Nothing Special   »   [go: up one dir, main page]

CN109057392B - Construction method of steel structure for reinforcement - Google Patents

Construction method of steel structure for reinforcement Download PDF

Info

Publication number
CN109057392B
CN109057392B CN201810995893.6A CN201810995893A CN109057392B CN 109057392 B CN109057392 B CN 109057392B CN 201810995893 A CN201810995893 A CN 201810995893A CN 109057392 B CN109057392 B CN 109057392B
Authority
CN
China
Prior art keywords
steel plate
steel
concrete floor
bolt
reinforcement
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201810995893.6A
Other languages
Chinese (zh)
Other versions
CN109057392A (en
Inventor
成勃
姜丽萍
刘伟
韦安磊
丁一旭
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shandong Jianke Architectural Design Co ltd
SHANDONG JIANKE SPECIAL BUILDING ENGINEERING TECHNOLOGY CENTER
Shandong Provincial Academy of Building Research
Original Assignee
Shandong Jianke Architectural Design Co ltd
SHANDONG JIANKE SPECIAL BUILDING ENGINEERING TECHNOLOGY CENTER
Shandong Provincial Academy of Building Research
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shandong Jianke Architectural Design Co ltd, SHANDONG JIANKE SPECIAL BUILDING ENGINEERING TECHNOLOGY CENTER, Shandong Provincial Academy of Building Research filed Critical Shandong Jianke Architectural Design Co ltd
Priority to CN201810995893.6A priority Critical patent/CN109057392B/en
Publication of CN109057392A publication Critical patent/CN109057392A/en
Application granted granted Critical
Publication of CN109057392B publication Critical patent/CN109057392B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G23/00Working measures on existing buildings
    • E04G23/02Repairing, e.g. filling cracks; Restoring; Altering; Enlarging
    • E04G23/0218Increasing or restoring the load-bearing capacity of building construction elements
    • E04G23/0237Increasing or restoring the load-bearing capacity of building construction elements of storey floors
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G23/00Working measures on existing buildings
    • E04G23/02Repairing, e.g. filling cracks; Restoring; Altering; Enlarging
    • E04G23/0288Repairing or restoring floor slabs

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Chemical & Material Sciences (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • Electrochemistry (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Working Measures On Existing Buildindgs (AREA)

Abstract

本发明公开了一种加固用钢结施工方法,主要应用于建筑科学技术领域的建筑结构加固改造中。其结构包括钢板,所述钢板包括板顶钢板和板底钢板,所述板顶钢板位于混凝土楼板的顶面上,所述板底钢板位于混凝土楼板的底面上,所述板顶钢板和板底钢板在纵向上对齐,所述板顶钢板和板底钢板固定安装在所述混凝土楼板上开洞部位的边缘处以实现混凝土楼板的加固;所述板顶钢板和板底钢板之间设有将两者连接起来的刚性连接装置。本发明的钢结构空间体系与混凝土楼板结合为一体,锚固效果好,承载力及刚度可以得到较大程度的提高;施工安装方便,解决了钢板锚固问题;不占用使用空间,用钢量少、成本低。

Figure 201810995893

The invention discloses a steel structure construction method for reinforcement, which is mainly used in the reinforcement and reconstruction of building structures in the field of building science and technology. Its structure includes a steel plate, the steel plate includes a top steel plate and a bottom steel plate, the top steel plate is located on the top surface of the concrete floor, the bottom steel plate is located on the bottom surface of the concrete floor, the top steel plate and the plate bottom The steel plates are aligned in the longitudinal direction, and the top steel plate and the bottom steel plate are fixedly installed at the edge of the opening on the concrete floor to realize the reinforcement of the concrete floor; A rigid connection device that connects the two. The steel structure space system of the invention is integrated with the concrete floor, the anchoring effect is good, the bearing capacity and rigidity can be greatly improved; the construction and installation are convenient, and the problem of steel plate anchoring is solved; low cost.

Figure 201810995893

Description

一种加固用钢结构施工方法A kind of steel structure construction method for reinforcement

技术领域technical field

本发明涉及建筑科学技术领域,具体地说是一种加固用钢结施工方法,主要应用于建筑结构加固改造中。The invention relates to the field of building science and technology, in particular to a steel structure construction method for reinforcement, which is mainly used in the reinforcement and reconstruction of building structures.

背景技术Background technique

混凝土结构工程加固改造项目中,有时因为出于安装设备、后加楼梯等考虑,需要在混凝土楼板上开洞。楼板开洞破坏了原来楼板的整体性,降低了楼板的承载能力;而安装的设备、楼梯等增加了楼板上的荷载,必须进行加固才能保证结构的安全性和适用性。In the reinforcement and reconstruction project of concrete structure engineering, sometimes it is necessary to open holes in the concrete floor due to the consideration of installing equipment and adding stairs later. The opening of the floor slab destroys the integrity of the original floor slab and reduces the bearing capacity of the floor slab; while the installed equipment and stairs increase the load on the floor slab, and reinforcement must be carried out to ensure the safety and applicability of the structure.

在国家标准《混凝土结构设计规范》GB50010-2010中,对于新建工程,当混凝土现浇板上预留洞口时,洞口周边一般需要增设配筋,当洞口较大时,可增设混凝土梁。In the national standard "Code for Design of Concrete Structures" GB50010-2010, for new construction, when openings are reserved on the cast-in-place concrete slab, reinforcements are generally required to be added around the openings. When the openings are large, concrete beams can be added.

在国家标准《混凝土结构加固设计规范》GB50367-2013没有对后设洞口的处理方法,在现有的加固方法中,只有增大截面法、表面粘贴钢板或复合纤维材料(FRP)法能够适用。In the national standard "Code for Design of Reinforcement of Concrete Structures" GB50367-2013, there is no treatment method for rear openings. Among the existing reinforcement methods, only the method of increasing the section, attaching steel plates to the surface or composite fiber material (FRP) method can be applied.

现有加固方法中,有增设型钢梁加固的方法,该方法是将型钢置于板底,用于承担板面传来的荷载,可以提高结构承载力,但该方法降低了使用净空,且型钢梁两端需要增设支座。Among the existing reinforcement methods, there is a method of adding profiled steel beams. This method is to place the profiled steel at the bottom of the slab to bear the load from the slab surface, which can improve the bearing capacity of the structure, but this method reduces the use clearance, and Supports need to be added at both ends of the steel beam.

现有加固方法中,有板表面粘贴钢板的加固方法,该方法中板顶和(或)板底钢板随板的变形而变形并产生一定的拉压力,用以提高板的承载力,但该方法中钢板仅依附于楼板的变形而变形,不能形成相对独立的空间体系,对楼板的刚度增加影响较小,且提高承载力的程度有限。Among the existing reinforcement methods, there is a reinforcement method in which steel plates are attached to the surface of the plate. In this method, the steel plates at the top and (or) bottom of the plate are deformed with the deformation of the plate and generate a certain tensile pressure to improve the bearing capacity of the plate. In the method, the steel plate is only deformed by the deformation of the floor slab, and cannot form a relatively independent space system.

而增大截面法不可避免地要牺牲使用空间,表面粘贴等方法对楼板刚度增加较小,且提高承载力有限。However, the method of increasing the cross-section inevitably sacrifices the use space, and the methods such as surface sticking increase the stiffness of the floor to a small extent, and the improvement of the bearing capacity is limited.

现有一种屋面加固防漏装置,采用屋面防漏技术充分利用对夹式法兰对屋面加固,使洞口切割的边由线接触转化为面接触,增大了接触面积,从而达到板式屋面抗压且防漏的目的;现有一种结构加固工程中预应力楼板开洞的施工方法在新增洞口内侧增设钢构件支垫,安装锚具并张拉,用于预应力楼板开洞时预应力筋的截断与锚固;现有技术中针对剪力墙开洞,有采用角钢进行加固改造的,但剪力墙受力与楼板受力不同,而且其改造方法不能较好地解决因开洞后对楼板两侧造成的应力集中问题。There is a roof reinforcement leak-proof device, which adopts the roof leak-proof technology to make full use of the wafer-type flange to reinforce the roof, so that the cut edge of the hole is converted from line contact to surface contact, and the contact area is increased, so as to achieve the compression resistance of the panel roof. And the purpose of leakage prevention; there is a construction method for opening a prestressed floor in a structural reinforcement project. Steel member support pads are added inside the newly added opening, and anchors are installed and tensioned, which are used for prestressed reinforcement when the prestressed floor is opened. In the prior art, angle steel is used for reinforcement and reconstruction of shear wall openings, but the force of shear walls is different from that of floor slabs, and the transformation method cannot solve the problems caused by opening holes. Stress concentration problems caused by both sides of the floor slab.

以上现有技术均不能起到加固楼板、使其增大承载能力,以及帮助消除预应力的作用。None of the above existing technologies can strengthen the floor slab, increase its bearing capacity, and help to eliminate prestress.

发明内容SUMMARY OF THE INVENTION

针对上述问题,为了弥补在混凝土结构加固改造中,混凝土楼板开洞后承载力的不足,保证混凝土楼板开洞后的结构安全性、适用性,本发明的目的在于提供一种加固用钢结构空间体系及施工方法。In view of the above problems, in order to make up for the lack of bearing capacity of the concrete floor slab after the opening of the concrete structure in the reinforcement and reconstruction of the concrete structure, and to ensure the structural safety and applicability of the concrete floor slab after the opening of the cavity, the purpose of the present invention is to provide a steel structure space for reinforcement. system and construction method.

本发明解决其技术问题所采取的技术方案包括:一种加固用钢结构空间体系,包括钢板,所述钢板包括板顶钢板和板底钢板,所述板顶钢板位于混凝土楼板的顶面上,所述板底钢板位于混凝土楼板的底面上,所述板顶钢板和板底钢板在纵向上对齐,所述板顶钢板和板底钢板固定安装在所述混凝土楼板上开洞部位的边缘处以实现混凝土楼板的加固;所述板顶钢板和板底钢板之间设有将两者连接起来的刚性连接装置,刚性连接装置上设有两个上下对称设置的栓帽,栓帽嵌于混凝土楼板内,栓帽靠近楼板顶面或底面的一端的尺寸大于另一端的尺寸,为减少连接处的应力集中现象,特设置栓帽,因洞口的设置,洞口周围混凝土楼板应力较为集中,尤其是楼板的顶部和底部,采用一端大于另一端的栓帽,较好地将应力通过栓帽分散到钢结构空间体系上,有效保证了开洞楼板的使用年限。The technical solution adopted by the present invention to solve the technical problem includes: a steel structure space system for reinforcement, comprising a steel plate, the steel plate includes a plate top steel plate and a plate bottom steel plate, and the plate top steel plate is located on the top surface of the concrete floor, The bottom steel plate is located on the bottom surface of the concrete floor, the top and bottom steel plates are aligned in the longitudinal direction, and the top and bottom steel plates are fixedly installed at the edge of the opening on the concrete floor to achieve Reinforcement of concrete floor slabs; a rigid connecting device is arranged between the top steel plate and the bottom steel plate to connect the two, and two bolt caps arranged symmetrically up and down are arranged on the rigid connecting device, and the bolt caps are embedded in the concrete floor slab The size of one end of the bolt cap close to the top or bottom surface of the floor is larger than that of the other end. In order to reduce the stress concentration at the connection, a bolt cap is specially set. Due to the setting of the opening, the stress of the concrete floor around the opening is relatively concentrated, especially the At the top and bottom, bolt caps with one end larger than the other end are used to better disperse the stress to the steel structure space system through the bolt caps, effectively ensuring the service life of the open floor slab.

从经济性、实用性以及连接的可靠性等角度考虑,进一步的技术方案为:所述的刚性连接装置为钢栓,所述钢栓的两端设有螺纹,所述钢栓同时穿过所述板顶钢板、混凝土楼板和板底钢板,所述钢栓的两端通过螺母锁紧。From the perspectives of economy, practicability and connection reliability, a further technical solution is: the rigid connection device is a steel bolt, two ends of the steel bolt are provided with threads, and the steel bolt passes through all the bolts at the same time. The top steel plate, the concrete floor plate and the bottom plate steel plate are used, and the two ends of the steel bolt are locked by nuts.

进一步的技术方案为:所述钢板与钢栓的连接处分别设有栓帽,所述栓帽为钢板与钢栓间的锥形连接件,所述栓帽设在与螺母相对的一侧,为加工方便,栓帽可以为锥形,外表设有花纹或者螺纹以增大与楼板的接触面积。A further technical solution is: the connection between the steel plate and the steel bolt is respectively provided with a bolt cap, the bolt cap is a conical connecting piece between the steel plate and the steel bolt, and the bolt cap is arranged on the side opposite to the nut, For the convenience of processing, the bolt cap can be tapered, and the surface is provided with patterns or threads to increase the contact area with the floor.

为了进一步的约束钢板和混凝土楼板间的相对位移,避免钢板与混凝土楼板间的滑脱破坏,进一步的技术方案为:所述钢板与混凝土楼板的连接处设有结构胶,所述钢栓与混凝土楼板之间的缝隙内设有结构胶。In order to further constrain the relative displacement between the steel plate and the concrete floor, and avoid the slippage damage between the steel plate and the concrete floor, a further technical solution is: a structural glue is provided at the connection between the steel plate and the concrete floor, and the steel bolt is connected to the concrete floor. There is structural glue in the gap between them.

进一步的技术方案为:所述钢板沿混凝土楼板的开洞部位单向或者双向布置。当混凝土楼板按单向板设计时,可采用单向布置的钢结构空间体系,所谓单向布置,即钢板在开洞部位两侧沿混凝土楼板计算跨度方向布置;当混凝土楼板按双向板设计时,可采用双向布置的钢结构空间体系,所谓双向布置,即沿混凝土楼板开洞部位的四周同时布置横向和纵向钢板。A further technical solution is: the steel plates are arranged in one direction or two directions along the opening of the concrete floor. When the concrete floor is designed according to the one-way slab, the steel structure space system with one-way arrangement can be adopted. , A two-way layout of the steel structure space system can be used. The so-called two-way layout means that horizontal and vertical steel plates are simultaneously arranged around the opening of the concrete floor.

为了保证加固效果的可靠,进一步的技术方案为:所述钢板的两端延伸至其所处的混凝土楼板的端部上。In order to ensure the reliability of the reinforcement effect, a further technical solution is: the two ends of the steel plate extend to the ends of the concrete floor where the steel plate is located.

加固用的钢板优选使用条形钢带。The steel plate for reinforcement is preferably a strip-shaped steel strip.

本发明解决其技术问题的技术方案还包括:一种加固用钢结构空间体系的施工方法,包括以下步骤:The technical solution of the present invention to solve the technical problem also includes: a construction method for reinforcing a steel structure space system, comprising the following steps:

步骤1):在混凝土楼板上开洞部位的外侧设置钢板安装位置的定位线;Step 1): Set the positioning line for the installation position of the steel plate on the outside of the opening on the concrete floor;

步骤2):按照所述定位线在混凝土楼板的顶面和底面均设置钢板,楼板顶面的钢板为板顶钢板,楼板底面的钢板为板底钢板;Step 2): according to the positioning line, steel plates are arranged on both the top surface and the bottom surface of the concrete floor slab, the steel plate on the top surface of the floor slab is the top steel plate, and the steel plate on the bottom surface of the floor slab is the slab bottom steel plate;

步骤3):通过刚性连接装置将板顶钢板、混凝土楼板和板底钢板固连为一体。Step 3): The top steel plate, the concrete floor and the bottom steel plate are fixedly connected into one through a rigid connection device.

进一步的技术方案为:所述板顶钢板、混凝土楼板和板底钢板之间通过钢栓和结构胶相连接,连接方法包括以下步骤:A further technical solution is: the top steel plate, the concrete floor and the bottom steel plate are connected by steel bolts and structural glue, and the connection method includes the following steps:

步骤a:在混凝土楼板上需要安装钢板的位置钻孔,在钢板上也钻出相同直径和间距的孔;Step a: Drill holes on the concrete floor where the steel plate needs to be installed, and drill holes with the same diameter and spacing on the steel plate;

步骤b:打磨混凝土楼板上需要安装钢板的位置,使其达到粘贴钢板的要求;Step b: Polish the position where the steel plate needs to be installed on the concrete floor so that it meets the requirements for sticking the steel plate;

步骤c:在钢板的粘贴面除锈;Step c: rust removal on the sticking surface of the steel plate;

步骤d:粘贴板底钢板,采用锥形栓帽将钢栓与板底钢板连接好,然后向钢栓与混凝土楼板上安装钢栓的孔之间注入结构胶,再粘贴板顶钢板,并采用栓帽连接钢栓与板顶钢板,所述栓帽为钢板与钢栓间的锥形连接件。Step d: Paste the bottom steel plate of the slab, connect the steel bolt with the bottom steel plate by using the conical bolt cap, then inject structural glue between the steel bolt and the hole where the steel bolt is installed on the concrete floor, and then paste the top steel plate, and use The bolt cap connects the steel bolt and the top steel plate, and the bolt cap is a conical connecting piece between the steel plate and the steel bolt.

为了发挥出最佳的加固效果,进一步的技术方案为:所述定位线位于混凝土楼板上开洞部位的外侧50mm~100mm的位置。In order to exert the best reinforcement effect, a further technical solution is as follows: the positioning line is located at a position 50 mm to 100 mm outside the opening on the concrete floor.

为保证钻孔过程中不受现有钢筋影响,进一步的技术方案为:所述步骤a中,在混凝土楼板上钻孔的孔径比钢栓的直径大4mm~6mm,间距为混凝土楼板中钢筋间距的1~3倍。In order to ensure that the drilling process is not affected by the existing steel bars, a further technical solution is: in the step a, the hole diameter of the holes drilled in the concrete floor is 4mm to 6mm larger than the diameter of the steel bolts, and the spacing is the spacing between the steel bars in the concrete floor. 1 to 3 times.

本发明的有益效果是:The beneficial effects of the present invention are:

1、通过刚性连接装置将钢结构空间体系和混凝土楼板结合为一体,锚固效果好,承载力及刚度可以得到较大程度的提高;同时,本发明的施工方法操作性强,安装方便,解决了钢板锚固问题,未增大混凝土楼板的截面,不占用使用空间,用钢量少、成本低。1. The steel structure space system and the concrete floor slab are combined into one through the rigid connection device, the anchoring effect is good, and the bearing capacity and rigidity can be greatly improved; The problem of steel plate anchorage does not increase the cross-section of the concrete floor, does not occupy the use space, uses less steel, and has low cost.

2、刚性连接装置有效约束了钢板与混凝土间的相对位移,另外设置了结构胶,避免了钢板与混凝土间的滑脱破坏,钢结构空间体系通过结构胶和刚性连接装置与混凝土楼板紧密结合,形成共同受力的整体,大幅度地提高了结构承载力和刚度。2. The rigid connection device effectively restrains the relative displacement between the steel plate and the concrete. In addition, a structural adhesive is installed to avoid the slippage damage between the steel plate and the concrete. The steel structure space system is closely combined with the concrete floor through the structural adhesive and the rigid connection device to form The whole of the common force greatly improves the bearing capacity and stiffness of the structure.

3、本发明的钢结构空间体系,结构简单,采用锥形的栓帽,能较好的解决因开挖洞口,导致洞口两侧中部楼板应力集中的问题,易于推广实施。3. The steel structure space system of the present invention has a simple structure and adopts a conical bolt cap, which can better solve the problem of stress concentration in the middle floor slabs on both sides of the hole due to the excavation of the hole, and is easy to popularize and implement.

附图说明Description of drawings

图1为本发明实施例的主视图;1 is a front view of an embodiment of the present invention;

图2为本发明实施例的立体结构示意图;FIG. 2 is a schematic three-dimensional structure diagram of an embodiment of the present invention;

图3为本发明实施例钢板与混凝土楼板组装后的剖视结构示意图;FIG. 3 is a schematic cross-sectional structural diagram of the assembled steel plate and the concrete floor according to the embodiment of the present invention;

图4为本发明实施例单向布置的结构示意图;4 is a schematic structural diagram of a unidirectional arrangement according to an embodiment of the present invention;

图5为本发明实施例双向布置的结构示意图;5 is a schematic structural diagram of a bidirectional arrangement according to an embodiment of the present invention;

图6为本发明实施例钢板的结构示意图;6 is a schematic structural diagram of a steel plate according to an embodiment of the present invention;

图7为本发明实施例钢栓、栓帽和螺母的结构示意图;7 is a schematic structural diagram of a steel bolt, a bolt cap and a nut according to an embodiment of the present invention;

图8(a)~图8(d)为本发明实施例的受力分析图;8(a) to 8(d) are force analysis diagrams of the embodiment of the present invention;

图9为本发明实施例的荷载-挠度曲线图。FIG. 9 is a load-deflection curve diagram of an embodiment of the present invention.

图中:1钢板,2钢栓,3栓帽,4螺母,5混凝土楼板,6开洞部位,7安装孔。In the picture: 1 steel plate, 2 steel bolts, 3 bolt caps, 4 nuts, 5 concrete floor plates, 6 opening parts, 7 mounting holes.

具体实施方式Detailed ways

下面结合说明书附图和具体实施例对本发明作进一步的描述:The present invention will be further described below in conjunction with the accompanying drawings and specific embodiments of the description:

如图1、图2及图3所示,一种加固用钢结构空间体系,包括钢板1,所述钢板包括板顶钢板和板底钢板,所述板顶钢板位于混凝土楼板5的顶面上,所述板底钢板位于混凝土楼板5的底面上,所述板顶钢板和板底钢板在纵向上对齐,所述板顶钢板和板底钢板固定安装在所述混凝土楼板5上开洞部位6的边缘处以实现混凝土楼板5的加固。As shown in Fig. 1, Fig. 2 and Fig. 3, a steel structure space system for reinforcement includes a steel plate 1, the steel plate includes a top steel plate and a bottom steel plate, and the top steel plate is located on the top surface of the concrete floor 5 , the bottom steel plate is located on the bottom surface of the concrete floor 5, the top steel plate and the bottom steel plate are longitudinally aligned, and the top steel plate and the bottom steel plate are fixedly installed on the opening part 6 of the concrete floor 5 The edge of the concrete floor slab 5 can be strengthened.

钢板1和混凝土楼板5通过钢栓2、栓帽3和螺母4进行连接,如图6所示,钢板1上设有供钢栓2穿过的安装孔7,同时,混凝土楼板5上也设有供钢栓2穿过的孔。如图7所示,所述钢栓2为螺柱,螺母4上设有与钢栓2相配合的螺纹,钢栓2同时穿过板顶钢板、混凝土楼板5和板底钢板,并在两端通过螺母4锁紧,栓帽3为钢板1与钢栓2间的锥形连接件,可减少连接处的应力集中现象,所述栓帽3设在与螺母4相对的一侧。The steel plate 1 and the concrete floor 5 are connected by the steel bolt 2, the bolt cap 3 and the nut 4. As shown in FIG. 6, the steel plate 1 is provided with an installation hole 7 for the steel bolt 2 to pass through. There are holes for the steel bolts 2 to pass through. As shown in FIG. 7 , the steel bolt 2 is a stud, and the nut 4 is provided with a thread that matches the steel bolt 2. The steel bolt 2 passes through the top steel plate, the concrete floor 5 and the bottom steel plate at the same time. The ends are locked by the nut 4, and the bolt cap 3 is a conical connecting piece between the steel plate 1 and the steel bolt 2, which can reduce the stress concentration at the connection.

钢板1与混凝土楼板5的连接处设有结构胶,钢栓2与混凝土楼板5之间的缝隙内也填充有结构胶。钢结构空间体系通过结构胶和钢栓2与混凝土楼板5紧密结合,形成共同受力的整体,大幅度地提高了结构承载力和刚度。The connection between the steel plate 1 and the concrete floor 5 is provided with structural glue, and the gap between the steel bolt 2 and the concrete floor 5 is also filled with structural glue. The steel structure space system is closely combined with the concrete floor 5 through structural glue and steel bolts 2 to form a whole under common stress, which greatly improves the bearing capacity and stiffness of the structure.

当混凝土楼板5按单向板设计时,可采用单向布置的钢结构空间体系,所谓单向布置,即钢板沿混凝土楼板5开洞部位6的任意两个相对的边缘横向或者纵向布置,如图4所示;当混凝土楼板按5双向板设计时,可采用双向布置的钢结构空间体系,所谓双向布置,即沿混凝土楼板5开洞部位6的四周同时布置横向和纵向钢板,如图5所示。When the concrete floor 5 is designed as a one-way slab, a steel structure space system with one-way arrangement can be used. As shown in Figure 4; when the concrete floor is designed according to 5 two-way slabs, a two-way layout of the steel structure space system can be used. The so-called two-way layout means that horizontal and vertical steel plates are simultaneously arranged along the circumference of the opening 6 of the concrete floor 5, as shown in Figure 5 shown.

所述钢板1的两端延伸至其所处的混凝土楼板5的端部上,加固用的钢板1优选使用条形钢带。Both ends of the steel plate 1 extend to the ends of the concrete floor 5 where the steel plate 1 is located, and the steel plate 1 for reinforcement is preferably a strip-shaped steel strip.

本实施例的施工方法为,包括以下步骤:The construction method of the present embodiment is, comprising the following steps:

首先进行加固准备:First prepare for reinforcement:

步骤1):将混凝土楼板5待开洞的部位定位,通过查阅图纸及现场勘测,确定混凝土楼板5开洞时截断纵横向钢筋的规格、型号、数量和截面积;Step 1): locate the position where the concrete floor slab 5 is to be opened, and determine the specification, model, quantity and cross-sectional area of the vertical and horizontal reinforcement bars when the concrete floor slab 5 is opened by consulting the drawings and on-site investigation;

步骤2):纵横向均按等强代换的原则,并考虑钢板1钻孔削弱的影响和一定的安全冗余,确定板底钢板的截面积;Step 2): Determine the cross-sectional area of the steel plate at the bottom of the plate according to the principle of equal-strength substitution in both vertical and horizontal directions, taking into account the impact of the weakening of the drilling of the steel plate 1 and a certain safety redundancy;

步骤3):板顶钢板规格和截面积与板底钢板同等配置;Step 3): The specification and cross-sectional area of the top steel plate are the same as those of the bottom steel plate;

步骤4):新增的板底钢板和板顶钢板的两端应伸至混凝土楼板5的端部上。Step 4): Both ends of the newly added bottom steel plate and top steel plate should extend to the end of the concrete floor 5 .

加固准备完成后,进行空间体系的安装:After the reinforcement preparation is completed, install the space system:

步骤5):在开洞部位6外侧50mm~100mm的位置,设置钢板1安装位置的定位线,垂直混凝土楼板5钻孔,孔径比钢栓2直径大4mm~6mm,间距为混凝土板中钢筋间距的1~3倍,一般取150mm~400mm,以保证钻孔过程中不受现有钢筋影响;Step 5): Set the positioning line for the installation position of the steel plate 1 at the position of 50mm to 100mm outside the opening part 6, and drill holes in the vertical concrete floor 5. The diameter of the hole is 4mm to 6mm larger than the diameter of the steel bolt 2, and the spacing is the spacing between the steel bars in the concrete slab. 1 to 3 times the size of the hole, generally 150mm to 400mm, to ensure that the drilling process is not affected by the existing steel bars;

步骤6):打磨混凝土楼板5上需要安装钢板1的位置,使其达到粘贴钢板1的要求;Step 6): polish the position where the steel plate 1 needs to be installed on the concrete floor 5 so as to meet the requirements of pasting the steel plate 1;

步骤7):在开洞部位6周边的楼板顶面和楼板底面均设置钢板1,并在上下两层钢板1间采用若干穿过混凝土楼板5的钢栓2连接,钢板1的截面尺寸、长度与楼板跨度、楼板开洞大小有关,应经过计算确定,以保证钢结构空间体系的抗弯承载力和抗弯刚度均不小于洞口原有混凝土楼板;Step 7): Steel plates 1 are arranged on the top surface of the floor and the bottom surface of the floor around the opening 6, and several steel bolts 2 passing through the concrete floor 5 are used to connect between the upper and lower steel plates 1. The section size and length of the steel plate 1 It is related to the floor span and the size of the floor opening, which should be determined by calculation to ensure that the flexural bearing capacity and flexural rigidity of the steel structure space system are not less than the original concrete floor at the opening;

步骤8):在钢板1上钻孔,以便安装钢栓2,钢板1上钻出的安装孔7与步骤5)中混凝土楼板5上钻出的孔直径和间距相等,在钢板的粘贴面除锈;Step 8): Drill holes on the steel plate 1 to install the steel bolts 2. The installation holes 7 drilled on the steel plate 1 have the same diameter and spacing as the holes drilled on the concrete floor 5 in step 5). rust;

步骤9):配置结构胶,结构胶采用现有的结构胶,按照使用说明进行配置即可;Step 9): configure the structural adhesive, the structural adhesive adopts the existing structural adhesive, and can be configured according to the instructions for use;

步骤10):将结构胶均匀涂抹在粘贴面上,粘贴板底钢板,采用栓帽3将钢栓2与板底钢板连接好,然后向板孔与钢栓2之间注入结构胶,再粘贴板顶钢板,并采用栓帽3连接钢栓2与板顶钢板,形成钢结构空间体系,利用钢结构空间体系对开洞后的混凝土楼板5加固。Step 10): Apply the structural glue evenly on the sticking surface, stick the steel plate at the bottom of the board, use the bolt cap 3 to connect the steel bolt 2 with the steel plate at the bottom of the plate, and then inject the structural glue between the plate hole and the steel bolt 2, and then paste it The roof steel plate, and the bolt cap 3 is used to connect the steel bolt 2 and the roof steel plate to form a steel structure space system, and the concrete floor 5 after the opening is reinforced by the steel structure space system.

下面对本发明的受力情况进行分析,该受力分析以单向布置的空间体系为例进行说明,加固结构形式如图4所示:The force-bearing situation of the present invention is analyzed below. The force-bearing analysis is described by taking the space system arranged in one direction as an example, and the reinforcement structure form is shown in Figure 4:

假设楼板厚度为h,对计算跨度方向(混凝土楼板长度方向)而言,开洞洞口宽度为B,截断主筋截面积为nAs,比较楼板开洞采用本发明进行补强后的承载力变化和刚度变化。Assuming that the thickness of the floor slab is h, for the calculation of the span direction (the length direction of the concrete floor slab), the width of the opening is B, and the cross-sectional area of the truncated main reinforcement is nA s . Stiffness changes.

一、承载力变化:First, the bearing capacity changes:

开洞后楼板抗弯承载力损失约为:The loss of flexural bearing capacity of the floor slab after opening is approximately:

M0=0.85fy·nAs·h0 M 0 =0.85f y ·nA s ·h 0

式中:fy为混凝土楼板5内钢筋的抗拉强度;In the formula: f y is the tensile strength of the steel bars in the concrete floor 5;

h0为混凝土楼板的计算厚度,即板顶至钢筋形心的距离。h 0 is the calculated thickness of the concrete floor, that is, the distance from the top of the slab to the centroid of the steel bar.

采用钢结构空间体系时,钢板型号为-t×b(-表示钢板,t表示厚度,b表示宽度),则洞口两侧板底钢板共两块,可提高承载力为:When using the steel structure space system, the steel plate type is -t×b (- means steel plate, t means thickness, b means width), then there are two steel plates at the bottom of the plate on both sides of the opening, and the bearing capacity can be improved as follows:

Figure BDA0001781835390000061
Figure BDA0001781835390000061

式中:f表示钢板1的抗拉强度。In the formula: f represents the tensile strength of the steel sheet 1 .

二、刚度变化:Second, the stiffness change:

不考虑钢筋的有利作用,被拆除洞口的原有混凝土楼板刚度为:Without considering the beneficial effect of reinforcement, the stiffness of the original concrete floor at the removed opening is:

Figure BDA0001781835390000062
Figure BDA0001781835390000062

式中:Ec为混凝土楼板的弹性模量;where E c is the elastic modulus of the concrete floor;

I0为混凝土楼板的换算截面惯性矩。I 0 is the converted section moment of inertia of the concrete floor.

以钢板1单向布置为例,采用钢结构空间体系时,钢板型号为-b×t,钢板1共四块,则洞口两侧钢板1提供的刚度为:Taking the one-way arrangement of steel plates 1 as an example, when the steel structure space system is used, the steel plate type is -b×t, and there are four steel plates 1 in total, so the stiffness provided by the steel plates 1 on both sides of the opening is:

Figure BDA0001781835390000063
Figure BDA0001781835390000063

式中:Es为钢板的弹性模量;In the formula: E s is the elastic modulus of the steel plate;

I1为钢板构成的空间体系的换算截面惯性矩。I 1 is the converted sectional moment of inertia of the space system composed of steel plates.

三、加固要求:3. Reinforcement requirements:

满足加固后提高的承载力和刚度均不小于拆除洞口的原有混凝土楼板承载力和刚度即可。对于单向板,可仅考虑单个受力方向;对于双向板,应考虑两跨度方向的受力。It suffices that the increased bearing capacity and stiffness after reinforcement are not less than the bearing capacity and stiffness of the original concrete floor slab of the demolished opening. For one-way slabs, only a single direction of force may be considered; for two-way slabs, forces in two span directions should be considered.

即:设置的加固用钢结构空间体系需要满足的条件为:That is, the conditions that need to be met for the set reinforcement steel structure space system are:

M1≥M0M 1 ≥M 0 ;

Es·I1≥Ec·I0 E s ·I 1 ≥E c ·I 0

确定钢板的截面尺寸和长度时,使钢板满足该条件即可。When determining the section size and length of the steel plate, it is sufficient that the steel plate meets this condition.

依然以单向布置的空间体系为例,下面结合本发明的实施效果对本发明作进一步的描述:Still taking the space system of unidirectional arrangement as an example, the present invention will be further described below in conjunction with the implementation effect of the present invention:

一、试验研究:1. Experimental research:

混凝土楼板跨度4200mm,宽度2000mm。采用C30混凝土,板厚120mm,内部配筋10@100(钢筋直径10mm,钢筋间距100mm)。拟开洞宽度1000mm,长度(跨度方向)2000mm,按单向板受力考虑。采用钢结构空间体系进行加固补强,钢板型号为Q235,尺寸为-t×b=-10×150。The concrete floor has a span of 4200mm and a width of 2000mm. C30 concrete is used, the plate thickness is 120mm, and the internal reinforcement is 10@100 (the diameter of the steel bar is 10mm, and the spacing between the steel bars is 100mm). The width of the proposed opening is 1000mm, and the length (span direction) is 2000mm, which is considered according to the force of the one-way plate. The steel structure space system is used for reinforcement and reinforcement. The steel plate type is Q235 and the size is -t×b=-10×150.

(一)计算分析:(1) Calculation analysis:

1.开洞后楼板削弱情况:1. The weakening of the floor after opening:

如图8(a)所示,混凝土楼板抗弯承载力损失约为:As shown in Figure 8(a), the flexural bearing capacity loss of the concrete floor is approximately:

M0=0.85fy·nAs·h0=0.85×300×10×78.5×90=18,015,750N·mmM 0 =0.85f y ·nA s ·h 0 =0.85×300×10×78.5×90=18,015,750N·mm

如图8(b)所示,混凝土楼板抗弯刚度损失约为:As shown in Figure 8(b), the flexural stiffness loss of the concrete floor is approximately:

Figure BDA0001781835390000071
Figure BDA0001781835390000071

2.采用钢结构空间体系进行加固补强,钢板型号为-t×b=-10×120。2. The steel structure space system is used for reinforcement and reinforcement, and the steel plate type is -t×b=-10×120.

如图8(c)所示,开洞部位6两侧钢板(板底共两块钢板)可提高承载力为:As shown in Figure 8(c), the steel plates on both sides of the opening 6 (two steel plates at the bottom of the plate) can improve the bearing capacity as follows:

Figure BDA0001781835390000072
Figure BDA0001781835390000072

如图8(d)所示,钢板板底、板顶共四块,则洞口两侧钢板提供的刚度为:As shown in Figure 8(d), there are four steel plates at the bottom and top of the plate, so the stiffness provided by the steel plates on both sides of the opening is:

Figure BDA0001781835390000073
Figure BDA0001781835390000073

(二)实测数据(2) Measured data

本次试验试件共三件,按单向板考虑,净跨均为4200mm,板宽均为2000mm,板厚120mm。试件A为完好的混凝土楼板;试件B为中心开洞,跨度方向2000mm,板宽方向1000mm,不采取加固措施的混凝土楼板;试件C为在试件B的基础上,采用本发明的钢结构空间体系进行加固补强的混凝土楼板,试件C中采用的加固用钢板型号为Q235,尺寸为-t×b=-10×150。There are three test specimens in this test. Considering the one-way plate, the net span is 4200mm, the plate width is 2000mm, and the plate thickness is 120mm. Specimen A is an intact concrete floor; Specimen B is a concrete floor with a hole in the center, 2000 mm in the span direction and 1000 mm in the width direction of the slab, and no reinforcement measures are taken; Specimen C is based on Specimen B, using the The steel structure space system is reinforced and reinforced concrete floor, the reinforcement steel plate used in specimen C is Q235, and the size is -t×b=-10×150.

采用板顶分级加载的方式,测试三件试件的承载力和挠度变形情况。The load-bearing capacity and deflection deformation of the three specimens were tested by the method of grading loading on the top of the plate.

1.承载力情况如下表所示:1. The bearing capacity is shown in the following table:

试件名称Specimen name 试件ASpecimen A 试件BSpecimen B 试件CSpecimen C 破坏荷载kN/mBreaking load kN/m 16.016.0 10.510.5 35.535.5

2.挠度变形情况如图9所示。2. The deflection deformation is shown in Figure 9.

二、分析结论:2. Analysis conclusion:

通过以上计算分析,采用本发明进行加固补强后,试件C的承载力比未加固的试件B提高了250%,比未开洞的混凝土楼板(试件A)承载力提高了100%;在板原设计荷载作用下(约8kN/m),挠度为试件A的11%,为试件B的42%。承载力和刚度均大于混凝土楼板开洞前,可以满足安全使用要求。Through the above calculation and analysis, after the reinforcement and reinforcement of the present invention, the bearing capacity of the specimen C is increased by 250% compared with the unreinforced specimen B, and the bearing capacity of the concrete floor slab without holes (specimen A) is increased by 100%. ; Under the original design load of the plate (about 8kN/m), the deflection is 11% of that of specimen A and 42% of that of specimen B. The bearing capacity and stiffness are greater than those of the concrete floor before opening, which can meet the requirements of safe use.

双向板受力分析与此雷同,不再赘述。The force analysis of the two-way plate is similar to this and will not be repeated here.

本发明中的结构胶不限于使用实施例中所述的结构胶,还可以采用其他的建筑用胶。The structural adhesive in the present invention is not limited to the structural adhesive described in the embodiments, and other construction adhesives can also be used.

以上所述仅为本发明的较佳实施例而已,并不是本发明的全部实施例,不用以限制本发明,凡在本发明的精神和原则之内,所作的任何修改、等同替换、改进等,均应包含在本发明的保护范围之内。The above are only preferred embodiments of the present invention, not all embodiments of the present invention, and are not intended to limit the present invention. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention , should be included within the protection scope of the present invention.

除说明书所述技术特征外,其余技术特征均为本领域技术人员已知技术,为了突出本发明的创新特点,上述技术特征在此不再赘述。Except for the technical features described in the description, other technical features are known to those skilled in the art, and in order to highlight the innovative features of the present invention, the above technical features are not repeated here.

Claims (3)

1.一种加固用钢结构空间体系的施工方法,其特征是,包括以下步骤:1. a construction method for reinforcing steel structure space system, is characterized in that, comprises the following steps: 步骤1):在混凝土楼板上开洞部位的外侧设置钢板安装位置的定位线;Step 1): Set the positioning line for the installation position of the steel plate on the outside of the opening on the concrete floor; 步骤2):按照所述定位线在混凝土楼板的顶面和底面均设置钢板,楼板顶面的钢板为板顶钢板,楼板底面的钢板为板底钢板;Step 2): according to the positioning line, steel plates are arranged on both the top surface and the bottom surface of the concrete floor slab, the steel plate on the top surface of the floor slab is the top steel plate, and the steel plate on the bottom surface of the floor slab is the slab bottom steel plate; 步骤3):通过刚性连接装置将板顶钢板、混凝土楼板和板底钢板固连为一体;Step 3): The top steel plate, the concrete floor and the bottom steel plate are fixedly connected into one through a rigid connection device; 所述板顶钢板、混凝土楼板和板底钢板之间通过钢栓和结构胶相连接,连接方法包括以下步骤:The top steel plate, the concrete floor and the bottom steel plate are connected by steel bolts and structural glue, and the connection method includes the following steps: 步骤a:在混凝土楼板上需要安装钢板的位置钻孔,在钢板上也钻出相同直径和间距的孔;Step a: Drill holes on the concrete floor where the steel plate needs to be installed, and drill holes with the same diameter and spacing on the steel plate; 步骤b:打磨混凝土楼板上需要安装钢板的位置,使其达到粘贴钢板的要求;Step b: Polish the position where the steel plate needs to be installed on the concrete floor so that it meets the requirements for sticking the steel plate; 步骤c:在钢板的粘贴面除锈;Step c: rust removal on the sticking surface of the steel plate; 步骤d:粘贴板底钢板,采用锥形栓帽将钢栓与板底钢板连接好,然后向钢栓与混凝土楼板上安装钢栓的孔之间注入结构胶,再粘贴板顶钢板,并采用栓帽连接钢栓与板顶钢板,所述栓帽为钢板与钢栓间的锥形连接件,外表设有花纹或者螺纹。Step d: Paste the bottom steel plate of the slab, connect the steel bolt with the bottom steel plate by using the conical bolt cap, then inject structural glue between the steel bolt and the hole where the steel bolt is installed on the concrete floor, and then paste the top steel plate, and use The bolt cap connects the steel bolt and the top steel plate, the bolt cap is a conical connecting piece between the steel plate and the steel bolt, and the outer surface is provided with patterns or threads. 2.根据权利要求1所述的施工方法,其特征是,所述定位线位于混凝土楼板上开洞部位的外侧50mm~100mm的位置。2 . The construction method according to claim 1 , wherein the positioning line is located at a position 50 mm to 100 mm outside the opening on the concrete floor. 3 . 3.根据权利要求1所述的施工方法,其特征是,所述步骤a中,在混凝土楼板上钻孔的孔径比钢栓的直径大4mm~6mm,间距为混凝土楼板中钢筋间距的1~3倍。3. construction method according to claim 1 is characterized in that, in described step a, the hole diameter of the hole in the concrete floor is larger than the diameter of the steel bolt by 4mm~6mm, and the spacing is 1~6mm of the spacing between steel bars in the concrete floor 3 times.
CN201810995893.6A 2016-04-15 2016-04-15 Construction method of steel structure for reinforcement Expired - Fee Related CN109057392B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810995893.6A CN109057392B (en) 2016-04-15 2016-04-15 Construction method of steel structure for reinforcement

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN201810995893.6A CN109057392B (en) 2016-04-15 2016-04-15 Construction method of steel structure for reinforcement
CN201610237156.0A CN105863289B (en) 2016-04-15 2016-04-15 A kind of reinforce uses steel construction three-dimensional system and its construction method

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
CN201610237156.0A Division CN105863289B (en) 2016-04-15 2016-04-15 A kind of reinforce uses steel construction three-dimensional system and its construction method

Publications (2)

Publication Number Publication Date
CN109057392A CN109057392A (en) 2018-12-21
CN109057392B true CN109057392B (en) 2020-09-18

Family

ID=56633199

Family Applications (2)

Application Number Title Priority Date Filing Date
CN201610237156.0A Expired - Fee Related CN105863289B (en) 2016-04-15 2016-04-15 A kind of reinforce uses steel construction three-dimensional system and its construction method
CN201810995893.6A Expired - Fee Related CN109057392B (en) 2016-04-15 2016-04-15 Construction method of steel structure for reinforcement

Family Applications Before (1)

Application Number Title Priority Date Filing Date
CN201610237156.0A Expired - Fee Related CN105863289B (en) 2016-04-15 2016-04-15 A kind of reinforce uses steel construction three-dimensional system and its construction method

Country Status (1)

Country Link
CN (2) CN105863289B (en)

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106592995B (en) * 2016-11-01 2018-10-26 中国建筑第八工程局有限公司 Open the installation method of overarm steel construction stress system
CN107338861B (en) * 2016-11-22 2019-08-02 浙江绿筑集成科技有限公司 The method for improving staggered truss chord member part anti-bending bearing capacity
CN107100376A (en) * 2017-04-15 2017-08-29 福州大学 Superstructure reinforcing device and its construction method
CN108678417B (en) * 2018-07-31 2023-07-21 天津市建筑设计院 Steel construction floor reforms transform node
CN110284728B (en) * 2019-07-19 2023-12-29 华侨大学 Slab-column structure floor reinforcing structure capable of preventing impact cutting damage and construction method thereof
CN112431436B (en) * 2020-12-14 2022-10-21 东莞理工学院 A construction method for punching shear reinforcement of beamless floor

Family Cites Families (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2819103B2 (en) * 1995-11-27 1998-10-30 ショーボンド建設株式会社 How to attach steel plates to concrete structures
KR20070056331A (en) * 2005-11-29 2007-06-04 재단법인 포항산업과학연구원 Wall structure extension system of building and its construction method
CN103321444B (en) * 2013-06-14 2015-09-09 罗海军 Concrete floor reinforced construction method
CN103628698B (en) * 2013-12-09 2015-11-25 中国建筑一局(集团)有限公司 Construction method for opening prestressed floor slab in structural reinforcement engineering
CN104179364B (en) * 2014-07-24 2016-06-29 北京筑福国际工程技术有限责任公司 Punch after a kind of shear wall ruggedized construction and construction method thereof
CN104763161B (en) * 2014-09-24 2017-05-31 温州振华建设有限公司 Punched after a kind of reinforced concrete floor and add the construction method of beam reinforced structure
CN204703495U (en) * 2015-04-01 2015-10-14 广东合迪科技股份有限公司 Aluminum alloy pattern plate back cord system
CN205476581U (en) * 2016-04-15 2016-08-17 山东省建筑科学研究院 Consolidate and use steel construction three -dimensional system

Also Published As

Publication number Publication date
CN105863289A (en) 2016-08-17
CN105863289B (en) 2018-10-02
CN109057392A (en) 2018-12-21

Similar Documents

Publication Publication Date Title
CN109057392B (en) Construction method of steel structure for reinforcement
CN209482113U (en) A simply supported I-shaped composite beam that can be quickly reinforced
CN102635060B (en) Concrete hollow slab bridge reinforced by transverse steel beam
CN101851970B (en) Horizontal seamed energy dissipation prestressed shear wall structure
CN204252286U (en) A kind of rectangular steel-tube concrete column-steel beam connecting joint
CN101328753A (en) A Fiber Reinforced Composite Material-Concrete Composite Beam
CN106522382A (en) Fabricated concrete-filled steel tube column-H type steel beam self-resetting energy consumption connection joint
CN108442514A (en) Add the assembled flexible concrete frame node structure of concealed damper
CN103195170A (en) Prefabricated reinforced concrete frame structure system
CN104727441A (en) Prestress assembled concrete beam column joint structure and construction method thereof
CN107338864A (en) Prefabricated reinforced concrete frame structure node
CN104499608B (en) The design and construction method of prestressing force section steel reinforcement shear wall
CN110258289A (en) Prestressed concrete continuous box girder bridge laterally spells wide structure
CN102535749A (en) Double-function multi-cavity steel tube concrete column provided with soft steel sleeve at bottom, and manufacturing method thereof
CN103485287A (en) Prestressed application method in concrete frame box culvert construction
CN209555782U (en) A truss I-beam composite cover beam hoop construction support
CN207673039U (en) A kind of floor plate reinforcement structure
CN104631318A (en) Bridge deck slab transverse unequal-strength steel-concrete combined bridge deck system and construction method thereof
CN109339237A (en) A steel beam-concrete column self-reset energy dissipation joint
CN108265855A (en) Reinforced concrete shear wall and its frame with anchor steel Shear Strengthening
CN107386483A (en) Curved scissors separates control type assembling-type metal damper
CN208762895U (en) Hinge seam bracing means
CN205476581U (en) Consolidate and use steel construction three -dimensional system
CN208604499U (en) Limit the built-in concrete beam bridge steel reinforced concrete anchoring piece of Local Cracking
CN105735666A (en) Method for reinforcing concrete column rapidly

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20200918

CF01 Termination of patent right due to non-payment of annual fee