CN108755358A - A kind of construction method on bank protection grinding coagulation dirt road road - Google Patents

A kind of construction method on bank protection grinding coagulation dirt road road Download PDF

Info

Publication number
CN108755358A
CN108755358A CN201810590541.2A CN201810590541A CN108755358A CN 108755358 A CN108755358 A CN 108755358A CN 201810590541 A CN201810590541 A CN 201810590541A CN 108755358 A CN108755358 A CN 108755358A
Authority
CN
China
Prior art keywords
concrete
bank protection
road
laid
base soil
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
CN201810590541.2A
Other languages
Chinese (zh)
Inventor
金波
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201810590541.2A priority Critical patent/CN108755358A/en
Publication of CN108755358A publication Critical patent/CN108755358A/en
Withdrawn legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C19/00Machines, tools or auxiliary devices for preparing or distributing paving materials, for working the placed materials, or for forming, consolidating, or finishing the paving
    • E01C19/48Machines, tools or auxiliary devices for preparing or distributing paving materials, for working the placed materials, or for forming, consolidating, or finishing the paving for laying-down the materials and consolidating them, or finishing the surface, e.g. slip forms therefor, forming kerbs or gutters in a continuous operation in situ
    • E01C19/4806Machines, tools or auxiliary devices for preparing or distributing paving materials, for working the placed materials, or for forming, consolidating, or finishing the paving for laying-down the materials and consolidating them, or finishing the surface, e.g. slip forms therefor, forming kerbs or gutters in a continuous operation in situ with solely rollers for consolidating or finishing
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C7/00Coherent pavings made in situ
    • E01C7/08Coherent pavings made in situ made of road-metal and binders
    • E01C7/32Coherent pavings made in situ made of road-metal and binders of courses of different kind made in situ
    • E01C7/325Joining different layers, e.g. by adhesive layers; Intermediate layers, e.g. for the escape of water vapour, for spreading stresses
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A30/00Adapting or protecting infrastructure or their operation
    • Y02A30/60Planning or developing urban green infrastructure

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Revetment (AREA)

Abstract

The invention discloses a kind of construction methods on bank protection grinding coagulation dirt road road, include the following steps:Preparation of construction, surveying and locating, base soil dispensing, base soil is laid with, base soil rolls, template construct and installation, prepares that mortar, screed and blotter are laid with, concrete cast, template takes out and late maintaining, the construction method is by sprinkling water in advance to bank protection, so that bank protection surface is easier and the consolidation of change, the support degree for improving concrete, prevents concrete road from collapsing;The construction method is by the way that mortar to be filled in the gap of rubble so that metalling is firmer, is laid with to road by multiple techniques, improves the intensity of concrete road, and the service life on bank protection grinding coagulation dirt road road can be improved by this method.

Description

A kind of construction method on bank protection grinding coagulation dirt road road
Technical field
The invention belongs to the realm of building construction, and in particular to a kind of construction method on bank protection grinding coagulation dirt road road.
Background technology
This building of bank protection is also commonly known as shore protection.The form of shore protection has directly protection and protection indirectly.Directly protect That Riparian buffers are directly reinforced, with resist flow wash away and scour.Common jackstone, dry-laid rubble, mortar flag stone, stone The builds such as cage and fascine.Protection is suitable for the section that riverbed is wider or protection length is larger indirectly, can build groynes, longitudinal dike and lattice Dam etc., flow is chosen from riverbank.It can be generally divided into two kinds according to the function of bank protection:1 is only the slope surface guarantor of weathering resistance and antiscour Nurse, the protection work are not subject to soil lateral pressure, and such as shotcrete bank protection, gridiron plant growing protection slope, plant growing protection slope etc. belongs to such, It is only applicable in side slope that is gentle and stablizing fricton-tight anxiety.2 provide the earth-retaining bank protection of skid resistance, can substantially divide into:(a) just Property dead-weight retaining wall is (such as:Masonry retaining wall, gravity retaining wall lean on wall type retaining wall, cantilever retaining wall, buttress type gear Cob wall), (b) flexible dead-weight retaining wall is (such as:Gabion retaining wall, crib retaining wall, formula of putting more energy into retaining wall), (c) anchor is pull-type Retaining wall is (such as:The pull-type lattice beam retaining wall of anchor, the pull-type campshed retaining wall of anchor).
Existing bank protection mostly uses the method for being directly laid with concrete, causes bank protection service life short, protect in construction Ability is poor, for this purpose, proposing a kind of construction method on bank protection grinding coagulation dirt road road.
Invention content
The purpose of the present invention is to provide a kind of construction methods on bank protection grinding coagulation dirt road road, to solve above-mentioned background skill The existing bank protection proposed in art mostly uses the method for being directly laid with concrete, causes bank protection service life short, prevent in construction The poor problem of shield ability.
To achieve the above object, present invention employs following technical solutions:
A kind of construction method on bank protection grinding coagulation dirt road road, includes the following steps:
S1, preparation of construction are marched into the arena road using two sides, are excavated and are built lower foundation pit temporary road, when as concrete construction The main construction road of the transport of materials such as template, concrete;
S2, surveying and locating, bank protection working face come out after, side slope carry out line setting, make the spats position line and Platform slope angle line;
S3, base soil dispensing carry out preparing base soil using clay mixing lime, and clay is 6 with lime ratio:1 prepares;
S4, base soil are laid with, and are sprinkled water first to bank protection so that and watering amount is 1-1.5L in every square metre of bank protection area, Then natural drying is carried out, humidity is measured to bank protection soil every 6-10 hours, when humidity is 26-35%, by base soil It is uniformly laid on bank protection so that base soil thickness reaches 14-17cm;
S5, base soil roll, and base soil is carried out surface and vibrated using plane equipment of vibrating, and is surveyed to the base soil after vibrating Measure the degree of packing so that the base soil degree of packing is 1-3MPa;
S6, template construct and installation, vertical framework use 12 channel steel Supreme Being of standard type, cross form to use the steel plate of 6mm thickness It makes, the making length of cross form is 984-994mm, and template is installed in strict accordance with the construction line-putting position and elevation, utilizes dike The straight guarantee plate stitch for pushing up and carrying foot stake hanging wire calibration template is straight;
S7, mortar is prepared, mortar ingredient is:Cement is 7-12%, and quick lime 10-16%, surplus is sand;
S8, screed and blotter are laid with, and are laid with blotter first, blotter can be used grain size 7-50mm's Gravel or rubble, metalling laying depth is 10-15cm, then mortar is laid at the top of metalling so that mortar layer thickness is 1- 4mm when being laid with mortar, carries out vibrations auxiliary using vibrations equipment and is laid with so that mortar can penetrate into the gap of metalling Interior, mortar is stood after the completion of being laid with, and can just continue to construct after mortar strength reaches 2.1-2.7MPa;
S9, concrete cast, then concrete is laid with by cast-in-place C25 concrete, when being laid with concrete, laying Concrete thickness is 15-24cm, is shakeout to concrete after concrete casting complete, and waiting concrete coagulation is then allowed to stand;
S10, template are taken out, and steel plate is vibrated and is extracted out after being detached from concrete, and carries out completion to the concrete of missing;
S11, late maintaining periodically carry out ultrasonic wave joint measurement to concrete revetment every the 3-6 months, crack occur and carry out in time It repairs.
Preferably, mechanical agitation is carried out when in the S3 prepared by clay and lime, whipping temp is 15-45 DEG C, when stirring Between be 0.6-1.4 hours.
Preferably, it vibrates to bank protection when bank protection humidity reaches 26-35% in the S4, is carried out at the same time and is laid with base soil.
Preferably, the maximum particle diameter of sand is not more than 6mm in the S7.
Preferably, the density of the S8 medium stones is more than 24kN/m3, and compression strength should be greater than 52MPa.
Preferably, it when being laid with concrete in the S9, maintains the temperature in 10-45 DEG C.
Preferably, vibrations are carried out to steel plate in such a way that speed is fast in the S10 and is detached from concrete, shake the shake of equipment Dynamic frequency is 106-230Hz.
Preferably, concrete revetment carries out periodically watering maintenance after completing latasuture in the S11.
The technique effect and advantage of the present invention:A kind of construction method on bank protection grinding coagulation dirt road road proposed by the present invention, Compared with prior art, it has the following advantages:
1, the construction method is by sprinkling water in advance to bank protection so that and bank protection surface is easier and the consolidation of change, The support degree for improving concrete, prevents concrete road from collapsing;
2, the construction method is by the way that mortar to be filled in the gap of rubble so that metalling is firmer, by multiple Technique is laid with road, improves the intensity of concrete road, and bank protection grinding coagulation dirt road can be improved by this method The service life on road.
Specific implementation mode
Below in conjunction with the content in the embodiment of the present invention, technical solution in the embodiment of the present invention carries out clear, complete Site preparation describes, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.Herein Described specific embodiment is only used to explain the present invention, is not intended to limit the present invention.Based on the embodiments of the present invention, Every other embodiment obtained by those of ordinary skill in the art without making creative efforts, belongs to this hair The range of bright protection.
Embodiment 1
The present invention provides a kind of construction methods on bank protection grinding coagulation dirt road road, include the following steps:
S1, preparation of construction are marched into the arena road using two sides, are excavated and are built lower foundation pit temporary road, when as concrete construction The main construction road of the transport of materials such as template, concrete;
S2, surveying and locating, bank protection working face come out after, side slope carry out line setting, make the spats position line and Platform slope angle line;
S3, base soil dispensing carry out preparing base soil using clay mixing lime, and clay is 6 with lime ratio:1 prepares, clay Mechanical agitation is carried out when being prepared with lime, whipping temp is 15 DEG C, and mixing time is 0.6 hour;
S4, base soil are laid with, and are sprinkled water first to bank protection so that watering amount is 1L in every square metre of bank protection area, then Natural drying is carried out, humidity is measured to bank protection soil every 6 hours, when humidity is 26%, base soil is uniformly laid on On bank protection so that base soil thickness reaches 14cm, and bank protection humidity vibrates to bank protection when reaching 26%, is carried out at the same time laying base Soil;
S5, base soil roll, and base soil is carried out surface and vibrated using plane equipment of vibrating, and is surveyed to the base soil after vibrating Measure the degree of packing so that the base soil degree of packing is 1MPa;
S6, template construct and installation, vertical framework use 12 channel steel Supreme Being of standard type, cross form to use the steel plate of 6mm thickness Make, the making length of cross form is 984mm, and template is installed in strict accordance with the construction line-putting position and elevation, using levee crown and The straight guarantee plate stitch for carrying foot stake hanging wire calibration template is straight;
S7, mortar is prepared, mortar ingredient is:Cement is 7%, quick lime 10%, and surplus is sand, and the maximum particle diameter of sand is not More than 6mm;
S8, screed and blotter are laid with, and are laid with blotter first, the gravel of grain size 7mm can be used in blotter Or rubble, metalling laying depth is 10cm, then mortar is laid at the top of metalling so that mortar layer thickness is 1mm, is laid with sand When slurry, vibrations auxiliary is carried out using vibrations equipment and is laid with so that mortar can penetrate into the gap of metalling, and mortar is laid with It is stood after the completion, can just continue to construct after mortar strength reaches 2.1MPa, the density of rubble is 27kN/m3, pressure resistance Degree is 58MPa;
S9, concrete cast, then concrete is laid with by cast-in-place C25 concrete, when being laid with concrete, laying Concrete thickness is 15cm, is shakeout to concrete after concrete casting complete, and waiting concrete coagulation is then allowed to stand, and is laid with When concrete, maintain the temperature in 10 DEG C;
S11, template are taken out, and steel plate is vibrated and is extracted out after being detached from concrete, and carries out completion to the concrete of missing, is used The fast mode of speed carries out vibrations to steel plate and is detached from concrete, and the vibration frequency for shaking equipment is 106Hz;
S12, late maintaining periodically carry out ultrasonic wave joint measurement to concrete revetment every March, crack occur and repaiied in time Multiple, concrete revetment carries out periodically watering maintenance after completing latasuture.
Embodiment 2
The present invention provides a kind of construction methods on bank protection grinding coagulation dirt road road, include the following steps:
S1, preparation of construction are marched into the arena road using two sides, are excavated and are built lower foundation pit temporary road, when as concrete construction The main construction road of the transport of materials such as template, concrete;
S2, surveying and locating, bank protection working face come out after, side slope carry out line setting, make the spats position line and Platform slope angle line;
S3, base soil dispensing carry out preparing base soil using clay mixing lime, and clay is 6 with lime ratio:1 prepares, clay Mechanical agitation is carried out when being prepared with lime, whipping temp is 45 DEG C, and mixing time is 1.4 hours;
S4, base soil are laid with, and are sprinkled water first to bank protection so that watering amount is 1.5L in every square metre of bank protection area, so After carry out natural drying, humidity is measured to bank protection soil every 10 hours, humidity be 35% when, by base soil uniformly be laid with On bank protection so that base soil thickness reaches 17cm, and bank protection humidity vibrates to bank protection when reaching 35%, is carried out at the same time laying base Soil;
S5, base soil roll, and base soil is carried out surface and vibrated using plane equipment of vibrating, and is surveyed to the base soil after vibrating Measure the degree of packing so that the base soil degree of packing is 3MPa;
S6, template construct and installation, vertical framework use 12 channel steel Supreme Being of standard type, cross form to use the steel plate of 6mm thickness Make, the making length of cross form is 994mm, and template is installed in strict accordance with the construction line-putting position and elevation, using levee crown and The straight guarantee plate stitch for carrying foot stake hanging wire calibration template is straight;
S7, mortar is prepared, mortar ingredient is:Cement is 12%, quick lime 16%, and surplus is sand, the maximum particle diameter of sand No more than 6mm;
S8, screed and blotter are laid with, and are laid with blotter first, the gravel of grain size 50mm can be used in blotter Stone or rubble, metalling laying depth is 15cm, then mortar is laid at the top of metalling so that mortar layer thickness is 4mm, is laid with When mortar, vibrations auxiliary is carried out using vibrations equipment and is laid with so that mortar can penetrate into the gap of metalling, mortar paving If being stood after the completion, it can just continue to construct after mortar strength reaches 2.7MPa, the density of rubble is 26kN/m3, resistance to compression Intensity is 54MPa;
S9, concrete cast, then concrete is laid with by cast-in-place C25 concrete, when being laid with concrete, laying Concrete thickness is 24cm, is shakeout to concrete after concrete casting complete, and waiting concrete coagulation is then allowed to stand, and is laid with When concrete, maintain the temperature in 45 DEG C;
S11, template are taken out, and steel plate is vibrated and is extracted out after being detached from concrete, and carries out completion to the concrete of missing, is used The fast mode of speed carries out vibrations to steel plate and is detached from concrete, and the vibration frequency for shaking equipment is 230Hz;
S12, late maintaining periodically carry out ultrasonic wave joint measurement to concrete revetment every June, crack occur and repaiied in time Multiple, concrete revetment carries out periodically watering maintenance after completing latasuture.
Embodiment 3
The present invention provides a kind of construction methods on bank protection grinding coagulation dirt road road, include the following steps:
S1, preparation of construction are marched into the arena road using two sides, are excavated and are built lower foundation pit temporary road, when as concrete construction The main construction road of the transport of materials such as template, concrete;
S2, surveying and locating, bank protection working face come out after, side slope carry out line setting, make the spats position line and Platform slope angle line;
S3, base soil dispensing carry out preparing base soil using clay mixing lime, and clay is 6 with lime ratio:1 prepares, clay Mechanical agitation is carried out when being prepared with lime, whipping temp is 16 DEG C, and mixing time is 0.7 hour;
S4, base soil are laid with, and are sprinkled water first to bank protection so that watering amount is 1.4L in every square metre of bank protection area, so After carry out natural drying, humidity is measured to bank protection soil every 7 hours, humidity be 27% when, by base soil uniformly be laid with On bank protection so that base soil thickness reaches 15cm, and bank protection humidity vibrates to bank protection when reaching 27%, is carried out at the same time laying base Soil;
S5, base soil roll, and base soil is carried out surface and vibrated using plane equipment of vibrating, and is surveyed to the base soil after vibrating Measure the degree of packing so that the base soil degree of packing is 2MPa;
S6, template construct and installation, vertical framework use 12 channel steel Supreme Being of standard type, cross form to use the steel plate of 6mm thickness Make, the making length of cross form is 985mm, and template is installed in strict accordance with the construction line-putting position and elevation, using levee crown and The straight guarantee plate stitch for carrying foot stake hanging wire calibration template is straight;
S7, mortar is prepared, mortar ingredient is:Cement is 8%, quick lime 11%, and surplus is sand, and the maximum particle diameter of sand is 5mm;
S8, screed and blotter are laid with, and are laid with blotter first, the gravel of grain size 8mm can be used in blotter Or rubble, metalling laying depth is 11cm, then mortar is laid at the top of metalling so that mortar layer thickness is 2mm, is laid with sand When slurry, vibrations auxiliary is carried out using vibrations equipment and is laid with so that mortar can penetrate into the gap of metalling, and mortar is laid with It is stood after the completion, can just continue to construct after mortar strength reaches 2.2MPa, the density of rubble is 25kN/m3, pressure resistance Degree is 53MPa;
S9, concrete cast, then concrete is laid with by cast-in-place C25 concrete, when being laid with concrete, laying Concrete thickness is 16cm, is shakeout to concrete after concrete casting complete, and waiting concrete coagulation is then allowed to stand, and is laid with When concrete, maintain the temperature in 11 DEG C;
S11, template are taken out, and steel plate is vibrated and is extracted out after being detached from concrete, and carries out completion to the concrete of missing, is used The fast mode of speed carries out vibrations to steel plate and is detached from concrete, and the vibration frequency for shaking equipment is 107Hz;
S12, late maintaining periodically carry out ultrasonic wave joint measurement to concrete revetment every April, crack occur and repaiied in time Multiple, concrete revetment carries out periodically watering maintenance after completing latasuture.
Finally it should be noted that:The foregoing is only a preferred embodiment of the present invention, is not intended to restrict the invention, Although the present invention is described in detail referring to the foregoing embodiments, for those skilled in the art, still may be used With technical scheme described in the above embodiments is modified or equivalent replacement of some of the technical features, All within the spirits and principles of the present invention, any modification, equivalent replacement, improvement and so on should be included in the present invention's Within protection domain.

Claims (8)

1. a kind of construction method on bank protection grinding coagulation dirt road road, it is characterised in that:Include the following steps:
S1, preparation of construction are marched into the arena road using two sides, are excavated and are built lower foundation pit temporary road, template when as concrete construction, The main construction road of the transport of materials such as concrete;
S2, surveying and locating, after bank protection working face comes out, side slope carries out line setting, makes the spats position line and platform Slope angle line;
S3, base soil dispensing carry out preparing base soil using clay mixing lime, and clay is 6 with lime ratio:1 prepares;
S4, base soil are laid with, and are sprinkled water first to bank protection so that watering amount is 1-1.5L in every square metre of bank protection area, then Natural drying is carried out, humidity is measured to bank protection soil every 6-10 hours, when humidity is 26-35%, base soil is uniformly spread It is located on bank protection so that base soil thickness reaches 14-17cm;
S5, base soil roll, and base soil is carried out surface and vibrated using plane equipment of vibrating, and is measured tightly to the base soil after vibrating Solidity so that the base soil degree of packing is 1-3MPa;
S6, template construct and installation, vertical framework use 12 channel steel Supreme Being of standard type, cross form to be made of the steel plate of 6mm thickness, The making length of cross form is 984-994mm, and template is installed in strict accordance with the construction line-putting position and elevation, using levee crown and carried The straight guarantee plate stitch of foot stake hanging wire calibration template is straight;
S7, mortar is prepared, mortar ingredient is:Cement is 7-12%, and quick lime 10-16%, surplus is sand;
S8, screed and blotter are laid with, and are laid with blotter first, blotter can be used grain size 7-50mm gravel or Rubble, metalling laying depth is 10-15cm, then mortar is laid at the top of metalling so that mortar layer thickness is 1-4mm, paving If when mortar, carrying out vibrations auxiliary using vibrations equipment and being laid with so that mortar can penetrate into the gap of metalling, mortar It is stood after the completion of being laid with, can just continue to construct after mortar strength reaches 2.1-2.7MPa;
S9, concrete cast, then concrete is laid with by cast-in-place C25 concrete, when being laid with concrete, the coagulation of laying Soil thickness is 15-24cm, is shakeout to concrete after concrete casting complete, and waiting concrete coagulation is then allowed to stand;
S10, template are taken out, and steel plate is vibrated and is extracted out after being detached from concrete, and carries out completion to the concrete of missing;
S11, late maintaining periodically carry out ultrasonic wave joint measurement to concrete revetment every the 3-6 months, crack occur and repaiied in time It is multiple.
2. a kind of construction method on bank protection grinding coagulation dirt road road according to claim 1, it is characterised in that:In the S3 Clay carries out mechanical agitation when being prepared with lime, whipping temp is 15-45 DEG C, and mixing time is 0.6-1.4 hours.
3. a kind of construction method on bank protection grinding coagulation dirt road road according to claim 1, it is characterised in that:In the S4 Bank protection humidity vibrates to bank protection when reaching 26-35%, is carried out at the same time and is laid with base soil.
4. a kind of construction method on bank protection grinding coagulation dirt road road according to claim 1, it is characterised in that:In the S7 The maximum particle diameter of sand is not more than 6mm.
5. a kind of construction method on bank protection grinding coagulation dirt road road according to claim 1, it is characterised in that:In the S8 The density of rubble is more than 24kN/m3, and compression strength should be greater than 52MPa.
6. a kind of construction method on bank protection grinding coagulation dirt road road according to claim 1, it is characterised in that:In the S9 When being laid with concrete, maintain the temperature in 10-45 DEG C.
7. a kind of construction method on bank protection grinding coagulation dirt road road according to claim 1, it is characterised in that:The S10 Middle to carry out vibrations disengaging concrete to steel plate in such a way that speed is fast, the vibration frequency for shaking equipment is 106-230Hz.
8. a kind of construction method on bank protection grinding coagulation dirt road road according to claim 1, it is characterised in that:The S11 Middle concrete revetment carries out periodically watering maintenance after completing latasuture.
CN201810590541.2A 2018-06-09 2018-06-09 A kind of construction method on bank protection grinding coagulation dirt road road Withdrawn CN108755358A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810590541.2A CN108755358A (en) 2018-06-09 2018-06-09 A kind of construction method on bank protection grinding coagulation dirt road road

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810590541.2A CN108755358A (en) 2018-06-09 2018-06-09 A kind of construction method on bank protection grinding coagulation dirt road road

Publications (1)

Publication Number Publication Date
CN108755358A true CN108755358A (en) 2018-11-06

Family

ID=63999723

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810590541.2A Withdrawn CN108755358A (en) 2018-06-09 2018-06-09 A kind of construction method on bank protection grinding coagulation dirt road road

Country Status (1)

Country Link
CN (1) CN108755358A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111254770A (en) * 2020-02-13 2020-06-09 佛山科学技术学院 Soil shoulder synchronous ridging construction method for preventing road surface structure layer from being polluted

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004097090A (en) * 2002-09-09 2004-04-02 North Green:Kk Landscape gardening method using charcoal powder
CN105386448A (en) * 2015-10-08 2016-03-09 中国水利水电第十二工程局有限公司 Filling construction method for backward slope in rock-fill dam slope treatment
CN106193066A (en) * 2016-08-01 2016-12-07 西北大学 A kind of Loess landslide administering method based on restoration of the ecosystem
CN207362798U (en) * 2017-10-10 2018-05-15 李明新 A kind of protection slope

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004097090A (en) * 2002-09-09 2004-04-02 North Green:Kk Landscape gardening method using charcoal powder
CN105386448A (en) * 2015-10-08 2016-03-09 中国水利水电第十二工程局有限公司 Filling construction method for backward slope in rock-fill dam slope treatment
CN106193066A (en) * 2016-08-01 2016-12-07 西北大学 A kind of Loess landslide administering method based on restoration of the ecosystem
CN207362798U (en) * 2017-10-10 2018-05-15 李明新 A kind of protection slope

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
张丰产: "试析水利水电工程的大坝混凝土护坡现浇施工技术", 《黑龙江科技信息》 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111254770A (en) * 2020-02-13 2020-06-09 佛山科学技术学院 Soil shoulder synchronous ridging construction method for preventing road surface structure layer from being polluted

Similar Documents

Publication Publication Date Title
CN106320120B (en) A kind of peg board formula is without dirt road base construction of the highway technique
CN108411802A (en) A kind of underwater method for repairing pile foundation and scour hole
CN205999903U (en) Environment-friendly type grass planting Concrete Highway protective slope structure
CN102776897B (en) Wash apron anti-settling anti-cracking construction method and structure
CN106759126B (en) Construction method of side slope support drainage channel
CN108166397A (en) Railway frame bridge construction method
CN109505229A (en) Highway high gradient slope stress equilibrium and vibration damping are taken precautions against natural calamities high bridge pier structure and construction method
CN105649093B (en) A kind of manufacture method for encircleing solid frame for public, railway tunnel
CN108396771A (en) Raw earth-retaining wall construction method is planted from embedded reinforcement
CN105569071B (en) A kind of slip casting under water of cement-based material or mud jacking block ground mass foundation construction
CN109083096A (en) A kind of step-like ecological slope protection structure of reservoir area fluctuating zone and its implementation method
CN107989049A (en) A kind of construction method of frame bank protection
CN106542769A (en) A kind of composite of laying porous pavement
CN110485313A (en) Bridge pier stream dead zone reinforcement means
CN107938456A (en) Fill out river road construction method
CN109706952A (en) Large-scale well-sinking construction method
CN106702845B (en) One kind preventing saline and alkaline permeable pavement structure
CN107032660B (en) Preparation method of composite material for paving permeable pavement
CN106012971A (en) Vegetation concrete protection slope and construction method thereof
CN108824460A (en) A kind of construction technology of cut subgrade banket
CN108755358A (en) A kind of construction method on bank protection grinding coagulation dirt road road
CN108867645A (en) Nearby Structure Larsen steel sheet pile pulls out construction method in pattern foundation pit supporting structure
CN103061352A (en) Salt lake region bridge foundation concrete anticorrosion structure and construction method
CN108316237A (en) Revetment barricade
CN109626898A (en) A kind of ecology is sowed grass seeds by duster concrete and its method of preparation and use

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WW01 Invention patent application withdrawn after publication

Application publication date: 20181106

WW01 Invention patent application withdrawn after publication