Nothing Special   »   [go: up one dir, main page]

CN110030001B - Construction method for mountain tunnel to go out of hole - Google Patents

Construction method for mountain tunnel to go out of hole Download PDF

Info

Publication number
CN110030001B
CN110030001B CN201910461546.XA CN201910461546A CN110030001B CN 110030001 B CN110030001 B CN 110030001B CN 201910461546 A CN201910461546 A CN 201910461546A CN 110030001 B CN110030001 B CN 110030001B
Authority
CN
China
Prior art keywords
tunnel
excavation
mountain
blasting
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201910461546.XA
Other languages
Chinese (zh)
Other versions
CN110030001A (en
Inventor
吴波
张子仪
黄惟
邓政
蒙国往
李静
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangxi University
Original Assignee
Guangxi University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangxi University filed Critical Guangxi University
Priority to CN201910461546.XA priority Critical patent/CN110030001B/en
Publication of CN110030001A publication Critical patent/CN110030001A/en
Application granted granted Critical
Publication of CN110030001B publication Critical patent/CN110030001B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/006Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries by making use of blasting methods

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Architecture (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Civil Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The invention discloses a construction method for a mountain tunnel to go out of a tunnel, wherein tunneling is suspended within a safe distance, a simple working platform is piled up by utilizing partial stone slag generated in the front-stage excavation process for construction advance support and blasting shock wave prevention, a protective net is hung by utilizing a grouting guide pipe which is dug outwards from the tunnel, then controlled blasting is carried out for a few times according to the designed construction sequence to form a slag-out funnel, and meanwhile, mechanical excavation is combined, so that the tunnel is gone out in a circular operation mode. According to the invention, the stone slag is used for piling the simple working platform and the inclination angle and the size of the slag discharging funnel are adjusted, so that the problems caused by adverse factors such as steep terrain, falling stones and flying stones in the tunnel discharging process are solved to a certain extent, the influence on the surrounding environment in the tunnel discharging process is minimized, and the construction environmental protection and safety are ensured.

