Nothing Special   »   [go: up one dir, main page]

CN103215958A - Construction method of dewatering and retaining and protecting of deep foundation pit in expansive-soil area - Google Patents

Construction method of dewatering and retaining and protecting of deep foundation pit in expansive-soil area Download PDF

Info

Publication number
CN103215958A
CN103215958A CN2013101399480A CN201310139948A CN103215958A CN 103215958 A CN103215958 A CN 103215958A CN 2013101399480 A CN2013101399480 A CN 2013101399480A CN 201310139948 A CN201310139948 A CN 201310139948A CN 103215958 A CN103215958 A CN 103215958A
Authority
CN
China
Prior art keywords
deep foundation
foundation pit
construction method
construction
soil
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2013101399480A
Other languages
Chinese (zh)
Inventor
熊启东
孙忠国
黄兴红
朱小玲
郭照云
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Seventh Engineering Division Corp Ltd
Original Assignee
China Construction Seventh Engineering Division Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Seventh Engineering Division Corp Ltd filed Critical China Construction Seventh Engineering Division Corp Ltd
Priority to CN2013101399480A priority Critical patent/CN103215958A/en
Publication of CN103215958A publication Critical patent/CN103215958A/en
Pending legal-status Critical Current

Links

Landscapes

  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

The invention discloses a construction method of dewatering and retaining and protecting of a deep foundation pit in an expansive-soil area. The construction method includes a first step of constructing densely-distributed bored concrete piles on the upstream face of the deep foundation pit; a second step of conducting shotcrete and protection on soil among the piles in the process of earth excavation; a third step of constructing anchor rods among the piles; a fourth step of conducting inner tube well dewatering construction on the foundation pit; a fifth step of constructing soil nailing walls on the downstream face of the foundation pit; and a sixth step of constructing a water-retaining cofferdam on the periphery of the foundation pit. The construction method of the dewatering and the retaining and protecting of the deep foundation pit in the expansive-soil area has the advantages that densely-distributed bored concrete piles are applied to the upstream face of the deep foundation pit, a combined bolting and shotcrete structure is applied to the earth among the piles, and a soil nailing wall combined bolting and shotcrete method is applied to the downstream face, so that potential safety hazards caused by slop instability of expansive soil can be effectively avoided. The construction method of the dewatering and the retaining and protecting of the deep foundation pit in the expansive-soil area further has the advantages of effectively saving resources and being economical and applicable due to the fact that the retaining and protecting in section is conducted according to the actual situation. In addition, the construction method of the dewatering and the retaining and protecting of the deep foundation pit in the expansive-soil area further has the advantages of effectively lowering the underground water level and being beneficial to foundation construction due to the fact that the foundation dip inner tube well dewatering construction is combined.

