EP3337752A1 - Mobile crane and method for angling a main boom extension in relation to a main boom of a mobile crane - Google Patents

Mobile crane and method for angling a main boom extension in relation to a main boom of a mobile crane

Info

Publication number
EP3337752A1
EP3337752A1 EP16798539.9A EP16798539A EP3337752A1 EP 3337752 A1 EP3337752 A1 EP 3337752A1 EP 16798539 A EP16798539 A EP 16798539A EP 3337752 A1 EP3337752 A1 EP 3337752A1
Authority
EP
European Patent Office
Prior art keywords
main boom
extension
mobile crane
boom extension
main
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
EP16798539.9A
Other languages
German (de)
French (fr)
Other versions
EP3337752B1 (en
Inventor
Roland Kuhn
Michael Martin
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Terex Global GmbH
Original Assignee
Terex Global GmbH
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Terex Global GmbH filed Critical Terex Global GmbH
Publication of EP3337752A1 publication Critical patent/EP3337752A1/en
Application granted granted Critical
Publication of EP3337752B1 publication Critical patent/EP3337752B1/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C23/00Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes
    • B66C23/62Constructional features or details
    • B66C23/64Jibs
    • B66C23/70Jibs constructed of sections adapted to be assembled to form jibs or various lengths
    • B66C23/701Jibs constructed of sections adapted to be assembled to form jibs or various lengths telescopic
    • B66C23/702Jibs constructed of sections adapted to be assembled to form jibs or various lengths telescopic with a jib extension boom
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C23/00Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes
    • B66C23/06Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes with jibs mounted for jibbing or luffing movements
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C23/00Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes
    • B66C23/18Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes specially adapted for use in particular purposes
    • B66C23/36Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes specially adapted for use in particular purposes mounted on road or rail vehicles; Manually-movable jib-cranes for use in workshops; Floating cranes
    • B66C23/42Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes specially adapted for use in particular purposes mounted on road or rail vehicles; Manually-movable jib-cranes for use in workshops; Floating cranes with jibs of adjustable configuration, e.g. foldable
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C23/00Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes
    • B66C23/62Constructional features or details
    • B66C23/64Jibs
    • B66C23/68Jibs foldable or otherwise adjustable in configuration
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C23/00Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes
    • B66C23/62Constructional features or details
    • B66C23/82Luffing gear

Definitions

  • the invention relates to a mobile crane with a rocker mounted thereon and erectable via a luffing cylinder main boom and with a detachably connected to a main boom head of the main boom on top bolts and lower bolts main boom extension, the Stilauslegerverrascherung starting from a basic position after loosening the upper bolt by means of a Abwinkelantriebs order a luffing axis relative to the main boom is angled, the Abwinkelantrieb engages a foot of the main boom extension, a provided for another task drive the mobile crane provides the kinetic energy for the Abwinkelantrieb.
  • the invention relates to a method for bending in a
  • Main boom extension relative to a main boom of a mobile crane the main boom is tiltably mounted on the mobile crane and erectable via a luffing cylinder, the main boom extension is releasably connected to a main boom head of the main boom via upper bolts and lower bolts, a Abwinkelantrieb engages a foot of the main boom extension, by means of the Abwinkelantriebs, which refers to the Abwinkein its kinetic energy from a drive of the mobile crane, which is otherwise provided for another task of the mobile crane, the main boom extension is raised from a basic position about a rocking axis relative to the main boom, as far as the upper pin relieves then the top bolts are removed.
  • German Utility Model DE 20 2004 020 760 U1 already discloses a mobile crane with a main boom and a main boom extension attached to its main boom head.
  • the main boom extension is from a home position in which the main boom extension with its
  • Longitudinal direction is aligned in extension of the longitudinal direction of the main boom, in a 20 ° position and a 40 ° position tiltable.
  • Main boom extension is usually over two lower in the range of lower boom of the main boom extension and two upper in the range of
  • the upper boom of the main boom extension bolts arranged releasably attached to the main boom head.
  • the two upper bolts are pulled and in a second step, hydraulic rocker cylinders, which engage the main boom head and the main boom extension, cause the rocker axes of the two rocker pins to rock from the basic position
  • Main boom extension effected.
  • the two upper pins are inserted and removed via a hydraulic bolting cylinder.
  • a self-sufficient hydraulic unit is arranged at the lower end of the main boom extension.
  • Hydraulic unit for example, a diesel engine or electric motor can be used in each case with an associated hydraulic pump.
  • the object of the invention is to provide a mobile crane and a method for tilting a main boom extension relative to a main boom of a mobile crane, with which the angle of the main boom extension is simplified.
  • the main boom extension in a mobile crane with a rockable mounted thereto and erectable via a luffing jib main boom and with a detachably connected to a main boom head of the main boom via upper bolts and lower bolts main boom extension, the main boom extension, starting from a normal position after loosening the upper bolt by means of a Abwinkelantriebs about a rocking axis relative to the main boom
  • the mobile crane provides the kinetic energy for the Abwinkelantrieb, a simplification achieved in that the Abwinkelantrieb is designed such that a telescoping cylinder of the main boom, the kinetic energy for the Abwinkelantrieb supplies. This ensures that the Abwinkein does not take place via external aids or additional auxiliary cylinder, but existing drives are used on the mobile crane, which are available anyway.
  • the angle is not over in addition
  • the Abwinkein in itself is largely on the floor or the storage position of the main boom, so that it is not necessary to work well above the top of the mobile crane.
  • the invention permits the deviation of the main boom extension with a mobile crane standing on a level ground with horizontally aligned telescopic boom.
  • the luffing cylinder of the main boom is used for the last part of the boom extension in a 20 ° or 40 ° position.
  • the Abwinkelantrieb on the one hand acts on the main boom and on the other hand on the main boom extension in the region of the upper flange.
  • the Abwinkelantrieb is designed such that the main boom extension against the gravitational force of the main boom extension about the rocking axis is pivotally raised and lowered.
  • Coupling rod comprises, the coupling rod is attached to a first coupling rod end to the upper flange of the main boom extension and attached to a second coupling rod end to the main boom, the length of the coupling rod is chosen so that a previously extended to a Ausfahrweg main boom is then so retractable and extendable in that the main boom extension is pivotally raisable and lowerable about the rocking axis against the force of gravity of the main boom extension.
  • Main boom extension relative to a main boom of a mobile crane, wherein the main boom is tiltably mounted on the mobile crane and erectable via a luffing cylinder, the main boom extension is releasably connected to a main boom head of the main boom via upper bolts and lower bolts, a
  • a mobile crane is understood as meaning both a mobile telescopic crane and a movable crawler crane with a lattice boom.
  • Figure 1 is a side view of a main boom with a
  • Figure 2a is a side view of a Abwinkellasche in a 40 ° position
  • FIG. 2b shows a sectional view of FIG. 2a
  • FIG. 2c shows a plan view of an angled lug in a transport position
  • FIG. 2d shows a sectional view of FIG. 2c
  • FIG. 2e shows a side view of an angled lug in a 20 ° position
  • FIG. 3 shows the main arm according to FIG. 1 with the main boom extension in a 20 ° position
  • FIG. 4 shows the main boom according to FIG. 1 with the main boom extension in a 40 ° position
  • FIG. 5 shows a detailed view of FIG. 4 with an angled lug in the stop position
  • FIG. 6 shows a detailed view from the area of the coupling of FIG
  • Main boom extension to the main boom and a tie rod to the angle
  • Figure 7 is a view as in Figure 6 in another position of
  • Main boom extension. 1 shows a side view of a main boom 1 of a telescopic crane, not shown, is shown. Of the telescopic crane only a base frame 2 of a superstructure is shown. On the base frame 2, the main boom 1 is pivotally mounted with its main boom 1 c in the usual manner about a substantially horizontal axis and a symbolically indicated by a line rocker cylinder 3, which acts on the base frame and the main boom 1, in
  • the main boom 1 is shown in a so-called stowed position, in which the main boom 1 is aligned with its longitudinal direction substantially horizontally.
  • the main boom 1 is designed as a telescopic boom with a base box 1 b and guided therein telescopic shots 1 d and has at its the base frame 2 of the upper carriage end facing away from a main boom head 1 b and thus at the innermost
  • the telescopic boom is arranged in the usual way via a not shown and in the innermost telescopic section 1 d
  • Telescopic cylinder extendable and retractable.
  • On the main boom head 1 b is a
  • the main boom extension 4 can be used temporarily or permanently with the telescopic crane to achieve over the largest boom length of the main boom 1 beyond even greater overall length of the boom or to allow working behind building edges.
  • This main boom extension 4 is designed as a lattice mast, which is a truss pipe construction in the usual way.
  • Main boom extension 4 are in Figure 1 in a 0 ° position or normal position in which the longitudinal direction H of the main boom 1 and the longitudinal direction V of the main boom extension 4 are aligned with each other or parallel to each other.
  • a so-called rocking angle a of the main boom 1 relative to the superstructure 2 is thus 0 ° in the stored position. With the rocking angle a, the erection of the main boom 1 relative to the superstructure 2 is described.
  • the main boom extension 4 is spaced in this basic position of a bottom 10 and is thus of the
  • Main boom 1 via a bolt on the main boom head 1 a worn.
  • Such main boom extensions 4 are basically constructed as modular systems of individual main elements and can be assembled according to the requirements of its length or carrying capacity. The single ones
  • Main elements have transportable dimensions and are not carried along with the telescopic crane in most cases, but are transported separately. If the axle loads of the telescopic crane and the size of the
  • Main boom extension 4 allow, if necessary, the
  • Main boom extension 4 are carried. This would then be in a transport position laterally next to and parallel to the main boom 1. A connection of the individual main elements to each other to the desired
  • Main boom extension 4 via bolt connections in corresponding Verbolzungs slaughter A, B, C and D.
  • the attachment to the main boom head 1 a can be made elementary or as a preassembled unit or units.
  • FIG. 2a shows a side view of an angled flap 9 in a maximally extended 40 ° position.
  • the Abwinkellasche 9 via the manual over a stop surface 9a (see Figure 2d) a displacement and thus the angle of deflection b is limited, consists essentially of a sliding tab 9b with a slot-shaped guide opening 9c, on which a guide tab 9d in
  • the sliding lug 9b is formed as an elongated flat profile with the stopper opening 9c and extends substantially parallel to the longitudinal direction V of the main boom extension 1.
  • On one of the main boom head 1 a end facing the sliding lug 9b has a bore 9j (see Figure 2d), via which the sliding latch 9b each with a connecting bolt 9e on the main boom head 1 a at one of the Verbolzungsstellen E and F is releasably attached.
  • the connecting bolt 9e is aligned with its longitudinal extension parallel to the upper or lower roller head axles 12a, 12b.
  • the guide plate 9d On the sliding tab 9b, the guide plate 9d is pushed, which for this purpose has a closed rectangular cross-section with a guide opening 9f (see Figure 2b), in which the sliding tab 9b is inserted and slidably guided.
  • the guide plate 9d per se is releasably secured to a main boom 1 a end facing via a respective further connecting pin 9i in one of the Verbolzungslitis G and H on the main boom extension 4.
  • the connecting pin 9i is aligned with its longitudinal extent parallel to the upper and lower roller head axles 12a, 12b.
  • the terminal pin 9i is passed through the stopper opening 9c of the slide tab 9b.
  • a first of the two stop holes 9g serves to limit the angle of deflection b to 20 ° and a second to 40 °.
  • the stop holes 9g for 40 ° are correspondingly closer to the main boom head 1a arranged to allow a larger displacement.
  • FIG. 2a shows a sectional view of FIG. 2a along section line AA. It can be seen that the guide tab 9d a rectangular
  • Cross-section having a central guide opening 9f, in which the sliding tab 9b is guided with its stop opening 9c.
  • FIG. 2c shows a plan view of an angled lug 9 in a transport position.
  • the Abwinkellasche 9 is not attached via the connecting bolt 9 e on the main boom head 1 a and the sliding tab 9 b is in the direction of the main boom extension 4 in the
  • FIG. 2d shows a sectional view of FIG. 2c along the section line B-B in FIG. 2c. In this view, the stopper opening 12c and the two
  • FIG. 2e shows a side view of an angled lug 9, which substantially corresponds to the angled lug 9 shown in FIG. 2a.
  • the Abwinkellasche 9 is not shown in the 40 ° position, but in the 20 ° - position.
  • the stopper pin 9h is inserted in the stopper hole 9g remote from the main jib head 1a.
  • Main boom extension 4 in a 20 ° position, the position described above is shown, in which the lowered tip 4a is supported on the bottom 10.
  • Main boom extension 1 a in a 40 ° position in which the lowered tip 4 a is supported on the floor 10.
  • FIG. 5 shows a detailed view of FIG. 4 from the area of the coupling of the main boom extension 4 to the main boom 1 with an angled lug 9 in the stop position to a desired maximum angle position.
  • FIG. 6 is a detail view of the coupling of the Main boom extension 4 to the main boom 1 shown in basic position.
  • the kinetic energy for bending the main boom extension 4 is provided here as an alternative to the previously described embodiment via a combination of a coupling rod 1 1 with a telescopic cylinder telescopic main boom 1 available.
  • the coupling rod 1 1 is aligned substantially parallel to the longitudinal direction H of the main boom 1 and to the longitudinal direction V of the main boom extension 4 and at a first
  • the opposite second coupling rod end 1 1 b is also via a horizontally extending bolt on a base box 1 b of the
  • Main boom 1 stored.
  • the length of the coupling rod 1 1 is chosen so that one extended by a Ausfahrweg x relative to the base box 1 b
  • Telescopic shot 1 c is then so retractable and extendable that the
  • Main boom extension 4 to the rocker axis W is pivotally raised and lowered.
  • the two coupling rod ends 1 1 a, 1 1 b the
  • Coupling rod 1 1 with a slot 1 1 c are provided to after a
  • Main boom extension 4 in a rocking angle a, which is enclosed by the longitudinal direction H of the main boom 1 and the horizontal of the bottom 10, as long as angled until the Abwinkellaschen 9 limit the bending in a preselected position. This position in which the
  • Main boom extension 4 is located to the main boom 1 in a 40 ° position, is shown in Figure 4. At the time of limiting the Abwinkelterrorism through the Abwinkellaschen 9, the tip 4c has just contact with the ground 10. In a further Auflippen of the main boom 1 then lifts the
  • Main boom extension 4 from the bottom 10 until the desired position for the main boom 1 with the main boom extension 4 arranged thereon is achieved in a 40 ° position thereto. In this position, the main boom extension 4 is held above its own weight. An appropriate lock in the
  • two are parallel to one another on the right and left sides of the
  • Main boom 1 extending coupling rods 1 1 provided.
  • Main boom extension 4 is already angled so far that the tip 4 c has reached the bottom 10.
  • the telescopic section 1 c is retracted and the coupling rod 1 1 is relieved.
  • the next step is the removal of the coupling rod 1 1 and the further bending over the interaction of setting up the main boom 1 and the Abwinkellaschen. 9
  • Main boom 1 is described as a telescopic boom and the skin extension boom 4 as a lattice boom, the invention is also on others
  • the main boom 1 may also be a lattice boom or a combination of telescopic boom, lattice boom and / or box boom.

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Jib Cranes (AREA)

Abstract

The invention relates to a mobile crane, comprising a main boom (1), which is supported on the mobile crane in such a way that the main boom can be rocked and which can be put upright by means of an elevating cylinder (3), and a main boom extension (4), which is releasably connected to a main boom head (1a) of the main boom (1) by means of upper pins (6) and lower pins (7), wherein main boom extension (4), proceeding from a home position, can be angled in relation to the main boom (1) about a rocking axis (W) by means of an angle drive after the upper pins (6) have been released, which angle drive acts on a base (4d) of the main boom extension (4), wherein a drive of the mobile crane provided for a different task provides the kinetic energy for the angle drive. In order to simplify angling of the main boom extension, the angle drive according to the invention is designed in such a way that a telescoping cylinder of the main boom (1) provides the kinetic energy for the angle drive. The invention further relates to a method for angling a main boom extension therefor.

Description

Mobilkran und Verfahren zum Abwinkein einer Hauptauslegerverlangerung relativ zu einem Hauptausleger eines Mobilkrans  A mobile crane and method for tuning a main boom extension relative to a main boom of a mobile crane
Die Erfindung betrifft einen Mobilkran mit einem wippbar hieran gelagerten und über einen Wippzylinder aufrichtbaren Hauptausleger und mit einer lösbar an einem Hauptauslegerkopf des Hauptauslegers über obere Bolzen und untere Bolzen verbundenen Hauptauslegerverlangerung, die Hauptauslegerverlangerung ausgehend von einer Grundstellung nach einem Lösen der oberen Bolzen mittels eines Abwinkelantriebs um eine Wippachse relativ zu dem Hauptausleger abwinkelbar ist, der Abwinkelantrieb an einem Fuß der Hauptauslegerverlangerung angreift, wobei ein für eine andere Aufgabe vorgesehener Antrieb des Mobilkrans die Bewegungsenergie für den Abwinkelantrieb liefert. The invention relates to a mobile crane with a rocker mounted thereon and erectable via a luffing cylinder main boom and with a detachably connected to a main boom head of the main boom on top bolts and lower bolts main boom extension, the Hauptauslegerverrascherung starting from a basic position after loosening the upper bolt by means of a Abwinkelantriebs order a luffing axis relative to the main boom is angled, the Abwinkelantrieb engages a foot of the main boom extension, a provided for another task drive the mobile crane provides the kinetic energy for the Abwinkelantrieb.
Auch betrifft die Erfindung ein Verfahren zum Abwinkein einer Also, the invention relates to a method for bending in a
Hauptauslegerverlangerung relativ zu einem Hauptausleger eines Mobilkrans, wobei der Hauptausleger wippbar an dem Mobilkran gelagert und über einen Wippzylinder aufrichtbar ist, die Hauptauslegerverlangerung lösbar an einem Hauptauslegerkopf des Hauptauslegers über obere Bolzen und untere Bolzen verbunden ist, ein Abwinkelantrieb an einem Fuß der Hauptauslegerverlangerung angreift, wobei mittels des Abwinkelantriebs, der für das Abwinkein seine Bewegungsenergie von einem Antrieb des Mobilkrans bezieht, der sonst für eine andere Aufgabe des Mobilkrans vorgesehen ist, die Hauptauslegerverlangerung ausgehend von einer Grundstellung um eine Wippachse relativ zu dem Hauptausleger angehoben wird, soweit bis die oberen Bolzen entlastet werden, dann die oberen Bolzen entfernt werden. Main boom extension relative to a main boom of a mobile crane, the main boom is tiltably mounted on the mobile crane and erectable via a luffing cylinder, the main boom extension is releasably connected to a main boom head of the main boom via upper bolts and lower bolts, a Abwinkelantrieb engages a foot of the main boom extension, by means of the Abwinkelantriebs, which refers to the Abwinkein its kinetic energy from a drive of the mobile crane, which is otherwise provided for another task of the mobile crane, the main boom extension is raised from a basic position about a rocking axis relative to the main boom, as far as the upper pin relieves then the top bolts are removed.
Aus dem deutschen Gebrauchsmuster DE 20 2004 020 760 U1 ist bereits ein Mobilkran mit einem Hauptausleger und einer an seinem Hauptauslegerkopf befestigten Hauptauslegerverlangerung bekannt. Die Hauptauslegerverlangerung ist aus einer Grundstellung, in der die Hauptauslegerverlangerung mit ihrer German Utility Model DE 20 2004 020 760 U1 already discloses a mobile crane with a main boom and a main boom extension attached to its main boom head. The main boom extension is from a home position in which the main boom extension with its
Längsrichtung in Verlängerung der Längsrichtung des Hauptauslegers ausgerichtet ist, in eine 20°-Stellung und eine 40°-Stellung wippbar. Die Longitudinal direction is aligned in extension of the longitudinal direction of the main boom, in a 20 ° position and a 40 ° position tiltable. The
Hauptauslegerverlängerung ist in üblicher weise über zwei untere im Bereich von Untergurten der Hauptauslegerverlängerung und zwei obere im Bereich von Main boom extension is usually over two lower in the range of lower boom of the main boom extension and two upper in the range of
Obergurten der Hauptauslegerverlängerung angeordnete Bolzen lösbar an dem Hauptauslegerkopf befestigt. Um die Hauptauslegerverlängerung um die als Wippachse dienenden unteren beiden Bolzen aus der Grundstellung heraus wippen zu können, werden in einem ersten Schritt die beiden oberen Bolzen gezogen und in einem zweiten Schritt über hydraulische Wippzylinder, die an dem Hauptauslegerkopf und an der Hauptauslegerverlängerung angreifen, das Wippen der The upper boom of the main boom extension bolts arranged releasably attached to the main boom head. Around the main boom extension around as In a first step, the two upper bolts are pulled and in a second step, hydraulic rocker cylinders, which engage the main boom head and the main boom extension, cause the rocker axes of the two rocker pins to rock from the basic position
Hauptauslegerverlängerung bewirkt. Das Stecken und Ziehen der beiden oberen Bolzen erfolgt jeweils über einen hydraulischen Verbolzungszylinder. Zur Versorgung der Wippzylinder und der Verbolzungszylinder ist ein autarkes Hydraulikaggregat an dem unteren Ende der Hauptauslegerverlängerung angeordnet. Als Main boom extension effected. The two upper pins are inserted and removed via a hydraulic bolting cylinder. To supply the luffing cylinder and the bolting cylinder, a self-sufficient hydraulic unit is arranged at the lower end of the main boom extension. When
Hydraulikaggregat kann beispielsweise ein Dieselmotor oder Elektromotor jeweils mit einer zugehörigen Hydraulikpumpe zum Einsatz kommen. Hydraulic unit, for example, a diesel engine or electric motor can be used in each case with an associated hydraulic pump.
Der Erfindung liegt die Aufgabe zu Grunde, einen Mobilkran und ein Verfahren zum Abwinkein einer Hauptauslegerverlängerung relativ zu einem Hauptausleger eines Mobilkrans zu schaffen, mit denen das Abwinkein der Hauptauslegerverlängerung vereinfacht wird. The object of the invention is to provide a mobile crane and a method for tilting a main boom extension relative to a main boom of a mobile crane, with which the angle of the main boom extension is simplified.
Diese Aufgabe wird durch einen Mobilkran mit den Merkmalen des Anspruchs 1 und durch ein Verfahren zum Abwinkein einer Hauptauslegerverlängerung relativ zu einem Hauptausleger eines Mobilkrans mit den Merkmalen des Anspruchs 6 gelöst. Vorteilhafte Ausgestaltungen der Erfindung sind in den Unteransprüchen 2 bis 5 angegeben. This object is achieved by a mobile crane having the features of claim 1 and by a method for tilting a main boom extension relative to a main boom of a mobile crane having the features of claim 6. Advantageous embodiments of the invention are specified in the subclaims 2 to 5.
Erfindungsgemäß wird bei einem Mobilkran mit einem wippbar hieran gelagerten und über einen Wippzylinder aufrichtbaren Hauptausleger und mit einer lösbar an einem Hauptauslegerkopf des Hauptauslegers über obere Bolzen und untere Bolzen verbundenen Hauptauslegerverlängerung, wobei die Hauptauslegerverlängerung ausgehend von einer Grundstellung nach einem Lösen der oberen Bolzen mittels eines Abwinkelantriebs um eine Wippachse relativ zu dem Hauptausleger According to the invention in a mobile crane with a rockable mounted thereto and erectable via a luffing jib main boom and with a detachably connected to a main boom head of the main boom via upper bolts and lower bolts main boom extension, the main boom extension, starting from a normal position after loosening the upper bolt by means of a Abwinkelantriebs about a rocking axis relative to the main boom
abwinkelbar ist, der Abwinkelantrieb an einem Fuß der Hauptauslegerverlängerung angreift, wobei ein für eine andere Aufgabe vorgesehener Antrieb des Mobilkrans die Bewegungsenergie für den Abwinkelantrieb liefert, eine Vereinfachung dadurch erreicht, dass der Abwinkelantrieb derart ausgebildet ist, dass ein Teleskopierzylinder des Hauptauslegers die Bewegungsenergie für den Abwinkelantrieb liefert. Hierdurch wird erreicht, dass das Abwinkein nicht über äußere Hilfsmittel oder zusätzliche Hilfszylinder erfolgt, sondern am Mobilkran vorhandene Antriebe verwendet werden, die ohnehin vorhanden sind. Das Abwinkein erfolgt nicht über zusätzlich can be bent, the Abwinkelantrieb engages a foot of the main boom extension, a provided for another task drive the mobile crane provides the kinetic energy for the Abwinkelantrieb, a simplification achieved in that the Abwinkelantrieb is designed such that a telescoping cylinder of the main boom, the kinetic energy for the Abwinkelantrieb supplies. This ensures that the Abwinkein does not take place via external aids or additional auxiliary cylinder, but existing drives are used on the mobile crane, which are available anyway. The angle is not over in addition
vorzusehende Hydraulikzylinder. Das Abwinkein an sich erfolgt weitestgehend am Boden beziehungsweise der Ablagestellung des Hauptauslegers, so dass es nicht erforderlich ist, weit oberhalb der Oberkante des Mobilkrans zu arbeiten. Die to be provided hydraulic cylinder. The Abwinkein in itself is largely on the floor or the storage position of the main boom, so that it is not necessary to work well above the top of the mobile crane. The
Erfindung erlaubt das Abwinkein der Hauptauslegerverlangerung bei auf einem ebenen Boden stehendem Mobilkran mit horizontal ausgerichtetem Teleskopausleger. Für den letzten Teil des Aufwippens der Hauptauslegerverlangerung in eine 20°- beziehungsweise 40°-Stellung wird der Wippzylinder des Hauptauslegers zu Hilfe genommen. The invention permits the deviation of the main boom extension with a mobile crane standing on a level ground with horizontally aligned telescopic boom. For the last part of the boom extension in a 20 ° or 40 ° position, the luffing cylinder of the main boom is used.
Hierbei ist vorgesehen, dass insbesondere der Abwinkelantrieb einerseits an dem Hauptausleger und andererseits an der Hauptauslegerverlangerung im Bereich ihres Obergurtes angreift. Außerdem ist vorteilhafterweise der Abwinkelantrieb derart ausgebildet, dass die Hauptauslegerverlangerung entgegen der Schwerkraftwirkung der Hauptauslegerverlangerung um die Wippachse schwenkend anhebbar und absenkbar ist. Hierbei ist insbesondere die Wippachse von einer unteren It is provided that in particular the Abwinkelantrieb on the one hand acts on the main boom and on the other hand on the main boom extension in the region of the upper flange. In addition, advantageously, the Abwinkelantrieb is designed such that the main boom extension against the gravitational force of the main boom extension about the rocking axis is pivotally raised and lowered. Here, in particular, the rocking axis of a lower
Rollenkopfachse gebildet. Roller head axle formed.
In einer vorteilhaften Variante ist vorgesehen, dass der Abwinkelantrieb eine In an advantageous variant it is provided that the Abwinkelantrieb a
Koppelstange umfasst, die Koppelstange an einem ersten Koppelstangenende an dem Obergurt der Hauptauslegerverlangerung befestigt ist und an einem zweiten Koppelstangenende an dem Hauptausleger befestigt ist, die Länge der Koppelstange so gewählt ist, dass ein zuvor um einen Ausfahrweg ausgefahrener Hauptausleger anschließend derart ein- und ausfahrbar ist, dass die Hauptauslegerverlängerung entgegen der Schwerkraftwirkung der Hauptauslegerverlängerung um die Wippachse schwenkend anhebbar und absenkbar ist. Coupling rod comprises, the coupling rod is attached to a first coupling rod end to the upper flange of the main boom extension and attached to a second coupling rod end to the main boom, the length of the coupling rod is chosen so that a previously extended to a Ausfahrweg main boom is then so retractable and extendable in that the main boom extension is pivotally raisable and lowerable about the rocking axis against the force of gravity of the main boom extension.
Erfindungsgemäß wird bei einem Verfahren zum Abwinkein einer According to the invention, in a method for bending in a
Hauptauslegerverlängerung relativ zu einem Hauptausleger eines Mobilkrans, wobei der Hauptausleger wippbar an dem Mobilkran gelagert und über einen Wippzylinder aufrichtbar ist, die Hauptauslegerverlängerung lösbar an einem Hauptauslegerkopf des Hauptauslegers über obere Bolzen und untere Bolzen verbunden ist, ein Main boom extension relative to a main boom of a mobile crane, wherein the main boom is tiltably mounted on the mobile crane and erectable via a luffing cylinder, the main boom extension is releasably connected to a main boom head of the main boom via upper bolts and lower bolts, a
Abwinkelantrieb an einem Fuß der Hauptauslegerverlängerung angreift, wobei mittels des Abwinkelantriebs, der für das Abwinkein seine Bewegungsenergie von einem Antrieb des Mobilkrans bezieht, der sonst für eine andere Aufgabe des Mobilkrans vorgesehen ist, die Hauptauslegerverlängerung ausgehend von einer Grundstellung um eine Wippachse relativ zu dem Hauptausleger angehoben wird, soweit bis die oberen Bolzen entlastet werden, dann die oberen Bolzen entfernt werden, eine Vereinfachung dadurch erreicht, dass zwischen dem Hauptauslegerkopf und einem Obergurt der Hauptauslegerverlängerung Abwinkellaschen eingesetzt werden beziehungsweise eingesetzt sind, über die eine gewünschte Abwinkelung der Hauptauslegerverlängerung zu dem Hauptausleger begrenzt ist, mittels des Abwinkelantrieb attacks on a foot of the main boom extension, wherein by means of the Abwinkelantriebs that refers to the Abwinkein its kinetic energy from a drive of the mobile crane, otherwise for another task of the mobile crane is provided, the main boom extension is raised starting from a basic position about a rocking axis relative to the main boom, as far as the upper bolts are relieved, then the upper bolts are removed, a simplification achieved by using Abwinkellaschen between the main boom head and a top flange of the main boom extension are used or, over which a desired bending of the main boom extension is limited to the main boom, by means of
Abwinkelantriebs die Hauptauslegerverlängerung abgesenkt wird, solange bis die maximale Abwinkelstellung erreicht wird oder eine Spitze der Abwinkelantriebs the main boom extension is lowered until the maximum Abwinkelstellung is reached or a tip of
Hauptauslegerverlängerung auf einem Boden zur Auflage kommt, der Antrieb des Mobilkrans von dem Abwinkelantrieb getrennt wird und wenn die maximale Main boom extension on a ground comes to rest, the propulsion of the mobile crane is disconnected from the angled drive and when the maximum
Abwinkelstellung noch nicht erreicht ist, mittels Aufrichten des Hauptauslegers die Hauptauslegerverlängerung bis zum Erreichen der gewünschten Abwinkelung abgewinkelt wird und zur Bereitstellung der Bewegungsenergie eine Koppelstange mit dem Hauptausleger und der Hauptauslegerverlängerung verbunden wird und über ein Ein- und Ausfahren des Hauptauslegers die Bewegungsenergie bereitgestellt wird. In Bezug auf die hiermit verbundenen Vorteile wird auf die Ausführungen zuvor für den Mobilkran verwiesen. Im Zusammenhang mit der vorliegenden Erfindung wird unter einem Mobilkran sowohl ein verfahrbarer Teleskopkran als auch ein verfahrbarer Raupenkran mit Gittermastausleger verstanden. Abwinkelstellung is not reached, by raising the main boom, the main boom extension is bent until reaching the desired angle and for providing the kinetic energy coupling rod is connected to the main boom and the main boom extension and on a retraction and extension of the main boom, the kinetic energy is provided. With regard to the advantages associated with this, reference is made to the statements above for the mobile crane. In the context of the present invention, a mobile crane is understood as meaning both a mobile telescopic crane and a movable crawler crane with a lattice boom.
Nachfolgend wird die Erfindung an Hand eines in einer Zeichnung dargestellten Ausführungsbeispiels näher erläutert. Es zeigen: The invention will be explained in more detail with reference to an embodiment shown in a drawing. Show it:
Figur 1 eine Seitenansicht eines Hauptauslegers mit einer Figure 1 is a side view of a main boom with a
Hauptauslegerverlängerung in einer Grundstellung, Figur 2a eine Seitenansicht einer Abwinkellasche in einer 40°-Stellung, Main boom extension in a basic position, Figure 2a is a side view of a Abwinkellasche in a 40 ° position,
Figur 2b eine Schnittansicht von Figur 2a, FIG. 2b shows a sectional view of FIG. 2a,
Figur 2c eine Draufsicht einer Abwinkellasche in einer Transport-Stellung, Figur 2d eine Schnittansicht von Figur 2c, FIG. 2c shows a plan view of an angled lug in a transport position, FIG. 2d shows a sectional view of FIG. 2c,
Figur 2e eine Seitenansicht einer Abwinkellasche in einer 20°-Stellung, Figur 3 den Hauptausleger nach Figur 1 mit der Hauptauslegerverlängerung in einer 20°-Stellung, FIG. 2e shows a side view of an angled lug in a 20 ° position, FIG. 3 shows the main arm according to FIG. 1 with the main boom extension in a 20 ° position,
Figur 4 den Hauptausleger nach Figur 1 mit der Hauptauslegerverlängerung in einer 40°-Stellung, 4 shows the main boom according to FIG. 1 with the main boom extension in a 40 ° position, FIG.
Figur 5 eine Detailansicht von Figur 4 mit einer Abwinkellasche in Anschlagstellung, FIG. 5 shows a detailed view of FIG. 4 with an angled lug in the stop position,
Figur 6 eine Detailansicht aus dem Bereich der Ankopplung der FIG. 6 shows a detailed view from the area of the coupling of FIG
Hauptauslegerverlängerung an den Hauptausleger und einer Koppelstange zum Abwinkein und Main boom extension to the main boom and a tie rod to the angle and
Figur 7 eine Ansicht wie in Figur 6 in einer anderen Stellung der Figure 7 is a view as in Figure 6 in another position of
Hauptauslegerverlängerung. In der Figur 1 ist eine Seitenansicht eines Hauptauslegers 1 eines nicht dargestellten Teleskopkrans gezeigt. Von dem Teleskopkran ist nur ein Grundrahmen 2 eines Oberwagens dargestellt. An dem Grundrahmen 2 ist der Hauptausleger 1 mit seinem Hauptauslegerfuß 1 c in üblicher weise um eine im Wesentlichen horizontale Achse schwenkbar gelagert und über einen symbolisch über eine Linie angedeuteten Wippzylinder 3, der am Grundrahmen und am Hauptausleger 1 angreift, in Main boom extension. 1 shows a side view of a main boom 1 of a telescopic crane, not shown, is shown. Of the telescopic crane only a base frame 2 of a superstructure is shown. On the base frame 2, the main boom 1 is pivotally mounted with its main boom 1 c in the usual manner about a substantially horizontal axis and a symbolically indicated by a line rocker cylinder 3, which acts on the base frame and the main boom 1, in
entsprechender Weise aufstell- und wippbar. In der Figur 1 ist der Hauptausleger 1 in einer sogenannten abgelegten Stellung gezeigt, in der der Hauptausleger 1 mit seiner Längsrichtung im Wesentlichen horizontal ausgerichtet ist. Der Hauptausleger 1 ist als Teleskopausleger mit einem Grundkasten 1 b und darin geführten Teleskopschüssen 1 d ausgebildet und weist an seinem dem Grundrahmen 2 des Oberwagens abgewandten Ende einen Hauptauslegerkopf 1 b und somit an dem innersten appropriate way set up and tapping. In the figure 1, the main boom 1 is shown in a so-called stowed position, in which the main boom 1 is aligned with its longitudinal direction substantially horizontally. The main boom 1 is designed as a telescopic boom with a base box 1 b and guided therein telescopic shots 1 d and has at its the base frame 2 of the upper carriage end facing away from a main boom head 1 b and thus at the innermost
Teleskopschuss 1 d20 auf. Der Teleskopausleger ist in üblicher weise über einen nicht dargestellten und im innersten Teleskopschuss 1 d angeordneten Telescopic shot 1 d20 on. The telescopic boom is arranged in the usual way via a not shown and in the innermost telescopic section 1 d
Teleskopzylinder aus- und einfahrbar. An dem Hauptauslegerkopf 1 b ist eine Telescopic cylinder extendable and retractable. On the main boom head 1 b is a
Verlängerung des Hauptauslegers 1 in Form einer Hauptauslegerverlängerung 4 lösbar befestigt. Die Hauptauslegerverlängerung 4 kann vorübergehend oder ständig mit dem Teleskopkran genutzt werden, um eine über die größte Auslegerlänge des Hauptauslegers 1 hinausgehende noch größere Gesamtlänge des Auslegers zu erzielen oder auch um ein Arbeiten hinter Gebäudekanten zu ermöglichen. Diese Hauptauslegerverlängerung 4 ist als Gittermast ausgebildet, die in üblicher weise eine Fachwerk-Rohrkonstruktion ist. Der Hauptausleger 1 und die Extension of the main boom 1 in the form of a main boom extension 4 releasably secured. The main boom extension 4 can be used temporarily or permanently with the telescopic crane to achieve over the largest boom length of the main boom 1 beyond even greater overall length of the boom or to allow working behind building edges. This main boom extension 4 is designed as a lattice mast, which is a truss pipe construction in the usual way. The main boom 1 and the
Hauptauslegerverlängerung 4 befinden sich in der Figur 1 in einer 0°-Stellung beziehungsweise Grundstellung, in der die Längsrichtung H des Hauptauslegers 1 und die Längsrichtung V der Hauptauslegerverlängerung 4 miteinander fluchten beziehungsweise parallel zueinander verlaufen. Ein sogenannter Wippwinkel a des Hauptauslegers 1 relativ zu dem Oberwagen 2 beträgt somit in der abgelegten Stellung 0°. Mit dem Wippwinkel a wird das Aufrichten des Hauptauslegers 1 relativ zu dem Oberwagen 2 beschrieben. Die Hauptauslegerverlängerung 4 ist in dieser Grundstellung von einem Boden 10 beabstandet und wird somit von dem Main boom extension 4 are in Figure 1 in a 0 ° position or normal position in which the longitudinal direction H of the main boom 1 and the longitudinal direction V of the main boom extension 4 are aligned with each other or parallel to each other. A so-called rocking angle a of the main boom 1 relative to the superstructure 2 is thus 0 ° in the stored position. With the rocking angle a, the erection of the main boom 1 relative to the superstructure 2 is described. The main boom extension 4 is spaced in this basic position of a bottom 10 and is thus of the
Hauptausleger 1 über eine Verbolzung an dem Hauptauslegerkopf 1 a getragen. Main boom 1 via a bolt on the main boom head 1 a worn.
Derartige Hauptauslegerverlängerungen 4 sind grundsätzlich als Baukastensysteme aus einzelnen Hauptelementen aufgebaut und können je nach Erfordernis an dessen Länge beziehungsweise Tragkraft zusammengestellt werden. Die einzelnen Such main boom extensions 4 are basically constructed as modular systems of individual main elements and can be assembled according to the requirements of its length or carrying capacity. The single ones
Hauptelemente weisen transportfähige Abmessungen auf und werden in den meisten Fällen nicht mit dem Teleskopkran mitgeführt, sondern werden separat transportiert. Wenn es die Achslasten des Teleskopkrans und die Baugröße der Main elements have transportable dimensions and are not carried along with the telescopic crane in most cases, but are transported separately. If the axle loads of the telescopic crane and the size of the
Hauptauslegerverlängerung 4 zulassen, kann bei Bedarf die Main boom extension 4 allow, if necessary, the
Hauptauslegerverlängerung 4 mitgeführt werden. Diese würde sich dann in einer Transportstellung seitlich neben und parallel zu dem Hauptausleger 1 befinden. Eine Verbindung der einzelnen Hauptelemente aneinander zu der gewünschten Main boom extension 4 are carried. This would then be in a transport position laterally next to and parallel to the main boom 1. A connection of the individual main elements to each other to the desired
Hauptauslegerverlängerung 4 erfolgt über Bolzenverbindungen in entsprechenden Verbolzungsstellen A, B, C und D. Der Anbau an den Hauptauslegerkopf 1 a kann hauptelementweise oder als vormontierte Einheit beziehungsweise Einheiten erfolgen. Main boom extension 4 via bolt connections in corresponding Verbolzungsstellen A, B, C and D. The attachment to the main boom head 1 a can be made elementary or as a preassembled unit or units.
Die Figur 2a zeigt eine Seitenansicht einer Abwinkellasche 9 in einer maximal ausgezogenen 40°-Stellung. Die Abwinkellasche 9, über die manuell über eine Anschlagfläche 9a (siehe Figur 2d) ein Verschiebeweg und somit der Abwinkelwinkel b begrenzbar ist, besteht im Wesentlichen aus einer Schiebelasche 9b mit einer langlochförmigen Führungsöffnung 9c, an der eine Führungslasche 9d in FIG. 2a shows a side view of an angled flap 9 in a maximally extended 40 ° position. The Abwinkellasche 9, via the manual over a stop surface 9a (see Figure 2d) a displacement and thus the angle of deflection b is limited, consists essentially of a sliding tab 9b with a slot-shaped guide opening 9c, on which a guide tab 9d in
Längsrichtung c der Schiebelasche 9b führbar ist. Die Schiebelasche 9b ist als langgestrecktes Flachprofil mit der Anschlagsöffnung 9c ausgebildet und verläuft im Wesentlichen parallel zur Längsrichtung V der Hauptauslegerverlängerung 1. An einem dem Hauptauslegerkopf 1 a zugewandten Ende weist die Schiebelasche 9b eine Bohrung 9j (siehe Figur 2d) auf, über die die Schiebelasche 9b jeweils mit einem Anschlussbolzen 9e an dem Hauptauslegerkopf 1 a an einer der Verbolzungsstellen E und F lösbar befestigt ist. Der Anschlussbolzen 9e ist mit seiner Längserstreckung parallel zur oberen beziehungsweise unteren Rollenkopfachse 12a, 12b ausgerichtet. Auf die Schiebelasche 9b ist die Führungslasche 9d aufgeschoben, die hierfür einen geschlossenen rechteckigen Querschnitt mit einer Führungsöffnung 9f aufweist (siehe Figur 2b), in die die Schiebelasche 9b eingeschoben und verschiebbar geführt ist. Die Führungslasche 9d an sich ist an einem dem Hauptauslegerkopf 1 a zugewandten Ende über jeweils einen weiteren Anschlussbolzen 9i in einer der Verbolzungsstellen G und H an der Hauptauslegerverlängerung 4 lösbar befestigt. Der Anschlussbolzen 9i ist mit seiner Längserstreckung parallel zur oberen beziehungsweise unteren Rollenkopfachse 12a, 12b ausgerichtet. Auch ist der Anschlussbolzen 9i hierbei durch die Anschlagöffnung 9c der Schiebelasche 9b hindurchgeführt. Um ein Verschieben der Führungslasche 9d auf der Schiebelasche 9b zu begrenzen, sind zwei durchgehende und in Längsrichtung der Führungslasche 9d voneinander Longitudinal direction c of the sliding tab 9b is feasible. The sliding lug 9b is formed as an elongated flat profile with the stopper opening 9c and extends substantially parallel to the longitudinal direction V of the main boom extension 1. On one of the main boom head 1 a end facing the sliding lug 9b has a bore 9j (see Figure 2d), via which the sliding latch 9b each with a connecting bolt 9e on the main boom head 1 a at one of the Verbolzungsstellen E and F is releasably attached. The connecting bolt 9e is aligned with its longitudinal extension parallel to the upper or lower roller head axles 12a, 12b. On the sliding tab 9b, the guide plate 9d is pushed, which for this purpose has a closed rectangular cross-section with a guide opening 9f (see Figure 2b), in which the sliding tab 9b is inserted and slidably guided. The guide plate 9d per se is releasably secured to a main boom 1 a end facing via a respective further connecting pin 9i in one of the Verbolzungsstellen G and H on the main boom extension 4. The connecting pin 9i is aligned with its longitudinal extent parallel to the upper and lower roller head axles 12a, 12b. Also, the terminal pin 9i is passed through the stopper opening 9c of the slide tab 9b. In order to limit a displacement of the guide tab 9d on the sliding tab 9b, two continuous and longitudinally of the guide tab 9d from each other
beabstandete Anschlagbohrungen 9g (siehe Figur 2d) in den Seitenteilen der Führungslasche 9d angeordnet. Eine erste der beiden Anschlagbohrungen 9g dient zu einem Begrenzen des Abwinkelwinkels b auf 20° und eine zweite auf 40°. Die Anschlagbohrungen 9g für 40° sind entsprechend näher zu dem Hauptauslegerkopf 1 a angeordnet, um einen größeren Verschiebeweg zuzulassen. Je nach spaced stop holes 9g (see Figure 2d) arranged in the side parts of the guide tab 9d. A first of the two stop holes 9g serves to limit the angle of deflection b to 20 ° and a second to 40 °. The stop holes 9g for 40 ° are correspondingly closer to the main boom head 1a arranged to allow a larger displacement. Depending on
gewünschtem Abwinkelwinkel b wird in die jeweilige Anschlagbohrung 9g ein desired angle of deflection b is in the respective stop hole 9g
Anschlagbolzen 9h eingesteckt, der dann durch die beiden gegenüberliegenden Anschlagbohrungen 9g und die dazwischenliegende Anschlagöffnung 9c verläuft. In der Figur 2a ist der Anschlagbolzen 9h in die zweite der beiden Anschlagbohrungen 9g eingesteckt, die den Abwinkelwinkel b auf 40° begrenzt. Der Anschlagbolzen 9h wird neben dem Bolzen 9i in der Anschlagöffnung 9c geführt. Der Bolzen 9i käme nur mit der gegenüber liegenden Anschlagfläche 9a der Anschlagöffnung 9c in Kontakt, wenn kein Anschlagbolzen 9h gesteckt ist. Die zweite der beiden Anschlagbohrungen 9g ist frei. In der Figur 2b ist eine Schnittansicht von Figur 2a entlang der Schnittlinie A-A dargestellt. Es ist erkennbar, dass die Führungslasche 9d einen rechteckigen Inserted stop pin 9h, which then passes through the two opposite stop holes 9g and the intermediate stop opening 9c. In FIG. 2a, the stop pin 9h is inserted into the second of the two stop bores 9g, which limits the angle of deflection b to 40 °. The stopper pin 9h is guided adjacent to the pin 9i in the stopper opening 9c. The bolt 9i would come into contact only with the opposing abutment surface 9a of the stopper opening 9c when no stopper bolt 9h is inserted. The second of the two stop holes 9g is free. FIG. 2b shows a sectional view of FIG. 2a along section line AA. It can be seen that the guide tab 9d a rectangular
Querschnitt mit einer zentralen Führungsöffnung 9f aufweist, in der die Schiebelasche 9b mit ihrer Anschlagöffnung 9c geführt ist. Cross-section having a central guide opening 9f, in which the sliding tab 9b is guided with its stop opening 9c.
Des Weiteren ist in der Figur 2c eine Draufsicht einer Abwinkellasche 9 in einer Transport-Stellung dargestellt. In dieser Transport-Stellung ist die Abwinkellasche 9 nicht über den Anschlussbolzen 9e am Hauptauslegerkopf 1 a befestigt und die Schiebelasche 9b ist in Richtung der Hauptauslegerverlängerung 4 in die Furthermore, FIG. 2c shows a plan view of an angled lug 9 in a transport position. In this transport position, the Abwinkellasche 9 is not attached via the connecting bolt 9 e on the main boom head 1 a and the sliding tab 9 b is in the direction of the main boom extension 4 in the
Führungslasche 9d eingeschoben. Der Anschlussbolzen 9e und der Anschlagbolzen 9h sind zur Aufbewahrung eingesteckt. Guide tab 9d inserted. The connecting bolt 9e and the stopper pin 9h are inserted for storage.
Die Figur 2d zeigt eine Schnittansicht von Figur 2c entlang der Schnittlinie B-B in Figur 2c. In dieser Ansicht sind die Anschlagsöffnung 12c und die beiden FIG. 2d shows a sectional view of FIG. 2c along the section line B-B in FIG. 2c. In this view, the stopper opening 12c and the two
Anschlagsbohrungen gut zu erkennen. Good to recognize stop holes.
In der Figur 2e ist eine Seitenansicht einer Abwinkellasche 9 dargestellt, die im Wesentlichen der in Figur 2a gezeigten Abwinkellasche 9 entspricht. Anders als in der Figur 2a ist die Abwinkellasche 9 nicht in der 40°-Stellung, sondern in der 20°- Stellung dargestellt. Entsprechender Weise ist der Anschlagbolzen 9h in der von dem Hauptauslegerkopf 1 a entfernten Anschlagsbohrung 9g eingesteckt. FIG. 2e shows a side view of an angled lug 9, which substantially corresponds to the angled lug 9 shown in FIG. 2a. Unlike in Figure 2a, the Abwinkellasche 9 is not shown in the 40 ° position, but in the 20 ° - position. Correspondingly, the stopper pin 9h is inserted in the stopper hole 9g remote from the main jib head 1a.
In der Figur 3, die den Hauptausleger 1 nach Figur 1 mit der In the figure 3, the main boom 1 of Figure 1 with the
Hauptauslegerverlängerung 4 in einer 20°-Stellung zeigt, ist die zuvor beschriebene Stellung gezeigt, in der die abgesenkte Spitze 4a sich auf dem Boden 10 abstützt. Main boom extension 4 in a 20 ° position, the position described above is shown, in which the lowered tip 4a is supported on the bottom 10.
Die Figur 4 zeigt den Hauptausleger 1 nach Figur 3 mit der 4 shows the main boom 1 of Figure 3 with the
Hauptauslegerverlängerung 1 a in einer 40°-Stellung, in der die abgesenkte Spitze 4a sich auf dem Boden 10 abstützt.  Main boom extension 1 a in a 40 ° position in which the lowered tip 4 a is supported on the floor 10.
Die Figur 5 zeigt eine Detailansicht von Figur 4 aus dem Bereich der Ankopplung der Hauptauslegerverlängerung 4 an den Hauptausleger 1 mit einer Abwinkellasche 9 in Anschlagstellung zu einer gewünschten maximalen Abwinkelstellung. In der Figur 6 ist eine Detailansicht aus dem Bereich der Ankopplung der Hauptauslegerverlangerung 4 an den Hauptausleger 1 in Grundstellung gezeigt. Die Bewegungsenergie zum Abwinkeln der Hauptauslegerverlangerung 4 wird hier alternativ zu dem zuvor beschriebenen Ausführungsbeispiel über eine Kombination einer Koppelstange 1 1 mit einem über einen Teleskopzylinder teleskopierbaren Hauptausleger 1 zur Verfügung gestellt. Die Koppelstange 1 1 ist im Wesentlichen parallel zur Längsrichtung H des Hauptauslegers 1 und zur Längsrichtung V der Hauptauslegerverlängerung 4 ausgerichtet sowie an einem ersten FIG. 5 shows a detailed view of FIG. 4 from the area of the coupling of the main boom extension 4 to the main boom 1 with an angled lug 9 in the stop position to a desired maximum angle position. In the figure 6 is a detail view of the coupling of the Main boom extension 4 to the main boom 1 shown in basic position. The kinetic energy for bending the main boom extension 4 is provided here as an alternative to the previously described embodiment via a combination of a coupling rod 1 1 with a telescopic cylinder telescopic main boom 1 available. The coupling rod 1 1 is aligned substantially parallel to the longitudinal direction H of the main boom 1 and to the longitudinal direction V of the main boom extension 4 and at a first
Koppelstangenende 1 1 a im Bereich des Obergurts 4a der Coupling rod end 1 1 a in the region of the upper chord 4a of
Hauptauslegerverlängerung 4 über einen horizontal verlaufenden Bolzen Main boom extension 4 via a horizontally extending bolt
angekoppelt. Das gegenüberliegende zweite Koppelstangenende 1 1 b ist ebenfalls über einen horizontal verlaufenden Bolzen an einem Grundkasten 1 b des coupled. The opposite second coupling rod end 1 1 b is also via a horizontally extending bolt on a base box 1 b of the
Hauptauslegers 1 gelagert. Die Länge der Koppelstange 1 1 ist so gewählt, dass ein um einen Ausfahrweg x gegenüber den Grundkasten 1 b ausgefahrener Main boom 1 stored. The length of the coupling rod 1 1 is chosen so that one extended by a Ausfahrweg x relative to the base box 1 b
Teleskopschuss 1 c anschließend derart ein- und ausfahrbar ist, dass die Telescopic shot 1 c is then so retractable and extendable that the
Hauptauslegerverlängerung 4 entgegen der Schwerkraftwirkung der Main boom extension 4 against the gravitational effect of
Hauptauslegerverlängerung 4 um die Wippachse W schwenkend anhebbar und absenkbar ist. An einem der beiden Koppelstangenenden 1 1 a, 1 1 b kann die Main boom extension 4 to the rocker axis W is pivotally raised and lowered. At one of the two coupling rod ends 1 1 a, 1 1 b, the
Koppelstange 1 1 mit einem Langloch 1 1 c versehen werden, um nach einem Coupling rod 1 1 with a slot 1 1 c are provided to after a
Ausfahren des Hauptauslegers 1 um den Ausfahrweg x die Koppelstange 1 1 leichter mit dem Hauptausleger 1 und der Hauptauslegerverlängerung 4 verbinden zu können. Ein erstes leichtes Anheben der Hauptauslegerverlängerung 4 ist erforderlich, um die oberen Bolzen 6 zu entlasten und anschließend zu entfernen. Anschließend wird der Teleskopschuss 1 c eingefahren und relativ gesehen die Länge der Koppelstange 1 1 frei gegeben, dass zu einem Abwinkeln der Hauptauslegerverlängerung 4 führt. Nach dem die Spitze 4c der Hauptauslegerverlängerung 4 auf dem Boden 10 zur Auflage kommt, wird die Koppelstange 1 1 entfernt. In einem weiteren Schritt wird durch ein Aufwippen des Hauptauslegers 1 die Hauptauslegerverlängerung 4 weiter Extending the main boom 1 to the extension path x the coupling rod 1 1 easier to connect to the main boom 1 and the main boom extension 4 can. A first slight lifting of the main boom extension 4 is required to relieve the upper bolt 6 and then remove. Subsequently, the telescopic section 1 c is retracted and relatively speaking, the length of the coupling rod 1 1 released that leads to angling of the main boom extension 4. After the tip 4c of the main boom extension 4 comes to rest on the floor 10, the coupling rod 1 1 is removed. In a further step, the main boom extension 4 is further by a Aufwippen the main boom 1
abgewinkelt und die Spitze 4c der Hauptauslegerverlängerung 4 gleitet hierdurch über den Boden 10 in Richtung des Oberwagens 2. Durch das Aufwippen wird die angled and the tip 4c of the main boom extension 4 slides through this over the bottom 10 in the direction of the superstructure 2. By the Aufwippen is the
Hauptauslegerverlängerung 4 in einen Wippwinkel a, der von der Längsrichtung H des Hauptauslegers 1 und der Horizontalen des Bodens 10 eingeschlossen ist, solange weiter abgewinkelt bis die Abwinkellaschen 9 das Abwinkeln in einer vorgewählten Stellung begrenzen. Diese Stellung, in der sich die Main boom extension 4 in a rocking angle a, which is enclosed by the longitudinal direction H of the main boom 1 and the horizontal of the bottom 10, as long as angled until the Abwinkellaschen 9 limit the bending in a preselected position. This position in which the
Hauptauslegerverlängerung 4 zu dem Hauptausleger 1 in einer 40°-Stellung befindet, ist in der Figur 4 dargestellt. Im Zeitpunkt der Begrenzung der Abwinkelbewegung durch die Abwinkellaschen 9 hat die Spitze 4c gerade noch Kontakt zu dem Boden 10. Bei einem weiteren Aufwippen des Hauptauslegers 1 hebt dann die Main boom extension 4 is located to the main boom 1 in a 40 ° position, is shown in Figure 4. At the time of limiting the Abwinkelbewegung through the Abwinkellaschen 9, the tip 4c has just contact with the ground 10. In a further Auflippen of the main boom 1 then lifts the
Hauptauslegerverlangerung 4 vom Boden 10 ab, bis die gewünschte Stellung für den Hauptausleger 1 mit der daran angeordneten Hauptauslegerverlangerung 4 in einer 40°-Stellung hierzu erreicht ist. In dieser Stellung wird die Hauptauslegerverlangerung 4 über ihr Eigengewicht gehalten. Eine entsprechende Verriegelung in den Main boom extension 4 from the bottom 10 until the desired position for the main boom 1 with the main boom extension 4 arranged thereon is achieved in a 40 ° position thereto. In this position, the main boom extension 4 is held above its own weight. An appropriate lock in the
Abwinkellaschen 9 ist aber in der vorliegenden Ausführung nicht vorgesehen. Abwinkellaschen 9 but is not provided in the present embodiment.
Bevorzugt sind zwei parallel zueinander an der rechten und linken Seite des Preferably, two are parallel to one another on the right and left sides of the
Hauptauslegers 1 verlaufende Koppelstangen 1 1 vorgesehen. Main boom 1 extending coupling rods 1 1 provided.
In der Figur 7 ist eine Ansicht wie in Figur 6 in einer anderen Stellung der In the figure 7 is a view as in Figure 6 in a different position of
Hauptauslegerverlangerung 4 gezeigt. Es ist ersichtlich, dass die Main boom extension 4 shown. It can be seen that the
Hauptauslegerverlangerung 4 bereits so weit abgewinkelt ist, dass die Spitze 4c den Boden 10 erreicht hat. Der Teleskopschuss 1 c ist eingefahren und die Koppelstange 1 1 ist entlastet. Wenn diese Stellung erreicht ist, erfolgt als nächster Schritt das Entfernen der Koppelstange 1 1 und das weitere Abwinkeln über das Zusammenspiel aus Aufstellen des Hauptauslegers 1 und den Abwinkellaschen 9. Main boom extension 4 is already angled so far that the tip 4 c has reached the bottom 10. The telescopic section 1 c is retracted and the coupling rod 1 1 is relieved. When this position is reached, the next step is the removal of the coupling rod 1 1 and the further bending over the interaction of setting up the main boom 1 and the Abwinkellaschen. 9
Ein Zurückwinkeln der Hauptauslegerverlangerung 4 erfolgt in umgekehrter A backward angle of the main boom extension 4 is reversed
Reihenfolge. Sequence.
Obwohl im Zusammenhang mit dem vorliegenden Ausführungsbeispiel der Although in the context of the present embodiment of the
Hauptausleger 1 als Teleskopausleger und die Hautauslegerverlängerung 4 als Gittermastausleger beschrieben sind, ist die Erfindung auch auf andere Main boom 1 is described as a telescopic boom and the skin extension boom 4 as a lattice boom, the invention is also on others
Ausgestaltungen von Hauptausleger 1 und Hautauslegerverlängerung 4 anwendbar. Der Hauptausleger 1 kann auch ein Gittermastausleger oder eine Kombination von Teleskopausleger, Gittermastausleger und/oder Kastenausleger sein. Für die Hautauslegerverlängerung 4 sind Gittermastausleger oder Kastenausleger oder Kombinationen hiervon denkbar. Bezugszeichenliste Embodiments of main boom 1 and skin extension boom 4 applicable. The main boom 1 may also be a lattice boom or a combination of telescopic boom, lattice boom and / or box boom. For the skin extension boom 4 lattice boom or box boom or combinations thereof are conceivable. LIST OF REFERENCE NUMBERS
1 Hauptausleger 1 main boom
1 a Hauptauslegerkopf  1 a main boom head
1 b Grundkasten 1 b basic box
1 c Hauptauslegerfuß 1 c main boom foot
1 d Teleskopschuss 1 d telescopic shot
2 Grundrahmen  2 basic frames
3 Wippzylinder  3 rocker cylinders
4 Hauptauslegerverlängerung 4a Obergurt  4 main boom extension 4a upper belt
4b Untergurt  4b bottom strap
4c Spitze 4c tip
4d Fuß 4d foot
5 oberer Bolzen  5 upper bolt
6 unterer Bolzen  6 lower bolt
7 Zugstange  7 drawbar
8 Verbolzungsstelle  8 bolting point
9 Abwinkellasche  9 Abwinkellasche
9a Anschlagfläche 9a stop surface
9b Schiebelasche 9b sliding latch
9c Anschlagsöffnung 9c stop opening
9d Führungslasche 9d guide strap
9e Anschlussbolzen 9e connecting bolts
9f Führungsöffnung 9f guide opening
9g Anschlagsbohrung 9g stop hole
9h Anschlagbolzen 9h stop bolt
9i Anschlussbolzen  9i connecting bolts
9j Bohrung 9j bore
10 Boden  10 floor
1 1 Koppelstange  1 1 coupling rod
1 1 a erstes Koppelstangenende 1 1 a zweites Koppelstangenende 1 1 c Langloch  1 1 a first coupling rod end 1 1 a second coupling rod end 1 1 c slot
12a obere Rollenkopfachse 12b untere Rollenkopfachse 12a upper roller head axle 12b lower roller head axle
A Verbolzungsstelle A bolting point
B Verbolzungsstelle B bolting point
C Verbolzungsstelle C bolting point
D Verbolzungsstelle D bolting point
E Verbolzungsstelle E bolting point
F Verbolzungsstelle F bolting point
G Verbolzungsstelle G Verbolzungsstelle
H Verbolzungsstelle a Wippwinkel H bolting point a Wippwinkel
b Abwinkelwinkel b angle of attack
c Längsrichtung c longitudinal direction
x Ausfahrweg x extension path
H Längsrichtung des Hauptauslegers  H longitudinal direction of the main boom
V Längsrichtung der Hauptauslegerverlängerung V Lengthwise direction of main boom extension
W Wippachse W rocking axis

Claims

Patentansprüche claims
1 . Mobilkran mit einem wippbar hieran gelagerten und über einen Wippzylinder (3) aufrichtbaren Hauptausleger (1 ) und mit einer lösbar an einem Hauptauslegerkopf (1 a) des Hauptauslegers (1 ) über obere Bolzen (5) und untere Bolzen (6) 1 . Mobile crane with a rocker mounted thereon and about a luffing cylinder (3) erectile main boom (1) and with a detachable on a main boom head (1 a) of the main boom (1) via upper bolt (5) and lower bolt (6)
verbundenen Hauptauslegerverlängerung (4), wobei die Hauptauslegerverlängerung (4) ausgehend von einer Grundstellung nach einem Lösen der oberen Bolzen (5) mittels eines Abwinkelantriebs um eine Wippachse (W) relativ zu dem Hauptausleger (1 ) abwinkelbar ist, der Abwinkelantrieb an einem Fuß (4d) der associated main boom extension (4), wherein the main boom extension (4) starting from a basic position after loosening the upper bolt (5) by means of a Abwinkelantriebs about a rocking axis (W) relative to the main boom (1) is bendable, the Abwinkelantrieb a foot ( 4d) the
Hauptauslegerverlängerung (4) angreift, wobei ein für eine andere Aufgabe vorgesehener Antrieb des Mobilkrans die Bewegungsenergie für den Abwinkelantrieb liefert, dadurch gekennzeichnet, dass der Abwinkelantrieb derart ausgebildet ist, dass ein Teleskopierzylinder des Hauptauslegers (1 ) die Bewegungsenergie für den Abwinkelantrieb liefert. Main boom extension (4) attacks, with a provided for another task drive the mobile crane provides kinetic energy for the Abwinkelantrieb, characterized in that the Abwinkelantrieb is designed such that a telescoping cylinder of the main boom (1) provides the kinetic energy for the Abwinkelantrieb.
2. Mobilkran nach Anspruch 1 , dadurch gekennzeichnet, dass der Abwinkelantrieb einerseits an dem Hauptausleger (1 ) und andererseits an der 2. Mobile crane according to claim 1, characterized in that the Abwinkelantrieb on the one hand to the main boom (1) and on the other hand on the
Hauptauslegerverlängerung (4) im Bereich ihres Obergurtes (4a) angreift. Main boom extension (4) in the region of its upper flange (4a) attacks.
3. Mobilkran nach Anspruch 1 oder 2, dadurch gekennzeichnet, dass der 3. Mobile crane according to claim 1 or 2, characterized in that the
Abwinkelantrieb derart ausgebildet ist, dass die Hauptauslegerverlängerung (4) entgegen der Schwerkraftwirkung der Hauptauslegerverlängerung (4) um die  Abwinkelantrieb is designed such that the main boom extension (4) against the force of gravity of the main boom extension (4) to the
Wippachse (W) schwenkend anhebbar und absenkbar ist. Rocking axis (W) can be raised and lowered by swiveling.
4. Mobilkran nach einem der Ansprüche 1 bis 3, dadurch gekennzeichnet, dass die Wippachse (W) von einer unteren Rollenkopfachse (12b) gebildet ist. 4. Mobile crane according to one of claims 1 to 3, characterized in that the rocking axis (W) of a lower roller head axis (12 b) is formed.
5. Mobilkran nach einem der Ansprüche 1 bis 4, dadurch gekennzeichnet, dass der Abwinkelantrieb eine Koppelstange (1 1 ) umfasst, die Koppelstange (1 1 ) an einem ersten Koppelstangenende (1 1 a) an dem Obergurt (4a) der 5. Mobile crane according to one of claims 1 to 4, characterized in that the Abwinkelantrieb comprises a coupling rod (1 1), the coupling rod (1 1) at a first coupling rod end (1 1 a) on the upper flange (4 a)
Hauptauslegerverlängerung (4) befestigt ist und an einem zweiten  Main boom extension (4) is attached and attached to a second
Koppelstangenende (1 1 b) an dem Hauptausleger (1 ) befestigt ist, die Länge der Koppelstange (1 1 ) so gewählt ist, dass ein zuvor um einen Ausfahrweg (x) ausgefahrener Hauptausleger (1 ) anschließend derart ein- und ausfahrbar ist, dass die Hauptauslegerverlängerung (4) entgegen der Schwerkraftwirkung der Hauptauslegerverlängerung (4) um die Wippachse (W) schwenkend anhebbar und absenkbar ist. Coupling rod end (1 1 b) is attached to the main boom (1), the length of the coupling rod (1 1) is selected so that a previously extended by a Ausfahrweg (x) main boom (1) is then retractable and extendable that the main boom extension (4) against the gravitational effect of Main boom extension (4) about the rocking axis (W) is pivotally raised and lowered.
6. Verfahren zum Abwinkein einer Hauptauslegerverlängerung (4) relativ zu einem Hauptausleger (1 ) eines Mobilkrans, insbesondere eines Mobilkrans nach einem der Ansprüche 1 bis 5, wobei der Hauptausleger (1 ) wippbar an dem Mobilkran gelagert und über einen Wippzylinder (3) aufrichtbar ist, die Hauptauslegerverlängerung (4) lösbar an einem Hauptauslegerkopf (1 a) des Hauptauslegers (1 ) über obere Bolzen (5) und untere Bolzen (6) verbunden ist, ein Abwinkelantrieb an einem Fuß (4d) der Hauptauslegerverlängerung (4) angreift, wobei mittels des Abwinkelantriebs, der für das Abwinkein seine Bewegungsenergie von einem Antrieb des Mobilkrans bezieht, der sonst für eine andere Aufgabe des Mobilkrans vorgesehen ist, die 6. A method for bending a main boom extension (4) relative to a main boom (1) of a mobile crane, in particular a mobile crane according to one of claims 1 to 5, wherein the main boom (1) stored tiltable on the mobile crane and a rocking cylinder (3) erectable is, the main boom extension (4) releasably connected to a main boom head (1 a) of the main boom (1) via upper bolts (5) and lower bolts (6), a Abwinkelantrieb on a foot (4d) of the main boom extension (4) attacks, wherein by means of the Abwinkelantriebs, which refers to the Abwinkein its kinetic energy from a drive of the mobile crane, which is otherwise provided for another object of the mobile crane, the
Hauptauslegerverlängerung (4) ausgehend von einer Grundstellung um eine Main boom extension (4) starting from a basic position by one
Wippachse (W) relativ zu dem Hauptausleger (1 ) angehoben wird, soweit bis die oberen Bolzen (5) entlastet werden, dann die oberen Bolzen (5) entfernt werden, dadurch gekennzeichnet, dass zwischen dem Hauptauslegerkopf (1 a) und einem Obergurt (4a) der Hauptauslegerverlängerung (4) Abwinkellaschen (9) eingesetzt werden beziehungsweise eingesetzt sind, über die eine gewünschte Abwinkelung der Hauptauslegerverlängerung (4) zu dem Hauptausleger (1 ) begrenzt ist, mittels des Abwinkelantriebs die Hauptauslegerverlängerung (4) abgesenkt wird, solange bis die maximale Abwinkelstellung erreicht wird oder eine Spitze (4c) der Wippachse (W) relative to the main boom (1) is raised, as far as the upper pin (5) are relieved, then the upper pin (5) are removed, characterized in that between the main boom head (1 a) and a top chord ( 4a) of the main boom extension (4) Abwinkellaschen (9) are used or are used, via which a desired bending of the main boom extension (4) is limited to the main boom (1), by means of Abwinkelantriebs the main boom extension (4) is lowered until the maximum angle position is achieved or a tip (4c) of the
Hauptauslegerverlängerung (4) auf einem Boden (10) zur Auflage kommt, der Antrieb des Mobilkrans von dem Abwinkelantrieb getrennt wird und wenn die maximale Abwinkelstellung noch nicht erreicht ist, mittels Aufrichten des Hauptauslegers (1 ) die Hauptauslegerverlängerung (4) bis zum Erreichen der gewünschten Abwinkelung abgewinkelt wird und zur Bereitstellung der Bewegungsenergie eine Koppelstange (1 1 ) mit dem Hauptausleger (1 ) und der Hauptauslegerverlängerung (4) verbunden wird und über ein Ein- und Ausfahren des Hauptauslegers (1 ) die Bewegungsenergie bereitgestellt wird. Main boom extension (4) on a floor (10) comes to rest, the drive of the mobile crane is separated from the Abwinkelantrieb and if the maximum Abwinkelstellung is not reached, by raising the main boom (1), the main boom extension (4) until reaching the desired Angling is bent and for providing the kinetic energy, a coupling rod (1 1) with the main boom (1) and the main boom extension (4) is connected and on a retraction and extension of the main boom (1) the kinetic energy is provided.
EP16798539.9A 2015-11-24 2016-11-22 Mobile crane and method for angling a main boom extension in relation to a main boom of a mobile crane Active EP3337752B1 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
DE102015120350.2A DE102015120350B3 (en) 2015-11-24 2015-11-24 Mobile crane for bending a main boom extension relative to a main boom of a mobile crane
PCT/EP2016/078467 WO2017089356A1 (en) 2015-11-24 2016-11-22 Mobile crane and method for angling a main boom extension in relation to a main boom of a mobile crane

Publications (2)

Publication Number Publication Date
EP3337752A1 true EP3337752A1 (en) 2018-06-27
EP3337752B1 EP3337752B1 (en) 2019-05-08

Family

ID=57354395

Family Applications (2)

Application Number Title Priority Date Filing Date
EP16798539.9A Active EP3337752B1 (en) 2015-11-24 2016-11-22 Mobile crane and method for angling a main boom extension in relation to a main boom of a mobile crane
EP16798537.3A Active EP3347300B1 (en) 2015-11-24 2016-11-22 Mobile crane for angling a main jib extension relative to a main jib of a mobile crane

Family Applications After (1)

Application Number Title Priority Date Filing Date
EP16798537.3A Active EP3347300B1 (en) 2015-11-24 2016-11-22 Mobile crane for angling a main jib extension relative to a main jib of a mobile crane

Country Status (5)

Country Link
US (2) US10640340B2 (en)
EP (2) EP3337752B1 (en)
CN (2) CN108883916B (en)
DE (1) DE102015120350B3 (en)
WO (2) WO2017089353A1 (en)

Families Citing this family (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP6531448B2 (en) * 2015-03-20 2019-06-19 株式会社タダノ Jib connection structure
DE102015119379B3 (en) 2015-11-10 2017-03-30 Terex Global Gmbh Mobile crane and method for bending a main boom extension relative to a main boom of a mobile crane
DE102015119381B3 (en) 2015-11-10 2017-04-27 Terex Global Gmbh Mobile crane and method for bending a main boom extension relative to a main boom of a mobile crane
DE102015120350B3 (en) 2015-11-24 2017-05-24 Terex Global Gmbh Mobile crane for bending a main boom extension relative to a main boom of a mobile crane
DE102016114837A1 (en) 2016-08-10 2018-02-15 Terex Global Gmbh Telescopic boom with guy system for a mobile crane and guying system
DE102017101113B3 (en) 2017-01-20 2018-07-12 Terex Global Gmbh Telescopic boom with pole tensioning system for a mobile crane and guying method
DE102017110412B4 (en) * 2017-05-12 2020-06-10 Liebherr-Werk Ehingen Gmbh Telescopic boom and mobile crane
DE102019104142B9 (en) * 2019-02-19 2020-11-19 Liebherr-Werk Ehingen Gmbh Foldable suspended ballast guide for a crane
DE102020101101B3 (en) 2020-01-17 2021-05-20 Tadano Demag Gmbh Boom system for a vehicle crane with anchoring device as well as a method for upgrading and dismantling an anchoring device of a vehicle crane
CN112141912B (en) * 2020-09-02 2022-01-07 中联重科股份有限公司 Pull plate assembly, crane boom and crane
JP2022084003A (en) 2020-11-25 2022-06-06 タダノ デマグ ゲーエムベーハー Telescopic jib system of mobile crane with basic telescopic jib and additional telescopic jib and corresponding method
CN113753772B (en) * 2021-08-31 2023-06-20 湖南三一中型起重机械有限公司 Pin inserting and pulling mechanism and crane

Family Cites Families (40)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE291531C (en)
US3085695A (en) * 1961-03-23 1963-04-16 Carl A Miller Hinge for crane boom
FR2075866A1 (en) 1969-12-31 1971-10-15 Inst Foerdertechnik
GB1470488A (en) 1975-05-21 1977-04-14 Hiab Foco Ab Crane adapted to be mounted on a vehicle
FR2409225A1 (en) * 1977-11-21 1979-06-15 Creusot Loire IMPROVEMENT WITH TELESCOPIC CRANES
US4318488A (en) 1980-07-28 1982-03-09 Harnischfeger Corporation Method of extending a jib of a telescopic crane
US4394941A (en) 1981-08-31 1983-07-26 Thomas L. Shannon, Jr. Fluid dispenser
JPS60100390A (en) * 1983-11-04 1985-06-04 株式会社デンソー Supporting structure of ceramic heater
JPS60100390U (en) * 1983-12-14 1985-07-09 株式会社 多田野鉄工所 Variable tilt device for auxiliary jib in hydraulic telescopic boom with auxiliary jib
US4653655A (en) * 1985-12-23 1987-03-31 Harnischfeger Corporation Crane boom having variable angle offset capability
JPS6327396A (en) 1986-07-21 1988-02-05 株式会社タダノ Jib extended to expansion boom
DD291531A5 (en) * 1990-01-08 1991-07-04 Maschinenbau "Karl Marx",De BOOMS WITH ONE DEVICE FOR ONE OR MULTIPLE TIPPABLE BOOM EXTENSIONS FOR CRANES, ESPECIALLY MOBILE CRANES
FR2719574B1 (en) 1994-05-06 1996-07-26 Ppm Extension set for telescopic boom of mobile crane and mobile crane when applying.
FR2732000B1 (en) 1995-03-22 1997-05-30 Potain Sa AUTOMATED MOUNT CRANE WITH FOLDABLE BOOM ON ITSELF
JPH09104588A (en) 1995-10-06 1997-04-22 Komatsu Ltd Auxiliary jib protrusion and storage device for crane
DE69727719T2 (en) * 1996-03-04 2005-01-13 Manitowoc Crane Companies, Inc., Reno Hinged connection for folding a luffing jib
CN2364010Y (en) 1999-03-26 2000-02-16 郑州铁路局工务机械厂 Hydraulic arm-folding crane
BE1012862A5 (en) 1999-08-31 2001-04-03 Lille Allebroer Leo Alix De Equipment for moving loads, making use of a mobile platform
DE10321493B4 (en) 2003-05-13 2006-07-20 Grove U.S. Llc Folding pinnacle bending
US7258242B2 (en) * 2003-08-22 2007-08-21 Terex-Demag Gmbh & Co. Kg Mobile crane boom having an autarchic hydraulic power unit mounted thereon
US7546928B2 (en) 2006-10-27 2009-06-16 Manitowoc Crane Companies, Inc. Mobile lift crane with variable position counterweight
EP2137093B1 (en) 2007-04-19 2016-09-28 Terex Cranes Germany GmbH Method for installing an auxiliary boom to a main boom on a mobile crane
DE202007012204U1 (en) * 2007-08-29 2007-10-31 Terex-Demag Gmbh & Co. Kg Element for connecting a grid system
CN101628691A (en) 2008-07-18 2010-01-20 卫华集团有限公司 Pitch winding mechanism of crane
DE102009007776A1 (en) 2009-02-04 2010-08-12 Terex Demag Gmbh Control for an adjustable boom extension of a mobile crane
DE102009010452A1 (en) * 2009-02-26 2010-09-02 Terex-Demag Gmbh Method and device for mounting and dismounting an attachment on the main boom of a mobile crane
DE102009022262A1 (en) 2009-05-22 2010-11-25 Terex Demag Gmbh Angular adjustment of a boom system
CN201458603U (en) 2009-08-12 2010-05-12 中国船舶重工集团公司第七一三研究所 Folding mechanism of lifting arm
DE102009053235A1 (en) 2009-11-06 2011-05-19 Gottwald Port Technology Gmbh Handling system for ISO containers with a container bridge
DE102010007545A1 (en) 2010-02-11 2011-08-11 Gottwald Port Technology GmbH, 40597 Crane, especially mobile harbor crane, with a hybrid propulsion system
DE102011053014A1 (en) 2011-08-26 2013-02-28 Demag Cranes & Components Gmbh Control arrangement for the parallel operation of at least two hoists, in particular cranes
CN102602825B (en) 2012-03-13 2014-07-16 中联重科股份有限公司 Auxiliary arm unfolding and folding device, arm support structure and crane
CN103359636A (en) 2012-03-28 2013-10-23 江苏华澄重工有限公司 Boom gravity center compensation device for single-boom portal crane
DE102012023814B4 (en) 2012-12-05 2015-02-05 Liebherr-Werk Ehingen Gmbh Folding tip for a mobile crane and method for pivoting the folding top
DE102014102121A1 (en) 2014-02-19 2015-08-20 Terex Mhps Gmbh Hafenkran
DE102014003831A1 (en) 2014-03-18 2015-09-24 Liebherr-Werk Ehingen Gmbh Crane boom system with a first boom element and a second cantilever element hinged thereto and tiltable crane
DE102015202734A1 (en) 2015-02-16 2016-08-18 Terex Cranes Germany Gmbh Crane and method for influencing a deformation of a boom system of such a crane
DE102015119381B3 (en) 2015-11-10 2017-04-27 Terex Global Gmbh Mobile crane and method for bending a main boom extension relative to a main boom of a mobile crane
DE102015119379B3 (en) 2015-11-10 2017-03-30 Terex Global Gmbh Mobile crane and method for bending a main boom extension relative to a main boom of a mobile crane
DE102015120350B3 (en) 2015-11-24 2017-05-24 Terex Global Gmbh Mobile crane for bending a main boom extension relative to a main boom of a mobile crane

Also Published As

Publication number Publication date
US10781083B2 (en) 2020-09-22
CN108290724A (en) 2018-07-17
DE102015120350B3 (en) 2017-05-24
WO2017089356A1 (en) 2017-06-01
US20180339889A1 (en) 2018-11-29
EP3347300B1 (en) 2019-05-08
CN108883916B (en) 2020-01-03
CN108290724B (en) 2019-09-27
CN108883916A (en) 2018-11-23
EP3337752B1 (en) 2019-05-08
WO2017089353A1 (en) 2017-06-01
EP3347300A1 (en) 2018-07-18
US10640340B2 (en) 2020-05-05
US20180346292A1 (en) 2018-12-06

Similar Documents

Publication Publication Date Title
EP3337752B1 (en) Mobile crane and method for angling a main boom extension in relation to a main boom of a mobile crane
DE102015119381B3 (en) Mobile crane and method for bending a main boom extension relative to a main boom of a mobile crane
DE102015119379B3 (en) Mobile crane and method for bending a main boom extension relative to a main boom of a mobile crane
EP2465809B1 (en) Telescopic system for crane boom and jib
DE102017101113B3 (en) Telescopic boom with pole tensioning system for a mobile crane and guying method
DE102011115355B4 (en) Boom element, telescopic boom and construction vehicle
DE102011102110A1 (en) Undercarriage for crawler crane, has left and right crawlers which have crawler supports that are indirectly/directly connected and slidably mounted on center frame
EP2288770B1 (en) Device for demolishing constructions
DE102007058553A1 (en) Lateral bracing for a lattice boom of a crane
DE102014012661B4 (en) Method of operating a crane and crane
EP3214258B1 (en) Construction device and method for erecting a mast
DE102017117958A1 (en) Crane and counterweight for a crane
DE102015001619B4 (en) Boom system for a mobile crane as well as a mobile crane
DE102013011173B4 (en) Method for assembling a crane as well as articulation, telescopic boom and crane
DE102017000389B4 (en) Crane boom, crane with such a crane boom and method for attaching a guy support to such a crane boom
DE102013006259A1 (en) Telescopic boom and crane
DE69810981T2 (en) Technique for erecting the mast for a telescopic crane
DE202017000243U1 (en) Boom adjustment device for a working device
DE4445165C2 (en) Method and stick tree for erecting lattice masts
EP4083346B1 (en) Supporting device for an automatic concrete pump
DE102011014585A1 (en) Method for erecting beam of crane, particularly for erecting lattice jib, involves erecting beam from laid down position, in which traction force is exerted on beam by traction element, particularly restraint
EP3480372B1 (en) Cable crane
EP1541520A1 (en) Mobile crane
DE202015008149U1 (en) Construction machine, especially crane, with A-Bock
DE102021130736A1 (en) Telescopic boom system of a mobile crane with a basic telescopic boom and an additional telescopic boom and method therefor

Legal Events

Date Code Title Description
STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: UNKNOWN

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: THE INTERNATIONAL PUBLICATION HAS BEEN MADE

PUAI Public reference made under article 153(3) epc to a published international application that has entered the european phase

Free format text: ORIGINAL CODE: 0009012

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: REQUEST FOR EXAMINATION WAS MADE

17P Request for examination filed

Effective date: 20180321

AK Designated contracting states

Kind code of ref document: A1

Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR

AX Request for extension of the european patent

Extension state: BA ME

GRAP Despatch of communication of intention to grant a patent

Free format text: ORIGINAL CODE: EPIDOSNIGR1

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: GRANT OF PATENT IS INTENDED

DAV Request for validation of the european patent (deleted)
DAX Request for extension of the european patent (deleted)
RIC1 Information provided on ipc code assigned before grant

Ipc: B66C 23/68 20060101AFI20190205BHEP

Ipc: B66C 23/70 20060101ALI20190205BHEP

Ipc: B66C 23/42 20060101ALI20190205BHEP

INTG Intention to grant announced

Effective date: 20190222

RAP1 Party data changed (applicant data changed or rights of an application transferred)

Owner name: TEREX GLOBAL GMBH

GRAS Grant fee paid

Free format text: ORIGINAL CODE: EPIDOSNIGR3

GRAA (expected) grant

Free format text: ORIGINAL CODE: 0009210

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: THE PATENT HAS BEEN GRANTED

AK Designated contracting states

Kind code of ref document: B1

Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR

REG Reference to a national code

Ref country code: GB

Ref legal event code: FG4D

Free format text: NOT ENGLISH

REG Reference to a national code

Ref country code: CH

Ref legal event code: EP

Ref country code: AT

Ref legal event code: REF

Ref document number: 1129825

Country of ref document: AT

Kind code of ref document: T

Effective date: 20190515

REG Reference to a national code

Ref country code: IE

Ref legal event code: FG4D

Free format text: LANGUAGE OF EP DOCUMENT: GERMAN

REG Reference to a national code

Ref country code: DE

Ref legal event code: R096

Ref document number: 502016004644

Country of ref document: DE

REG Reference to a national code

Ref country code: NL

Ref legal event code: MP

Effective date: 20190508

REG Reference to a national code

Ref country code: LT

Ref legal event code: MG4D

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: NO

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20190808

Ref country code: ES

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20190508

Ref country code: LT

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20190508

Ref country code: HR

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20190508

Ref country code: NL

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20190508

Ref country code: PT

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20190908

Ref country code: SE

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20190508

Ref country code: AL

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20190508

Ref country code: FI

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20190508

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: RS

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20190508

Ref country code: LV

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20190508

Ref country code: GR

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20190809

Ref country code: BG

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20190808

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: CZ

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20190508

Ref country code: SK

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20190508

Ref country code: EE

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20190508

Ref country code: DK

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20190508

Ref country code: RO

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20190508

REG Reference to a national code

Ref country code: DE

Ref legal event code: R097

Ref document number: 502016004644

Country of ref document: DE

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: SM

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20190508

Ref country code: IT

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20190508

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: FR

Payment date: 20191219

Year of fee payment: 5

PLBE No opposition filed within time limit

Free format text: ORIGINAL CODE: 0009261

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: NO OPPOSITION FILED WITHIN TIME LIMIT

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: TR

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20190508

26N No opposition filed

Effective date: 20200211

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: PL

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20190508

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: SI

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20190508

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: MC

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20190508

Ref country code: LU

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20191122

REG Reference to a national code

Ref country code: BE

Ref legal event code: MM

Effective date: 20191130

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: IE

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20191122

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: BE

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20191130

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: CH

Payment date: 20201118

Year of fee payment: 5

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: CY

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20190508

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: IS

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20190908

GBPC Gb: european patent ceased through non-payment of renewal fee

Effective date: 20201122

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: HU

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT; INVALID AB INITIO

Effective date: 20161122

Ref country code: MT

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20190508

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: GB

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20201122

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: MK

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20190508

REG Reference to a national code

Ref country code: CH

Ref legal event code: PL

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: FR

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20211130

REG Reference to a national code

Ref country code: AT

Ref legal event code: MM01

Ref document number: 1129825

Country of ref document: AT

Kind code of ref document: T

Effective date: 20211122

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: AT

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20211122

P01 Opt-out of the competence of the unified patent court (upc) registered

Effective date: 20230530

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: LI

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20220630

Ref country code: CH

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20220630

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: DE

Payment date: 20231121