondence between line numbers and control panels (structures not related to the center). The connection DB manages route connection data using route numbers and start / end manholes. The mounting pipe DB manages the data of the mounting pipe public fence, and manages the starting point manhole name and the starting point manhole name in order.
While assigned to these DBs, internal numbers, internal numbers, and line numbers are uniquely managed on the GIS.
また、本発明では、図14に示すように構造物の図面、工事費、及び制御図を同時に表示することもできる。すなわわち、メインパネルに表示される制御図には種々のものがあるが、そこで施工箇所を指定すると、指定位置情報表示パネルに対応する図面・帳票、施行材料及び工事費が表示される。 Moreover, in this invention, as shown in FIG. 14, the drawing of a structure, a construction cost, and a control diagram can also be displayed simultaneously. In other words, there are various types of control diagrams displayed on the main panel, but when a construction location is designated there, the drawing / form corresponding to the designated position information display panel, execution materials and construction costs are displayed. .
(設計図の再利用)
上述のとおり、本発明においては前の作業で作成した図面を繰り返し利用することで、図面作成に伴う作業負荷を大幅に削減している。各作業においてベースとする設計書と出力の関係を示したものが図15である。
概略設計においては、認可設計時に作成した(A)認可設計図を予算要望、交付申請の各作業において利用し、詳細設計、請負設計においては(D)実施設計図を、出来高設計においては、(G)工事実施管理図を、維持管理においては(H)出来高管理図を再利用している。
(Reuse of blueprints)
As described above, in the present invention, by repeatedly using the drawing created in the previous work, the workload associated with drawing creation is greatly reduced. FIG. 15 shows the relationship between the design document and output based on each work.
In rough design, (A) approved design drawing created at the time of approved design is used in each budget request and grant application work, (D) implementation design drawing in detailed design and contract design, and ( G) Reuse construction control charts and (H) Volume control charts for maintenance.
(データ関連図)
図16は、本発明に係るシステムのデータ関連図を示したものである。本発明においては、認可設計又は実施設計に関するデータを地理情報に関連付けて保持している。これにより、画面上に表示された制御図を用いて、工事費の積算を行うことを可能としている。
図16の例では、GISの画面右側のウィンドウに制御図が表示され、画面左下の指定位置情報表示パネルに累加事業量及び工事費が表示される。
(Data relationship diagram)
FIG. 16 shows a data relation diagram of the system according to the present invention. In the present invention, data relating to the authorized design or the implementation design is held in association with the geographical information. As a result, the construction cost can be accumulated using the control diagram displayed on the screen.
In the example of FIG. 16, the control diagram is displayed in the window on the right side of the GIS screen, and the cumulative project amount and the construction cost are displayed on the designated position information display panel in the lower left of the screen.
以下では、本発明の詳細を実施例で説明する。本発明は、これらの実施例により何ら限定されるものではない。 Hereinafter, details of the present invention will be described by way of examples. The present invention is not limited in any way by these examples.
実施例1は、埋設管工事において工事費積算を行う際のシステム処理手順を示している。図17a〜17cに示すとおり、本実施例においては、数量データDBに補修部材数量データを入力し、属性データに家屋データを入力することで、埋設管工事における埋設管管理及び補修費積算を行うことを可能としている。 Example 1 has shown the system processing procedure at the time of performing construction cost accumulation | storage in a buried pipe construction. As shown in FIGS. 17a to 17c, in this embodiment, the repair member quantity data is input to the quantity data DB, and the house data is input to the attribute data, thereby performing embedded pipe management and repair cost accumulation in the buried pipe work. Making it possible.
本発明に係る出来高管理モデルの登録方法を、道路工事の実施例で説明する。
図18の下段は、道路工事における平面図であり、道路を上面から見た図面である。平面図において使用される符号は、符号の説明に記載の構造物である。
道路工事の場合は、通常道路の長手方向に向かって概ね一定間隔で杭打ちがなされ、中心線がひかれる。中心線上の杭と杭の間の区間を中心線区間といい、例えば、測点番号No.0とNo.1の間、No.1とNo.2の間の区間がそれに該当する。図18の上段は、中心線と直角の線上の断面方向の標準横断図(代表的な構造物を示す)である。図19は、中心線から離れた構造物32はNo数字の多い進行方向の右側の擁壁41と左側の側溝40と集水桝44、中心構造として土工46、舗装45である。制御図にあらわす記号としては擁壁41、側溝40は線で表し、集水桝44は白抜きの四角であらわす。また、土工46と舗装45は中心線の両側にそれぞれ線であらわす。
A method for registering a volume management model according to the present invention will be described in an embodiment of road construction.
The lower part of FIG. 18 is a plan view in road construction, and is a view of the road as viewed from above. The code | symbol used in a top view is a structure as described in description of a code | symbol.
In the case of road construction, piles are made at regular intervals in the longitudinal direction of the normal road, and the center line is drawn. A section between the piles on the center line is called a center line section, for example, a section between station numbers No. 0 and No. 1 and a section between No. 1 and No. 2 corresponds to it. The upper part of FIG. 18 is a standard cross-sectional view (a typical structure is shown) in a cross-sectional direction on a line perpendicular to the center line. In FIG. 19, the structure 32 apart from the center line is a retaining wall 41 on the right side, a left side groove 40 and a water collecting basin 44 in the traveling direction with a large number, and an earthwork 46 and a pavement 45 as the center structure. As symbols shown in the control diagram, the retaining wall 41 and the side groove 40 are represented by lines, and the water collecting basin 44 is represented by a white square. Moreover, the earthwork 46 and the pavement 45 are represented by lines on both sides of the center line.
図19は、本実施例に係る道路の制御図の詳細情報を示したものであり、システム上に入力される全ての情報が説明の便宜上表現されている。
平面図上の中心線と直角な直線である14a〜14gは、横断方向線であり、横断方向線と横断方向線の間が中心線区間である。本実施例における道路工においては全ての構造物に中心線区間情報を持たせることにより、中心線を指定することで中心線区間に存在する全ての構造物の積算管理を行うことができる。横断方向線で区切られた構造物は、対応する横断方向線の若い方のアルファベットが付されており、例えば、「33、40a」と付された構造物は、中心線14aと14bの間にある、中心線区間共有構造物である側溝を意味する。
FIG. 19 shows the detailed information of the road control diagram according to the present embodiment, and all information input on the system is expressed for convenience of explanation.
14a to 14g, which are straight lines perpendicular to the center line on the plan view, are transverse lines, and the section between the transverse line and the transverse line is a center line section. In the road construction in the present embodiment, by providing centerline section information to all structures, it is possible to perform integration management of all structures existing in the centerline section by designating the centerline. The structures separated by the transverse lines are given the younger alphabet of the corresponding transverse lines. For example, the structures marked “33, 40a” are between the center lines 14a and 14b. It means a side groove that is a centerline section shared structure.
図20は、本実施例に係るシステム上に表示される制御図であり、実際のシステム上には図19の一部の情報のみを記載した制御図が表示される。当該制御図上で構造物の記号を指定すると、指定された構造物の記号が太字で着色表示され、構造物が指定されたことを確認することができる。なお、図20においては、説明の便宜上すべての構造物の記号を指定している。 FIG. 20 is a control diagram displayed on the system according to the present embodiment, and a control diagram describing only a part of the information in FIG. 19 is displayed on the actual system. When the symbol of the structure is designated on the control diagram, the symbol of the designated structure is colored and displayed in bold and it can be confirmed that the structure is designated. In FIG. 20, symbols for all structures are designated for convenience of explanation.
図21は、本実施例に係る出来高管理モデルの設定表であり、実施設計の数量計算書を各測点間の数量に区切り、名称に出来高管理モデルコードを打った数量データベースである。 FIG. 21 is a setting table of a volume management model according to the present embodiment, which is a quantity database in which the quantity calculation sheet of the implementation design is divided into quantities between each measurement point, and the volume management model code is entered in the name.
図22は、道路工の認可設計における従来例と本実施例2の比較表であり、図23は、実施設計における従来例と本実施例2の比較表である。 FIG. 22 is a comparison table between the conventional example in the approved design of the road engineer and the present Example 2, and FIG.
図24a及び24bは、本実施例に係る工種別、区間・ヶ所毎部材名称の数量積算様式の中間処理の出力結果である。
図24aの上段の説明(構造物の分類及び数量計算書様式)は、従来から定められた様式に関するものである。
24a and 24b show the output results of the intermediate processing of the quantity integration style of the construction type, section / location member name according to the present embodiment.
