CN106592995B - Open the installation method of overarm steel construction stress system - Google Patents
Open the installation method of overarm steel construction stress system Download PDFInfo
- Publication number
- CN106592995B CN106592995B CN201610939179.6A CN201610939179A CN106592995B CN 106592995 B CN106592995 B CN 106592995B CN 201610939179 A CN201610939179 A CN 201610939179A CN 106592995 B CN106592995 B CN 106592995B
- Authority
- CN
- China
- Prior art keywords
- overarm
- steel
- sides
- installation method
- stress system
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G23/00—Working measures on existing buildings
- E04G23/02—Repairing, e.g. filling cracks; Restoring; Altering; Enlarging
- E04G23/0218—Increasing or restoring the load-bearing capacity of building construction elements
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Chemical & Material Sciences (AREA)
- Chemical Kinetics & Catalysis (AREA)
- Electrochemistry (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
The invention discloses the installation methods of a kind of overarm steel construction stress system, including step:A. need to be transformed be mounted at the top of building structure both sides to support steel beam;B. channel steel is installed between the top of the pairs of support steel beam in the both sides;C. it is fixedly connected with one in the downward vertical channel steel direction of the channel steel and hangs drawing girder steel;D. in the bottom installation overarm for hanging drawing girder steel;E. the lower section that drawing girder steel is hung at this lifts steelframe.Step e includes being respectively fixedly connected with sunpender at the overarm both sides for drawing steel beam bottom hanging, and hang drawing by the sunpender and install the steelframe.This overarm is made of interior card overarm and both sides overarm, and interior card overarm is connected respectively by branch sleeve and both sides overarm.The both sides overarm end is each passed through corresponding support steel beam, interior card overarm bending place and hangs and draws steel beam bottom alignment and fixation.
Description
Technical field
The present invention relates to the installation methods of a kind of overarm steel construction stress system, more particularly to one kind being based on building renovation
The installation method of the overarm steel construction stress system of engineering.
Background technology
Social progress and development promote the transformation of building and reinforcing engineering to be on the increase, and building renovation and reinforcing engineering
In Steel Structure Installation it is also more and more important, it is more and more common.Current building is reinforced in improvement project, is built due to that need to be transformed
The original structure built, common lifting machine can be by larger restrictions to the installation of steel construction;If setting up scaffold etc. to steel knot
Structure is installed, and not only the construction time is long, but also expends a large amount of manpower and materials.Therefore, it is necessary to a kind of convenient and accurately push up
Portion's Steel Structure Installation construction method.
Invention content
Technical problem to be solved by the invention is to provide the installation methods of a kind of overarm steel construction stress system, eliminate
The influence of building original structure, convenient accurate installation top steel construction need to be transformed.
To realize above-mentioned technique effect, the invention discloses the installation methods of a kind of overarm steel construction stress system, use
To carry out strengthening reconstruction, including step to building structure need to be transformed:
A. need to be transformed be mounted at the top of building structure to support steel beam;
B. channel steel is installed between the top of the pairs of support steel beam;
C. it is fixedly connected with one in the downward vertical channel steel direction of the channel steel and hangs drawing girder steel;
D. the installation overarm between this hangs the support steel beam for drawing the bottom of girder steel pairs of;
E. the lower section that drawing girder steel is hung at this lifts steelframe.
The improvement that the present invention opens the installation method of overarm steel construction stress system is that pairs of support steel beam is horizontal respectively
The top of building structure both sides need to be transformed by being fixedly mounted on;Channel steel is that level is fixedly mounted on the pairs of supporting steel back in the both sides
Between portion, and it is vertical with the channel steel.
The present invention open the installation method of overarm steel construction stress system further improvement lies in that, overarm both ends part
It Chuan Guo not support steel beam;This overarm is made of interior card overarm and both sides overarm connection, that is, has the end of both sides overarm
Portion is each passed through corresponding girder steel supported on both sides.
The present invention open the installation method of overarm steel construction stress system further improvement lies in that, interior card overarm both ends
Portion is correspondingly connected with by branch sleeve and the one end of both sides overarm respectively.
The present invention open the installation method of overarm steel construction stress system further improvement lies in that, hanging draw girder steel lower section
The step of lifting steelframe further comprises:
Sunpender is fixedly mounted respectively at the overarm both sides for drawing steel beam bottom hanging;
And drawing installation steelframe is hung by the sunpender.
The present invention open the installation method of overarm steel construction stress system further improvement lies in that, hang draw steel beam bottom
Overarm is fixedly connected with branch sleeve respectively at both sides, and sunpender is then penetrated to hang by screw thread and helps pull a cart cylinder and tighten company with cylinder of helping pull a cart is hung
It connects, is thus fixedly mounted on sunpender and hangs drawing steel beam bottom.
The present invention open the installation method of overarm steel construction stress system further improvement lies in that, overarm with hang drawing girder steel
Be fixedly connected, and overarm and hang draw girder steel between stiffener is installed.
The present invention opens in the installation method of overarm steel construction stress system, and support steel beam is I-steel, and both sides overarm is
It is each passed through the web of support steel beam, and stiffener, the company of enhancing overarm and support steel beam are fixed respectively in the web both sides
Connect reliability.
The installation method of above-mentioned steel construction stress system, it is easy for construction, and keep steel structure system harder by an overarm
Gu not only saving the time, but also it is avoided that a large amount of scaffolds of setting up install existing security risk when steel construction.
Description of the drawings
Fig. 1 is the schematic diagram that channel steel is fixedly mounted in the installation method of the invention for opening overarm steel construction stress system;
Fig. 2 is the schematic diagram of support steel beam in the installation method of the invention for opening overarm steel construction stress system;
Fig. 3 is to hang the schematic diagram for drawing steel girder erection in the installation method of the invention for opening overarm steel construction stress system;
Fig. 4 is the schematic diagram of an overarm installation in the installation method of the invention for opening overarm steel construction stress system;
Fig. 5, which hangs oneself from a beam and hangs drawing girder steel for interior card in the installation method of the present invention overarm steel construction stress system and fix, to be connected
The schematic diagram connect;
Fig. 6 is that overarm one section of portion in both sides passes through supporting steel in the installation method of the invention for opening overarm steel construction stress system
The schematic diagram of beam;
Fig. 7 is the schematic diagram of the installation method middle hanger and steelframe installation of the present invention overarm steel construction stress system;
Fig. 8 is the fixed schematic diagram of installation method middle hanger of the present invention overarm steel construction stress system;
Fig. 9 is the installation method schematic diagram that installation is complete of the present invention overarm steel construction stress system;
Figure 10 is the installation method schematic top plan view that installation is complete of the present invention overarm steel construction stress system.
Specific implementation mode
Below in conjunction with the accompanying drawings and specific implementation mode the present invention is described in further detail.
The installation method that the present invention opens overarm steel construction stress system is mainly used in the reinforcing and improvement project of building.
The present invention opens the installation method of overarm steel construction stress system, as depicted in figs. 1 and 2, building need to be transformed first
Support steel beam 2, and the water between the top of girder steel 2 supported on both sides are fixed in the top of 1 both sides of structure by the way that anchor bolt 18 is horizontal respectively
Flat fixation is welded to connect channel steel 3, and 3 vertical support girder steel 2 of channel steel.In conjunction with Fig. 3, after the completion of channel steel 3 is welded and fixed, in channel steel 3
Bottom installation, which is hung, draws girder steel 4.When drawing girder steel 4 is hung in installation, the mode for first passing through surveying setting-out draws girder steel 4 fixed on channel steel 3 to hanging
Position, and the position hung and draw girder steel 4 is marked, then a cloth bag 5 is set in hang and is drawn outside girder steel 4, and two are used by truck crane 6
Cloth bag 5 is lifted to the marked locations hung and draw girder steel 4 on channel steel 3 by the mode of point lifting, will hang drawing steel in cloth bag 5 later
Beam 4, which is fixedly welded on channel steel 3, hangs oneself and draws the marked locations of girder steel 4, wherein the bottom for hanging the top and the channel steel 3 that draw girder steel 4 is solid
Surely it is welded to connect, thus completes to hang the installation for drawing girder steel 4.
As shown in Figures 4 to 6, it hangs and draws girder steel 4 after installation is complete, truck crane 6 passes through the automobile still in working condition
It hangs 6 and carries out an installation for overarm 7.Releasing control line in the bottom for hanging drawing girder steel 4 first, (this is this field routine techniques, in figure
It is not shown), which is two-wire, and spacing is equal to a diameter for overarm 7 between the bilinear con- trol line;Then drawing steel is being hung
Bottle gouard moved by hands 8 is installed in the bottom of beam 4, by truck crane 6 by 70 lifting of interior card overarm, later by interior card overarm 70 and manually
Cucurbit 8 connects, and interior card overarm 70 is promoted by bottle gouard moved by hands 8, and carry out position adjusting to an overarm 70, until interior card is outstanding
The bending place of beam 70 and hanging draw the bottom of girder steel 4 against and ensureing interior card overarm 70 in bilinear con- trol line, at this point, automobile
Hang 6 and bottle gouard moved by hands 8 be in tension.Then both sides overarm 71 is worn out of support steel beam 2 reserved opening respectively
It crosses, and the one end of the both sides overarm 71 is connect by branch sleeve 9 with the both ends of interior card overarm 70 respectively, herein
It is adjusted mutually in connection procedure, final connection ensures the bending place of interior card overarm 70 and hangs the bottom pair for drawing girder steel 4 when completing
Quasi- is aligned at the bending place of both sides overarm 71 and the reserved opening of support steel beam 2.After the completion of position is adjusted, it will hang and draw girder steel 4
Bottom and interior card overarm 70 bending place be welded and fixed, and close to the place of the being welded and fixed both sides hanging draw girder steel 4 and in
Between be welded and fixed stiffener 10 between overarm 70, enhancing overarm 7 with hang the connection reliability for drawing girder steel 4.
In a preferred embodiment, support steel beam 2 is I-steel, and the reserved opening of support steel beam 2 is set on its web
It sets, both sides overarm 71 passes through the reserved opening on 2 web of support steel beam, and ensures bending place and the support of both sides overarm 71
The reserved opening of girder steel 2 is aligned, i.e., is aligned with the web of support steel beam 2.Then at reserved opening support steel beam 2 web two
Stiffener 11 is respectively set in side, and fixation is respectively welded in the web both sides of the stiffener 11 and support steel beam 2, at this time both sides overarm
71 pass through the stiffener 11, and the gap between both sides overarm 71 and stiffener 11 is filled up by weld seam.The stiffener 11
The effectively connection reliability of enhancing overarm 7 and support steel beam 2.
After the completion of opening 7 lifting of overarm, as shown in Figure 7 to 9, the installation of sunpender 12 is carried out.It hangs and the bottom of girder steel 4 is drawn to fix
It is welded with two and hangs cylinder 13 of helping pull a cart, this hangs the both sides that cylinder 13 of helping pull a cart is located at interior card overarm 70, this hangs inside cylinder 13 of helping pull a cart
Equipped with screw thread, sunpender 12 also is provided with screw thread with hanging on the outside of the one end that cylinder 13 is connect of helping pull a cart, the screw thread in 12 outside of sunpender with
The line for hanging 13 inside spiral shell of cylinder of helping pull a cart matches.12 one end of sunpender, which penetrates, to be hung and helps pull a cart cylinder 13, and is hung cylinder 13 of helping pull a cart with this and twisted
It fastens, completes the installation of sunpender 12, then carry out the lifting of steelframe 14.Welding four is hung first on four angles of steelframe 14
Point is hung four suspension centres for drawing steelframe 14 by bottle gouard moved by hands, and adjusts steelframe 14, so that steelframe 14 is located at its setting position, will be hung
Bar 12 passes through steelframe 14 and tightens fixation with nut, completes the lifting of steelframe 14.Then steel pipe inclined ladder 16 is set up, the steel pipe is passed through
Steel plate 17 is transported to the top surface of steelframe 14 by inclined ladder 16, and carries out the installation of steel plate 17, thus completes entirely overarm steel construction
The installation of stress system.Figure 10 is the invention overarm steel construction stress system installation method top plan view that installation is complete signal
Figure.
The present invention opens in the installation method of overarm steel construction stress system, and both sides 71 ends of overarm are equipped with external screw thread, in
Between the both ends of overarm 70 also be provided with external screw thread, the both sides 71 end external screw threads of overarm and interior card are hung oneself from a beam 70 both ends
External screw thread is matched with 9 internal thread of branch sleeve, and the both sides overarm 71 and interior card overarm 70 are tightened with branch sleeve 9 respectively
It is fixed, and mutually adjusted in this tightens fixation procedure, guarantee tighten it is fixed when completing, the bending place of interior card overarm 70 with hang
The bottom alignment of girder steel 4 is drawn, is aligned at the bending place of both sides overarm 71 and the reserved opening of support steel beam 2, in realizing
Between overarm 70 and both sides hang oneself from a beam and 71 be fixedly connected.
The present invention opens the installation method of overarm steel construction stress system, simple operation, and an overarm makes entire steel construction more
Add sturdy and durable, to be built after extension transformation usage time;It is original since building need to be transformed during basic solution building renovation
The problem of structure impacts lifting machine use.
Claims (8)
1. the installation method of a kind of overarm steel construction stress system, to carry out strengthening reconstruction to building structure need to be transformed,
It is characterized in that, including step:
A. need to be transformed be mounted at the top of building structure to support steel beam;
B. channel steel is installed between the top of the pairs of support steel beam;
C. it is fixedly connected with one in the downward vertical channel steel direction of the channel steel and hangs drawing girder steel;
D. installation overarm between the bottom and pairs of support steel beam of drawing girder steel is hung described;
E. the lower section of girder steel is drawn to lift steelframe in described hang.
2. the installation method of overarm steel construction stress system as described in claim 1, it is characterised in that:The pairs of branch
Support girder steel is respectively and fixedly installed to that the top of building structure both sides need to be transformed;The channel steel is fixedly mounted on described in both sides pairs of
Between at the top of support steel beam.
3. the installation method of overarm steel construction stress system as described in claim 1, it is characterised in that:Described overarm
Both ends are each passed through the pairs of support steel beam.
4. the installation method of the overarm steel construction stress system as described in claim 1 or 3, it is characterised in that:Described outstanding
Beam is made of interior card overarm and both sides overarm connection, and the end of the both sides overarm is each passed through corresponding supporting steel
Beam.
5. the installation method of overarm steel construction stress system as claimed in claim 4, it is characterised in that:The interior card is outstanding
The both ends of beam are correspondingly connected with by branch sleeve and the one end of the both sides overarm respectively.
6. the installation method of overarm steel construction stress system as described in claim 1, which is characterized in that hang drawing steel described
The step of lower section lifting steelframe of beam, further comprises:
Sunpender is fixedly mounted respectively at the overarm both sides for drawing steel beam bottom in described hang;
Drawing is hung by the sunpender, and the steelframe is installed.
7. the installation method of overarm steel construction stress system as claimed in claim 6, it is characterised in that:It is described to hang drawing girder steel
It is fixedly connected with branch sleeve respectively at the overarm both sides of bottom, the sunpender is fixedly mounted on by hanging cylinder of helping pull a cart hangs respectively
Draw steel beam bottom.
8. the installation method of overarm steel construction stress system as described in claim 1, it is characterised in that:Described overarm with
It is described hang draw girder steel be fixedly connected, and described overarm and it is described hang draw girder steel between stiffener is installed.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610939179.6A CN106592995B (en) | 2016-11-01 | 2016-11-01 | Open the installation method of overarm steel construction stress system |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610939179.6A CN106592995B (en) | 2016-11-01 | 2016-11-01 | Open the installation method of overarm steel construction stress system |
Publications (2)
Publication Number | Publication Date |
---|---|
CN106592995A CN106592995A (en) | 2017-04-26 |
CN106592995B true CN106592995B (en) | 2018-10-26 |
Family
ID=58589605
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610939179.6A Active CN106592995B (en) | 2016-11-01 | 2016-11-01 | Open the installation method of overarm steel construction stress system |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106592995B (en) |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113107092B (en) * | 2021-03-29 | 2022-11-22 | 中铁十二局集团建筑安装工程有限公司 | Overhung conversion construction method for super high-rise steel structure |
Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH09242183A (en) * | 1996-03-11 | 1997-09-16 | Tomoe Corp | Earthquake-resistant frame structure |
JP2000336748A (en) * | 1999-05-25 | 2000-12-05 | Koichi Tanaka | Erection method of two-story house |
GB2403230A (en) * | 2003-06-26 | 2004-12-29 | Harvey Peter | Principal roof truss for loft conversion |