Description

Swelled ground area deep foundation pit precipitation and construction method for supporting
Technical field
The present invention relates to a kind of swelled ground area deep foundation ditch building operations precipitation method, especially a kind of swelled ground area deep foundation pit precipitation and construction method for supporting.
Background technology
Development along with the modern city construction; building density is strengthening day by day; the building operations space is subjected to restriction to a certain degree; normal operation in order to ensure construction project; and protection adjacent building; structure; the safe handling of underground utilities etc.; often needing that base pit engineering is carried out foundation ditch handles and supporting; in the expansive soil distributed area; when the excavation of foundation pit degree of depth surpasses the buried depth of expansive soil; the expansive soil rainwater expands; the characteristic that dehydration is shunk will constitute the most direct threat to the stability of excavation slope; cause the example of side slope unstability of common occurrence thus; expansive soil undisturbed soil can be also different with soil permeability after disturbance is reinvented; the height of the water content of expansive soil is in soil body penetration; stress; strain stress relation and shear strength have close and complicated relation, so expansive soil area deep foundation pit precipitation and pattern foundation pit supporting structure are one technical barrier to be solved is arranged.
Summary of the invention
The technical problem to be solved in the present invention provides a kind of swelled ground area deep foundation pit precipitation and construction method for supporting, can effectively prevent the potential safety hazard that causes because of the expansive soil unstability in the swelled ground area deep foundation ditch operation process, guarantees that construction normally carries out.
For solving the problems of the technologies described above, the technical solution used in the present invention is: a kind of swelled ground area deep foundation pit precipitation and construction method for supporting may further comprise the steps:
The first step: the deep foundation ditch upstream face concrete spouting pile driving construction that gathers;
Second step: in the soil excavation process, carry out the inter-pile soil spray and protect;
The 3rd step: anchor bolt construction between stake;
The 4th step: tube well dewatering construction in the deep foundation ditch;
The 5th step: deep foundation ditch back side construction of soil-nailed wall;
The 6th step: water-retaining cofferdam construction around the deep foundation ditch;
The described first step comprise bury that casing, slurrying, rig are in place underground, pore-forming, reinforcing cage fabrication and installation and concrete spouting.
The sand factor of mud is smaller or equal to 8% in the described pore-forming metapore, and mud viscosity is smaller or equal to 28S, and mud balance is less than 1.25.
The slump of described perfusion is 180-220mm, and water/binder ratio is 0.5-0.55.
Described second step comprises deep pit digging, hole wall hanging net and sprayed mortar, finishes sprayed mortar in deep pit digging 2-3 hour.
Described the 3rd step comprises boring, steel wire bundle making, slip casting, inserting or withdrawing sleeves and anchorage cable stretching, and described boring step adopts hydraulic pressure boring, and the water/binder ratio of the cement paste that described slip casting step adopts is 0.45-0.5, and grouting pressure is controlled at 0.3M.
Described the 4th step comprise determine that the precipitation well location is put, pore-forming, clear hole and water pump is installed.
Described the 5th step comprises soil nailing making, pore-forming, slip casting, steel mesh reinforcement establishment, sprayed mortar surface layer and bears down on one, described soil nailing adopts welded steel pipe to make, its sidewall upper edge uniform diameter of its axis is the injected hole of 5-15mm, and the welded steel pipe that seal the bottom is driven underground.
Described slip casting step comprises hole, bottom grouting and mud jacking clearly, adopts neat slurry, and water/binder ratio is 0.5-0.55.
Described the 6th step is included in deep foundation ditch and goes out to build water-retaining cofferdam for outer 1.5 meters, the basis rammed earth of water-retaining cofferdam, and on the basis, build waterwall by laying bricks or stones.
Beneficial effect of the present invention is as follows: adopt the cast-in-place concrete pile that gathers at the deep foundation ditch upstream face, inter-pile soil combined bolting and shotcrete structure, back side adopts soil nailing wall combined bolting and shotcrete method, effectively prevent from the potential safety hazard brought because of the expansive soil slope unstability from, effectively to economize on resources according to actual conditions segmentation supporting, economic and practical, in conjunction with tube well dewatering measure in the foundation ditch, effectively dewatering is convenient to carry out foundation construction simultaneously.
The specific embodiment
In sum, the invention discloses a kind of swelled ground area deep foundation pit precipitation and construction method for supporting, it is characterized in that: may further comprise the steps:
The first step: the deep foundation ditch upstream face concrete spouting pile driving construction that gathers; The described first step comprise bury that casing, slurrying, rig are in place underground, pore-forming, reinforcing cage fabrication and installation and concrete spouting.The sand factor of mud is smaller or equal to 8% in the described pore-forming metapore, and mud viscosity is smaller or equal to 28S, and mud balance is less than 1.25.
The slump of described perfusion is 180-220mm, and water/binder ratio is 0.5-0.55.
Second step: in the soil excavation process, carry out the inter-pile soil spray and protect; Described second step comprises deep pit digging, hole wall hanging net and sprayed mortar, finishes sprayed mortar in deep pit digging 2-3 hour.
The 3rd step: anchor bolt construction between stake; Described the 3rd step comprises boring, steel wire bundle making, slip casting, inserting or withdrawing sleeves and anchorage cable stretching, and described boring step adopts hydraulic pressure boring, and the water/binder ratio of the cement paste that described slip casting step adopts is 0.45-0.5, and grouting pressure is controlled at 0.3M.
The 4th step: tube well dewatering construction in the deep foundation ditch; Because the expansive soil permeability is minimum, it is little to cheat outer dewatering effect, so precipitation adopts tube well dewatering in the technical ability, gutter and collecting well are set around deep foundation ditch simultaneously, employing is fallen, row, every the precipitation method that combines, effective dewatering, this step comprises determines that the precipitation well location puts, pore-forming, clear hole and installation water pump, at first determine that according to actual conditions each precipitation well location puts in the concrete work progress, adopt circulation to be drilled to the hole then, the aperture generally is controlled at 600-800mm, uses mud off, clear immediately hole behind the pore-forming, and the installation well casing, the filter pipe part of well casing should be placed in the proper range in aquifer, and at well casing springtail rubble filtrate between hole wall, water pump money is installed with the clear filter well of compressed air, is installed behind the water pump and can come into operation after water pump and control system thereof detected.
The 5th step: deep foundation ditch back side construction of soil-nailed wall; Described the 5th step comprises soil nailing making, pore-forming, slip casting, steel mesh reinforcement establishment, sprayed mortar surface layer and bears down on one, described soil nailing adopts welded steel pipe to make, its sidewall upper edge uniform diameter of its axis is the injected hole of 5-15mm, and the welded steel pipe that seal the bottom is driven underground.
The steel mesh reinforcement of being worked out is generally two-way layout, the adjacent steel bar end 500mm that staggers, steel mesh reinforcement adopts the screw-thread steel overlap joint between welded steel pipe, the slip casting step comprises hole, bottom grouting and mud jacking clearly, adopt neat slurry, water/binder ratio is 0.5-0.55, and construction artificial fluid concrete of employing or construction of shotcrete bear down on one at deep foundation ditch periphery top, thickness remains on 80-100mm, and arrangement of reinforcement is identical in the steel mesh reinforcement arrangement of reinforcement.Carry out the bright worker of applying of foundation ditch after deep foundation ditch back side construction of soil-nailed wall finishes, sump is set in deep foundation ditch, and the excavation gutter, the gutter is communicated with in sump, and intermittently draws water in sump with slush pump.
The 6th step: water-retaining cofferdam construction around the foundation ditch; Be included in deep foundation ditch and go out to build water-retaining cofferdam for outer 1.5 meters, the basis rammed earth of water-retaining cofferdam, and on the basis, build waterwall by laying bricks or stones, the high 300mm of waterwall, wide 240mm.
Adopt the cast-in-place concrete pile that gathers at the deep foundation ditch upstream face, inter-pile soil combined bolting and shotcrete structure, back side adopts soil nailing wall combined bolting and shotcrete method, effectively prevent from the potential safety hazard brought because of the expansive soil slope unstability from, effectively to economize on resources according to actual conditions segmentation supporting, economic and practical, in conjunction with tube well dewatering measure in the deep foundation ditch, effectively dewatering is convenient to carry out foundation construction simultaneously.

Claims (10)

1. swelled ground area deep foundation pit precipitation and construction method for supporting is characterized in that: may further comprise the steps:
The first step: the deep foundation ditch upstream face concrete spouting pile driving construction that gathers;
Second step: in the soil excavation process, carry out the inter-pile soil spray and protect;
The 3rd step: anchor bolt construction between stake;
The 4th step: tube well dewatering construction in the deep foundation ditch;
The 5th step: deep foundation ditch back side construction of soil-nailed wall;
The 6th step: water-retaining cofferdam construction around the deep foundation ditch.
2. swelled ground area deep foundation pit precipitation according to claim 1 and construction method for supporting is characterized in that: the described first step comprise bury that casing, slurrying, rig are in place underground, pore-forming, reinforcing cage fabrication and installation and concrete spouting.
3. swelled ground area deep foundation pit precipitation according to claim 2 and construction method for supporting is characterized in that: the sand factor of mud is smaller or equal to 8% in the described pore-forming metapore, and mud viscosity is smaller or equal to 28S, and mud balance is less than 1.25.
4. swelled ground area deep foundation pit precipitation according to claim 2 and construction method for supporting is characterized in that: the slump of described perfusion is 180-220mm, and water/binder ratio is 0.5-0.55.
5. swelled ground area deep foundation pit precipitation according to claim 1 and construction method for supporting is characterized in that: described second step comprises deep pit digging, hole wall hanging net and sprayed mortar, finishes sprayed mortar in deep pit digging 2-3 hour.
6. swelled ground area deep foundation pit precipitation according to claim 1 and construction method for supporting, it is characterized in that: described the 3rd step comprises boring, steel wire bundle making, slip casting, inserting or withdrawing sleeves and anchorage cable stretching, described boring step adopts hydraulic pressure boring, the water/binder ratio of the cement paste that described slip casting step adopts is 0.45-0.5, and grouting pressure is controlled at 0.3M.
7. swelled ground area deep foundation pit precipitation according to claim 1 and construction method for supporting is characterized in that: described the 4th step comprise determine that the precipitation well location is put, pore-forming, clear hole and water pump is installed.
8. swelled ground area deep foundation pit precipitation according to claim 1 and construction method for supporting, it is characterized in that: described the 5th step comprises soil nailing making, pore-forming, slip casting, steel mesh reinforcement establishment, sprayed mortar surface layer and bears down on one, described soil nailing adopts welded steel pipe to make, its sidewall upper edge uniform diameter of its axis is the injected hole of 5-15mm, and the welded steel pipe that seal the bottom is driven underground.
9. swelled ground area deep foundation pit precipitation according to claim 8 and construction method for supporting is characterized in that: described slip casting step comprises hole, bottom grouting and mud jacking clearly, adopts neat slurry, and water/binder ratio is 0.5-0.55.
10. swelled ground area deep foundation pit precipitation according to claim 1 and construction method for supporting is characterized in that: described the 6th step is included in deep foundation ditch and goes out to build water-retaining cofferdam for outer 1.5 meters, the basis rammed earth of water-retaining cofferdam, and on the basis, build waterwall by laying bricks or stones.
CN2013101399480A 2013-04-22 2013-04-22 Construction method of dewatering and retaining and protecting of deep foundation pit in expansive-soil area Pending CN103215958A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2013101399480A CN103215958A (en) 2013-04-22 2013-04-22 Construction method of dewatering and retaining and protecting of deep foundation pit in expansive-soil area

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2013101399480A CN103215958A (en) 2013-04-22 2013-04-22 Construction method of dewatering and retaining and protecting of deep foundation pit in expansive-soil area

Publications (1)

Publication Number Publication Date
CN103215958A true CN103215958A (en) 2013-07-24

Family

ID=48814083

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2013101399480A Pending CN103215958A (en) 2013-04-22 2013-04-22 Construction method of dewatering and retaining and protecting of deep foundation pit in expansive-soil area

Country Status (1)

Country Link
CN (1) CN103215958A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104831737A (en) * 2015-04-29 2015-08-12 孔志坚 Construction method of basement support for subway station
CN106088121A (en) * 2016-06-07 2016-11-09 中国十七冶集团有限公司 The micro-expansion soil Method on Dewatering of Foundation Pit that a kind of subsoil water soaks
CN107090837A (en) * 2017-06-29 2017-08-25 中国建筑第二工程局有限公司 Pit-in-pit reinforced concrete retaining wall composite supporting structure and construction method thereof
CN110029673A (en) * 2019-04-16 2019-07-19 潮峰钢构集团有限公司 Anchor cable drilling pilework and its enclosing method suitable for Extra-Deep Foundation Pit
CN110359473A (en) * 2019-07-24 2019-10-22 青岛东建建设有限公司 A kind of closed precipitation environmental protection and energy saving construction technology of deep basal pit
CN112553991A (en) * 2020-11-30 2021-03-26 中交路桥建设有限公司 Weak expansive soil old roadbed reinforcing method and widening method

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1348037A (en) * 2000-10-18 2002-05-08 首钢总公司 Continuous wall foundation pit supporting method with short brad
CN1540107A (en) * 2003-04-26 2004-10-27 曾宪明 Soft soil slope soil nail supporting construction method
KR100468034B1 (en) * 2002-06-19 2005-01-27 주식회사 도담이앤씨 Construction Method of Reinforced Earth Retaining-Wall for using Anchoring
CN101225661A (en) * 2008-02-02 2008-07-23 浙江环宇建设集团有限公司 Pile-anchor foundation ditch supporting construction method
CN101736732A (en) * 2009-12-17 2010-06-16 上海隧道工程股份有限公司 Pressure and water reduction construction method of ultra-deep foundation pit confined water
CN101892667A (en) * 2010-07-23 2010-11-24 中国建筑第二工程局有限公司 Foundation pit supporting device and construction method
CN102828518A (en) * 2012-09-17 2012-12-19 中国建筑第二工程局有限公司 Prestressed anchor cable anchoring structure of manual hole digging support pile and construction method thereof

