CN111894010A - A foundation pit enclosure structure and construction method based on prefabricated slabs and diagonal braces - Google Patents
A foundation pit enclosure structure and construction method based on prefabricated slabs and diagonal braces Download PDFInfo
- Publication number
- CN111894010A CN111894010A CN202010784294.7A CN202010784294A CN111894010A CN 111894010 A CN111894010 A CN 111894010A CN 202010784294 A CN202010784294 A CN 202010784294A CN 111894010 A CN111894010 A CN 111894010A
- Authority
- CN
- China
- Prior art keywords
- prefabricated
- foundation pit
- plate
- basement
- slabs
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Withdrawn
Links
- 238000010276 construction Methods 0.000 title claims abstract description 27
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 80
- 239000010959 steel Substances 0.000 claims abstract description 80
- 239000002689 soil Substances 0.000 claims abstract description 33
- 239000011150 reinforced concrete Substances 0.000 claims description 9
- 239000004567 concrete Substances 0.000 claims description 5
- 239000004568 cement Substances 0.000 claims description 3
- 238000004873 anchoring Methods 0.000 claims 1
- 238000009412 basement excavation Methods 0.000 description 5
- 238000010586 diagram Methods 0.000 description 4
- 238000000034 method Methods 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000011065 in-situ storage Methods 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 238000012423 maintenance Methods 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 230000003014 reinforcing effect Effects 0.000 description 1
- 239000002699 waste material Substances 0.000 description 1
- 238000004078 waterproofing Methods 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/02—Foundation pits
- E02D17/04—Bordering surfacing or stiffening the sides of foundation pits
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/34—Concrete or concrete-like piles cast in position ; Apparatus for making same
- E02D5/46—Concrete or concrete-like piles cast in position ; Apparatus for making same making in situ by forcing bonding agents into gravel fillings or the soil
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
Abstract
Description
技术领域technical field
本发明涉及一种基坑围护结构及施工方法,特别涉及一种新型的基于预制板和斜撑的基坑围护结构及施工方法。The invention relates to a foundation pit enclosure structure and a construction method, in particular to a novel foundation pit enclosure structure and construction method based on prefabricated slabs and diagonal braces.
背景技术Background technique
随着城市汽车保有量的迅速增加,建筑物普遍设置地下室便于汽车的停放。为了获得较大的地下室空间,建筑设计常常将地下室的外墙边线紧贴建筑用地红线,同时建筑用地红线又往往紧邻周边建筑物和道路,这些都造成了地下室基坑常常采取几乎垂直的方式进行开挖,必须对基坑采取围护结构。With the rapid increase in the number of cars in the city, buildings are generally set up with basements to facilitate the parking of cars. In order to obtain a larger basement space, the architectural design often makes the outer wall of the basement close to the red line of the building land, and the red line of the building land is often close to the surrounding buildings and roads. Excavation, must adopt the enclosure structure for the foundation pit.
基坑设置围护结构的目的是确保基坑边坡的稳定,便于土方开挖,保护基坑周边建筑物、道路和管线等的安全。常规的基坑围护结构造价高、工期长,而且在地下室施工完毕后常被埋在回填土体中,造成了极大的浪费。此外,被埋在地下的基坑围护结构还对地下管线的埋设造成障碍。因此,将围护结构作为地下室主体结构的一部分是基坑围护设计和施工的迫切要求。The purpose of setting up the enclosure structure of the foundation pit is to ensure the stability of the foundation pit slope, facilitate earthwork excavation, and protect the safety of buildings, roads and pipelines around the foundation pit. The conventional foundation pit enclosure structure has high cost and long construction period, and is often buried in the backfill soil after the basement construction is completed, resulting in a great waste. In addition, the enclosing structure of the foundation pit buried in the ground also hinders the burying of the underground pipeline. Therefore, it is an urgent requirement for the design and construction of the foundation pit enclosure to take the enclosure structure as a part of the main structure of the basement.
发明内容SUMMARY OF THE INVENTION
针对现有技术存在的问题,本发明提供了一种结构简单、施工快速、造价较低、可回收的基坑围护结构和施工方法。Aiming at the problems existing in the prior art, the present invention provides a foundation pit enclosure structure and a construction method with simple structure, rapid construction, low cost and recyclability.
为实现上述目的,本发明提供如下技术方案:To achieve the above object, the present invention provides the following technical solutions:
一种基于预制板和斜撑的基坑围护结构,包括预制板、三轴水泥土搅拌桩、冠梁、钢斜撑、连接板,所述预制板插入三轴水泥土搅拌桩中,所述的冠梁现浇锚固在预制板上,所述连接板现浇锚固在相邻两块预制板之间,所述基坑的底部设置地下室底板,所述基坑的顶部设置地下室顶板,所述钢斜撑在基坑内倾斜设置,其上端与预制板固定连接,其下端与地下室底板固定连接,所述连接板上设置有侧边凹槽和中部凹槽,所述侧边凹槽对称设置在预制板截面短边沿长边的方向,所述中部凹槽设置在预制板对应地下室底板的位置,所述地下室底板延伸并连接至中部凹槽内,所述连接板固定连接至侧边凹槽。A foundation pit enclosure structure based on prefabricated slabs and diagonal braces, including prefabricated slabs, triaxial cement-soil mixing piles, crown beams, steel diagonal braces, and connecting plates, the prefabricated slabs are inserted into the triaxial cement-soil mixing piles, so The crown beam is cast-in-place anchored on the prefabricated plate, the connecting plate is cast-in-place anchored between two adjacent prefabricated slabs, the basement bottom plate is set at the bottom of the foundation pit, and the basement top plate is set at the top of the foundation pit, so the The steel diagonal brace is inclined in the foundation pit, its upper end is fixedly connected with the prefabricated plate, and its lower end is fixedly connected with the basement floor, the connecting plate is provided with a side groove and a middle groove, and the side grooves are symmetrically arranged In the direction of the short side along the long side of the cross section of the prefabricated panel, the middle groove is arranged at the position of the prefabricated panel corresponding to the basement floor, the basement floor extends and is connected to the middle groove, and the connecting plate is fixedly connected to the side grooves .
更进一步的,所述预制板为预应力钢筋混凝土预制构件,朝向基坑的侧边预留螺栓孔。Further, the prefabricated plate is a prestressed reinforced concrete prefabricated member, and bolt holes are reserved toward the side of the foundation pit.
更进一步的,所述预制板的长度为基坑深度的2倍,预制板顶部伸出有顶部带肋钢筋,所述顶部带肋钢筋嵌入冠梁中,所述侧边凹槽的内侧向外均伸出有侧边带肋钢筋,侧边凹槽的宽度为预制板宽度的1/2,所述中部凹槽的内侧向外伸出有中部带肋钢筋,中部凹槽的宽度与地下室底板的宽度一致。Further, the length of the prefabricated plate is twice the depth of the foundation pit, the top ribbed steel bar protrudes from the top of the prefabricated plate, the top ribbed steel bar is embedded in the crown beam, and the inner side of the side groove is outward. There are side ribbed steel bars protruding, the width of the side grooves is 1/2 of the width of the prefabricated plate, the middle ribbed steel bars are protruding from the inner side of the middle groove, and the width of the middle groove is the same as that of the basement floor. of the same width.
更进一步的,所述顶部带肋钢筋的长度为0.3m,间距为0.5m,所述侧边凹槽和中部凹槽的深度均为0.2m,侧边带肋钢筋和中部带肋钢筋的长度均为0.1m,间距均为0.2m。Further, the length of the top ribbed steel bar is 0.3m, the spacing is 0.5m, the depth of the side groove and the middle groove are both 0.2m, and the length of the side ribbed steel bar and the middle ribbed steel bar is 0.2m. Both are 0.1m, and the spacing is 0.2m.
更进一步的,所述三轴水泥土搅拌桩的宽度为预制板宽度的1.5倍。Further, the width of the triaxial cement-soil mixing pile is 1.5 times the width of the prefabricated plate.
更进一步的,所述冠梁设置于预制板的顶部,为现浇钢筋混凝土结构,所述冠梁的高度为0.5m,宽度超过预制板宽度的1/3。Furthermore, the crown beam is arranged on the top of the prefabricated slab and is a cast-in-place reinforced concrete structure, the height of the crown beam is 0.5m, and the width exceeds 1/3 of the width of the prefabricated slab.
更进一步的,所述钢斜撑为支撑预制板,其截面为圆形,直径为0.3~0.6m,间距2~4m。Further, the steel diagonal brace is a supporting prefabricated plate, the cross section is circular, the diameter is 0.3-0.6 m, and the spacing is 2-4 m.
更进一步的,所述连接板为现浇钢筋混凝土结构,用于连接相邻两块预制板,所述连接板上设置有受力钢筋,通过钢筋套筒将连接板的受力钢筋与侧边带肋钢筋进行机械连接。Further, the connecting plate is a cast-in-place reinforced concrete structure, which is used to connect two adjacent prefabricated plates, and the connecting plate is provided with a stressed steel bar, and the stressed steel bar of the connecting plate is connected to the side edge through a steel sleeve. Ribbed steel bars are mechanically connected.
一种基于预制板和斜撑的基坑围护结构的施工方法,包括:A construction method for a foundation pit enclosure structure based on prefabricated slabs and diagonal braces, comprising:
步骤1:开挖地下室外墙的沟槽,先施工两段三轴水泥土搅拌桩,然后在桩体初凝前,将一块预制板依靠其自重插入桩体内,循环反复,直至完成所有的三轴水泥土搅拌桩和预制板的施工;Step 1: Excavate the trench for the exterior wall of the basement, first construct two sections of three-axis cement-soil mixing piles, and then insert a prefabricated board into the pile body by its own weight before the initial setting of the pile body, and repeat the cycle until all three steps are completed. Construction of shaft cement-soil mixing piles and prefabricated slabs;
步骤2:在所有的预制板的顶部一次现浇混凝土冠梁,锚入顶部带肋钢筋;待冠梁达到设计强度要求后,从中部向四周开挖地下室基坑,直至坑内中部土体达到设计标高并仅剩余四周斜坡;在基坑底部现浇地下室底板,板边缘预留螺栓孔;待地下室底板达到设计强度要求后,在斜坡上将钢斜撑固定安装在预制板和地下室底板上;Step 2: Cast in-situ concrete crown beams on top of all precast slabs, and anchor the top ribbed steel bars; after the crown beams meet the design strength requirements, excavate the basement foundation pit from the middle to the surrounding areas until the soil in the middle of the pit reaches the design strength Elevation and only the surrounding slopes remain; cast the basement floor at the bottom of the foundation pit, and reserve bolt holes on the edge of the plate; after the basement floor meets the design strength requirements, fix the steel bracing on the slope on the prefabricated slab and the basement floor;
步骤3:挖除钢斜撑下方剩余的坑内土体和相邻预制板间的水泥土,将地下室底板的受力钢筋和中部带肋钢筋通过套筒连接在一起,继续浇筑地下室底板,将其延长至预制板侧边凹槽内;Step 3: Excavate the remaining soil in the pit below the steel bracing and the cement and soil between the adjacent prefabricated slabs, connect the stressed steel bars of the basement floor and the ribbed steel bars in the middle through the sleeve, and continue to pour the basement floor and put it together. Extend into the groove on the side of the prefabricated board;
步骤4:将连接板的受力钢筋和侧边带肋钢筋通过套筒连接在一起,随后由下而上浇筑所有预制板间的连接板,最后浇筑地下室顶板;Step 4: Connect the stressed steel bar and the side ribbed steel bar of the connecting plate together through the sleeve, then pour the connecting plate between all the prefabricated plates from bottom to top, and finally pour the basement roof;
步骤5:待地下室顶板的强度达到设计强度后,拆除钢斜撑,完成地下室施工。Step 5: After the strength of the basement roof reaches the design strength, remove the steel bracing to complete the basement construction.
与现有技术相比,本发明的有益效果是:Compared with the prior art, the beneficial effects of the present invention are:
(1)围护结构一部分可作为地下室主体结构,另一部分可回收,工程造价低。常规围护结构较少回收,基坑回填时被掩埋在土体中,而本发明所述预制板可作为地下室的结构外墙,基坑土方不用回填,而且钢斜撑还可回收,因此具有造价低的优点。(1) Part of the enclosure structure can be used as the main structure of the basement, and the other part can be recycled, so the project cost is low. The conventional enclosure structure is less recycled, and is buried in the soil when the foundation pit is backfilled, while the prefabricated panel of the present invention can be used as the structural outer wall of the basement, the earthwork of the foundation pit does not need to be backfilled, and the steel diagonal bracing can be recycled, so it has The advantage of low cost.
(2)工期短,质量可控。常规基坑围护结构采用现浇混凝土,而本发明所述基坑围护结构中预应力预制板在工厂预制,质量可控,运到工地里直接插入三轴搅拌桩中,节省了混凝土养护工期,便于土方开挖,同时钢斜撑采用拼装的安装方法,进一步节省了工期。(2) The construction period is short and the quality is controllable. The conventional foundation pit enclosure structure adopts cast-in-place concrete, while the prestressed prefabricated slabs in the foundation pit enclosure structure of the present invention are prefabricated in the factory, with controllable quality, and are transported to the construction site and directly inserted into the three-axis mixing piles, saving concrete maintenance. The construction period is convenient for earthwork excavation. At the same time, the steel diagonal bracing adopts the assembled installation method, which further saves the construction period.
(3)适用范围广。目前全国95%以上的地下室为1~2层,基坑开挖深度为5~12m,本发明所述基坑围护结构中均适用。(3) Wide range of application. At present, more than 95% of the basements in the country have 1-2 floors, and the excavation depth of the foundation pit is 5-12 m, which are all applicable to the foundation pit enclosure structure of the present invention.
附图说明Description of drawings
图1为预制板插入三轴水泥土搅拌桩的示意图;Fig. 1 is the schematic diagram of the prefabricated plate inserted into the three-axis cement-soil mixing pile;
图2为预制板立面和侧面的示意图;Figure 2 is a schematic diagram of the prefabricated panel facade and side;
图3为连接板俯视的示意图;Fig. 3 is the schematic diagram of the top view of the connecting plate;
图4为连接板立面的示意图;Fig. 4 is the schematic diagram of connecting plate elevation;
图5为围护结构的施工步骤图。Figure 5 shows the construction steps of the enclosure structure.
图中:1、基坑内土体;2、预制板;3、顶部带肋钢筋;4、三轴水泥土搅拌桩;5、冠梁;6、钢斜撑;7、地下室底板;8、地下室顶板;9、连接板;10、侧边凹槽;11、螺栓孔;12、中部凹槽;13、侧边带肋钢筋;14、中部带肋钢筋。In the picture: 1. Soil in foundation pit; 2. Prefabricated slab; 3. Ribbed steel bar on top; 4. Triaxial cement-soil mixing pile; 5. Crown beam; 6. Steel diagonal brace; 7. Basement floor; 8. Basement Top plate; 9, connecting plate; 10, side groove; 11, bolt hole; 12, middle groove; 13, side ribbed steel bar; 14, middle ribbed steel bar.
具体实施方式Detailed ways
下面结合说明书附图和具体的实施例,对本发明作详细描述。The present invention will be described in detail below with reference to the accompanying drawings and specific embodiments.
本实施例提供一种如图1-5所示的基于预制板和斜撑的基坑围护结构,该基坑围护结构包括预制板2、三轴水泥土搅拌桩4、冠梁5、钢斜撑6、连接板9。预制板2插入三轴水泥土搅拌桩4中。所冠梁5现浇锚固在预制板2上,顶部带肋钢筋3嵌入冠梁5中。钢斜撑6与预制板2采取螺栓连接。钢斜撑6通过预留的螺栓孔11,将预制板2和地下室底板7螺栓装配连接为整体。连接板9现浇锚固在相邻两块预制板2之间。地下室底板7延伸至中部凹槽12内,地下室底板7中受力钢筋与中部带肋钢筋14采用钢筋套筒连接在一起。连接板9连接相邻的两块预制板2,连接板9中受力钢筋与侧边带肋钢筋13采用钢筋套筒连接在一起。This embodiment provides a foundation pit enclosure structure based on prefabricated slabs and diagonal braces as shown in Figures 1-5. The foundation pit enclosure structure includes a
预制板2为预应力钢筋混凝土预制构件,朝向基坑的侧边预留螺栓孔。预制板2长度为拟建基坑深度的2倍,截面尺寸根据基坑深度由设计确定。预制板2顶部伸出两排顶部带肋钢筋3,钢筋长度均为0.3m,间距均为0.5m。预制板2上有两段凹槽,深度均为0.2m,凹槽内侧向外均伸出的两排带肋钢筋,钢筋长度均为0.1m,间距均为0.2m。其中一段凹槽对称设置在预制板截面短边沿长边的方向,即侧边凹槽10,凹槽宽度为预制板宽度的1/2。另一段凹槽设置在预制板对应地下室底板的位置,即侧边凹槽12,凹槽宽度与地下室底板7设计的宽度一致。The
三轴水泥土搅拌桩4作用为加固坑边土体和防水止水,宽度为预制板2宽度的1.5倍。在三轴水泥土搅拌4桩初凝前,将预制板2插入,待终凝后再进行土方开挖。The triaxial cement-
冠梁5在预制板2的顶部,为现浇钢筋混凝土结构。冠梁5高度为0.5m,宽度超过预制板2宽度的1/3。为使所有预制板2连成整体,施工时需将预制板2的顶部带肋钢筋3锚入冠梁5。The
钢斜撑6作用为支撑预制板2,减小其水平变形。钢斜撑6截面为圆形,直径为0.3~0.6m,间距2~4m。钢斜撑6两端分别与预制板2和地下室底板7进行螺栓连接。The steel
连接板9为现浇钢筋混凝土结构,作用为连接相邻两块预制板2。施工时利用钢筋套筒将连接板9的受力钢筋与预制板2的侧边凹槽10外露的钢筋进行机械连接。The connecting
本实施例还提供一种如图5所示的基于预制板和斜撑的基坑围护结构的施工方法,包括以下步骤:The present embodiment also provides a construction method for a foundation pit enclosure structure based on prefabricated slabs and diagonal braces as shown in Figure 5, comprising the following steps:
步骤1:开挖地下室外墙的沟槽,先施工两段三轴水泥土搅拌桩4,然后在桩体初凝前,用吊机将一块预制板2依靠其自重插入桩体内,循环反复,直至完成所有的三轴水泥土搅拌桩4和预制板2的施工。Step 1: Excavate the trench of the basement exterior wall, first construct two sections of three-axis cement-
步骤2:在所有的预制板2的顶部一次现浇混凝土冠梁5,锚入顶部带肋钢筋3。待冠梁5达到设计强度要求后,从中部向四周开挖地下室基坑,直至坑内中部土体1达到设计标高并仅剩余四周斜坡。在基坑底部现浇地下室底板7,板边缘预留螺栓孔11。待地下室底板7达到设计强度要求后,在斜坡上将钢斜撑6螺栓安装在预制板2和地下室底板7上。Step 2: One-time cast-in-place
步骤3:挖除钢斜撑6下方剩余的坑内土体1和相邻预制板2间的水泥土,将地下室底板7的受力钢筋和中部带肋钢筋14通过套筒连接在一起,继续浇筑地下室底板7,将其延长至预制板2侧边凹槽10内。Step 3: Excavate the remaining
步骤4:将连接板9的受力钢筋和侧边带肋钢筋13通过套筒连接在一起,随后由下而上浇筑所有预制板2间的连接板9,最后浇筑地下室顶板8。Step 4: Connect the stressed steel bar of the connecting
步骤5:待地下室顶板8强度达到设计强度后,拆除钢斜撑6,完成地下室施工。Step 5: After the strength of the
以上所述仅为本发明的较佳实施例而已,并不用以限制本发明。凡在本发明的精神和原则之内所作的任何修改、等同替换和改进等,均应包含在本发明的保护范围之内。The above descriptions are only preferred embodiments of the present invention, and are not intended to limit the present invention. Any modifications, equivalent replacements and improvements made within the spirit and principle of the present invention shall be included within the protection scope of the present invention.
Claims (9)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202010784294.7A CN111894010A (en) | 2020-08-06 | 2020-08-06 | A foundation pit enclosure structure and construction method based on prefabricated slabs and diagonal braces |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202010784294.7A CN111894010A (en) | 2020-08-06 | 2020-08-06 | A foundation pit enclosure structure and construction method based on prefabricated slabs and diagonal braces |
Publications (1)
Publication Number | Publication Date |
---|---|
CN111894010A true CN111894010A (en) | 2020-11-06 |
Family
ID=73246606
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202010784294.7A Withdrawn CN111894010A (en) | 2020-08-06 | 2020-08-06 | A foundation pit enclosure structure and construction method based on prefabricated slabs and diagonal braces |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN111894010A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN119145428A (en) * | 2024-11-14 | 2024-12-17 | 上海建工七建集团有限公司 | Supporting structure for basement foundation pit |
-
2020
- 2020-08-06 CN CN202010784294.7A patent/CN111894010A/en not_active Withdrawn
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN119145428A (en) * | 2024-11-14 | 2024-12-17 | 上海建工七建集团有限公司 | Supporting structure for basement foundation pit |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN201125354Y (en) | Steep hill road bed branch block reinforced structure | |
CN109944250B (en) | Foundation pit forward and backward combined construction method of non-permanent vertical supporting system | |
CN106759439B (en) | Tower crane foundation for foundation pit and construction method thereof | |
CN107806101B (en) | Construction method for strip foundation pit cast-in-place concrete diagonal bracing prefabricated connecting beam | |
CN112575789A (en) | Diagonal space truss foundation pit inner support system | |
CN104631440A (en) | Stiffening core lengthening foundation pit support structure for existing large-diameter bored concrete pile and construction method | |
KR100313720B1 (en) | Composite Underground Structure Construction Method | |
CN109914470A (en) | Road shoulder retaining wall and construction method thereof | |
CN107326932B (en) | Quasi-semi-reverse construction method for underground garage | |
CN213143117U (en) | Assembled keyway basis retaining wall structure | |
CN111894010A (en) | A foundation pit enclosure structure and construction method based on prefabricated slabs and diagonal braces | |
CN211547686U (en) | Prestressed concrete-filled steel tube pipe curtain structure based on prefabricated concrete-filled steel tube connection | |
CN112554206A (en) | PC plate beam shared by foundation pit support structure and basement outer wall and installation method thereof | |
CN214657161U (en) | Rectangular staggered joint assembled well wall structure | |
CN116464060A (en) | A construction method for accelerating high-span area structures at high-span areas of basement floors | |
CN212452765U (en) | A two-wall-integrated underground pipe gallery structure | |
CN212248261U (en) | Foundation pit support structure using steel sheet piles and precast concrete piles | |
CN211006701U (en) | Foundation pit supporting structure integrating pile and wall | |
CN210421112U (en) | Foundation ditch SMW worker method stake supporting construction | |
CN111305268B (en) | Underground pipe gallery and underlying space cooperative enclosure structure and construction method thereof | |
KR200219236Y1 (en) | A mold assembly for reinforced concrete girders execution | |
CN106988337A (en) | Reinforcing method for reducing uneven settlement of strip-shaped shallow foundation house | |
CN112814003A (en) | Rectangular staggered joint assembled well wall structure and assembling method thereof | |
CN113653064A (en) | Front-support rear-pull type foundation pit enclosure system and construction method thereof | |
CN113090066A (en) | Construction method for newly added entrances and exits of existing buildings and elevator shaft |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
WW01 | Invention patent application withdrawn after publication | ||
WW01 | Invention patent application withdrawn after publication |
Application publication date: 20201106 |