CN104358519B - 一种逐段式完井方法 - Google Patents
一种逐段式完井方法 Download PDFInfo
- Publication number
- CN104358519B CN104358519B CN201410466667.0A CN201410466667A CN104358519B CN 104358519 B CN104358519 B CN 104358519B CN 201410466667 A CN201410466667 A CN 201410466667A CN 104358519 B CN104358519 B CN 104358519B
- Authority
- CN
- China
- Prior art keywords
- tubular column
- completion
- lowered
- completion tubular
- hampered
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 238000000034 method Methods 0.000 title claims abstract description 22
- 238000005553 drilling Methods 0.000 claims abstract description 11
- 230000000694 effects Effects 0.000 abstract description 4
- VNWKTOKETHGBQD-UHFFFAOYSA-N methane Chemical compound C VNWKTOKETHGBQD-UHFFFAOYSA-N 0.000 abstract description 4
- 239000007789 gas Substances 0.000 abstract description 3
- 210000000481 breast Anatomy 0.000 abstract description 2
- 239000003245 coal Substances 0.000 abstract description 2
- 239000003345 natural gas Substances 0.000 abstract description 2
- 238000010276 construction Methods 0.000 description 2
- 239000000725 suspension Substances 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 235000019994 cava Nutrition 0.000 description 1
- 230000007812 deficiency Effects 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 208000015181 infectious disease Diseases 0.000 description 1
- 238000003032 molecular docking Methods 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21B—EARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
- E21B7/00—Special methods or apparatus for drilling
- E21B7/20—Driving or forcing casings or pipes into boreholes, e.g. sinking; Simultaneously drilling and casing boreholes
Landscapes
- Life Sciences & Earth Sciences (AREA)
- Engineering & Computer Science (AREA)
- Geology (AREA)
- Mining & Mineral Resources (AREA)
- Physics & Mathematics (AREA)
- Environmental & Geological Engineering (AREA)
- Fluid Mechanics (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Earth Drilling (AREA)
Abstract
本发明涉及一种石油、天然气、页岩气及煤层气钻完井方法,特别涉及一种逐段式完井方法。该方法步骤如下:下完井管柱前充分通井,并记录通井遇阻情况,根据通井遇阻情况将设计完井管柱分成若干段,首先将带有引鞋的第一段完井管柱下入到尽可能深的位置,最好下到设计井深,然后丢手起出送入钻具。本发明实现了能够在无法准确判断下部井眼通畅能力的前提下,保证完井管柱下入到可能的最深处,最大限度的起到支撑井壁的作用,在管柱下入过程中提前遇阻时,易于调整管柱组配结构,保证管柱悬挂点在设计位置座挂,避免悬挂点上移带来的后期钻修井无法操作的问题。
Description
技术领域:
本发明涉及一种石油、天然气、页岩气及煤层气钻完井方法,特别涉及一种逐段式完井方法。
背景技术:
油气开发的完井过程中,常常遇到轨迹变化幅度大或者井眼缩颈、塌卡等问题,导致完井管柱无法下到预定深度,尾管悬挂器被迫上移座挂等问题,影响后期的钻修井施工作业的正常进行。对于分支井施工影响更是突出,下分支完井管柱悬挂点的提高将迫使分支窗口上移,甚至出现分支完井管柱送入遇阻时,主分支连接处无法正常贯通的严重工程事故。有时为避免完井管柱悬挂点上移,不得不减少管柱长度,下部井眼裸眼完井。这种情况下,地层后期坍塌可能会损失井眼长度。因此非常有必要研究简便可行的完井方法确保完井管柱下入到位的同时,又避免悬挂点上移的风险。
发明内容:
本发明要解决的技术问题是提供一种逐段式完井方法,该方法实现了能够在无法准确判断下部井眼通畅能力的前提下,保证完井管柱下入到可能的最深处,最大限度的起到支撑井壁的作用,在管柱下入过程中提前遇阻时,易于调整管柱组配结构,保证管柱悬挂点在设计位置座挂,避免悬挂点上移带来的后期钻修井无法操作的问题。克服了现有完井管柱无法下到预定深度,尾管悬挂器被迫上移座挂的不足。
本发明所采取的技术方案是:一种逐段式完井方法,该方法步骤如下:下完井管柱前充分通井,并记录通井遇阻情况,根据通井遇阻情况将完井管柱分成若干段,首先将带有引鞋的第一段完井管柱下入到尽可能深的位置,然后丢手起出送入钻具,根据下入遇阻情况及尾管悬挂点位置,计算第二段完井管柱长度,接着下入第二段完井管柱,第一段与第二段之间靠管柱连接器可靠连接和密封,按照同样的方法下入和连接剩余的分段完井管柱,直至完成,上部的完井管柱在设计悬挂点处悬挂。
本发明的有益效果是:本发明由于采用了将设计完井管柱分成若干段分批下入的方式,因而具有能够在无法准确判断下部井眼通畅能力的前提下,保证完井管柱下入到可能的最深处的功能,最大限度的起到支撑井壁的作用,在管柱下入过程中提前遇阻时,易于调整管柱组配结构,保证管柱悬挂点在设计位置座挂,避免悬挂点上移带来的后期钻修井无法操作的问题。
附图说明:
下面结合附图和具体实施方式对本发明做进一步详细的说明。
图1为本发明的示意图。
具体实施方式:
一种逐段式完井方法,该方法步骤如下:下完井管柱前充分通井,并记录通井遇阻情况,根据通井遇阻情况将完井管柱分成若干段,首先将带有引鞋的第一段完井管柱下入到尽可能深的位置,然后丢手起出送入钻具,根据下入遇阻情况及尾管悬挂点位置,计算第二段完井管柱长度,接着下入第二段完井管柱,第一段与第二段之间靠管柱连接器可靠连接和密封,按照同样的方法下入和连接剩余的分段完井管柱,直至完成,上部的完井管柱在设计悬挂点处悬挂。
本发明在完井井眼轨迹变化幅度大、磨阻大或者井眼缩颈、塌卡等复杂井下条件下具有明显优势。
实施例1
如图1所示,完井前,进行充分通井,并仔细记录通井遇阻情况。根据通井遇阻情况将完井管柱分成若干段,通常在每个遇阻卡点设管柱连接器连接上、下段完井管柱,将带有引鞋1的第一段完井管柱2与管柱连接器Ⅰ下部组件3用螺纹连接好,第一段完井管柱2由套管、筛管、固井附件及封隔器等组成。利用送入钻具将第一段完井管柱2下入到设计井深或者遇阻最深处,丢手起出送入钻具。然后根据下入遇阻情况及尾管悬挂点位置,设计计算第二段完井管柱5长度。管柱连接器Ⅰ上部组件4、第二段完井管柱5、管柱连接器Ⅱ下部组件6顺次丝扣连接。利用送入钻具将第二段完井管柱5下入,管柱连接器Ⅰ上部组件4与管柱连接器Ⅰ下部组件3对接实现锁定连接和密封,将第一段完井管柱2和第二段完井管柱5刚性连接成一体。如果存在第三段完井管柱、第四段完井管柱、…第n段完井管柱,按照同样的方法下入和连接。最后各段完井管柱相互连接成一体,上部的完井管柱在设计悬挂点处悬挂。
可以理解的是,以上关于本发明的具体描述,仅用于说明本发明而并非受限于本发明实施例所描述的技术方案,本领域的普通技术人员应当理解,仍然可以对本发明进行修改或等同替换,以达到相同的技术效果;只要满足使用需要,都在本发明的保护范围之内。
Claims (1)
1.一种逐段式完井方法,其特征在于:该方法步骤如下:下完井管柱前充分通井,并记录通井遇阻情况,根据通井遇阻情况将完井管柱分成若干段,首先将带有引鞋的第一段完井管柱下入到尽可能深的位置,然后丢手起出送入钻具,根据下入遇阻情况及尾管悬挂点位置,计算第二段完井管柱长度,接着下入第二段完井管柱,第一段与第二段之间靠管柱连接器可靠连接和密封,按照同样的方法下入和连接剩余的分段完井管柱,直至完成,上部的完井管柱在设计悬挂点处悬挂。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410466667.0A CN104358519B (zh) | 2014-09-12 | 2014-09-12 | 一种逐段式完井方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410466667.0A CN104358519B (zh) | 2014-09-12 | 2014-09-12 | 一种逐段式完井方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN104358519A CN104358519A (zh) | 2015-02-18 |
CN104358519B true CN104358519B (zh) | 2016-05-11 |
Family
ID=52525816
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201410466667.0A Active CN104358519B (zh) | 2014-09-12 | 2014-09-12 | 一种逐段式完井方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104358519B (zh) |
Families Citing this family (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109322618B (zh) * | 2018-10-19 | 2020-04-07 | 成都科盛石油科技有限公司 | 非均质页岩气井储层段完钻方法 |
CN109162643B (zh) * | 2018-10-19 | 2020-01-07 | 北京中海沃邦能源投资有限公司 | 用于连续型页岩储层的完钻方法 |
Family Cites Families (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US7147068B2 (en) * | 1994-10-14 | 2006-12-12 | Weatherford / Lamb, Inc. | Methods and apparatus for cementing drill strings in place for one pass drilling and completion of oil and gas wells |
US7475742B2 (en) * | 2000-06-09 | 2009-01-13 | Tesco Corporation | Method for drilling with casing |
CN101503955A (zh) * | 2008-12-12 | 2009-08-12 | 中国石油化工股份有限公司胜利油田分公司采油工艺研究院 | 分段完井方法及管柱 |
US8281878B2 (en) * | 2009-09-04 | 2012-10-09 | Tesco Corporation | Method of drilling and running casing in large diameter wellbore |
CN101864921B (zh) * | 2010-06-11 | 2013-05-01 | 大港油田集团有限责任公司 | 水平井的完井、采油管柱及其完井、采油工艺 |
CN103806837A (zh) * | 2012-11-12 | 2014-05-21 | 中国石油天然气股份有限公司 | 一种油田水平井完井工艺 |
-
2014
- 2014-09-12 CN CN201410466667.0A patent/CN104358519B/zh active Active
Also Published As
Publication number | Publication date |
---|---|
CN104358519A (zh) | 2015-02-18 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
MX2022008819A (es) | Sistema de compensacion de empuje para ensamblar una cadena de perforacion. | |
CN102852490A (zh) | 复杂结构井抽放高瓦斯气工艺方法 | |
CN104053855A (zh) | 用于规划和/或钻探井眼的方法和系统 | |
CN204941480U (zh) | 可实现分段开采的水平井完井套管及其构成的管柱 | |
CN104358519B (zh) | 一种逐段式完井方法 | |
CN202882846U (zh) | 一种井下隔离阀 | |
CN204532261U (zh) | 一种可控型可溶球座多级压裂滑套 | |
CN102767349A (zh) | 煤层气水平井悬挂筛管完井方法 | |
CN204126624U (zh) | 裸眼水平井不动管柱水力喷射分段完井压裂管柱 | |
CN103089193A (zh) | 一种筛管顶部膨胀套管封堵的尾管完井的方法 | |
CN201924839U (zh) | 一次生产管柱 | |
CN104912480B (zh) | 煤层气近端对接水平井的钻完井方法 | |
CN103233694B (zh) | 下放悬挂采动区地面煤层气井生产套管的方法及套管装置 | |
CN209261540U (zh) | 一种分支井结构 | |
CN105971504A (zh) | 一种不确定目标储层所在地层时的钻井结构,方法与装置 | |
CN103206191B (zh) | 稠油尾管固井挤窜一体方法 | |
CN103711473A (zh) | 双循环接力式煤层复合井眼钻完井方法 | |
CN203584359U (zh) | 单筒双井非对称套管头 | |
CN102182403B (zh) | 鱼刺井分支井眼钻削式完井工艺 | |
CN205172513U (zh) | 一种基于膨胀套管的桥塞装置 | |
CN103122760B (zh) | 一种延缓底水锥进的完井管柱 | |
CN102758608B (zh) | 一种投球式释放方法及用于该方法的钻具 | |
CN107366525A (zh) | 一种大斜度井用小尺寸膨胀筛管完井管柱 | |
CN104018812A (zh) | 井下钻孔与地面直井对接联合抽采煤层气的方法 | |
CN105298431A (zh) | 一种水平井触动封隔分段完井工艺管柱 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
TR01 | Transfer of patent right |
Effective date of registration: 20200930 Address after: 100120 Beijing Xicheng District six laying Kang Patentee after: CHINA NATIONAL PETROLEUM Corp. Patentee after: China National Petroleum Corporation Great Wall Drilling Engineering Co.,Ltd. Address before: 124010 Xinglongtai, Liaoning Province, oil street, No. 96, No. Patentee before: China National Petroleum Corporation Great Wall Drilling Engineering Co.,Ltd. |
|
TR01 | Transfer of patent right |