The upper description of FIG. 24a (structure classification and quantity calculation form) relates to a conventionally defined form.
(区間構造物)
区間構造物は、測点毎に断面積・法長が変化するものであり、構造物が中心線に並行している構造物については、平均断面方式(A様式)を使用する。
測点毎に断面積・法長が変化するもので、構造物が中心線と並行でない構造物については、中心距離とは別に測定した距離を使用して断面平均方式(B1様式)を使用する。なお、材料名称毎に算式を立てて数量を計算する展開図方式(B2様式)もあるが、本実施例ではB1様式をB様式としてあらわすものとする。
構造物の型式が一定の場合の様式としては、型式調書方式を使用する。型式長所方式には、測点区間毎に延長を区切るC1様式と構造物名と起終点を示す全延長をあらわすC2様式があるが、本実施例では、C1様式をC様式としてあらわすものとする。
(Section structure)
The section structure has a cross-sectional area and a length that change every measurement point, and the average cross-section method (A style) is used for a structure in which the structure is parallel to the center line.
For structures where the cross-sectional area and method length vary from station to station and the structure is not parallel to the center line, use the cross-section average method (B1 style) using the distance measured separately from the center distance. . In addition, there is a development view method (B2 style) for calculating the quantity by formulating for each material name, but in this embodiment, the B1 style is represented as the B style.
A model record method is used as a form when the structure type is constant. There are C1 styles that divide the extension for each station section and C2 styles that represent the entire extension that indicates the name of the structure and the start and end points. In this embodiment, the C1 style is represented as the C style. .
(位置構造物)
位置構造物は材料名称毎に算式を立てて、数量を計算する構造物単体方式(D様式)を使用する。
下段の内部演算明細書は、本発明の内部計算様式を示すものである。
各様式共通事項は、下記の通りである。
すなわち、
1.数量を測点間毎に区切る。
2.制御図と出来高管理モデルをリンクする。
3.名称毎に単価と出来高管理モデルをリンクする。
4.区間毎に名称数量×単価=金額を内部計算する。
5.制御図で指定された区間と出来高管理モデルを区間の横方向に集計して金額を出し、諸経費を加えて区間工事費とする。
6.工事費を縦計して累加工事費を求める。
(Position structure)
The position structure uses a structure single unit method (D style) for calculating the quantity by formulating each material name.
The lower internal operation specification shows the internal calculation mode of the present invention.
Items common to each form are as follows.
That is,
1. Divide the quantity between stations.
2. Link the control diagram with the volume management model.
3. Link the unit price and volume management model for each name.
4). Internally calculate name quantity x unit price = amount of money for each section.
5). The section specified in the control chart and the volume management model are totaled in the horizontal direction of the section, and the amount is calculated.
6). Calculate the total processing cost by verticalizing the construction cost.
図24bは、内部演算イメージ図である。左側が全体設計における設計様式を示した物であり、中央のGISは表示された制御図との関連を示し、右側の年度・工区設計は、制御図を指定して目標工事費に達して出力したものである。なお、出力は従来定められた様式であり、また、図面は着色されて出力される。 FIG. 24b is an internal calculation image diagram. The left side shows the design style in the overall design, the central GIS shows the relationship with the displayed control chart, and the right year / section design shows the target construction cost and outputs it by specifying the control chart It is a thing. The output is in a conventionally defined format, and the drawings are colored and output.