Description

Construction method for mountain tunnel to go out of hole
Technical Field
The invention relates to the technical field of tunnel construction methods, in particular to a construction method for a mountain tunnel to go out of a tunnel.
Background
Tunnels are engineering structures buried in the ground and are a form of human use of underground space. The tunnel can be divided into a traffic tunnel, a hydraulic tunnel, a municipal tunnel and a mine tunnel. The structure of the tunnel comprises two parts, namely a main building and accessory equipment. The main building is composed of a tunnel body and a tunnel door, the auxiliary equipment comprises a car-avoiding tunnel, fire-fighting equipment, emergency communication and water-proof and drainage equipment, and the long and large tunnel is also provided with special ventilation and lighting equipment.
At present, the mode of tunneling from a tunnel entrance to a tunnel exit at the other end by using a single head is mostly adopted for the tunnel exit of a short tunnel and a small tunnel, and when the tunnel exit is constructed, a large amount of stone slag is usually generated and directly discharged from the tunnel exit. When residential buildings, roads, crops and the like exist under the mountains, certain damage can be caused, and obviously, the extensive construction mode is not preferable. Meanwhile, considering the problem of ecological environment protection, it is very important to adopt an economic, environment-friendly and effective hole-exiting mode.
Therefore, how to change the current situation that the rock ballast damages the surrounding environment when the tunnel is constructed to the exit hole in the prior art is a problem to be solved urgently by the technical personnel in the field.
Disclosure of Invention
The invention aims to provide a construction method for mountain tunnel cave exit, which aims to solve the problems in the prior art and ensure that tunnel cave exit construction can effectively protect existing buildings or landforms under mountains.
In order to achieve the purpose, the invention provides the following scheme: the invention provides a construction method for mountain tunnel exit, which comprises the following steps:
step one, when a tunnel body is excavated to a tunnel outlet, a tunnel face is suspended to be driven forwards, stone slag generated by excavation of the tunnel body is accumulated to form a simple working platform, and a gap is formed between the simple working platform and a surrounding rock face to be excavated;
step two, arranging a pipe shed support at the top of the excavated tunnel face, wherein the distance between the pipe shed support and the hole outlet is equal to the diameter of the hole body, and a steel pipe of the pipe shed support is obliquely and obliquely arranged towards the hole outlet;
thirdly, arranging a grouting guide pipe at the bottom of the inverted arch, wherein the axis of the grouting guide pipe is parallel to the axis of the tunnel, the grouting guide pipe extends out of the mountain side slope, a protective net is arranged outside the mountain side slope, one end of the protective net is fixed on the grouting guide pipe, and the height of the protective net is higher than that of the tunnel body;
step four, smooth blasting construction
A. Forming a free face through a vertical wedge-shaped cut, wherein the aperture, the blast hole row spacing and the hole depth of the vertical wedge-shaped cut are set according to the type of surrounding rock;
B. carrying out blasting design according to actual surrounding rock conditions, excavation sections, blasting equipment and construction difficulty;
C. blasting construction is carried out from top to bottom in a mode of multiple times and small quantity, and a slag discharging funnel is formed after blasting due to the fact that the palm surface has gradient;
D. excavating the residual rock mass in the blasting range by a mechanical excavation mode to penetrate through the tunnel face, wherein during excavation, the cross section direction of the tunnel is according to the excavation sequence from two sides to the middle, and the vertical direction is according to the excavation sequence from top to bottom;
E. the novel stone slag generated by blasting excavation is accumulated to form a novel simple working platform, the novel simple working platform is used for primary support, and the stone slag which is not needed in the prior simple working platform is transported out from the hole inlet;
F. circularly operating by adopting the A-E method until the excavation of the tunnel face is finished;
and fifthly, after the tunnel face is excavated, transporting all the residual stone slag in the tunnel out of the tunnel entrance to finish the tunnel exit.
Preferably, in the first step, when the distance between the excavated hole body and the hole outlet is 4-8m, forward tunneling is suspended.
Preferably, in the step one, the simple working platform is trapezoidal.
Preferably, in the second step, the diameter of the steel pipe supported by the pipe shed is 96 mm.
Preferably, in the third step, the distance of the grouting guide pipe extending out of the mountain slope is 2 m.
Preferably, in the fourth step, a method of shortening or staggering the blast hole and controlling the total explosive quantity is adopted to reduce the disturbance to the surrounding rock.
Preferably, the tunnel is in a bolting mode.
Compared with the prior art, the invention has the following technical effects: the construction method for the mountain tunnel to go out of the tunnel stops tunneling within a safe distance, utilizes part of stone slag generated in the front-section excavation process to pile up a simple working platform for construction advance support and blasting shock wave prevention, utilizes a grouting guide pipe which is dug outwards from the interior of the tunnel to hang a protective net, then carries out controlled blasting for a small number of times according to the designed construction sequence to form a slag discharging funnel, and simultaneously combines mechanical excavation to go out of the tunnel in a circular operation mode. According to the invention, the stone slag is used for piling the simple working platform and the inclination angle and the size of the slag discharging funnel are adjusted, so that the problems caused by adverse factors such as steep terrain, falling stones and flying stones in the tunnel discharging process are solved to a certain extent, the influence on the surrounding environment in the tunnel discharging process is minimized, and the construction environmental protection and safety are ensured.
Drawings
In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings needed to be used in the embodiments will be briefly described below, and it is obvious that the drawings in the following description are only some embodiments of the present invention, and it is obvious for those skilled in the art to obtain other drawings without inventive exercise.
FIG. 1 is a construction flow chart of a construction method for mountain tunnel cave exit according to the present invention;
FIG. 2 is a schematic view of the construction environment of the mountain tunnel exit construction method of the present invention;
FIG. 3 is a schematic cross-sectional view illustrating a construction of a tunnel exit according to the method for constructing a tunnel exit in a mountain tunnel of the present invention;
FIG. 4 is a schematic axial cross-sectional view of a construction of a tunnel exit according to the method of the present invention;
wherein, 1 is the rock mass that the entrance to a cave did not excavate, 2 is the tunnel design outline line, 3 is simple and easy work platform, 4 is the slip casting pipe, 5 is the protection network, 6 is indestructible building, 7 is the stock support, 8 is the pipe shed support, 9 is the inverted arch, 10 is the funnel of slagging tap, 11 is interim steel bow member, 12 is the excavation face, 13 is the stone ballast that the excavation produced, α is the funnel inclination of slagging tap.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
The invention aims to provide a construction method for mountain tunnel cave exit, which aims to solve the problems in the prior art and ensure that tunnel cave exit construction can effectively protect existing buildings or landforms under mountains.
In order to make the aforementioned objects, features and advantages of the present invention comprehensible, embodiments accompanied with figures are described in further detail below.
Referring to fig. 1 to 4, fig. 1 is a construction flow chart of a construction method of a mountain tunnel of the present invention, fig. 2 is a schematic view of a construction environment of the construction method of the mountain tunnel of the present invention, fig. 3 is a schematic view of a cross section of a tunnel exit of the construction method of the mountain tunnel of the present invention, and fig. 4 is a schematic view of an axial cross section of the tunnel exit of the construction method of the mountain tunnel of the present invention.
The invention provides a construction method for mountain tunnel exit, which comprises the following steps:
step one, building a construction platform
When tunnel excavation shaft to a tunnel outlet one section distance, in excavation face safe distance, pile up the stone ballast that the shaft excavation produced and form simple and easy work platform 3, simple and easy work platform 3 and wait to have the clearance between the country rock face of excavation.
Step two, pre-supporting at the hole outlet
Arranging a pipe shed support at the top of the excavated tunnel face, wherein the length of a steel pipe of the pipe shed support is medium, the distance between the pipe shed support and the hole outlet is equal to the diameter of the hole body, and the steel pipe of the pipe shed support is obliquely and obliquely arranged towards the hole outlet; during construction, holes are drilled above an excavated face according to the designed drilling direction, diameter, elevation angle, depth and annular interval, and a steel pipe is inserted and grouted in time after each hole is drilled.
Step three, installation protection measures
The grouting guide pipe 4 is arranged at the bottom of the inverted arch, the axis of the grouting guide pipe 4 is parallel to the axis of the tunnel, the grouting guide pipe 4 extends out of the mountain slope, the grouting guide pipe 4 can be used as a part of pre-support for tunnel excavation, and after the tunnel is excavated, only the part of the grouting guide pipe 4 extending out of the mountain slope needs to be cut, so that the operation is convenient. A protective net 5 is arranged outside the mountain slope, one end of the protective net 5 is fixed on a grouting guide pipe 4, the grouting guide pipe 4 can provide support for the protective net 5, and the protective net 5 is higher than the hole body.
Step four, smooth blasting construction
A. A free face is formed through the vertical wedge-shaped cut, and the aperture, the blast hole row spacing and the hole depth of the vertical wedge-shaped cut are set according to the type of the surrounding rock.
B. And blasting design is carried out according to actual surrounding rock conditions, excavation sections, blasting equipment and construction difficulty.
C. Adopt a small amount of mode many times during the blasting, blast the construction from top to bottom, because the palm face has the gradient, form slag discharging funnel 10 after the blasting, not hard up rock mass leaks down because of the action of gravity, utilizes the slope formation of excavation palm face to slag discharging funnel 10, leaks the slabstone sediment through the action of gravity and can reduce operating personnel work load, improves work efficiency. In this embodiment, the angle of inclination of the tapping funnel 10 is 5 ° to 10 °.
D. Excavating the residual rock mass in the blasting range by a mechanical excavation mode to penetrate through the tunnel face, wherein during excavation, the cross section direction of the tunnel is according to the excavation sequence from two sides to the middle, and the vertical direction is according to the excavation sequence from top to bottom; referring to the figure, the left upper section is excavated in the horizontal direction, the right upper section is excavated, the upper middle section is excavated, and the upper middle section is excavated in the vertical direction from top to bottom. A small amount of smooth blasting for multiple times is combined with a mechanical excavation hole outlet mode, so that disturbance to surrounding rocks in the construction process can be effectively reduced, and falling rocks and flying rocks generated by blasting are reduced.
E. The blasting excavation generates new stone slag, the new stone slag generated by the excavation is accumulated to form a new simple working platform 3, the new simple working platform 3 is used for primary support, and the stone slag which is not needed in the previous simple working platform 3 is transported out from the hole inlet. It should be noted here that the simple work platform 3 formed by stacking the ballast is not fixed, and in the process of going out of the tunnel, while the new ballast generated by excavation continues to stack the new simple work platform 3, the ballast used for stacking the simple work platform 3 that is not needed before is transported out from the tunnel entrance, that is, the simple work platform 3 is continuously updated and moves towards the excavation direction, and the simple work platform 3 not only can be used as a construction platform for supporting an advanced pipe shed, but also can effectively block shock waves generated during blasting construction.
F. And circularly operating by adopting the A-E method until the excavation of the tunnel face is finished. The invention adopts smooth blasting, and the micro-vibration controlled blasting is combined with the slag-out funnel 10 formed in the blasting process and the protective net 5 outside the hole, so that the influence of hole discharging construction on the surrounding environment is reduced to the minimum, the construction period can be shortened, and the working efficiency is improved.
And fifthly, after the tunnel face is excavated, transporting all the residual stone slag in the tunnel out of the tunnel entrance to finish the tunnel exit, wherein the buildings under the hill are not influenced by the tunnel exit construction.
In the specific implementation mode, in the step one, when the distance between the excavated cavity body and the hole outlet is 4-8m, forward tunneling is suspended, and forward tunneling is stopped when the hole outlet is excavated to a certain distance, wherein the distance is related to specific factors such as geological conditions.
Specifically, in the first step, the simple working platform 3 is trapezoidal, and the trapezoidal simple working platform 3 provides stable support for construction.
In addition, in the second step, the diameter of the steel pipe of the pipe shed support is 96mm, and the reliability of the pipe shed support is improved.
More specifically, in the third step, the distance that the grouting guide pipe 4 extends out of the mountain slope is 2m, and the grouting guide pipe 4 provides stable support for the protective net 5.
Furthermore, in the fourth step, when the surrounding rock condition is poor, a method of shortening or staggering blastholes and controlling the total explosive quantity is adopted to reduce the disturbance to the surrounding rock.
Furthermore, the tunnel adopts an anchor bolt supporting mode, and the anchor bolt supporting effect is good, the cost is low, and the operation is simple and convenient.
The construction method of the mountain tunnel cave-out is suitable for the conditions that an indestructible building exists below a mountain body, land acquisition cannot be realized and the like, the adverse effect on the mountain tunnel cave-out construction is reduced as much as possible, tunneling is suspended within a safe distance, a simple working platform 3 is piled up by utilizing partial rock ballast generated in the front-stage excavation process and used for construction advanced support and blasting shock wave prevention, a protective net 5 is hung by utilizing a grouting guide pipe 4 which is dug outwards from the inside of the cave, blasting is controlled for a plurality of times in a small amount according to the designed construction sequence to form a slag discharging funnel 10, and meanwhile, the cave-out is realized in a circular operation mode by combining mechanical excavation. According to the invention, the stone slag piling simple working platform 3 and the inclination angle and the size of the slag discharging funnel 10 are adjusted, so that the problems caused by adverse factors such as steep terrain, falling stones and flying stones in the tunnel discharging process are solved to a certain extent, the influence on the surrounding environment in the tunnel discharging process is minimized, and the construction environmental protection and safety are ensured. Meanwhile, the construction method for the mountain tunnel to exit has low construction difficulty, reduces the complexity of personnel, machinery and construction method adjustment, reduces the construction cost, and more importantly, can flexibly adjust the positions of the piled simple working platform 3 and the exit and the inclination angle and the size of the slag funnel 10 according to the actual conditions of surrounding rocks and surrounding environments.
The principle and the implementation mode of the invention are explained by applying a specific example, and the description of the embodiment is only used for helping to understand the method and the core idea of the invention; meanwhile, for a person skilled in the art, according to the idea of the present invention, the specific embodiments and the application range may be changed. In view of the above, the present disclosure should not be construed as limiting the invention.

Claims (7)

1. A construction method for mountain tunnel exit is characterized by comprising the following steps:
step one, when a tunnel body is excavated to a tunnel outlet, a tunnel face is suspended to be driven forwards, stone slag generated by excavation of the tunnel body is accumulated to form a simple working platform, and a gap is formed between the simple working platform and a surrounding rock face to be excavated;
step two, arranging a pipe shed support at the top of the excavated tunnel face, wherein the distance between the pipe shed support and the hole outlet is equal to the diameter of the hole body, and a steel pipe of the pipe shed support is obliquely and obliquely arranged towards the hole outlet;
thirdly, arranging a grouting guide pipe at the bottom of the inverted arch, wherein the axis of the grouting guide pipe is parallel to the axis of the tunnel, the grouting guide pipe extends out of the mountain side slope, a protective net is arranged outside the mountain side slope, one end of the protective net is fixed on the grouting guide pipe, and the height of the protective net is higher than that of the tunnel body;
step four, smooth blasting construction
A. Forming a free face through a vertical wedge-shaped cut, wherein the aperture, the blast hole row spacing and the hole depth of the vertical wedge-shaped cut are set according to the type of surrounding rock;
B. carrying out blasting design according to actual surrounding rock conditions, excavation sections, blasting equipment and construction difficulty;
C. blasting construction is carried out from top to bottom in a mode of multiple times and small quantity, and a slag discharging funnel is formed after blasting due to the fact that the palm surface has gradient;
D. excavating the residual rock mass in the blasting range by a mechanical excavation mode to penetrate through the tunnel face, wherein during excavation, the cross section direction of the tunnel is according to the excavation sequence from two sides to the middle, and the vertical direction is according to the excavation sequence from top to bottom;
E. the novel stone slag generated by blasting excavation is accumulated to form a novel simple working platform, the novel simple working platform is used for primary support, and the stone slag which is not needed in the prior simple working platform is transported out from the hole inlet;
F. circularly operating by adopting the A-E method until the excavation of the tunnel face is finished;
and fifthly, after the tunnel face is excavated, transporting all the residual stone slag in the tunnel out of the tunnel entrance to finish the tunnel exit.
2. The mountain tunnel cave-out construction method according to claim 1, wherein: in the first step, when the distance between the excavated tunnel body and the tunnel outlet is 4-8m, forward tunneling is suspended.
3. The mountain tunnel cave-out construction method according to claim 1, wherein: in the first step, the simple working platform is in a trapezoid shape.
4. The mountain tunnel cave-out construction method according to claim 1, wherein: and in the second step, the diameter of the steel pipe supported by the pipe shed is 96 mm.
5. The mountain tunnel cave-out construction method according to claim 1, wherein: in the third step, the distance of the grouting guide pipe extending out of the mountain slope is 2 m.
6. The mountain tunnel cave-out construction method according to claim 1, wherein: in the fourth step, a method of shortening or staggering blast holes and controlling the total explosive quantity is adopted to reduce disturbance to surrounding rocks.
7. The mountain tunnel cave-out construction method according to claim 1, wherein: the tunnel adopts anchor bolt support mode.
CN201910461546.XA 2019-05-30 2019-05-30 Construction method for mountain tunnel to go out of hole Active CN110030001B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910461546.XA CN110030001B (en) 2019-05-30 2019-05-30 Construction method for mountain tunnel to go out of hole

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910461546.XA CN110030001B (en) 2019-05-30 2019-05-30 Construction method for mountain tunnel to go out of hole

Publications (2)

Publication Number Publication Date
CN110030001A CN110030001A (en) 2019-07-19
CN110030001B true CN110030001B (en) 2020-06-30

Family

ID=67243646

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910461546.XA Active CN110030001B (en) 2019-05-30 2019-05-30 Construction method for mountain tunnel to go out of hole

Country Status (1)

Country Link
CN (1) CN110030001B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110513121B (en) * 2019-08-20 2024-03-26 中国电建集团贵阳勘测设计研究院有限公司 Eggshell-shaped grouting tunnel car-avoiding tunnel structure
CN112880501B (en) * 2021-03-24 2021-10-19 山东科技大学 Flight-limited hole drilling and blasting method for controlling tunnel blasting flyrock

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07229390A (en) * 1994-02-17 1995-08-29 Teruki Fujiyama Tunnel
CN102620614A (en) * 2012-04-19 2012-08-01 中铁二局股份有限公司 Construction method for cave depot slag funnel
CN104533428A (en) * 2014-11-28 2015-04-22 大连市市政设计研究院有限责任公司 Steep cliff tunnel hole excavation construction method
CN104596372A (en) * 2014-12-31 2015-05-06 中国铁道科学研究院铁道建筑研究所 Tunneling method for improving explosion driving rate and lowering explosion vibration
CN109707399A (en) * 2019-02-21 2019-05-03 中铁二院工程集团有限责任公司 Tunnel outlet support structure and its construction method
CN109812277A (en) * 2019-02-28 2019-05-28 中铁十八局集团有限公司 A kind of vertical cliff tunnel active defense bimetallic tube canopy of high drop is appeared safely method

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07229390A (en) * 1994-02-17 1995-08-29 Teruki Fujiyama Tunnel
CN102620614A (en) * 2012-04-19 2012-08-01 中铁二局股份有限公司 Construction method for cave depot slag funnel
CN104533428A (en) * 2014-11-28 2015-04-22 大连市市政设计研究院有限责任公司 Steep cliff tunnel hole excavation construction method
CN104596372A (en) * 2014-12-31 2015-05-06 中国铁道科学研究院铁道建筑研究所 Tunneling method for improving explosion driving rate and lowering explosion vibration
CN109707399A (en) * 2019-02-21 2019-05-03 中铁二院工程集团有限责任公司 Tunnel outlet support structure and its construction method
CN109812277A (en) * 2019-02-28 2019-05-28 中铁十八局集团有限公司 A kind of vertical cliff tunnel active defense bimetallic tube canopy of high drop is appeared safely method

Also Published As

Publication number Publication date
CN110030001A (en) 2019-07-19

Similar Documents

Publication Publication Date Title
CN105298507B (en) A kind of underground pipe gallery construction method of top open cut bottom tunneler construction
CN104532818A (en) Treatment method for strip mine goaf
CN106121657B (en) A kind of multifunctional numerical control shaft sinking device and construction method
CN102748040B (en) Main structure for metro long-span station and pillar arching construction method thereof
CN109736827B (en) Method for excavating urban subway hard rock stratum communication channel by high-pressure gas expansion fracturing
CN103726495B (en) Coastal waters deep foundation pit supporting structure and construction method thereof
CN105648921A (en) Suspension bridge rock mass and reinforced concrete plate composited type anchorage and construction method thereof
CN110030001B (en) Construction method for mountain tunnel to go out of hole
CN112031738A (en) Construction method of vertical shaft slag sliding well raise boring machine with diameter of 4-6 m
CN104457466B (en) A kind of blasting method of tunnel open excavation section
CN105909262B (en) A kind of bored tunnel driving method
CN113605903B (en) Quick, simple and easy-to-operate new excavation and lining method for tunnel or arch base chamber of special anchorage
CN204495211U (en) A kind of blasting hole arrangement system of tunnel open excavation section
CN108755719A (en) Seabed municipal tunnel over strait cofferdam open cutting construction method
CN103362133B (en) Arch dam-arch shoulder grooving method in mountain narrow canyon
CN216159751U (en) Anti-slide pile hole digging construction structure
CN113737781B (en) Combined type hole digging pile construction structure and construction method thereof
CN104389609A (en) No-blasting mechanical digging method
CN108590662A (en) Construction method of ventilation shaft of subway station tunnel with high and steep slope
CN107905792A (en) A kind of embedded shaft excavation construction technology
CN110144903B (en) Construction method for foundation pit support in air defense cavity
CN110273708B (en) Roadway support structure body control drainage method
CN203846517U (en) Vertical anchor bolt supporting structure
Radkevych et al. Overview of technologies for constructing the facilities at the Dniester pumped storage power station
CN112901175A (en) Method for constructing underground laboratory spiral downward slope by applying TBM

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant