Nothing Special   »   [go: up one dir, main page]

CN110344394A - A kind of surrounding deep foundation pit shallow embedding structure base ruggedized construction and construction method - Google Patents

A kind of surrounding deep foundation pit shallow embedding structure base ruggedized construction and construction method Download PDF

Info

Publication number
CN110344394A
CN110344394A CN201910547691.XA CN201910547691A CN110344394A CN 110344394 A CN110344394 A CN 110344394A CN 201910547691 A CN201910547691 A CN 201910547691A CN 110344394 A CN110344394 A CN 110344394A
Authority
CN
China
Prior art keywords
slip casting
steel plate
steel pipe
foundation pit
plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910547691.XA
Other languages
Chinese (zh)
Inventor
宗朝阳
韩毓殷
周小亮
陈鹏
潘传宇
雷波
周旋
李淋淋
周坤
黄兴昌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China State Railway Investment Construction Group Co Ltd
Original Assignee
China State Railway Investment Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China State Railway Investment Construction Group Co Ltd filed Critical China State Railway Investment Construction Group Co Ltd
Priority to CN201910547691.XA priority Critical patent/CN110344394A/en
Publication of CN110344394A publication Critical patent/CN110344394A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00Improving or preserving soil or rock, e.g. preserving permafrost soil
    • E02D3/12Consolidating by placing solidifying or pore-filling substances in the soil
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D37/00Repair of damaged foundations or foundation structures

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Agronomy & Crop Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Soil Sciences (AREA)
  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

The invention discloses a kind of surrounding deep foundation pit shallow embedding structure base ruggedized construction and construction methods, including antidumping plate, slip casting steel pipe, fixation steel plate, the antidumping plate by framework of steel reinforcement and pour coagulation local soil type in existing basic surrounding at, slip casting steel pipe links together after being fixed along existing basic surrounding quincuncial arrangement and by fixation steel plate with antidumping slab tendons skeleton, its construction procedure is that preparation of construction → injected hole is drilled with → mud jacking → excavation of foundation pit → tie with reinforcing bar and fixation steel plate welding → concreting and maintenance, by setting slip casting steel pipe grouting and reinforcing ground in existing basic surrounding, then slip casting steel pipe is fixed in antidumping plate main reinforcement by strengthening steel slab, finally pour antidumping board concrete, form one " pile framing ", can the effective solution existing based process time it is long, consolidation effect is unknown The problems such as aobvious, ensure that and expand existing foundation bearing capacity and its stability, while having the characteristics that speed of application is fast, good in economic efficiency.

Description

A kind of surrounding deep foundation pit shallow embedding structure base ruggedized construction and construction method
Technical field
The invention belongs to architectural engineering ground base enforcement technical field of construction, and in particular to a kind of surrounding deep foundation pit shallow embedding Structure base ruggedized construction is mainly used in the reinforcing of surrounding deep foundation pit shallow embedding structure base, guarantees existing shallow embedding structures Safety, also relates to the construction method of surrounding deep foundation pit shallow embedding structure base ruggedized construction.
Background technique
With the development of urbanization, engineering construction place surrounding enviroment become increasingly complex, can not in Deep Excavation The meeting avoided generates disturbance to existing stratum, so as to cause foundation pit deformation and the land movement of foundation pit periphery, pacifies to surrounding building It impacts entirely, especially the important structure building in foundation pit periphery, it is extremely harsh to ground stability requirement, such as take no action to It is reinforced, once it is more than allowed band that foundation pit deformation, which occurs, during foundation pit construction, easily structures is caused to sink It drops or topples, cause extremely severe social influence and irremediable economic loss.
It for the structures of surrounding deep foundation pit, generally takes to move and changes or grouting and reinforcing reduces construction risk: being changed using moving When mode, need to be reported to the higher authorities at different levels for approval, existing buildings remove, new construction of structures construction etc. programs, process is longer and uncontrollable, work Phase risk of time delay is larger;When using grouting and reinforcing mode, the structures periphery soil body can only be reinforced, it can not be to structures base The soil body is effectively reinforced below plinth, and consolidation effect is unobvious.It therefore, is reduction surrounding deep foundation pit structures in digging process Security risk, to cut feasible surrounding deep foundation pit structures shallow foundation reinforcement technique particularly important for research and grasp.
Summary of the invention
The first purpose of this invention be to provide a kind of structure it is simple, it is easy for construction, to existing shallow foundation structures shadow Ring small, the good surrounding deep foundation pit shallow embedding structure base ruggedized construction of consolidation effect.
The first purpose of this invention is realized by technical measures below: a kind of surrounding deep foundation pit shallow embedding structures base Plinth ruggedized construction, it is described including fixation steel plate, slip casting steel pipe and the antidumping plate set gradually outward along existing basic outer Antidumping plate includes framework of steel reinforcement and pours in the concrete of existing basic surrounding, the fixation steel plate be square be set to it is existing Fundamental external is simultaneously located in the concrete poured, and the fixation steel plate is equipped with according to slip casting steel pipe position reserving hole, The slip casting steel pipe is circumferentially disposed along existing basic surrounding, and arrangement quantity is no less than 2 rings, and adjacent 2 ring slip casting steel pipe is in quincunx Interlaced arrangement, same ring slip casting steel pipe tail end pass through fixation steel plate reserving hole and are welded and fixed together with fixation steel plate.
As an improvement, the framework of steel reinforcement is double layer bar, the framework of steel reinforcement and existing basis use the side of bar planting Formula is attached.
As an improvement, the conehead that slip casting steel pipe front end is equipped with, tail end is equipped with only slurry section, between middle section is equipped with equidistantly Every the extravasating hole of setting.
As an improvement, the degree of the conehead is not less than 10cm, the length of the only slurry section is not less than 1.5m, the extravasating hole Spacing be 15cm, the extravasating hole is in quincuncial arrangement and aperture is 10~16mm.
As an improvement, slip casting steel pipe is connected into an entirety by the fixation steel plate, and it is welded and fixed securely with framework of steel reinforcement, The fixation steel plate includes first layer fixation steel plate, second layer fixation steel plate, the fixed steel of the first layer fixation steel plate, the second layer Plate is located at the over and under of framework of steel reinforcement.
As an improvement, the fixation steel plate is made by 1cm steel plate, the fixation steel plate width is slip casting diameter of steel tube 3 times.
As an improvement, the fixation steel plate along it is existing basis outward setting there are two.
As an improvement, its construction method, feature comprise the steps of:
Step 1: preparation of construction
Field investigation is organized, it is comprehensive to the existing basal perimeter line conditions progress of quasi- reinforcing to sound out the people in a given scope one by one in order to break a criminal case, verify underground utilities Position;Carry out levelling of the land and people, machine, material preparation.
Step 2: injected hole is drilled with
Strengthening of foundation range is 3~5 times of existing foundation widths, injected hole along the existing basic double quincuncial arrangement of surrounding, Pitch-row 1.3m × 1.3m, interior row's injected hole are not less than 1m away from existing basis outside spacing;Slip casting bore dia is than slip casting diameter of steel tube Big 5~10mm, hole depth is according to 10m and enters rock stratum not less than 2m dual control, and slip casting steel pipe top absolute altitude and the structures reinforced were both There is basic top surface absolute altitude identical, error must not exceed ± 50mm to injected hole hole location in length and breadth, and verticality allowable error is not to be exceeded 3 ‰, sediment thickness is not more than 50mm after borehole cleaning.
Step 3: mud jacking
1 slip casting of slip casting steel pipe uses M30 cement grout, and the ratio of mud is generally 0.5~1 (being determined by grouting test), And appropriate retarder is mixed, cement uses P.O.42.5 ordinary portland cement, and mixing water uses drinking water;Using mudjack into Row mud jacking uses underflow sealing of hole at the end of mud jacking, and controlled grouting pressure is in 0.2~0.5MPa or so.
Step 4: excavation of foundation pit
The existing basal perimeter earthwork of the structures that need to be reinforced is excavated using excavator, excavates gradient 1:1.5, is excavated 0.5~1.0m of depth, nearby the 10cm soil body uses people using artificial clear bottom to excavation of foundation pit line 301 within the scope of the 50cm of basis Work is excavated, and when excavation should be noted the protection reinforced to slip casting steel pipe, is avoided slip casting steel pipe and is fractureed, is damaged.
Step 5: tie with reinforcing bar and fixation steel plate welding
To structures existing surface of base chisel face gently hammer into shape, dabbing, and clean out existing surface of base discrete particles and Dross dust sets bar planting hole according to the position of framework of steel reinforcement on the basis of existing;First layer fixation steel plate is penetrated into slip casting steel It manages and is welded and fixed, start tie with reinforcing bar, second layer fixation steel plate is penetrated after the completion of tie with reinforcing bar, will and will fix Steel plate carries out two-sided be fully welded with framework of steel reinforcement contact site and connect.
Step 6: concreting and maintenance
Template installation is carried out and on existing basis in antidumping plate contact position brushing interfacial agents according to antidumping board size It is handled, then carries out antidumping board concrete and pour;After concreting, watering should be covered in 12h under normal temperature conditions Maintenance, for irrigation times to keep concrete is wet to be advisable, curing time is no less than sennight.
Compared with prior art, the present invention has the advantage that
(1) by the existing ground of slip casting steel pipe grouting and reinforcing, while slip casting steel pipe and antidumping plate have been integrally formed one " pile framing ", is effectively increased the bearing capacity and stability on existing basis, and consolidation effect is good.
(2) construction technology of the present invention is simpler, and avoidable existing buildings, which move, changes brought relevant issues, speed of application Fastly, high-efficient.
(3) present invention carries out original place reinforcing to foundation pit periphery structure base, and the resources such as machinery, the material of investment are less, Compared with structures move and change, without removing and creating, operating expenses is reduced obviously, and economic benefit is good.
Detailed description of the invention
Fig. 1 is that the slip casting steel pipe of a kind of surrounding deep foundation pit shallow embedding structure base ruggedized construction and construction method of the invention shows It is intended to.
Fig. 2 is that the slip casting steel pipe of a kind of surrounding deep foundation pit shallow embedding structure base ruggedized construction and construction method of the invention is flat Face arrangement schematic diagram.
Fig. 3 is that the excavation of foundation pit of a kind of surrounding deep foundation pit shallow embedding structure base ruggedized construction and construction method of the invention cuts open Face schematic diagram.
Fig. 4 be a kind of surrounding deep foundation pit shallow embedding structure base ruggedized construction of the present invention and construction method framework of steel reinforcement with Fixation steel plate connects floor map.
Fig. 5 be a kind of surrounding deep foundation pit shallow embedding structure base ruggedized construction of the present invention and construction method framework of steel reinforcement with Fixation steel plate connects diagrammatic cross-section.
Fig. 6 is that the reinforcing of a kind of surrounding deep foundation pit shallow embedding structure base ruggedized construction and construction method of the invention is integrally cutd open Face schematic diagram.
Appended drawing reference: 1, slip casting steel pipe, 101, conehead, 102, only slurry section, 103, extravasating hole, 2, fixation steel plate, 201, the One layer of fixation steel plate, 202, second layer fixation steel plate, 3, antidumping plate, 301, excavation of foundation pit line, 302, framework of steel reinforcement, 4, existing Basis.
Specific embodiment
For a better understanding of the technical solution of the present invention, below with reference to embodiment attached drawing to the present invention further specifically It is bright.It should be appreciated that described herein, specific examples are only used to explain the present invention, is not intended to limit the present invention.
A kind of surrounding deep foundation pit shallow embedding structure base ruggedized construction, it is characterised in that: including along existing basic 4 outer to Fixation steel plate 2, slip casting steel pipe 1 and the antidumping plate 3 set gradually outside, the antidumping plate 3 include framework of steel reinforcement 302 and pour It builds in the concrete of existing basic 4 surrounding, the fixation steel plate 2 is square to be set to existing basic 4 outside and be located at and pour In concrete, the fixation steel plate 2 is equipped with according to 1 position reserving hole of slip casting steel pipe, and the slip casting steel pipe (1) was along both There is basic (4) surrounding circumferentially disposed, arrangement quantity is no less than 2 rings, and adjacent 2 ring slip casting steel pipe (1) is in quincunx interlaced arrangement, together One ring slip casting steel pipe (1) tail end passes through fixation steel plate (2) reserving hole and is welded and fixed together with fixation steel plate (2).
As the present embodiment better embodiment, the framework of steel reinforcement 302 is double layer bar, the framework of steel reinforcement 302 are attached by the way of bar planting with existing basic 4.
As the present embodiment better embodiment, the conehead 101 that 1 front end of slip casting steel pipe is equipped with, tail end is equipped with Section 102 is only starched, middle section is equipped with the extravasating hole 103 of equidistant interval setting.
As the present embodiment better embodiment, the degree of the conehead 101 is not less than 10cm, the only slurry section 102 Length be not less than 1.5m, the spacing of the extravasating hole 103 is 15cm, and the extravasating hole 103 is in quincuncial arrangement and aperture 10~16mm.
As the present embodiment better embodiment, the fixation steel plate 2 slip casting steel pipe 1 is connected it is integral, and It is welded and fixed securely with framework of steel reinforcement 302, the fixation steel plate 2 includes first layer fixation steel plate 201, second layer fixation steel plate 202, the first layer fixation steel plate 201, second layer fixation steel plate 202 are located at the over and under of framework of steel reinforcement 302.
As the present embodiment better embodiment, the fixation steel plate 2 is made by 1cm steel plate, the fixation 2 width of steel plate is about 3 times of 1 diameter of slip casting steel pipe.
A kind of surrounding deep foundation pit shallow embedding structure base ruggedized construction construction method, feature comprise the steps of:
Step 1: preparation of construction
Field investigation is organized, it is comprehensive to the existing basic 4 periphery line conditions progress of quasi- reinforcing to sound out the people in a given scope one by one in order to break a criminal case, verify underground utilities Position;Carry out levelling of the land and people, machine, material preparation.
Step 2: injected hole is drilled with
Strengthening of foundation range is 3~5 times of existing basic 4 width, and injected hole is along the existing basic double quincunx cloth of 4 surrounding It sets, pitch-row 1.3m × 1.3m, interior row's injected hole is not less than 1m away from existing basic 4 outside spacing;Slip casting bore dia is than slip casting steel pipe 1 Big 5~the 10mm of diameter, hole depth is according to 10m and enters rock stratum not less than 2m dual control, and 1 top mark height of slip casting steel pipe is constructed with what is reinforced The existing basic 4 top surface absolute altitude of object is identical, and error must not exceed ± 50mm to injected hole hole location in length and breadth, and verticality allowable error should not surpass 3 ‰ are crossed, sediment thickness is not more than 50mm after borehole cleaning.
Step 3: mud jacking
1 slip casting of slip casting steel pipe uses M30 cement grout, and the ratio of mud is generally 0.5~1 (being determined by grouting test), And appropriate retarder is mixed, cement uses P.O.42.5 ordinary portland cement, and mixing water uses drinking water;Using mudjack into Row mud jacking uses underflow sealing of hole at the end of mud jacking, and controlled grouting pressure is in 0.2~0.5MPa or so.
Step 4: excavation of foundation pit
It is excavated using excavator basic 4 periphery cubic metre of earth existing to the structures that need to be reinforced, excavates gradient 1:1.5, open 0.5~1.0m of depth is dug, nearby the 10cm soil body is used within the scope of the 50cm of basis excavation of foundation pit line 301 using artificial clear bottom Hand excavation, when excavation, should be noted the protection reinforced to slip casting steel pipe 1, avoid slip casting steel pipe 1 and fracture, is damaged.
Step 5: the binding of framework of steel reinforcement 302 and fixation steel plate 2 weld
Basic 4 surface chisel existing to structures face gently hammers into shape, dabbing, and cleans out the discrete particles on existing basic 4 surface And dross dust, bar planting hole is set on existing basic 4 according to the position of framework of steel reinforcement 1;First layer fixation steel plate 201 is penetrated Slip casting steel pipe is simultaneously welded and fixed, and starts framework of steel reinforcement 302 and binds, and the fixed steel of the second layer is penetrated after the completion of the binding of framework of steel reinforcement 302 Fixation steel plate 2 will and be carried out two-sided be fully welded with 302 contact site of framework of steel reinforcement and connect by plate 202.
Step 6: concreting and maintenance
Template installation is carried out and existing basic 4 in 3 contact position brushing interface of antidumping plate according to 3 size of antidumping plate Agent is handled, and 3 concreting of antidumping plate is then carried out;After concreting, it should cover pour in 12h under normal temperature conditions Water curing, for irrigation times to keep concrete is wet to be advisable, curing time is no less than sennight.
The above embodiment of the present invention be only to clearly illustrate example of the present invention, and not be to the present invention The restriction of embodiment can also make on the basis of the above description for those of ordinary skill in the art Other various forms of variations or variation here can not be exhaustive all embodiments, all to belong to skill of the invention The obvious changes or variations that art scheme is extended out are still in the scope of protection of the present invention.

Claims (7)

1. a kind of surrounding deep foundation pit shallow embedding structure base ruggedized construction, it is characterised in that: including along existing basic (4) outer to Fixation steel plate (2), slip casting steel pipe (1) and the antidumping plate (3) set gradually outside, the antidumping plate (3) includes reinforcing bar It frame (302) and pours in the concrete of existing basic (4) surrounding, the fixation steel plate (2), which is square, is set to existing basic (4) Outside is simultaneously located in the concrete poured, and the fixation steel plate (2) is equipped with according to slip casting steel pipe (1) position preformed hole Hole, the slip casting steel pipe (1) is circumferentially disposed along existing basic (4) surrounding, and arrangement quantity is no less than 2 rings, adjacent 2 ring slip casting steel pipe It (1) is in quincunx interlaced arrangement, same ring slip casting steel pipe (1) tail end passes through fixation steel plate (2) reserving hole and fixation steel plate (2) It is welded and fixed together.
2. a kind of surrounding deep foundation pit shallow embedding structure base ruggedized construction according to claim 1, it is characterised in that: described Framework of steel reinforcement (302) is double layer bar, and the framework of steel reinforcement (302) is connected by the way of bar planting with existing basic (4) It connects.
3. a kind of surrounding deep foundation pit shallow embedding structure base ruggedized construction according to claim 1, it is characterised in that: described The conehead (101) that slip casting steel pipe (1) front end is equipped with, tail end are equipped with only slurry section (102), and middle section is equipped with equidistant interval setting Extravasating hole (103).
4. a kind of surrounding deep foundation pit shallow embedding structure base ruggedized construction according to claim 3, it is characterised in that: described The degree of conehead (101) is not less than 10cm, and the length of only slurry section (102) is not less than 1.5m, the spacing of the extravasating hole (103) For 15cm, the extravasating hole (103) is 10~16mm in quincuncial arrangement and aperture.
5. a kind of surrounding deep foundation pit shallow embedding structure base ruggedized construction according to claim 1, it is characterised in that: described Fixation steel plate (2) is integral by slip casting steel pipe (1) connection, and is welded and fixed securely with framework of steel reinforcement (302), the fixed steel Plate (2) includes first layer fixation steel plate (201), second layer fixation steel plate (202), the first layer fixation steel plate (201), second Layer fixation steel plate (202) is located at the over and under of framework of steel reinforcement (302).
6. a kind of surrounding deep foundation pit shallow embedding structure base ruggedized construction according to claim 5, it is characterised in that: described Fixation steel plate (2) is made by 1cm steel plate, and fixation steel plate (2) width is 3 times of 1 diameter of slip casting steel pipe.
7. a kind of construction method of above-mentioned surrounding deep foundation pit shallow embedding structure base ruggedized construction, feature comprise the steps of:
Step 1: preparation of construction
Field investigation is organized, basic (4) periphery line conditions progress existing to quasi- reinforcing is comprehensive to sound out the people in a given scope one by one in order to break a criminal case, and verifies underground utilities position It sets;Carry out levelling of the land and people, machine, material preparation.
Step 2: injected hole is drilled with
Strengthening of foundation range is 3~5 times of existing basic (4) width, and injected hole is along the double quincunx cloth of existing basic (4) surrounding It sets, pitch-row 1.3m × 1.3m, interior row's injected hole is not less than 1m away from spacing on the outside of existing basic (4);Slip casting bore dia is than slip casting steel Manage the big 5~10mm of (1) diameter, hole depth according to 10m and enter rock stratum be not less than 2m dual control, slip casting steel pipe (1) top mark height with it is added Solid existing basic (4) top surface absolute altitude of structures it is identical, error must not exceed ± 50mm to injected hole hole location in length and breadth, and verticality allows Error is not to be exceeded 3 ‰, and sediment thickness is not more than 50mm after borehole cleaning.
Step 3: mud jacking
(1) slip casting of slip casting steel pipe uses M30 cement grout, and the ratio of mud is generally 0.5~1 (being determined by grouting test), and Appropriate retarder is mixed, cement uses P.O.42.5 ordinary portland cement, and mixing water uses drinking water;It is carried out using mudjack Mud jacking uses underflow sealing of hole at the end of mud jacking, and controlled grouting pressure is in 0.2~0.5MPa or so.
Step 4: excavation of foundation pit
It is excavated using excavator basic (4) periphery cubic metre of earth existing to the structures that need to be reinforced, excavates gradient 1:1.5, excavate 0.5~1.0m of depth, nearby the 10cm soil body is used within the scope of the 50cm of basis excavation of foundation pit line (301) using artificial clear bottom Hand excavation, when excavation, should be noted the protection reinforced to slip casting steel pipe 1, avoid slip casting steel pipe 1 and fracture, is damaged.
Step 5: framework of steel reinforcement (302) binding and fixation steel plate (2) welding
It is existing to structures basis (4) surface chisel face gently hammer, dabbing, and clean out it is existing basis (4) surface discrete particles And dross dust, bar planting hole is set on existing basic (4) according to the position of framework of steel reinforcement (1);By first layer fixation steel plate (201) it penetrates slip casting steel pipe and is welded and fixed, start framework of steel reinforcement (302) binding, penetrated after the completion of framework of steel reinforcement (302) binding Fixation steel plate (2) will and be carried out two-sided be fully welded with framework of steel reinforcement (302) contact site and connect by second layer fixation steel plate (202).
Step 6: concreting and maintenance
Template installation is carried out and in existing basic (4) in antidumping plate (3) contact position brushing circle according to antidumping plate (3) size Face agent is handled, and antidumping plate (3) concreting is then carried out;After concreting, it should be covered in 12h under normal temperature conditions Lid water seasoning, for irrigation times to keep concrete is wet to be advisable, curing time is no less than sennight.
CN201910547691.XA 2019-06-24 2019-06-24 A kind of surrounding deep foundation pit shallow embedding structure base ruggedized construction and construction method Pending CN110344394A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910547691.XA CN110344394A (en) 2019-06-24 2019-06-24 A kind of surrounding deep foundation pit shallow embedding structure base ruggedized construction and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910547691.XA CN110344394A (en) 2019-06-24 2019-06-24 A kind of surrounding deep foundation pit shallow embedding structure base ruggedized construction and construction method

Publications (1)

Publication Number Publication Date
CN110344394A true CN110344394A (en) 2019-10-18

Family

ID=68182838

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910547691.XA Pending CN110344394A (en) 2019-06-24 2019-06-24 A kind of surrounding deep foundation pit shallow embedding structure base ruggedized construction and construction method

Country Status (1)

Country Link
CN (1) CN110344394A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110761288A (en) * 2019-10-30 2020-02-07 中国铁建重工集团股份有限公司 Concrete pouring method for deep foundation pit
CN114232598A (en) * 2021-11-23 2022-03-25 广州市市政工程机械施工有限公司 Grouting isolation wall for protecting existing building/structure foundation

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201567574U (en) * 2010-01-07 2010-09-01 贵州省交通规划勘察设计研究院 Prestressed anchorage anchor pier slope reinforcing and fixing structure
CN106499413A (en) * 2016-11-19 2017-03-15 中铁十二局集团有限公司 A kind of Shallow-buried section tunnel stratum consolidation construction method
CN108914927A (en) * 2018-07-30 2018-11-30 中铁二十三局集团有限公司 The miniature steel pipe pile reinforced construction method of existing line base insuring highway' slope
CN109208627A (en) * 2018-09-11 2019-01-15 中建五局土木工程有限公司 Structure and its construction method are protected in high-rise structures strengthening of foundation
CN210827422U (en) * 2019-06-24 2020-06-23 中建铁路投资建设集团有限公司 Peripheral shallow structure foundation reinforced structure that buries of deep basal pit

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201567574U (en) * 2010-01-07 2010-09-01 贵州省交通规划勘察设计研究院 Prestressed anchorage anchor pier slope reinforcing and fixing structure
CN106499413A (en) * 2016-11-19 2017-03-15 中铁十二局集团有限公司 A kind of Shallow-buried section tunnel stratum consolidation construction method
CN108914927A (en) * 2018-07-30 2018-11-30 中铁二十三局集团有限公司 The miniature steel pipe pile reinforced construction method of existing line base insuring highway' slope
CN109208627A (en) * 2018-09-11 2019-01-15 中建五局土木工程有限公司 Structure and its construction method are protected in high-rise structures strengthening of foundation
CN210827422U (en) * 2019-06-24 2020-06-23 中建铁路投资建设集团有限公司 Peripheral shallow structure foundation reinforced structure that buries of deep basal pit

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110761288A (en) * 2019-10-30 2020-02-07 中国铁建重工集团股份有限公司 Concrete pouring method for deep foundation pit
CN110761288B (en) * 2019-10-30 2021-09-10 中国铁建重工集团股份有限公司 Concrete pouring method for deep foundation pit
CN114232598A (en) * 2021-11-23 2022-03-25 广州市市政工程机械施工有限公司 Grouting isolation wall for protecting existing building/structure foundation

Similar Documents

Publication Publication Date Title
WO2021223573A1 (en) Construction structure for communication and connection between newly added mined channel and existing station hall layer
CN106958256B (en) A kind of placement layer by layer, the open caisson construction technique repeatedly sunk
CN107542108B (en) A kind of reverse construction method of building basement structure
CN104612162B (en) A kind of Deep Foundation Pit of Metro Stations excavation construction method
CN110821503B (en) Construction method for main body of ultra-deep shield section air shaft after tunnel advance
CN102518135B (en) Horizontal jet grouting soil anchor and castinplace pile Composite Foundation Pit supporting construction engineering method
CN108442382B (en) In-situ protection and enclosure soil-retaining structure for pressure pipeline crossing deep foundation pit and construction method
CN102061923B (en) Tunnel construction method capable of protecting existing building
CN107447765A (en) Side slope construction supported with framed anchor construction
CN107859145A (en) A kind of drainpipe is plugged into construction method under water
CN105155550A (en) Construction method for digging deep foundation pit in large-thickness highly weathered sandstone stratum in combined supporting mode
CN106150506A (en) A kind of gateway open excavation section inverted side-wall construction method
CN113669073B (en) Construction method for controlling adjacent building deformation of water-rich sandy stratum by tunneling before station
CN110004991A (en) Underground structure anti-floating system and construction method based on raised type tangs plate
CN111455977A (en) Underground continuous wall construction method
CN106065628B (en) Based on the major diameter running water pipe security protection construction method faced forever with reference to theory
CN102235007B (en) Method for supporting deep foundation with upper nail-lower pile combination
CN109610473A (en) A kind of construction method of the large-scale pool structure foundation pit supporting system of municipal administration
CN109706952A (en) Large-scale well-sinking construction method
CN108914945A (en) A kind of deep basal pit pile for prestressed pipe, prestress anchorage cable combined supporting construction method
CN103215958A (en) Construction method of dewatering and retaining and protecting of deep foundation pit in expansive-soil area
CN110344394A (en) A kind of surrounding deep foundation pit shallow embedding structure base ruggedized construction and construction method
CN101994314A (en) Longhole rectangular terraced antiskid pile jump-preventing excavating construction
CN107059904A (en) A kind of underground pipe gallery ponding well excavation method
CN110529120B (en) Construction method for removing invasion limiting structure by chiseling VI-level surrounding rock shallow-buried underground excavation loess tunnel

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination