CN110397018A - A kind of building lot reinforcement means suitable for soft clay area - Google Patents

A kind of building lot reinforcement means suitable for soft clay area Download PDF

Info

Publication number
CN110397018A
CN110397018A CN201910749811.4A CN201910749811A CN110397018A CN 110397018 A CN110397018 A CN 110397018A CN 201910749811 A CN201910749811 A CN 201910749811A CN 110397018 A CN110397018 A CN 110397018A
Authority
CN
China
Prior art keywords
building
foundation
foundation pit
jack
soft clay
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910749811.4A
Other languages
Chinese (zh)
Inventor
赵文
程诚
路博
柏谦
王志国
金文强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Northeastern University China
Original Assignee
Northeastern University China
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Northeastern University China filed Critical Northeastern University China
Priority to CN201910749811.4A priority Critical patent/CN110397018A/en
Publication of CN110397018A publication Critical patent/CN110397018A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00Improving or preserving soil or rock, e.g. preserving permafrost soil
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00Improving or preserving soil or rock, e.g. preserving permafrost soil
    • E02D3/11Improving or preserving soil or rock, e.g. preserving permafrost soil by thermal, electrical or electro-chemical means

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Structural Engineering (AREA)
  • Agronomy & Crop Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Soil Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)

Abstract

The present invention provides a kind of building lot reinforcement means suitable for soft clay area, step is reinforced including building external and building lower part reinforces step, wherein, the lower part reinforces step are as follows: a series of foundation pits are arranged in the lower section of building, one foundation pit of every setting sets up jack after carrying out electric osmose reinforcing in the foundation pit, after whole building is propped up by jack, pile foundation is performed between the two neighboring jack, after the completion of the pile foundation performs, jack is symmetrically recycled from centre to four sides, backfills the soil body after jack recycles operation.Technical solution of the present invention solves the problems, such as soft clay area ground moisture content height, bearing capacity bottom in the prior art.

Description

A kind of building lot reinforcement means suitable for soft clay area
Technical field
The present invention relates to architectural engineering and ground foundation engineering fields, specifically, more particularly to a kind of suitable for weak soil The building lot reinforcement means in area.
Background technique
With the development of the times with the raising of the level of urbanization, Chinese national economy rapid growth, overall national strength increasingly increases Long, infrastructure is grown rapidly, and China is made to become building big country, and gross floors area ranks the first in the world.Eighties of last century is built up Building be increasingly becoming history relic, and the influence with surrounding enviroment overload unloading to existing building, historical building also by Gradually step into " quality is made reprisals the phase ".Due to setting of ground and building is older does not repair, and building is caused to be sunk cracking, roofing deformation, Seriously jeopardize the safety of building, it is necessary to adopt an effective measure and consolidation process is carried out to the foundation of building.According to China The requirement of " Law For the Preservation of Antiques ", the repairerment of cultural relic building must comply with the principle of " not changing historical relic original state ".Therefore, can pass through It improves the methods of foundation bearing capacity, reduction foundation deformation to be handled, takes suitable foundation stabilization measure, can repair even The use to building is improved, compared with removing and rebuilding, there is greater advantage in terms of Social benefit and economic benefit.
In recent years, there is Lack of support in historical building foundation, excessive is caused historical building uneven by disturbing The problems such as even sedimentation, occurs again and again, and demand of the people to foundation is reinforced again gradually increases, the requirement to foundation consolidating technology Also higher and higher, so foundation stabilization is concerned in building field.Existing construction foundation reinforcement means mainly has: pouring reinforcement Concrete raft plate increases bottom of foundation area method, anchor rod pressing pile technique, and reinforced concrete fortifield village covers method, concrete precast pile foundation underpinning Method etc..But the above method, construction way are complicated, the duty cycle is longer, and project cost is higher, and be only applicable to geological conditions compared with Good engineering.And soft clay area, geological conditions is poor, moisture content is higher, and bearing capacity is lower, currently without one set of construction method Stiffening basic ground suitable for soft clay area historical building.Therefore, it is necessary to propose a kind of new foundation reinforcement method with Solve the problems, such as soft clay area ground moisture content height, bearing capacity bottom.
Summary of the invention
The complicated, project cost according to existing building foundation reinforcement method construction way existing in the prior art set forth above It is higher and be only applicable to the preferable engineering of geological conditions and be difficult to solve that soft clay area ground moisture content is high, technology of bearing capacity bottom Problem, and a kind of building lot reinforcement means suitable for soft clay area is provided.The present invention mainly utilizes the outside around building to set It is externally reinforced to set campshed progress, by electric osmose reinforcement principle after excavation pit, electric osmose reinforcing is carried out to existing ground, passes through thousand Temporary support is done on jin top, and pile foundation is performed below building, is recycled jack and is backfilled the soil body, to realize to building lot The reinforcing on basis.
The technological means that the present invention uses is as follows: a kind of building lot reinforcement means suitable for soft clay area, including builds It builds externally reinforced step and building lower part reinforces step, wherein the lower part reinforces step are as follows: one system is set in the lower section of building Column foundation pit, one foundation pit of every setting sets up jack after carrying out electric osmose reinforcing in the foundation pit, until whole building is very heavy After having shored, pile foundation is performed between the two neighboring jack, after the completion of the pile foundation performs, from centre to four sides pair Claim recycling jack, backfills the soil body after jack recycles operation.
Further, described externally reinforced for several campsheds being equally spaced are arranged around the external of building, reinforce building The periphery soil body has an impact surrounding soil when to prevent excavation of foundation pit, and building is caused to deform, and the campshed adds as permanent Gu measure is not recycled;The diameter of the campshed is 600mm, and the spacing of the axis of the two neighboring campshed is 1m.
Further, the set-up mode of the foundation pit is that foundation pit is internally successively arranged from the edge of building, In, first along the longitudinally disposed foundation pit of building, then along the lateral setting foundation pit of building, wherein the size of the foundation pit is 2m × 2m × 2m, the spacing at the center of the two neighboring foundation pit are 2m, and the setting of foundation pit can avoid differential settlement.
Further, the set-up mode of above-mentioned foundation pit specifically refer to first from the edge of building be arranged foundation pit, four It is the outermost layer construction layer of building at circumferential edges, it is first along the longitudinally disposed foundation pit of building, i.e., symmetrical below building Both sides of the edge at start simultaneously at setting, set gradually from longitudinal starting point to longitudinal terminal, the foundation pit at longitudinal both sides of the edge After being provided with, along and longitudinally perpendicular lateral setting foundation pit, i.e., below building at the symmetrical both sides of the edge in front and back simultaneously Start setting up, set gradually from lateral starting point to lateral terminal, after the foundation pit of both lateral sides edge is provided with, start to Foundation pit is arranged in building interior direction, i.e., foundation pit is being arranged close to outermost inside one layer of construction layer, setting sequence repeats above-mentioned Process continues inwardly setting foundation pit later, and all foundation pits are provided with below whole building;
Longitudinal starting point of the foundation pit and longitudinal terminal are respectively positioned on the four corners for building current construction layer, the transverse direction starting point Close to longitudinal starting point or longitudinal terminal, the transverse direction terminal is close to longitudinal starting point or longitudinal terminal.
Further, the electric osmose reinforcing refers at the foundation pit, water pump is connected using iontophoresis device, by the foundation pit The water at place is all delivered to collecting gutter by the water pump, tamps to ground, is reinforced using electric osmose and carries out draining at foundation pit It reinforces, construction is simple is convenient, and it is adaptable, and low cost.
Further, the erection jack refers to places large-scale jack in the foundation pit, the jack it is upper End and lower end are respectively connected with steel plate, adjust the height of the jack, connect the steel plate and building bottom surface, setting Steel plate can increase foundation area, reduce footprint pressure, wherein the diameter of the steel plate is 1.5m, with a thickness of 15mm.
Further, it is described perform pile foundation refer to building lower section setting inside for cavity steel pipe as pile foundation The bottom surface of plinth, the top of the pile foundation and the building connects, and the upper end side of the pile foundation is equipped with reserving hole, From the entrance of the reserving hole to the inside concrete perfusion of the steel pipe, when concreting is completed and reaches intensity requirement When, concrete filled steel tube bored concrete pile foundation performs completion, wherein the spacing of adjacent two pile foundations is 2m, the pile foundation is equal 1m is driven underground, refers to that the bottom end of the pile foundation is located at the lower section of the foundation pit bottom end, and the bottom end of the pile foundation and institute Stating the distance between bottom end of foundation pit is 1m.
Further, the iontophoresis device is made of cathode, anode and power supply, is arranged using annular electrode, the annular Electrode arrangement refers to that the cathode is centrally located, the anode around the cathode arrange, wherein the cathode with it is described Distance between anode is 1.5m, and the height of the cathode and the anode is 1m, equal buried depth 1m, refers to the cathode and described The bottom end of anode is located at the lower section of the foundation pit bottom end, and the bottom end of the cathode and the anode and the bottom end of the foundation pit it Between distance be 1m.
Further, the anode is at least provided with 4, it is ensured that reinforcing area can be drained uniformly, can be according to requirement of engineering, ground Depending on base soil moisture content height.
Compared with the prior art, the invention has the following advantages that
1, the building lot reinforcement means provided by the invention suitable for soft clay area adds building lower section ground Gu it is externally reinforced by several campsheds progress of external setting around building, by electric osmose reinforcement principle after excavation pit, to both It the problems such as thering is ground to carry out electric osmose reinforcing, effectively solving soft clay area ground moisture content high-bearing capacity bottom, is done and is faced by jack When support, the recycling of jack achievees the purpose that save the cost, and subsequent that pile foundation is performed below building, recycling jack is simultaneously The soil body is backfilled, to realize the reinforcing to building foundation.
2, the building lot reinforcement means provided by the invention suitable for soft clay area, efficiently solves soft clay area ground The problems such as moisture content height, bearing capacity bottom, construction way is simple, has saved engineering cost.
To sum up, it applies the technical scheme of the present invention and is able to solve existing building foundation reinforcement method existing in the prior art Construction way is complicated, project cost is higher and is only applicable to the preferable engineering of geological conditions and is difficult to solve soft clay area ground to contain The problem of water rate height, bearing capacity bottom.
The present invention can be widely popularized in the fields such as architectural engineering and ground foundation engineering based on the above reasons.
Detailed description of the invention
In order to more clearly explain the embodiment of the invention or the technical proposal in the existing technology, to embodiment or will show below There is attached drawing needed in technical description to do simply to introduce, it should be apparent that, the accompanying drawings in the following description is this hair Bright some embodiments for those of ordinary skill in the art without any creative labor, can be with It obtains other drawings based on these drawings.
Fig. 1 is campshed arrangement schematic diagram in the present invention.
Fig. 2 is excavation of foundation pit schematic diagram in the present invention.
Fig. 3 is electrode arrangement schematic diagram in the present invention.
Fig. 4 is pump and cathode connection schematic diagram in the present invention.
Fig. 5 is the structural schematic diagram of jack and steel plate in the present invention.
Fig. 6 is jack arrangement schematic diagram in the present invention.
Fig. 7 is concrete filled steel tube bored concrete pile layout drawing in the present invention.
In figure: 1, building;2, foundation pit has been dug;3, anode;4, cathode;5, pumping line;6, it pumps;7, jack;8, steel plate;9, Concrete filled steel tube bored concrete pile;10, reserving hole;11, campshed.
Specific embodiment
In order to enable those skilled in the art to better understand the solution of the present invention, below in conjunction in the embodiment of the present invention Attached drawing, technical scheme in the embodiment of the invention is clearly and completely described, it is clear that described embodiment is only The embodiment of a part of the invention, instead of all the embodiments.Based on the embodiments of the present invention, ordinary skill people The model that the present invention protects all should belong in member's every other embodiment obtained without making creative work It encloses.
Embodiment
As shown in figs. 1-7, the present invention provides a kind of building lot reinforcement means suitable for soft clay area, including building Externally reinforced step and building lower part reinforce step, wherein the lower part reinforces step are as follows: excavate in the lower section of building a series of Foundation pit, one foundation pit of every excavation sets up jack after carrying out electric osmose reinforcing in the foundation pit, until whole building is by jack After propping up, pile foundation is performed between two neighboring jack, after the completion of pile foundation performs, is symmetrically recycled from centre to four sides very heavy Top backfills the soil body after jack recycles operation.
As shown in Figure 1, the campshed that externally reinforced one circle of external construction for around building in the present embodiment is equally spaced, adds Admittedly the building periphery soil body has an impact surrounding soil when to prevent excavation of foundation pit, building is caused to deform, and campshed is as permanent Reinforcement measure does not recycle;The diameter of campshed is 600mm, and the spacing of the axis of two neighboring campshed is 1m.
As shown in Fig. 2, the digging mode of the foundation pit in the present embodiment is internally successively to open from the edge of building Dig foundation pit, wherein first along longitudinal excavation pit of building, then along the lateral excavation pit of building, wherein the size of foundation pit is 2m The spacing of × 2m × 2m, the center of two neighboring foundation pit are 2m, and excavation pit can avoid differential settlement.
The digging mode of above-mentioned foundation pit specifically refers to the edge excavation pit first from building, and edge is The outermost layer construction layer of building is both sides of the edge symmetrical below building first along longitudinal excavation pit of building Place starts simultaneously at excavation, successively excavates from longitudinal starting point to longitudinal terminal, after the completion of the excavation of foundation pit at longitudinal both sides of the edge, Edge and longitudinally perpendicular lateral excavation pit, to be in start simultaneously at excavation at the symmetrical both sides of the edge in front and back below building, from Lateral starting point is successively excavated to lateral terminal, after the completion of the excavation of foundation pit of both lateral sides edge, is started to building interior side To excavation pit, i.e., close to outermost inside one layer of construction layer excavation pit, sequence of excavation is repeated the above process, it is subsequent Continue inside excavation pit, all excavation of foundation pit are completed below whole building.
Longitudinal starting point of foundation pit in the present embodiment and longitudinal terminal are respectively positioned on the four corners for building current construction layer, left and right Longitudinal starting point on both sides is located at the rear side of building, and longitudinal terminal of the right and left is located at the front side of building;The transverse direction on front and back both sides Starting point is located at the right side of building, and respectively close to longitudinal starting point or longitudinal terminal, the lateral terminal on front and back both sides is located at building Left side, and respectively close to longitudinal starting point and longitudinal terminal.
As shown in Figure 3, Figure 4, the electric osmose reinforcing in the present embodiment refers at foundation pit, connects water pump using iontophoresis device, Water at foundation pit is all delivered to collecting gutter by water pump, ground is tamped, is reinforced using electric osmose and carries out row at foundation pit Water is reinforced, and construction is simple is convenient, adaptable, and low cost.
Above-mentioned iontophoresis device is made of cathode, anode and power supply, is arranged using annular electrode, it should be noted that annular Electrode arrangement refers to that cathode is centrally located, anode surrounding cathode arrangement;Water pump is connected by pumping line on the top of cathode, Since water is polar molecule, after energization, water to movable cathode and can be gathered in cathode, by water pump that the water assembled at cathode is defeated It send to collecting gutter, wherein anode is equipped with 4, it is ensured that reinforcing area can be drained uniformly, and multianode is disposed with to be added conducive to soil body draining Gu the number of anode can be according to requirement of engineering, depending on foundation soil body moisture content height.Each anode between cathode at a distance from be The height of 1.5m, cathode and anode is 1m, equal buried depth 1m, refers to that the bottom end of cathode and anode is located at the lower section of foundation pit bottom end, And the distance between the bottom end of bottom end and foundation pit of cathode and anode is 1m.
As shown in Figure 5, Figure 6, the erection jack in the present embodiment refers to places large-scale jack, jack in foundation pit Top and bottom be respectively connected with steel plate, adjust the height of jack, make steel plate and building bottom surface connect, the steel plate of setting Foundation area can be increased, reduce footprint pressure, wherein the diameter of steel plate is 1.5m, with a thickness of 15mm.
As shown in fig. 7, in the present embodiment perform pile foundation refer to building lower section setting inside be cavity steel pipe As pile foundation, the top of pile foundation and the bottom surface of building are connected, and the upper end side of pile foundation is equipped with reserving hole, from pre- Box out hole inside concrete perfusion from entrance to steel pipe, when concreting is completed and when reaching intensity requirement, steel tube concrete Native bored concrete pile foundation performs completion, wherein the spacing on adjacent two piles basis is 2m, pile foundation is driven underground 1m, refers to pile foundation The bottom end of plinth is located at the lower section of foundation pit bottom end, and the distance between the bottom end of pile foundation and the bottom end of foundation pit are 1m.
Finally, it should be noted that the above embodiments are only used to illustrate the technical solution of the present invention., rather than its limitations;To the greatest extent Pipe present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that: its according to So be possible to modify the technical solutions described in the foregoing embodiments, or to some or all of the technical features into Row equivalent replacement;And these are modified or replaceed, various embodiments of the present invention technology that it does not separate the essence of the corresponding technical solution The range of scheme.

Claims (8)

1. a kind of building lot reinforcement means suitable for soft clay area, which is characterized in that including building external reinforce step and It builds lower part and reinforces step, wherein the lower part reinforces step are as follows: a series of foundation pits, every setting one are set in the lower section of building A foundation pit sets up jack after carrying out electric osmose reinforcing in the foundation pit, after whole building is propped up by jack, adjacent Pile foundation is performed between two jack, after the completion of the pile foundation performs, symmetrically recycles jack from centre to four sides, when The soil body is backfilled after jack recycling operation.
2. the building lot reinforcement means according to claim 1 suitable for soft clay area, which is characterized in that the outside The campshed being equally spaced for the external setting around building is reinforced, the diameter of the campshed is 600mm, the two neighboring campshed The spacing of axis is 1m.
3. the building lot reinforcement means according to claim 1 suitable for soft clay area, which is characterized in that the foundation pit Set-up mode be that from the edge of building foundation pit is internally successively set, wherein first along the longitudinally disposed foundation pit of building, Again along the lateral setting foundation pit of building, wherein the size of the foundation pit is 2m × 2m × 2m, the center of the two neighboring foundation pit Spacing be 2m.
4. the building lot reinforcement means according to claim 1 suitable for soft clay area, which is characterized in that the electric osmose Reinforcing refers at the foundation pit, connects water pump using iontophoresis device, and the water at the foundation pit is all defeated by the water pump It send to collecting gutter, ground is tamped.
5. the building lot reinforcement means according to claim 1 suitable for soft clay area, which is characterized in that the erection Jack refers to places large-scale jack in the foundation pit, and the top and bottom of the jack are respectively connected with steel plate, adjust The height of the jack connects the steel plate and building bottom surface, wherein the diameter of the steel plate is 1.5m, thickness For 15mm.
6. the building lot reinforcement means according to claim 1 suitable for soft clay area, which is characterized in that described to perform Pile foundation refers to the steel pipe inside the setting of the lower section of building for cavity as pile foundation, and the top of the pile foundation is built with described The bottom surface built connects, and the upper end side of the pile foundation is equipped with reserving hole, from the entrance of the reserving hole to described The inside concrete perfusion of steel pipe, when concreting is completed and reaches intensity requirement, concrete filled steel tube bored concrete pile foundation is applied It completes, wherein the spacing of adjacent two pile foundations is 2m, the pile foundation is driven underground 1m, refers to the pile foundation Bottom end be located at the lower section of the foundation pit bottom end, and the distance between the bottom end of the pile foundation and the bottom end of the foundation pit are 1m。
7. the building lot reinforcement means according to claim 1 or 4 suitable for soft clay area, which is characterized in that described Iontophoresis device is made of cathode, anode and power supply, is arranged using annular electrode, and the annular electrode arrangement refers to the cathode position In middle position, the anode around the cathode arrange, wherein the cathode between the anode at a distance from be 1.5m, institute The height for stating cathode and the anode is 1m, and equal buried depth 1m refers to that the bottom end of the cathode and the anode is located at the base The lower section of bottom end is cheated, and the bottom end of the cathode and the anode and the distance between the bottom end of the foundation pit are 1m.
8. the building lot reinforcement means according to claim 7 suitable for soft clay area, which is characterized in that the anode At least provided with 4.
CN201910749811.4A 2019-08-14 2019-08-14 A kind of building lot reinforcement means suitable for soft clay area Pending CN110397018A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910749811.4A CN110397018A (en) 2019-08-14 2019-08-14 A kind of building lot reinforcement means suitable for soft clay area

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910749811.4A CN110397018A (en) 2019-08-14 2019-08-14 A kind of building lot reinforcement means suitable for soft clay area

Publications (1)

Publication Number Publication Date
CN110397018A true CN110397018A (en) 2019-11-01

Family

ID=68328277

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910749811.4A Pending CN110397018A (en) 2019-08-14 2019-08-14 A kind of building lot reinforcement means suitable for soft clay area

Country Status (1)

Country Link
CN (1) CN110397018A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112523253A (en) * 2020-11-23 2021-03-19 中建桥梁有限公司 Construction method of reusable retaining wall
CN117646571A (en) * 2024-01-29 2024-03-05 内蒙古工业大学 Historical building restoration device and traditional village restoration method

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08302723A (en) * 1995-04-28 1996-11-19 Kajima Corp Construction method of uneven settlement correcting
CN105714762A (en) * 2016-02-01 2016-06-29 浙江大学 Change-filling and tamping improved soft clay electroosmosis strengthening method
CN107700521A (en) * 2017-10-27 2018-02-16 西安建筑科技大学 One kind is built(Structure)Build thing foundation stabilization and underpin pier and its construction method
CN108798065A (en) * 2018-06-20 2018-11-13 桐乡市乌镇内利仿古园林建设有限公司 A kind of integral jacking method of heritage buildings

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08302723A (en) * 1995-04-28 1996-11-19 Kajima Corp Construction method of uneven settlement correcting
CN105714762A (en) * 2016-02-01 2016-06-29 浙江大学 Change-filling and tamping improved soft clay electroosmosis strengthening method
CN107700521A (en) * 2017-10-27 2018-02-16 西安建筑科技大学 One kind is built(Structure)Build thing foundation stabilization and underpin pier and its construction method
CN108798065A (en) * 2018-06-20 2018-11-13 桐乡市乌镇内利仿古园林建设有限公司 A kind of integral jacking method of heritage buildings

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112523253A (en) * 2020-11-23 2021-03-19 中建桥梁有限公司 Construction method of reusable retaining wall
CN117646571A (en) * 2024-01-29 2024-03-05 内蒙古工业大学 Historical building restoration device and traditional village restoration method
CN117646571B (en) * 2024-01-29 2024-05-28 内蒙古工业大学 Historical building restoration device and traditional village restoration method

Similar Documents

Publication Publication Date Title
CN105804119A (en) Underground corridor structure with dual-purpose pile foundations and construction method of underground corridor structure
CN109024662A (en) Method of the anchor pile underpinning without basement building underground space increasing layer
CN110397018A (en) A kind of building lot reinforcement means suitable for soft clay area
CN109989392A (en) Sand construction of diaphragm wall grooving technology
CN207003421U (en) A kind of steel plate pilework for being seated hard rock top surface
CN105780766A (en) Drilling backfill end bearing pile foundation and construction method thereof
CN216713040U (en) Full-prefabricated pier type portal inclined support pile structure system
CN109056870A (en) A kind of rammed earth trench machine equipment built for house
CN110565686A (en) Construction method for penetrating river channel under pipe gallery
CN212612520U (en) Combined type inclined pile anchor rod foundation pit supporting system
CN112942377A (en) Novel support shear-resistant structure and construction method thereof
CN111794258A (en) Foundation pit dewatering system
CN203684215U (en) Carbon fiber cloth bag type cast-in-situ anti-arch curved surface combined special-shaped pile
CN110144894A (en) A kind of pile end grouting miniature steel pipe static pressed pile
CN215441921U (en) Novel support shear structure
CN111894036B (en) Construction method for additionally arranging basement on strip-shaped foundation building
CN110206053A (en) The construction method of building pile foundation
CN213233538U (en) Elevator pit steel structure
CN212656252U (en) Novel transmission line tower foundation
CN210827425U (en) Retaining wall type underground continuous wall structure
CN211172006U (en) Front-mounted pile throwing support supporting structure
CN218437153U (en) Pre-reinforcing device for spray anchor steel arch frame foundation
CN216839492U (en) High fill foundation structure
CN210562288U (en) Trapezoidal pipe gallery system that combines with major structure is strutted in slope
CN217501674U (en) Tunnel section level spouts stake soon in advance to consolidate with direction bearing structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20191101

RJ01 Rejection of invention patent application after publication