CN201908448U (en) * | 2010-07-28 | 2011-07-27 | 上海同华加固工程有限公司 | Novel shock-proof reinforced steel pull rod |
CN102864875A (en) * | 2012-10-11 | 2013-01-09 | 北京筑福建设工程有限责任公司 | A-shaped roof truss steel rod structure system and construction method thereof |
CN102936968A (en) * | 2012-11-15 | 2013-02-20 | 北京筑福建设工程有限责任公司 | Inner steel frame reinforced structure of pseudo-classic architecture and construction method thereof |
CN203430059U (en) * | 2013-08-22 | 2014-02-12 | 中国十七冶集团有限公司 | Temporary fixing device used for installing large-span steel structure roof primary truss |
CN203603522U (en) * | 2013-10-12 | 2014-05-21 | 北京筑福国际工程技术有限责任公司 | Steel frame concrete structure used for transforming inner portion of old factory building in floor adding mode |
CN105863289A (en) * | 2016-04-15 | 2016-08-17 | 山东省建筑科学研究院 | Steel structure spatial system for reinforcement and construction method thereof |
-
2016
- 2016-11-01 CN CN201610939179.6A patent/CN106592995B/en active Active
Patent Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH09242183A (en) * | 1996-03-11 | 1997-09-16 | Tomoe Corp | Earthquake-resistant frame structure |
JP2000336748A (en) * | 1999-05-25 | 2000-12-05 | Koichi Tanaka | Erection method of two-story house |
GB2403230A (en) * | 2003-06-26 | 2004-12-29 | Harvey Peter | Principal roof truss for loft conversion |
CN201908448U (en) * | 2010-07-28 | 2011-07-27 | 上海同华加固工程有限公司 | Novel shock-proof reinforced steel pull rod |
CN102864875A (en) * | 2012-10-11 | 2013-01-09 | 北京筑福建设工程有限责任公司 | A-shaped roof truss steel rod structure system and construction method thereof |
CN102936968A (en) * | 2012-11-15 | 2013-02-20 | 北京筑福建设工程有限责任公司 | Inner steel frame reinforced structure of pseudo-classic architecture and construction method thereof |
CN203430059U (en) * | 2013-08-22 | 2014-02-12 | 中国十七冶集团有限公司 | Temporary fixing device used for installing large-span steel structure roof primary truss |
CN203603522U (en) * | 2013-10-12 | 2014-05-21 | 北京筑福国际工程技术有限责任公司 | Steel frame concrete structure used for transforming inner portion of old factory building in floor adding mode |
CN105863289A (en) * | 2016-04-15 | 2016-08-17 | 山东省建筑科学研究院 | Steel structure spatial system for reinforcement and construction method thereof |
Also Published As
Publication number | Publication date |
---|---|
CN106592995A (en) | 2017-04-26 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101858057B (en) | Method for rapidly mounting reinforced concrete crash barrier steel form | |
CN104895197B (en) | A kind of profile steel concrete column reinforced beam joint connecting method | |
CN103123016B (en) | Construction method for laying gas pipelines along bridge | |
CN102071644A (en) | Lifting installation method of integral bridge arch rib | |
CN103264968A (en) | Super high-rise core tube internal and external hanging tower crane support beam structure and construction method thereof | |
CN109538242A (en) | Building method of tunnel construction formwork support | |
CN107313360A (en) | Overhead cable formula is without support bearing replacement operating platform | |
CN106592995B (en) | Open the installation method of overarm steel construction stress system | |
CN205036070U (en) | Device is set up in complete pre -buried installation of cantilever frame roof beam side | |
CN109869153A (en) | The whole of rapid construction vertical shaft lining cutting promotes cantilever form device and construction method | |
CN106284103A (en) | Steel reinforced concrete combination beam roof steel bar concrete high-altitude cantilever pouring construction method | |
CN207191310U (en) | One kind is used for ship plank construction portable unit | |
CN206986741U (en) | A kind of Cast-in-situ Beam wing plate integral support support | |
CN206667042U (en) | Bridge expanssion joint installation and adjustment instrument | |
CN208516837U (en) | One kind is for borehole filling pile cage of reinforcement overlapped hanging apparatus | |
CN107201725A (en) | A kind of steel box-girder decoration hanging scaffold and its construction method | |
CN209277521U (en) | A kind of builder's jack support construction | |
CN104372746B (en) | The prefabricated post stretching Simple T-Girders note concrete form support of railroad bridge and mounting process thereof | |
CN206828977U (en) | A kind of steel box-girder decoration hanging scaffold | |
CN206693663U (en) | A kind of strengthening of steel bridge special purpose device | |
CN205476391U (en) | Builder's jack | |
CN209308379U (en) | A kind of driven hanging basket balance weight mechanism | |
CN209367607U (en) | A kind of mounting structure that people's goods elevator attached wall lengthening rods are fixed | |
CN206646838U (en) | Self-interacting type steel plate wall corrects trivet | |
CN106285017B (en) | Thermal control boiler steel vertical shaft installation method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |