Pre-reinforcing device for spray anchor steel arch frame foundation Download PDF

Info

Publication number
CN218437153U
CN218437153U CN202221871214.2U CN202221871214U CN218437153U CN 218437153 U CN218437153 U CN 218437153U CN 202221871214 U CN202221871214 U CN 202221871214U CN 218437153 U CN218437153 U CN 218437153U
Authority
CN
China
Prior art keywords
foundation
tunnel
steel arch
bow member
concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202221871214.2U
Other languages
Chinese (zh)
Inventor
王庆凯
杨斌
高庆国
刘丹
宋乐然
段丽知
李兴花
孙少杰
张洪武
朱攀登
徐红中
张敏敏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Huaihe Engineering Group Co ltd
Original Assignee
Huaihe Engineering Group Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Huaihe Engineering Group Co ltd filed Critical Huaihe Engineering Group Co ltd
Priority to CN202221871214.2U priority Critical patent/CN218437153U/en
Application granted granted Critical
Publication of CN218437153U publication Critical patent/CN218437153U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/20Hydro energy

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

The utility model provides a spout anchor steel bow member basis pre-reinforcing apparatus, including the tunnel basal plane and the tunnel face that is located tunnel basal plane top, still including setting up the upper portion steel bow member that is used for promoting the holding power and prevents both sides infiltration on the tunnel basal plane and spout the concrete, upper portion steel bow member and spout the concrete and be arch hollow structure, the arch is inside to be tunnel face, upper portion steel bow member and spout concrete bottom welding basis pre-reinforcement material, in the basis pre-reinforcement material squeezes into the tunnel basal plane, the utility model discloses squeeze into upper portion steel bow member and spout the concrete in tunnel basal plane pipe canopy department, can consolidate the tunnel top surface effectively and prevent both sides infiltration, upper portion steel bow member and spout the concrete bottom surface and seal by the closed steel bow member in basis lower part, improved bearing capacity, can effectively prevent the infiltration of tunnel bottom simultaneously, upper portion steel bow member and spout concrete bottom welding basis pre-reinforcement material, promoted bearing capacity and reinforcing performance.

Description

Shotcrete anchor steel bow member basis pre-reinforcing apparatus
Technical Field
The invention belongs to the field of underground building construction excavation, and particularly relates to a device for pre-reinforcing a spray anchor steel arch frame foundation.
Background
In the tunnel construction and excavation, the construction method of the shotcrete steel arch is commonly used, but if the upper structure is a broken rock stratum and the foundation is a sandy or other weak base layer and has high water content, such as an ancient river bed foundation; after the construction of the spray anchor steel arch frame is completed at the upper part, the excavation of the foundation construction of the lower steel arch frame cannot be safely carried out, and the steel arch frame cannot be closed. Therefore, it is necessary to design an efficient and safe excavation method for pre-reinforcing the shotcrete steel arch foundation in the excavation process of the tunnel.
SUMMERY OF THE UTILITY MODEL
For overcoming not enough among the background art, the utility model provides a shotcrete steel bow member basis pre-reinforcing apparatus, can be high-efficient, safe carry out type tunnel excavation.
In order to achieve the purpose, the utility model adopts the following technical scheme:
the utility model provides a spout anchor steel bow member basis pre-reinforcing apparatus, includes the tunnel basal surface and is located the tunnel face of tunnel basal surface top, still including erectting the upper portion steel bow member that is used for promoting the holding power and prevents both sides infiltration on the tunnel basal surface and spout the concrete, upper portion steel bow member and spout the concrete and be arch hollow structure, the arch is inside to be tunnel face, upper portion steel bow member and spout the concrete bottom and welding the basis and in advance the reinforcement material, the basis is in advance the reinforcement material squeezes into in the tunnel basal surface.
Preferably, the upper steel arch and the bottom of the concrete spraying are welded with a foundation lower closed steel arch, the foundation lower closed steel arch closes the upper steel arch and the bottom of the concrete spraying, and the foundation lower closed steel arch is buried under the foundation surface of the tunnel.
Preferably, the upper steel arch frame and the outer surface of the concrete spraying are uniformly distributed with more than one group of pipe sheds, and the pipe sheds are tightly matched with the upper steel arch frame and the outer surface of the concrete spraying.
Preferably, the foundation pre-reinforcing materials are high-strength steel plate materials, the number of the foundation pre-reinforcing materials is two, the two groups of the foundation pre-reinforcing materials are respectively welded on the two sides of the upper steel arch frame and the two sides of the bottom of the sprayed concrete, and the two groups of the foundation pre-reinforcing materials are parallel to each other.
The invention has the beneficial effects that: the upper portion steel bow member is squeezed into and the concrete is spouted in tunnel base face pipe canopy department, can consolidate the tunnel top surface effectively and prevent both sides infiltration, upper portion steel bow member and spout the concrete bottom surface and seal by basic lower part closed steel bow member, bearing capacity is improved, can prevent effectively simultaneously that the tunnel bottom from seeping water, upper portion steel bow member and spout concrete bottom welding basic pre-reinforcement material, bearing capacity and reinforcement performance have been promoted, basic pre-reinforcement material and basic lower part closed steel bow member are buried underground under the tunnel basal plane, make this device itself more firm.
Drawings
FIG. 1 is a schematic cross-sectional view B-B of a pre-reinforced cross section of a shotcrete steel arch foundation excavated in a cavern;
FIG. 2 isbase:Sub>A schematic sectional view of the pre-reinforced longitudinal section A-A of the excavation spray anchor steel arch foundation of the cavity of the invention;
in the figure: 1. the upper steel arch frame and the concrete spraying 2, the pipe shed 3, the tunnel foundation surface 4, the foundation lower closed steel arch frame 5, the foundation pre-reinforcing material 6 and the tunnel face.
Detailed Description
In order to make the technical solutions of the present invention better understood by those skilled in the art, the present invention will be described in detail with reference to the accompanying drawings and specific embodiments.
Example 1: as shown in figures 1 and 2, the pre-reinforcing device for the spray anchor steel arch foundation comprises an upper steel arch, spray concrete 1, a lower closed steel arch and a pre-reinforcing material, wherein the pre-reinforcing material is cast by high-strength steel. The utility model discloses a from up spiral lift excavation technology method down sets up central steel box culvert as swift current sediment passageway, adopts from last conventional excavation method to the excavation of accomplishing the vertical cavity in big tunnel footpath down to the cavity top after spiral excavation to the cavity top. The method comprises the following steps of (1) using a spray anchor steel arch frame for construction in soft geological cavern excavation, firstly designing the models and the densities of a pipe shed and the steel arch frame according to field geological conditions, namely after the construction of the pipe shed is completed, carrying out steel arch frame support, namely supporting one section, excavating one section, and carrying out lower part step; and gradually extending the steel arch frame to the foundation direction along with excavation of two sides. However, if the foundation is excavated downwards and the water content of the foundation is gradually increased when the foundation is in a weak layer, the simple excavation and supporting cannot be safely carried out, the extending engineering and the closing of the steel arch can not be completed, and the construction of the tunnel foundation engineering can not be completed. At the moment, steel sheet piles can be inserted into two sides of a foundation surface which cannot be safely constructed, namely the lower part of a steel arch frame in advance according to the field condition to pre-reinforce the two sides, and the insertion depth of the steel sheet piles exceeds the outer side line of the tunnel design excavation by more than 1 meter; so at first can provide the holding power through being connected of steel sheet pile and upper portion steel bow member, moreover can prevent both sides infiltration entering excavation basis, provide tunnel foundation excavation dry land construction environment.
As shown in fig. 1, the tunnel excavation is performed by firstly performing a first supporting project for a tunnel foundation surface 3 according to a conventional shotcrete steel arch method, then performing construction of a foundation and a reinforcing material 5, i.e., steel sheet piles, performing foundation excavation between the steel sheet piles after the construction of the steel sheet piles is completed, further completing (4) a foundation lower part closed steel arch project, and finally completing a supporting project for a tunnel upper part steel arch and shotcrete 1.
As shown in figure 2, the tunnel excavation is gradually completed with the upper anchor-spraying steel arch and the concrete-spraying 1 work according to a step method in stages, after the excavation surface reaches the foundation surface, the construction of steel sheet piles is carried out on the two sides of the foundation, the steel sheet pile project is divided into three sections in a circulating and reciprocating way, in order to ensure the safe construction, the three sections are in a state of 5-1 completion of foundation steel arch closing and permanent foundation supporting project, 5-2 completion of foundation excavation and foundation steel arch closing construction, and 5-3 completion of steel sheet pile construction. The core of the foundation circular excavation is the closing construction process of the 5-2 foundation steel arch, in order to ensure the safe construction of the 5-2 steel arch, the 5-1 steel arch needs to be finished to ensure the safety of the upper steel arch, and a foundation seepage path is increased to prevent seepage water from entering a foundation pit of the 5-2 steel arch; meanwhile, in order to ensure the safety of personnel and equipment of the 5-2 steel arch and a safe passage, namely, the permanent supporting construction of the 5-1 steel arch and the part of the 5-2 steel arch needs to be completed before the foundation of the 5-2 steel arch is closed.
Finally, it should be noted that: although the present invention has been described in detail with reference to the foregoing embodiments, it will be apparent to those skilled in the art that modifications and variations can be made in the embodiments or in part of the technical features of the embodiments without departing from the spirit and the scope of the invention.

Claims (4)

1. The utility model provides a shotcrete steel bow member basis pre-reinforcing apparatus, includes tunnel foundation face (3) and tunnel face (6) that are located tunnel foundation face (3) top, its characterized in that: still including erectting the upper portion steel bow member that is used for promoting the holding power and prevents both sides infiltration on tunnel foundation face (3) and spouting concrete (1), upper portion steel bow member and spout concrete (1) be arch hollow structure, the arch is inside to be tunnel face (6), upper portion steel bow member and spout concrete (1) bottom welding basis pre-reinforcement material (5), the basis is in the tunnel foundation face (3) of squeezing into in pre-reinforcement material (5).
2. The device for pre-reinforcing the foundation of the shotcrete steel arch frame according to claim 1, wherein: the bottom of the upper steel arch frame and the bottom of the concrete spraying frame (1) are welded with a foundation lower closed steel arch frame (4), the foundation lower closed steel arch frame (4) closes the bottom of the upper steel arch frame and the bottom of the concrete spraying frame (1), and the foundation lower closed steel arch frame (4) is buried under a tunnel foundation surface (3).
3. The device for pre-reinforcing the foundation of the shotcrete steel arch according to claim 1 or 2, wherein: the outer surfaces of the upper steel arch frame and the concrete spraying frame (1) are uniformly distributed with pipe sheds (2), the number of the pipe sheds (2) is more than one, and the pipe sheds (2) are tightly matched with the outer surfaces of the upper steel arch frame and the concrete spraying frame (1).
4. The device for pre-reinforcing the foundation of the shotcrete steel arch according to claim 1, wherein: the foundation pre-reinforcing materials (5) are made of high-strength steel plates, the two groups of foundation pre-reinforcing materials (5) are respectively welded on two sides of the bottom of the upper steel arch frame and the sprayed concrete (1), and the two groups of foundation pre-reinforcing materials (5) are parallel to each other.
CN202221871214.2U 2022-07-20 2022-07-20 Pre-reinforcing device for spray anchor steel arch frame foundation Expired - Fee Related CN218437153U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202221871214.2U CN218437153U (en) 2022-07-20 2022-07-20 Pre-reinforcing device for spray anchor steel arch frame foundation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202221871214.2U CN218437153U (en) 2022-07-20 2022-07-20 Pre-reinforcing device for spray anchor steel arch frame foundation

Publications (1)

Publication Number Publication Date
CN218437153U true CN218437153U (en) 2023-02-03

Family

ID=85091492

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202221871214.2U Expired - Fee Related CN218437153U (en) 2022-07-20 2022-07-20 Pre-reinforcing device for spray anchor steel arch frame foundation

Country Status (1)

Country Link
CN (1) CN218437153U (en)

Similar Documents

Publication Publication Date Title
CN110017144B (en) Loess tunnel three-step construction method considering substrate reinforcement treatment
CN105756091B (en) A kind of Metro station excavation construction method of control adjacent building composition deformation
CN108589771B (en) Construction method for layer-adding transfer node of operated underground station
CN105697021B (en) The prefabricated tunnel and construction method in the shallow earthing riverbed of shield crossing
CN109610473A (en) A kind of construction method of the large-scale pool structure foundation pit supporting system of municipal administration
CN111236259A (en) Combined lattice-shaped prefabricated pile wall supporting structure and construction method thereof
CN111779022A (en) Novel structure of underground comprehensive pipe gallery in anti-settling and anti-inclining soft soil foundation and construction method thereof
CN110565686A (en) Construction method for penetrating river channel under pipe gallery
CN109898556A (en) A kind of underground pipe gallery structure and sunk type construction method
CN111255462B (en) Pipe curtain cover excavation top-down construction method for subway station construction
CN218437153U (en) Pre-reinforcing device for spray anchor steel arch frame foundation
CN208815566U (en) The transverse direction that open cut or lid dig underground main structure below existing building digs construction
CN111636483A (en) Waterproof device for reverse construction concrete structure gap and construction method
CN110565666A (en) Construction method of flat combined sheet pile ground connecting wall type water retaining cofferdam
CN111894036B (en) Construction method for additionally arranging basement on strip-shaped foundation building
CN210887256U (en) Straight combined sheet pile-ground wall-connecting type frame of water retaining cofferdam
CN210122735U (en) Underground structure anti-floating system based on outward-protruding wing foot plate
CN115198806A (en) Underground wall post-cast strip template reinforcing and installing construction method
CN109653193B (en) Reverse construction method for underground continuous wall
CN209722944U (en) Karst hole plugging structure that falls into water
CN110318419B (en) Construction method of one-lining door opening support of underpass type pipe gallery
CN112627231A (en) Construction device for deep guide wall of soft soil
CN215289967U (en) Structure for diversion flood control of pre-buried culvert of dam foundation of flexible dam
CN221568492U (en) A stable structure for super shallow shield tunnel passes through water
CN205399504U (en) Open section tunnel structure's anti structure of floating

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20230203