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1348037A (en) * 2000-10-18 2002-05-08 首钢总公司 Continuous wall foundation pit supporting method with short brad
KR100468034B1 (en) * 2002-06-19 2005-01-27 주식회사 도담이앤씨 Construction Method of Reinforced Earth Retaining-Wall for using Anchoring
CN1540107A (en) * 2003-04-26 2004-10-27 曾宪明 Soft soil slope soil nail supporting construction method
CN101225661A (en) * 2008-02-02 2008-07-23 浙江环宇建设集团有限公司 Pile-anchor foundation ditch supporting construction method
CN101736732A (en) * 2009-12-17 2010-06-16 上海隧道工程股份有限公司 Pressure and water reduction construction method of ultra-deep foundation pit confined water
CN101892667A (en) * 2010-07-23 2010-11-24 中国建筑第二工程局有限公司 Foundation pit supporting device and construction method
CN102828518A (en) * 2012-09-17 2012-12-19 中国建筑第二工程局有限公司 Prestressed anchor cable anchoring structure of manual hole digging support pile and construction method thereof

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104831737A (en) * 2015-04-29 2015-08-12 孔志坚 Construction method of basement support for subway station
CN106088121A (en) * 2016-06-07 2016-11-09 中国十七冶集团有限公司 The micro-expansion soil Method on Dewatering of Foundation Pit that a kind of subsoil water soaks
CN107090837A (en) * 2017-06-29 2017-08-25 中国建筑第二工程局有限公司 Pit-in-pit reinforced concrete retaining wall composite supporting structure and construction method thereof
CN110029673A (en) * 2019-04-16 2019-07-19 潮峰钢构集团有限公司 Anchor cable drilling pilework and its enclosing method suitable for Extra-Deep Foundation Pit
CN110029673B (en) * 2019-04-16 2023-10-13 潮峰钢构集团有限公司 Anchor cable bored pile structure suitable for deep foundation pit support and support method thereof
CN110359473A (en) * 2019-07-24 2019-10-22 青岛东建建设有限公司 A kind of closed precipitation environmental protection and energy saving construction technology of deep basal pit
CN112553991A (en) * 2020-11-30 2021-03-26 中交路桥建设有限公司 Weak expansive soil old roadbed reinforcing method and widening method

Similar Documents

Publication Publication Date Title
CN110093928B (en) Foundation pit supporting structure and earth excavation construction method
CN104612162B (en) A kind of Deep Foundation Pit of Metro Stations excavation construction method
CN107542108B (en) A kind of reverse construction method of building basement structure
CN103147442B (en) Ultra-deep foundation pit press-grouting pile and prestressed anchor combined supporting construction method
CN111733828A (en) Large-section deep foundation pit fender pile and prestressed anchor cable supporting construction technology
CN204491626U (en) The foundation pit enclosure structure that Larsen steel sheet pile and prestressed anchor combine
CN104110038A (en) Construction method for large-area pit support structure in deep-sludge type soft soil area
CN103215958A (en) Construction method of dewatering and retaining and protecting of deep foundation pit in expansive-soil area
CN110735600B (en) Mechanical pore-forming pile construction process for karst geology
CN103758123A (en) Method for constructing protecting wall lining of cast-in-place manual hole digging pile
Godavarthi et al. Contiguous pile wall as a deep excavation supporting system
CN105155550A (en) Construction method for digging deep foundation pit in large-thickness highly weathered sandstone stratum in combined supporting mode
CN108049417A (en) A kind of high-locality landslide body reinforces method of disposal
CN111560962A (en) Backfill area foundation pit supporting structure and construction method thereof
CN201801872U (en) Deep foundation pit excavated on corrode geology through combined support
CN112160324A (en) Construction method for deep foundation pit support
CN107869351A (en) A kind of method of the high narrow large-scale solution cavity Cavity treatment security protection of type
CN104264683B (en) Building concave shape ultra-deep foundation pit subregion supporting method is protected for three around literary composition
CN113356289B (en) Deep foundation pit brick chimney reinforcing method
CN106065628B (en) Based on the major diameter running water pipe security protection construction method faced forever with reference to theory
CN212077981U (en) Combined slope supporting structure
JP7292772B2 (en) External expansion pipe construction method for drilling in the mining zone
CN101597903B (en) Construction method of cylindrical slurry core pile for retaining and protecting foundation pit
CN102995647A (en) Underground water control method used for grouting and seepage insulation of pile hole
CN114032928A (en) Soil nailing wall construction method for pre-reinforcing slope rock-soil mass

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C12 Rejection of a patent application after its publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20130724