以下、図19の道路工の擁壁工において、起点・方向指定手段を選択した場合の工事費算出手順を具体的に説明する。
まず、起点をNO.0、方向をNO.nと指定し、目標工事費 3,000,000円と入力する。すると、図15の最右列に示すように、終点を各Noとした場合の累加工事費が算出される。累加工事費を順次演算していくと、NO.3の地点において累加工事費が3,371,486円となり、目標工事費の3,000,000円を超える。そこでNO.2とNO.3の区間で按分計算を行い、目標工事費を満足する地点算出する。
例えば、NO.2から7.5m地点における左から3列目の断面は{(NO.3断面-NO.2断面)/区間距離}*調整区間距離+NO.2断面=NO.2+7.5から{(3.245-2.465)/10.0}*7.50+2.465=3.050 が算出され、左から4列目の平均断面は(NO.2断面+NO.2+7.5断面)/2=NO.2+7.5から(2.465+3.050)/2=2.76が算出され、左から5列目の立積は(NO.2+7.5平均断面*調整区間距離)=NO.2+7.5から(2.76*7.5)=20.68が算出される。
以上の結果から、下から2行目の最右列に示すように、NO.2から7.5mの地点における工事費は3,000,418円となるから、擁壁工の累加事業費は延長27.5mとなる。画面上には、累加事業量=27.5m、工事費=3,000,418円が表示されると共に、図26に示すように調整区間が着色表示される。
Hereinafter, the construction cost calculation procedure when the starting point / direction specifying means is selected in the retaining wall work of the road work in FIG. 19 will be specifically described.
First, specify NO.0 as the starting point, NO.n as the direction, and enter the target construction cost of 3,000,000 yen. Then, as shown in the rightmost column of FIG. 15, the cumulative processing cost when the end point is set to each No is calculated. If the progressive machining costs are calculated sequentially, the cumulative machining costs at the No. 3 point will be 3,371,486 yen, exceeding the target construction cost of 3,000,000 yen. Therefore, apportionment calculation is performed in the section of NO.2 and NO.3 to calculate the point that satisfies the target construction cost.
For example, the cross section in the third row from the left at a point 7.5 m from NO.2 is {(NO.3 cross section-NO.2 cross section) / section distance} * adjustment section distance + NO.2 cross section = NO.2 + 7.5 {(3.245-2.465) /10.0} * 7.50 + 2.465 = 3.050 is calculated, and the average cross section in the fourth column from the left is (NO.2 cross section + NO.2 + 7.5 cross section) /2=NO.2+7.5 (2.465 + 3.050) /2=2.76 is calculated, and the product in the fifth column from the left is (NO.2 + 7.5 average cross section * adjustment section distance) = NO.2 + 7.5 to (2.76 * 7.5) = 20.68 Calculated.
From the above result, as shown in the rightmost column in the second row from the bottom, the construction cost at the point of 7.5m from NO.2 will be 3,000,418 yen, so the cumulative project cost of retaining wall will be extended 27.5m . On the screen, the cumulative project amount = 27.5 m and the construction cost = 3,000,418 yen are displayed, and the adjustment section is displayed in color as shown in FIG.
図27に本実施例に係るシステム処理手順を示す。 FIG. 27 shows a system processing procedure according to the present embodiment.
2 パーソナルコンピュータ
10 中心線
11 測点番号
12 中心線区間
13 中心線位置
22 中心構造物
23 中心区間構造物
24 中心位置構造物
25 中心分岐構造物
32 中心線から離れた構造物
33 中心線区間共有構造物
34 中心線位置共有構造物
40 側溝
41 擁壁
42 ガードレール
43 ブロック積
44 集水桝
45 舗装
46 土工
47 L型水路
48 下水管渠
49 下水管土工
50 下水管舗装
51 マンホール
52 取付管
53 公共桝
54 マンホールポンプ
60 構造物の着色記号
2 Personal computer 10 Center line 11 Station number 12 Center line section 13 Center line position 22 Center structure 23 Center section structure 24 Center position structure 25 Center branch structure 32 Structure away from center line 33 Sharing center line section Structure 34 Centerline shared structure 40 Side groove 41 Retaining wall 42 Guard rail 43 Block 44 44 Drainage tank 45 Pavement 46 Earthwork 47 L-shaped waterway 48 Sewer pipe 49 Sewer pipe earthwork 50 Sewer pipe pavement 51 Manhole 52 Mounting pipe 53 Public桝 54 Manhole pump 60 Structure coloring symbol
Claims (2)
記憶手段から図面データ、出来高管理モデルデータ、設計諸元データ及び数量データを読み出し、これらの関連付けがなされ出来高管理モデルにより構造物が示された設計諸元データ付き平面図である制御図をGISの機能を用いて作成し、作成した制御図データを記憶手段に記憶する手段と、
記憶手段から制御図データを読み出し、表示手段に制御図を表示させる手段と、
表示手段により表示された制御図において入力手段により任意の区間・ヶ所および出来高管理モデルを選択可能とする選択手段と、
表示手段により表示された制御図において選択された区間・ヶ所および出来高管理モデルを着色して表示させる手段と、
選択された区間・ヶ所および出来高管理モデルに基づき、記憶手段から出来高管理モデルデータ、設計諸元データ、数量データ及び積算データを読み出し、累加事業量及び累加事業費を自動積算する積算手段と、
自動積算した累加事業量及び累加工事費を表示手段に表示させる手段と、
予算要望書、補助金交付申請書、委託設計書、請負設計書、変更設計書、及び出来高設計書を含む帳票を表示手段に表示させる手段を有する設計・管理支援システム。 Input means, display means and on volume management model data including drawing data, volume management model classified into several models for each process the volume of construction is possible structures across year including the plan view, the tube type GIS comprising storage means for registering design specification data including pipe diameter, earthwork type and earth retaining type, quantity data including work type and member name, and accumulated data including amount per unit quantity of member name A design and management support system for buried pipe work and civil engineering work using
Drawing data, volume management model data, design specification data, and quantity data are read from the storage means, and the control diagram, which is a plan view with design specification data in which the structure is shown by the volume management model, is related to GIS. Means created using the function and storing the created control diagram data in the storage means;
Means for reading out the control diagram data from the storage means and displaying the control diagram on the display means;
A selection means for enabling selection of an arbitrary section / location and a volume management model by an input means in the control diagram displayed by the display means;
Means for coloring and displaying the section / location and the volume management model selected in the control diagram displayed by the display means;
Based on the selected section / location and the volume management model , the volume management model data, the design specification data, the quantity data, and the accumulation data are read from the storage means, and the accumulation means for automatically accumulating the accumulated project amount and the accumulated project cost,
Means for displaying on the display means the automatically accumulated cumulative business volume and cumulative processing costs;
A design / management support system having means for displaying a form including a budget request, subsidy grant application, consignment design, contract design, change design, and volume design on a display .
(A)入力手段により起点、方向及び目標工事費を入力することにより、区間とヶ所の荷重平均又は按分計算に基づき目標工事費に到達するまでヶ所・区間を自動指定する手段、
(B)入力手段により起点及び終点を入力することにより、起点から終点までを自動指定する手段、
(C)入力手段により中間点を含む起点及び中間点を含む終点を入力することにより、中間点を含む起点から中間点を含む終点までを自動指定する手段、
を含むことを特徴とする請求項1の設計・管理支援システム。 The selection means includes
(A) By automatically entering the starting point, direction, and target construction cost using the input means, the means to automatically specify the location / section until the target construction cost is reached based on the load average of the section and location or apportionment calculation ,
(B) means for automatically specifying from the start point to the end point by inputting the start point and end point by the input means;
(C) means for automatically designating from the start point including the intermediate point to the end point including the intermediate point by inputting the start point including the intermediate point and the end point including the intermediate point by the input means;
The design / management support system according to claim 1, comprising:
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2004240179A JP4565494B2 (en) | 2003-08-19 | 2004-08-19 | Design and management support system for buried pipe work and civil engineering work |
Applications Claiming Priority (3)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2003295663 | 2003-08-19 | ||
JP2003393198 | 2003-11-25 | ||
JP2004240179A JP4565494B2 (en) | 2003-08-19 | 2004-08-19 | Design and management support system for buried pipe work and civil engineering work |
Related Child Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2010104834A Division JP5114528B2 (en) | 2003-08-19 | 2010-04-30 | Design and management support system for buried pipe work and civil engineering work |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2005182750A JP2005182750A (en) | 2005-07-07 |
JP4565494B2 true JP4565494B2 (en) | 2010-10-20 |
Family
ID=34799276
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2004240179A Expired - Fee Related JP4565494B2 (en) | 2003-08-19 | 2004-08-19 | Design and management support system for buried pipe work and civil engineering work |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP4565494B2 (en) |
Families Citing this family (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP5435639B2 (en) * | 2009-12-28 | 2014-03-05 | 株式会社進日本工業 | Management system for water pipe repair work |
JP7418069B1 (en) | 2022-02-16 | 2024-01-19 | 株式会社Gacci | Transaction information management server, transaction information management system, transaction information management method, transaction information management program |
CN114996798B (en) * | 2022-04-28 | 2023-04-11 | 中铁长江交通设计集团有限公司 | Automatic dredging construction drawing creating method and system based on Civil3D |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0728873A (en) * | 1993-07-09 | 1995-01-31 | Meidensha Corp | Drawing input device for piping design of city water |
JP2001249985A (en) * | 1999-12-27 | 2001-09-14 | Ohbayashi Corp | Execution plan supporting system, execution plan supporting method, and recording medium recorded with computer program for realizing execution plan supporting system |
JP2001325310A (en) * | 2000-05-16 | 2001-11-22 | Jekku:Kk | Support system for sewerage construction designing |
-
2004
- 2004-08-19 JP JP2004240179A patent/JP4565494B2/en not_active Expired - Fee Related
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0728873A (en) * | 1993-07-09 | 1995-01-31 | Meidensha Corp | Drawing input device for piping design of city water |
JP2001249985A (en) * | 1999-12-27 | 2001-09-14 | Ohbayashi Corp | Execution plan supporting system, execution plan supporting method, and recording medium recorded with computer program for realizing execution plan supporting system |
JP2001325310A (en) * | 2000-05-16 | 2001-11-22 | Jekku:Kk | Support system for sewerage construction designing |
Also Published As
Publication number | Publication date |
---|---|
JP2005182750A (en) | 2005-07-07 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP5114528B2 (en) | Design and management support system for buried pipe work and civil engineering work | |
Bansal | Use of GIS and topology in the identification and resolution of space conflicts | |
Bansal et al. | Potential of geographic information systems in building cost estimation and visualization | |
CN111428306A (en) | Road fine design method | |
US7830373B1 (en) | System and methods of civil engineering objects model | |
CN112733247A (en) | Large project field planning method | |
O'Brien et al. | Benefits of three-and four-dimensional computer-aided design model applications for review of constructability | |
Sharma et al. | Location-based planning and scheduling of highway construction projects in hilly terrain using GIS | |
Tanoli et al. | 3D design modeling application in machine guidance system for earthwork operations | |
Kang et al. | Development of methodology and virtual system for optimised simulation of road design data | |
JP5217462B2 (en) | Road information management device | |
JP4565494B2 (en) | Design and management support system for buried pipe work and civil engineering work | |
CN115239281A (en) | BIM + GIS-based road migration management system, method and storage medium | |
Jeonghwan et al. | 3D earthwork BIM design and its application in an advanced construction equipment operation | |
JP2001325310A (en) | Support system for sewerage construction designing | |
JP2984262B1 (en) | Underground line support system | |
Maier et al. | Automation in Highway Construction Part II: Design Guidance and Guide Specification Manual | |
de Lima et al. | Optimization of earthmoving operations planning: a novel approach considering interferences | |
JP6568989B1 (en) | Fixed asset management system | |
Tanoli et al. | PAD Based 3D Earthwork BIM Design Module for Machine Guidance | |
JP4164745B2 (en) | 3D surveying support method and apparatus | |
Reeder et al. | 3D engineered models for highway construction: the Iowa experience. | |
WO2015139086A1 (en) | Method of preparing an application to make an improvement to a site | |
Rezouki et al. | Application of geographic information system for preparing the bill of quantities of construction projects | |
Wolf | The Development of a Site Plan and Flatwork Design for Good Rest Orphanage |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20070604 |
|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20090826 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20090902 |
|
A521 | Request for written amendment filed |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20091102 Free format text: JAPANESE INTERMEDIATE CODE: A821 Effective date: 20091102 |
|
A02 | Decision of refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A02 Effective date: 20100202 |
|
A521 | Request for written amendment filed |
Free format text: JAPANESE INTERMEDIATE CODE: A821 Effective date: 20100430 Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20100430 |
|
A911 | Transfer to examiner for re-examination before appeal (zenchi) |
Free format text: JAPANESE INTERMEDIATE CODE: A911 Effective date: 20100511 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20100728 |
|
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20100729 |
|
R150 | Certificate of patent or registration of utility model |
Ref document number: 4565494 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130813 Year of fee payment: 3 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
LAPS | Cancellation because of no payment of annual fees |