PEMERINTAH KABUPATEN MUNA BARAT

DINAS PEKERJAAN UMUM DAN PENATAAN RUANG

HARGA SATUAN BAHAN DAN UPAH KERJA


KABUPATEN MUNA BARAT TAHUN 2020

HARGA SATUAN TANPA IMB

NO URAIAN SATUAN WILAYAH


DARATAN
(Rp)
BAHAN TOKO
I SEMEN
1 Semen/PC (50 Kg) zak 85,000
2 Semen Warna Putih/PC (40 Kg) Kg 3,800
II BAHAN BESI DAN KAWAT
1 Baut/Mur Kg 34,000
2 Besi Strip Kg 15,000
3 Paku Campuran (5,7,10 Cm) Kg 20,000
4 Paku Seng Kg 37,000
III BAHAN KERAMIK
1 Keramik Warna 40 x 40 Cm Dos 148,000
IV BAHAN KACA
1 Kaca Bening 3 mm M2 200,000
VII BAHAN ATAP
1 Seng Gelombang BJLS20 UK 90X240 CM Lbr 138,000
2 Seng Plat BWG BJLS 0.20 mm (lebar 45 Cm) Lbr 28,000
VIII BAHAN CAT DAN MINYAK
1 Minyak Cat Ltr 35,000
2 Cat Many Kayu/Besi Kg 25,000
3 Cat Kilap Kayu (Sejenis Avian) Ltr 72,000
4 Lem Kayu (Fox) Kg 25,000
5 Plamur Tembok Kg 13,800
6 Amplas Kasar Kayu Lembar 7,000
7 Kuas 4" Buah 25,000
KUNCI - KUNCI
1 Grendel Pintu Biasa Buah 27,000
2 Engsel Pintu H Kupu-kupu Kuningan Pasang 33,000
3 Engsel Jendela H Kupu-kupu Kuningan bh 15,000
4 Hak Angin Biasa Buah 7,000
II PASIR (LOKASI)
1 Pasir Urug M3 285,000
2 Pasir Pasangan M3 285,000
III BATU
1 Batu Merah Biji 900
2 Batu Belah 15/25-25/35 cm M3 238,000
VI BAHAN KAYU (PENAMPUNG)
1 Papan Kayu Klas II A (Sejenis) M3 2,356,000
2 Balok Kayu Klas II A (Sejenis) M3 2,356,000
UPAH KERJA
1 Mandor Org/Hari 125,000
2 Kepala Tukang Org/Hari 150,000
3 Tukang Org/Hari 125,000
- Tukang Listrik Org/Hari 125,000
- Tukang Batu Org/Hari 125,000
- Tukang Kayu Org/Hari 125,000
- Tukang Besi Org/Hari 125,000
- Tukang Cat Org/Hari 125,000
4 Pekerja
- Pekerja Terlatih Org/Hari 110,000
- Pekerja Agak terlatih Org/Hari 100,000
- Pekerja Tak terlatih Org/Hari 90,000
5 Sopir Org/Hari 150,000
6 Pembantu Sopir Org/Hari 100,000
7 Operator Alat Berat Org/Hari 450,000
8 Pembantu Operator Alat Berat Org/Hari 100,000
9 Mekanik Org/Hari 200,000
10 Penjaga Malam Org/Hari 100,000

KETERANGAN :
1 HARGA BELUM TERMASUK PROFIT, OVERHEAD Dan PPN
2 HARGA BBM MERUPAKAN HARGA INDUSTRI (Sumber PERTAMINA)
3 HARGA KAYU MENGIKUTI HARGA YANG DITETAPKAN OLEH DINAS KEHUTANAN KAB. MUNA

Raha, Oktober 2019

Mengetahui Disiapkan Oleh


Kepala Dinas Pekerjaan Umum dan Penataan Ruang Kepala Dinas Pekerjaan Umum dan Penataan Ruang
Kabupaten Muna Kabupaten Muna

EDDY UGA, SH. M.Si EDDY UGA, SH. M.Si


NIP. 19660707 199303 1 008 NIP. 19660707 199303 1 008
1. HARGA BBM MERUPAKAN HARGA INDUSTRI (Sumber PERTAMINA)
2. HARGA KAYU SUDAH TERMASUK ONGKOS ANGKUT KE LOKASI PEKERJAAN (Sumber DINAS KEHUTANAN KAB. MUNA)

MENGETAHUI/SETUJU
KEPALA DINAS PEKERJAAN UMUM
KABUPATEN MUNA

Ir. MUH.YAMIN IMRAN


NIP. 19561225 198903 1 003
II PEKERJAAN TANAH DAN PASIR
1 Pek. Galian Fondasi
Panjang 18.45 m
Lebar 0.90 m
Tinggi 0.45 m
Volume 7.47 m3

2 Pek. Urugan Tanah Kembali Alur Fondasi


Ditaksir = 1/4 Galian
Volume 1.87 m3

3 Pek. Urugan Tanah Alas Lantai


Panjang Bangunan 13.25 m
Lebar Bangunan 5.20 m
Tinggi Urugan 0.45 m
Volume 31.01 m3

4 Pek. Urugan Pasir Alas Lantai


Panjang Bangunan 13.25 m
Lebar Bangunan 5.20 m
Tinggi Urugan 0.10 m
Volume 6.89 m3

III PEKERJAAN PASANGAN


1 Pek. Pasangan Batu Kosong
Panjang. Fondasi 18.45 m
Lebar Pas. Batu Kosong 0.90 m
Tinggi 0.20 m
Volume 3.32 m3

2 Pek. Pasangan Fondasi Camp. 1:4


Lebar Atas Fondasi 0.25 m
Lebar Bawah Fondasi 0.70 m
Tinggi Fondasi 0.70 m
Panjang Fondasi 18.45 m
Volume 6.13 m3

3 Pek. Pasangan Bata Merah 1 : 4


Keliling Bangunan 52.40 m
Tinggi Pasangan 0.80 m
Volume Bruto 41.92 m2
Pengurangan Volume Dinding Bata
- Kusen Pintu
Lebar 0.90
Tinggi Terpakai 0.80
Jumlah 4.00
Volume Pengurang 2.88 m2
Volume Pasangan Bata 39.04 m2

IV PEKRJAAN PLESTERAN DAN ACIAN


1 Pek. Plesteran Dinding Camp 1 : 4
Volume 78.08 m2

2 Pek. Plesteran Area Luar Fondasi


Panjang 18.45 m
Lebar 0.52 m
Volume 9.59 m2

3 Pek. Acian Air Cement Area Luar Fondasi


Panjang 18.45 m
Lebar 0.52 m
Volume 9.59 m2

V PEKERJAAN KUDA KUDA / ATAP


1 Pek. Kuda Kuda Kaki 6.16
Panjang 10/10 16.42 m Skoor 2.66
Lebar 0.10 m Tarik 5.95
Tebal 0.10 m Raja 1.65
Jumlah 5.00 m 16.42
Volume 0.82 m3

Balok 6/10
Panjang 10/10 4.00 m
Lebar 0.10 m
Tebal 0.06 m
Jumlah 5.00 m
Volume 0.12 m3

2 Pek. Gording Kayu Ukr. 6/10


Panjang 6/10 22.40 m
Lebar 0.10 m
Tebal 0.06 m
Jumlah 7.00 m
Volume 0.94 m3

3 Pekerjaan Atap Seng 7 Kaki


Lebar 7.70 m
Panjang 14.65 m
Volume 112.81 m2
4 Pekerjaan Plat Atap Seng
Panjang 16.16
Volume 69.00 30.80
22.40
69.36

5 Pekerjaan Lesplank
Keliling 52.40 m1
Lebar 0.25 m2
Volume 13.10 m2

VI PEKERJAAN RANGKA KAYU


1 Pek. Tiang Induk Ukr. 10/10
Tinggi 3.00 m
Lebar 0.10
Tebal 0.10
Jumlah 7.00 Btg
Volume 0.21 m3

2 Pek. Balok Atas Ukr 10/10


Kll. Bangunan 52.40 m
Lebar Balok 0.10 m
Tinggi Balok 0.10 m
Volume 0.52 m3

3 Pek. Balok Siku Ukr 10/10


Panjang Balok Siku 0.60 m
Lebar Balok Siku 0.10 m
Tebal Balok Siku 0.10 m
Jumlah Balok Siku 17.00 Bh
Volume 0.10 m3

4 Pek. Balok Penguat Kusen Ukr. 5/7


Panjang 21.00 m
Lebar 0.05 m
Tebal 0.07 m
Volume 0.07 m3

5 Pek. Balok Penguat Pintu


Panjang 8.00 m
Lebar 0.10 m
Tebal 0.10 m
Volume 0.08 m3

6 Pek. Dinding Papan Kayu Kelas II


Kll 36.90 m
Tinggi 2.20 m
Volume Bruto 81.18 m2
Pengurangan Volume
Kusen Jendela
Lebar 0.90
Tinggi 1.00
Jumlah 9.00
Volume Pengurang 8.10

Kusen Pintu
Lebar 0.90
Tinggi 2.00
Jumlah 4.00
Volume Pengurang 7.20
Total Pengurang 15.30 m2

Volume Dinding Papan 65.88

VII PEKERJAAN LANTAI


Pek. Tegel 30 x 30
Lebar 5.20 m
Panjang 13.25 m
Volume 68.90 m2

VII PEKERJAAN KUSEN JENDELA & PINTU


1 Pek. Kusen Pintu
Panjang 20.40 m x 1.10
Lebar 0.10 m y 16.00
Tebal 0.10 m
Volume 0.20 m3

2 Pek. Kusen Jendela


Panjang 21.60 m x 10.80
Lebar 0.10 m y 10.80
Tebal 0.10 m 21.60
Volume 0.22 m3

3 Pek. Daun Pintu


Lebar 0.76 m
Tinggi 0.96 m
Jumlah 4.00 BH
Volume 2.92 m2

4 Daun Jendela
Area 0.15 m
Jumlah 6.00 BH
Volume 0.88 m2

IX PEKERJAAN KUNCI DAN KACA


1 Pek. Kunci Pintu 2 x Putar
Volume 4.00 BH
2 Pek. Engsel Pintu
Volume 12.00 BH
3 Pek. Engsel Jendela
Volume 12.00 BH
4 Pek. Grendel Jendela
Volume 6.00 BH
5 Pek. Kaca Mati
Panjang 0.72 m
Lebar 0.42 m
Jumlah 6.00 BH
Volume 1.81 m2

X PEKERJAAN FINISHING
1 Cat Tembok Baru
Keliling 47.20 m
Tinggi 0.80 m
Jumlah Pias 2.00 m
Volume 75.52 m2

2 Pek Cat Dinding Papan


Volume 131.76 m2

3 Pek. Cat Kusen Pintu / Jendela


Volume 10.50 m2

4 Pek Cat Daun Pintu / Jendela


Volume 7.59 m2

5 Pek. Cat Lesplank


Volume 26.20 m2

XI PEKERJAAN FINISHING
1.10 1.10 1.10 4.40
16.00
20.40
PEMERINTAH KABUPATEN MUNA BARAT
DINAS…………………………
Alamat Jalan ……………………………..

DAFTAR KWANTITAS DAN HARGA


ESTIMATE ENGINEERING (EE)
KEGIATAN : …………………………
PEKERJAAN : ……………………………..
LOKASI : ……………………………….
VOLUME : ………………..
TA : 2020
HARGA JUMLAH
NO. URAIAN DAN JENIS PEKERJAAN SAT VOLUME SATUAN HARGA
(Rp) (Rp)
1 2 3 5 6
I PEKERJAAN PERSIAPAN
2 Papan Nama Kegiatan Ls 1.00 300,000.00 300,000.00
3 Dokumentasi / P3K Ls 1.00 500,000.00 500,000.00
4 Back Up Data Dan Laporan Ls 1.00 2,000,000.00 2,000,000.00
Jumlah 2,800,000.00
II PEKERJAAN TANAH DAN PASIR
1 Pek. Galian Fondasi m3 7.47 98,468.75 735,783.12
2 Pek. Urugan Tanah Kembali Alur Fondasi m2 1.87 70,437.50 131,581.65
3 Pek. Urugan Tanah Alas Lantai m3 31.01 67,375.00 2,088,961.88
4 Pek. Urugan Pasir Alas Lantai m3 6.89 432,687.50 2,981,216.88
Jumlah 5,937,543.52
III PEKERJAAN PASANGAN
1 Pek. Pasangan Batu Kosong m3 3.32 637,094.25 2,115,790.00
2 Pek. Pasangan Fondasi Canp 1 : 4 m3 6.13 1,138,816.25 6,986,210.64
3 Pek. Pasangan Batu Bata Canp 1 : 4 m2 39.04 165,232.00 6,450,657.28
Jumlah 15,552,657.92
IV PEKERJAAN PLESTERAN / ACIAN AIR CEMENT
1 Plesteran Tembok Camp. 1 : 4 m2 0.00 84,321.45 0.00
2 Pek. Plesteran Area Luar Fondasi Camp 1 : 4 m2 9.59 84,321.45 808,979.99
3 Pek. Acian Air Cement Fondasi Terlihat m2 9.59 49,191.25 471,940.85
Jumlah 1,280,920.84
V PEK.KUDA - KUDA DAN ATAP
1 Pek. Kuda - Kuda Kayu Kelas II m3 0.94 7,770,636.25 7,312,168.71
2 Pek. Gording Dan Rangka Kayu Kelas II m3 0.94 7,439,896.25 6,999,454.39
3 Pek. Atap Seng Bjls 0.28 m2 112.81 137,643.50 15,526,875.02
4 Pek. Pasang Plat Atap Seng BJLS 0.3 m1 69.00 62,717.17 4,327,484.50
5 Pek. Lesplank Papan Kayu Kelas II m1 13.10 77,130.27 1,010,406.54
Jumlah 35,176,389.16
VI PEKERJAAN RANGKA DAN DINDING PAPAN
1 Pekerjaan Rangka m2 68.90 171,888.20 11,843,096.98
2 Pek. Dinding Papan Kayu Kelas II m2 65.88 235,283.10 15,500,450.63
Jumlah 27,343,547.61
VII PEKERJAAN LANTAI
1 Pek. Lantai Tegel 30 x 30 m2 68.90 252,298.50 17,383,366.65
Jumlah 17,383,366.65
VIII PEK. KUSEN PINTU, JENDELA DAN DAUN PINTU/ JENDELA
1 Pek. Kusen Pintu Dan Jendela Kayu Kelas II m3 0.42 7,710,721.25 3,238,502.93
2 Pek. Daun Pintu Kayu Kelas II m3 1.00 3,683,277.50 3,683,277.50
3 Pek. Daun Jendela Kayu Kelas II m3 1.00 3,683,277.50 3,683,277.50
Jumlah 10,605,057.93
IX PEKERJAAN KUNCI DAN KACA
1 Pek. Pasang Kunci Pintu 2 x Putar BH 4.00 113,533.75 454,135.00
2 Pek. Pasang Engsel Pintu Kupu - Kupu BH 12.00 43,412.50 520,950.00
3 Pek. Pasang Engsel Jendela Kupu - Kupu BH 12.00 43,412.50 520,950.00
4 Pek. Pasang Hak Angin BH 6.00 34,212.50 205,275.00
5 Pek. Kaca Mati m2 1.81 279,248.75 506,668.93
Jumlah 2,207,978.93
X PEKERJAAN PENGECATAN
1 Pekerjaan Cat Dinding Bata m2 75.52 14,691.25 1,109,483.20
2 Pek. Cat Dinding Papan m2 131.76 49,266.00 6,491,288.16
3 Pek. Cat Kusen Pintu/ Jendela m2 10.50 49,266.00 517,293.00
4 Pek. Cat Daun Pintu / Jendela m2 7.59 49,266.00 374,106.30
5 Pek. Cat Lisplank m2 26.20 49,266.00 1,290,769.20
Jumlah 9,782,939.86
X PEK.FINISHING
1 Pek. Pembersihan Kembali Seluruh Lokasi Pekerjaan Ls 1.00 500,000.00 500,000.00
Jumlah 500,000.00
REKAPITULASI DAFTAR KWANTITAS DAN HARGA
KEGIATAN : …………………………
PEKERJAAN : ……………………………..
LOKASI : ……………………………….
VOLUME : ………………..

SAT.
NO. URAIAN DAN JENIS PEKERJAAN Jumlah Harga
(Rp.)

1 2 4 5
I PEKERJAAN PERSIAPAN Rp. 2,800,000.00
II PEKERJAAN TANAH DAN PASIR Rp. 5,937,543.52
III PEKERJAAN PASANGAN Rp. 15,552,657.92
IV PEKERJAAN PLESTERAN / ACIAN AIR CEMENT Rp. 1,280,920.84
V PEK.KUDA - KUDA DAN ATAP Rp. 35,176,389.16
VI PEKERJAAN RANGKA DAN DINDING PAPAN Rp. 27,343,547.61
VII PEKERJAAN LANTAI Rp. 17,383,366.65
VIII PEK. KUSEN PINTU, JENDELA DAN DAUN PINTU/ JENDELA Rp. 10,605,057.93
IX PEKERJAAN KUNCI DAN KACA Rp. 2,207,978.93
X PEKERJAAN PENGECATAN 9,782,939.86
XI PEK.FINISHING Rp. 500,000.00

A REAL COST Rp. 128,570,402.42


B PPN ( 10% x A ) Rp. 12,857,040.24
C TOTAL COST ( A + B ) Rp. 141,427,442.66
D DIBULATKAN Rp. 141,420,000.00
TERBILANG : ……………………………………………………………………

Laworo, 2020
Diperiksah :
Pejabat Pembuat Komitmen (PPK)
Dinas …………………..

………………………………………..
…………………………………………….
Jenis Pekerjaan : Galian Tanah Biasa Sedalam 1 m
Satuan / Unit : m3
Analisa : AHSP PU A.2.3.1.1

HARGA JUMLAH
NO. URAIAN KODE SAT KOEF SAT HARGA
(Rp) (Rp)
A TENAGA :
Pekerja L.01 0.7500 110,000.00 82,500.00
Mandor L.04 0.0250 125,000.00 3,125.00
Jumlah Tenaga Kerja 85,625.00
B BAHAN :
- - -
- - -
Jumlah Harga Bahan -
C PERALATAN :
-
-
Jumlah Harga Alat -
D JUMLAH A + B + C 85,625.00
E OVERHEAD ₰ PROVIT 15% x D 12,843.75
F HARGA SATUAN PEKERJAAN (D + E) 98,468.75
Jenis Pekerjaan : Pengurugan Kembali Galian Tanah
Satuan / Unit : m3
Analisa : AHSP PU A.2.3.1.9

HARGA JUMLAH
NO. URAIAN KODE SAT KOEF SAT HARGA
(Rp) (Rp)
A TENAGA :
Pekerja L.01 0.5000 110,000.00 55,000.00
Mandor L.04 0.0500 125,000.00 6,250.00
Jumlah Tenaga Kerja 61,250.00
B BAHAN :
- - -
- - -
Jumlah Harga Bahan -
C PERALATAN :
-
-
Jumlah Harga Alat -
D JUMLAH A + B + C 61,250.00
E OVERHEAD ₰ PROVIT 15% x D 9,187.50
F HARGA SATUAN PEKERJAAN (D + E) 70,437.50
Jenis Pekerjaan : Urugan Pasir
Satuan / Unit : m3
Analisa : AHSP PU A.2.3.1.11

HARGA JUMLAH
NO. URAIAN KODE SAT KOEF SAT HARGA
(Rp) (Rp)
A TENAGA :
Pekerja L.01 0.3000 110,000.00 33,000.00
Mandor L.04 0.0100 125,000.00 1,250.00
Jumlah Tenaga Kerja 34,250.00
B BAHAN :
Pasir Urug m3 1.2000 285,000.00 342,000.00

Jumlah Harga Bahan 342,000.00


C PERALATAN :
-
-
Jumlah Harga Alat -
D JUMLAH A + B + C 376,250.00
E OVERHEAD ₰ PROVIT 15% x D 56,437.50
F HARGA SATUAN PEKERJAAN (D + E) 432,687.50
Jenis Pekerjaan : Pengurugan Kembali Galian Tanah
Satuan / Unit : m3
Analisa : AHSP PU A.2.3.1.9

HARGA JUMLAH
NO. URAIAN KODE SAT KOEF SAT HARGA
(Rp) (Rp)
A TENAGA :
Pekerja L.01 0.5000 110,000.00 55,000.00
Mandor L.04 0.0500 125,000.00 6,250.00
Jumlah Tenaga Kerja 61,250.00
B BAHAN :
- - -
- - -
Jumlah Harga Bahan -
C PERALATAN :
-
-
Jumlah Harga Alat -
D JUMLAH A + B + C 61,250.00
E OVERHEAD ₰ PROVIT 15% x D 6,125.00
F HARGA SATUAN PEKERJAAN (D + E) 67,375.00
Jenis Pekerjaan : Pemasangan Batu Kosong (Anstamping)
Satuan / Unit : m3
Analisa : AHSP PU A.3.2.1.9

HARGA JUMLAH
NO. URAIAN KODE SAT KOEF SAT HARGA
(Rp) (Rp)
A TENAGA :
Pekerja L.01 0.7800 110,000.00 85,800.00
Tukang L.02 0.3900 125,000.00 48,750.00
Kepala Tukang L.03 0.0390 150,000.00 5,850.00
Mandor L.04 0.0390 125,000.00 4,875.00
Jumlah Tenaga Kerja 145,275.00
B BAHAN :
Batu Belah m3 1.2000 238,000.00 285,600.00
Pasir Urug m3 0.4320 285,000.00 123,120.00
Jumlah Harga Bahan 408,720.00
C PERALATAN :
-
-
Jumlah Harga Alat -
D JUMLAH A + B + C 553,995.00
E OVERHEAD ₰ PROVIT 15% x D 83,099.25
F HARGA SATUAN PEKERJAAN (D + E) 637,094.25
Jenis Pekerjaan : Pemasangan Fondasi Batu Belah Camp 1Pc : 4Ps
Satuan / Unit : m3
Analisa : AHSP PU A.3.2.1.2

HARGA JUMLAH
NO. URAIAN KODE SAT KOEF SAT HARGA
(Rp) (Rp)
A TENAGA :
Pekerja L.01 1.5000 110,000.00 165,000.00
Tukang L.02 0.7500 125,000.00 93,750.00
Kepala Tukang L.03 0.0750 150,000.00 11,250.00
Mandor L.04 0.0750 125,000.00 9,375.00
Jumlah Tenaga Kerja 279,375.00
B BAHAN :
Batu Belah m3 1.20 238,000.00 285,600.00
Semen Portland Kg 163.00 1,700.00 277,100.00
Pasir Pasang m3 0.52 285,000.00 148,200.00
Jumlah Harga Bahan 710,900.00
C PERALATAN :
-
Jumlah Harga Alat -
D JUMLAH A + B + C 990,275.00
E OVERHEAD ₰ PROVIT 15% x D 148,541.25
F HARGA SATUAN PEKERJAAN (D + E) 1,138,816.25
Jenis Pekerjaan : Pemasangan Fondasi Batu Belah Camp 1Pc : 4Ps
Satuan / Unit : m3
Analisa : AHSP PU A.3.2.1.2

HARGA JUMLAH
NO. URAIAN KODE SAT KOEF SAT HARGA
(Rp) (Rp)
A TENAGA :
Pekerja L.01 0.3000 110,000.00 33,000.00
Tukang L.02 0.1000 125,000.00 12,500.00
Kepala Tukang L.03 0.0100 150,000.00 1,500.00
Mandor L.04 0.0150 125,000.00 1,875.00
Jumlah Tenaga Kerja 48,875.00
B BAHAN :
Batu Bata m3 70.00 900.00 63,000.00
Semen Portland Kg 11.50 1,700.00 19,550.00
Pasir Pasang m3 0.04 285,000.00 12,255.00
Jumlah Harga Bahan 94,805.00
C PERALATAN :
-
Jumlah Harga Alat -
D JUMLAH A + B + C 143,680.00
E OVERHEAD ₰ PROVIT 15% x D 21,552.00
F HARGA SATUAN PEKERJAAN (D + E) 165,232.00
Jenis Pekerjaan : Plesteran 1 Sp : 4 Pp, Tebal 15 mm
Satuan / Unit : m2
Analisa : AHSP PU A.4.4.2.4

HARGA JUMLAH
NO. URAIAN KODE SAT KOEF SAT HARGA
(Rp) (Rp)
A TENAGA :
Pekerja L.01 0.3000 110,000.00 33,000.00
Tukang L.02 0.1500 125,000.00 18,750.00
Kepala Tukang L.03 0.0150 150,000.00 2,250.00
Mandor L.04 0.0150 125,000.00 1,875.00
Jumlah Tenaga Kerja 55,875.00
B BAHAN :
Semen Portland Kg 6.2400 1,700.00 10,608.00
Pasir Pasang m3 0.0240 285,000.00 6,840.00
Jumlah Harga Bahan 17,448.00
C PERALATAN :
-
Jumlah Harga Alat -
D JUMLAH A + B + C 73,323.00
E OVERHEAD ₰ PROVIT 15% x D 10,998.45
F HARGA SATUAN PEKERJAAN (D + E) 84,321.45
Jenis Pekerjaan : Acian Air Cement
Satuan / Unit : m2
Analisa : AHSP PU A.4.4.2.27
HARGA JUMLAH
NO. URAIAN KODE SAT KOEF SAT HARGA
(Rp) (Rp)
A TENAGA :
Pekerja L.01 0.2000 110,000.00 22,000.00
Tukang L.02 0.1000 125,000.00 12,500.00
Kepala Tukang L.03 0.0100 150,000.00 1,500.00
Mandor L.04 0.0100 125,000.00 1,250.00
Jumlah Tenaga Kerja 37,250.00
B BAHAN :
Sement Portland Kg 3.2500 1,700.00 5,525.00
Jumlah Harga Bahan 5,525.00
C PERALATAN :
-
Jumlah Harga Alat -
D JUMLAH A + B + C 42,775.00
E OVERHEAD ₰ PROVIT 15% x D 6,416.25
F HARGA SATUAN PEKERJAAN (D + E) 49,191.25
Jenis Pekerjaan : Pemasangan 1 m3 Konstruksi Kuda - Kuda EXPOSE, Kayu
Kelas I
Satuan / Unit : m2
Analisa : AHSP PU A.4.6.1.14

HARGA JUMLAH
NO. URAIAN KODE SAT KOEF SAT HARGA
(Rp) (Rp)
A TENAGA :
Pekerja L.01 6.7000 110,000.00 737,000.00
Tukang L.02 20.1000 125,000.00 2,512,500.00
Kepala Tukang L.03 2.0100 150,000.00 301,500.00
Mandor L.04 0.3350 125,000.00 41,875.00
Jumlah Tenaga Kerja 3,592,875.00
B BAHAN :
Balok Kayu m3 1.2000 2,356,000.00 2,827,200.00
Besi Strip Tebal 5mm Kg 15.0000 15,000.00 225,000.00
Paku 12 Cm Kg 5.6000 20,000.00 112,000.00
Jumlah Harga Bahan 3,164,200.00
C PERALATAN :
-
Jumlah Harga Alat -
D JUMLAH A + B + C 6,757,075.00
E OVERHEAD ₰ PROVIT 15% x D 1,013,561.25
F HARGA SATUAN PEKERJAAN (D + E) 7,770,636.25
Jenis Pekerjaan : Pemasangan 1 mᶟ Konstruksi Gordeng, Kayu Kelas II
Satuan / Unit : m3
Analisa : AHSP PU A.4.6.1.15
HARGA JUMLAH
NO. URAIAN KODE SAT KOEF SAT HARGA
(Rp) (Rp)
A TENAGA :
Pekerja L.01 6.7000 110,000.00 737,000.00
Tukang L.02 20.1000 125,000.00 2,512,500.00
Kepala Tukang L.03 2.0100 150,000.00 301,500.00
Mandor L.04 0.3350 125,000.00 41,875.00
Jumlah Tenaga Kerja 3,592,875.00
B BAHAN :
Balok Kayu m3 1.1000 2,356,000.00 2,591,600.00
Besi Strip Tebal 5mm Kg 15.0000 15,000.00 225,000.00
Paku 12 Cm Kg 3.0000 20,000.00 60,000.00
Jumlah Harga Bahan 2,876,600.00
C PERALATAN :
-
Jumlah Harga Alat -
D JUMLAH A + B + C 6,469,475.00
E OVERHEAD ₰ PROVIT 15% x D 970,421.25
F HARGA SATUAN PEKERJAAN (D + E) 7,439,896.25
Jenis Pekerjaan : Pemasangan 1 mᶟ Konstruksi Gordeng, Kayu Kelas II
Satuan / Unit : m3
Analisa : AHSP PU A.4.6.1.15
HARGA JUMLAH
NO. URAIAN KODE SAT KOEF SAT HARGA
(Rp) (Rp)
A TENAGA :
Pekerja L.01 7.0000 110,000.00 770,000.00
Tukang L.02 21.0000 125,000.00 2,625,000.00
Kepala Tukang L.03 2.0100 150,000.00 301,500.00
Mandor L.04 0.3350 125,000.00 41,875.00
Jumlah Tenaga Kerja 3,738,375.00
B BAHAN :
Balok Kayu Kelas I Atau Kls II m3 1.1000 2,356,000.00 2,591,600.00
Paku Campur 5, 10 ,12 Kg 15.0000 20,000.00 300,000.00
Lem Kayu Kg 3.0000 25,000.00 75,000.00
Jumlah Harga Bahan 2,966,600.00
C PERALATAN :
-
Jumlah Harga Alat -
D JUMLAH A + B + C 6,704,975.00
E OVERHEAD ₰ PROVIT 15% x D 1,005,746.25
F HARGA SATUAN PEKERJAAN (D + E) 7,710,721.25
Jenis Pekerjaan : Buat Dan Pasang Daun Pintu Panil Kayu Kls. II
Satuan / Unit : m2
Analisa : AHSP PU A.4.6.1.5
HARGA JUMLAH
NO. URAIAN KODE SAT KOEF SAT HARGA
(Rp) (Rp)
A TENAGA :
Pekerja L.01 1.0000 110,000.00 110,000.00
Tukang L.02 3.0000 125,000.00 375,000.00
Kepala Tukang L.03 0.3000 150,000.00 45,000.00
Mandor L.04 0.0500 125,000.00 6,250.00
Jumlah Tenaga Kerja 536,250.00
B BAHAN :
Papan Kayu m3 1.1000 2,356,000.00 2,591,600.00
Lem Kayu Kg 3.0000 25,000.00 75,000.00
Jumlah Harga Bahan 2,666,600.00
C PERALATAN :
-
Jumlah Harga Alat -
D JUMLAH A + B + C 3,202,850.00
E OVERHEAD ₰ PROVIT 15% x D 480,427.50
F HARGA SATUAN PEKERJAAN (D + E) 3,683,277.50
Jenis Pekerjaan : Pemasangan 1m² Atap Seng Gelombang
Satuan / Unit : m1
Analisa : AHSP PU A.4.5.2.39

HARGA JUMLAH
NO. URAIAN KODE SAT KOEF SAT HARGA
(Rp) (Rp)
A TENAGA :
Pekerja L.01 0.1200 110,000.00 13,200.00
Tukang L.02 0.0600 125,000.00 7,500.00
Kepala Tukang L.03 0.0060 150,000.00 900.00
Mandor L.04 0.0060 125,000.00 750.00
Jumlah Tenaga Kerja 22,350.00
B BAHAN :
Seng Gelombang 3' x 6' Lbr 0.7000 138,000.00 96,600.00
Paku 1/2' - 1' Kg 0.0200 37,000.00 740.00
Jumlah Harga Bahan 97,340.00
C PERALATAN :
-
-
Jumlah Harga Alat -
D JUMLAH A + B + C 119,690.00
E OVERHEAD ₰ PROVIT 15% x D 17,953.50
F HARGA SATUAN PEKERJAAN (D + E) 137,643.50
Jenis Pekerjaan : Pemasangan 1m1 Plat Atap Seng Gelombang
Satuan / Unit : m1
Analisa : AHSP PU A.4.5.2.39

HARGA JUMLAH
NO. URAIAN KODE SAT KOEF SAT HARGA
(Rp) (Rp)
A TENAGA :
Pekerja L.01 0.1250 110,000.00 13,750.00
Tukang L.02 0.2500 125,000.00 31,250.00
Kepala Tukang L.03 0.0250 150,000.00 3,750.00
Mandor L.04 0.0060 125,000.00 750.00
Jumlah Tenaga Kerja 49,500.00
B BAHAN :
Bumbung Stel Gel Lbr 0.4000 11,666.67 4,666.67
Paku 1/2' - 1' Kg 0.0600 6,166.67 370.00
Jumlah Harga Bahan 5,036.67
C PERALATAN :
-
-
Jumlah Harga Alat -
D JUMLAH A + B + C 54,536.67
E OVERHEAD ₰ PROVIT 15% x D 8,180.50
F HARGA SATUAN PEKERJAAN (D + E) 62,717.17
Jenis Pekerjaan : A.4.6.1.21 Pemasangan 1 mˡ Lesplank Ukuran (3 x 20 )
Cm Kayu Kelas I Atau Kayu Kelas II
Satuan / Unit : m1
Analisa : AHSP PU A.4.6.1.21

HARGA JUMLAH
NO. URAIAN KODE SAT KOEF SAT HARGA
(Rp) (Rp)
A TENAGA :
Pekerja L.01 0.1000 110,000.00 11,000.00
Tukang L.02 0.2000 125,000.00 25,000.00
Kepala Tukang L.03 0.0200 150,000.00 3,000.00
Mandor L.04 0.0050 125,000.00 625.00
Jumlah Tenaga Kerja 39,625.00
B BAHAN :
Papan Kayu m3 0.0108 2,356,000.00 25,444.80
Paku 5 Dan 10 Cm Kg 0.1000 20,000.00 2,000.00
Jumlah Harga Bahan 27,444.80
C PERALATAN :
-
-
Jumlah Harga Alat -
D JUMLAH A + B + C 67,069.80
E OVERHEAD ₰ PROVIT 15% x D 10,060.47
F HARGA SATUAN PEKERJAAN (D + E) 77,130.27
Jenis Pekerjaan : Pemasangan 1m2 Lantai Ubin Warna Ukuran 40 x 40 Cm
Satuan / Unit : m2
Analisa : AHSP PU A.4.4.3.4

HARGA JUMLAH
NO. URAIAN KODE SAT KOEF SAT HARGA
(Rp) (Rp)
A TENAGA :
Pekerja L.01 0.1000 110,000.00 11,000.00
Tukang L.02 0.2000 125,000.00 25,000.00
Kepala Tukang L.03 0.0200 150,000.00 3,000.00
Mandor L.04 0.0050 125,000.00 625.00
Jumlah Tenaga Kerja 39,625.00
B BAHAN :
Ubin Warna Bh 6.6300 22,322.78 148,000.00
Sement Portland Kg 9.8000 1,700.00 16,660.00
Sement Warna Kg 0.6000 3,800.00 2,280.00
Pasir Pasang m3 0.0450 285,000.00 12,825.00

Jumlah Harga Bahan 179,765.00


C PERALATAN :
-
-
Jumlah Harga Alat -
D JUMLAH A + B + C 219,390.00
E OVERHEAD ₰ PROVIT 15% x D 32,908.50
F HARGA SATUAN PEKERJAAN (D + E) 252,298.50
Jenis Pekerjaan : A.4.6.2.2 Pemasangan 1 Buah Kunci Tanam Biasa
Satuan / Unit : Bh
Analisa : AHSP PU A.4.6.2.2

HARGA JUMLAH
NO. URAIAN KODE SAT KOEF SAT HARGA
(Rp) (Rp)
A TENAGA :
Pekerja L.01 0.0100 110,000.00 1,100.00
Tukang L.02 0.5000 125,000.00 62,500.00
Kepala Tukang L.03 0.0500 150,000.00 7,500.00
Mandor L.04 0.0050 125,000.00 625.00
Jumlah Tenaga Kerja 71,725.00
B BAHAN :
Kunci Tanam Biasa Bh 1.0000 27,000.00 27,000.00
Jumlah Harga Bahan 27,000.00
C PERALATAN :
-
-
Jumlah Harga Alat -
D JUMLAH A + B + C 98,725.00
E OVERHEAD ₰ PROVIT 15% x D 14,808.75
F HARGA SATUAN PEKERJAAN (D + E) 113,533.75
Jenis Pekerjaan : Pemasangan Buah Engsel Pintu
Satuan / Unit : Bh
Analisa : AHSP PU A.4.6.2.5

HARGA JUMLAH
NO. URAIAN KODE SAT KOEF SAT HARGA
(Rp) (Rp)
A TENAGA :
Pekerja L.01 0.0150 110,000.00 1,650.00
Tukang L.02 0.1500 125,000.00 18,750.00
Kepala Tukang L.03 0.0150 150,000.00 2,250.00
Mandor L.04 0.0008 125,000.00 100.00
Jumlah Tenaga Kerja 22,750.00
B BAHAN :
Engsel Pintu Bh 1.0000 15,000.00 15,000.00
Jumlah Harga Bahan 15,000.00
C PERALATAN :
-
-
Jumlah Harga Alat -
D JUMLAH A + B + C 37,750.00
E OVERHEAD ₰ PROVIT 15% x D 5,662.50
F HARGA SATUAN PEKERJAAN (D + E) 43,412.50
Jenis Pekerjaan : Pemasangan 1 Bh Kait Angin
Satuan / Unit : Bh
Analisa : AHSP PU A.4.6.2.9

HARGA JUMLAH
NO. URAIAN KODE SAT KOEF SAT HARGA
(Rp) (Rp)
A TENAGA :
Pekerja L.01 0.0150 110,000.00 1,650.00
Tukang L.02 0.1500 125,000.00 18,750.00
Kepala Tukang L.03 0.0150 150,000.00 2,250.00
Mandor L.04 0.0008 125,000.00 100.00
Jumlah Tenaga Kerja 22,750.00
B BAHAN :
Hak Angin Bh 1.0000 7,000.00 7,000.00
Jumlah Harga Bahan 7,000.00
C PERALATAN :
-
-
Jumlah Harga Alat -
D JUMLAH A + B + C 29,750.00
E OVERHEAD ₰ PROVIT 15% x D 4,462.50
F HARGA SATUAN PEKERJAAN (D + E) 34,212.50
Jenis Pekerjaan : 1 M2 Pasang rangka dinding pemisah ( 60 x 120)cm kayu
kelas II atau III
Satuan / Unit : m2
Analisa : SNI 6.6.58
HARGA JUMLAH
NO. URAIAN KODE SAT KOEF SAT HARGA
(Rp) (Rp)
A TENAGA :
Pekerja L.01 0.1500 110,000.00 16,500.00
Tukang L.02 0.4500 125,000.00 56,250.00
Kepala Tukang L.03 0.0450 150,000.00 6,750.00
Mandor L.04 0.0080 125,000.00 1,000.00
Jumlah Tenaga Kerja 80,500.00
B BAHAN :
Balok Kayu Kelas I Atau Kls II m3 0.0280 2,356,000.00 65,968.00
Paku Campur 5, 10 ,12 Kg 0.1500 20,000.00 3,000.00
Jumlah Harga Bahan 68,968.00
C PERALATAN :
-
Jumlah Harga Alat -
D JUMLAH A + B + C 149,468.00
E OVERHEAD ₰ PROVIT 15% x D 22,420.20
F HARGA SATUAN PEKERJAAN (D + E) 171,888.20
Jenis Pekerjaan : Pemasangan 1 m2 Dinding Papan Diketam
Satuan / Unit : m2
Analisa : SNI Suplement
HARGA JUMLAH
NO. URAIAN KODE SAT KOEF SAT HARGA
(Rp) (Rp)
A TENAGA :
Pekerja L.01 0.2800 110,000.00 30,800.00
Tukang L.02 0.8000 125,000.00 100,000.00
Kepala Tukang L.03 0.0800 150,000.00 12,000.00
Mandor L.04 0.0100 125,000.00 1,250.00
Jumlah Tenaga Kerja 144,050.00
B BAHAN :
Papan Kayu m3 0.0240 2,356,000.00 56,544.00
Paku Campur 5, 10 ,12 Kg 0.2000 20,000.00 4,000.00
Jumlah Harga Bahan 60,544.00
C PERALATAN :
-
Jumlah Harga Alat -
D JUMLAH A + B + C 204,594.00
E OVERHEAD ₰ PROVIT 15% x D 30,689.10
F HARGA SATUAN PEKERJAAN (D + E) 235,283.10
Jenis Pekerjaan : Pengecatan Bidang Kayu Baru (1 Lapis Plamuur, 1 Lapis
Cat Dasar 2 Kali Cat Penutup
Satuan / Unit : m2
Analisa : AHSP PU A.4.7.1.4

HARGA JUMLAH
NO. URAIAN KODE SAT KOEF SAT HARGA
(Rp) (Rp)
A TENAGA :
Pekerja L.01 0.0700 110,000.00 7,700.00
Tukang L.02 0.0090 125,000.00 1,125.00
Kepala Tukang L.03 0.0060 150,000.00 900.00
Mandor L.04 0.0030 125,000.00 375.00
Jumlah Tenaga Kerja 10,100.00
B BAHAN :
Cat Menie Kayu/ Besi Kg 0.2000 25,000.00 5,000.00
Plamuur Tembok Boyo Kg 0.1500 13,800.00 2,070.00
Cat Dasar Meni Kayu/ Besi Kg 0.1700 25,000.00 4,250.00
Cat Penutup Kayu Avian Kg 0.2600 72,000.00 18,720.00
Kuas Buah 0.0100 25,000.00 250.00
Pengencer ( Minyak Cat) Kg 0.0300 35,000.00 1,050.00
Amplas Lbr 0.2000 7,000.00 1,400.00
Jumlah Harga Bahan 32,740.00
C PERALATAN :
-
Jumlah Harga Alat -
D JUMLAH A + B + C 42,840.00
E OVERHEAD ₰ PROVIT 15% x D 6,426.00
F HARGA SATUAN PEKERJAAN (D + E) 49,266.00
Jenis Pekerjaan : Pemasangan Fondasi Batu Belah Camp 1Pc : 4Ps
Satuan / Unit : m3
Analisa : AHSP PU A.3.2.1.2

HARGA JUMLAH
NO. URAIAN KODE SAT KOEF SAT HARGA
(Rp) (Rp)
A TENAGA :
Pekerja L.01 0.0200 110,000.00 2,200.00
Tukang L.02 0.0630 125,000.00 7,875.00
Kepala Tukang L.03 0.0063 150,000.00 945.00
Mandor L.04 0.0030 125,000.00 375.00
Jumlah Tenaga Kerja 11,395.00
B BAHAN :
Plamur m3 0.10 13,800.00 1,380.00
Cat Dasar Kg 0.10 -
Cat Penutup m3 0.26 -
Jumlah Harga Bahan 1,380.00
C PERALATAN :
-
Jumlah Harga Alat -
D JUMLAH A + B + C 12,775.00
E OVERHEAD ₰ PROVIT 15% x D 1,916.25
F HARGA SATUAN PEKERJAAN (D + E) 14,691.25
Jenis Pekerjaan : Pemasangan 1 m2 Kaca Tebal 3mm
Satuan / Unit : m2
Analisa : AHSP PU A.4.6.2.16
HARGA JUMLAH
NO. URAIAN KODE SAT KOEF SAT HARGA
(Rp) (Rp)
A TENAGA :
Pekerja L.01 0.0150 110,000.00 1,650.00
Tukang L.02 0.1500 125,000.00 18,750.00
Kepala Tukang L.03 0.0150 150,000.00 2,250.00
Mandor L.04 0.0008 125,000.00 100.00
Jumlah Tenaga Kerja 22,750.00
B BAHAN :
Kaca Tbal 3mm m2 1.1000 200,000.00 220,000.00
Sealen Kg 0.0500 1,500.00 75.00
Jumlah Harga Bahan 220,075.00
C PERALATAN :
-
Jumlah Harga Alat -
D JUMLAH A + B + C 242,825.00
E OVERHEAD ₰ PROVIT 15% x D 36,423.75
F HARGA SATUAN PEKERJAAN (D + E) 279,248.75
Besi 6 44,641.00 0.22 Kg/m 12.00 2.64 Kg 16,909 Kg 44,641.00
Besi 8 70,041.00 0.39 Kg/m 12.00 4.68 Kg 14,966 Kg 70,041.00
Besi 10 100,521.00 0.62 Kg/m 12.00 7.44 Kg 13,511 Kg 100,521.00
Besi 12 139,891.00 0.89 Kg/m 12.00 10.68 Kg 13,098 Kg 139,891.00
Besi 14 171,641.00 1.54 Kg/m 12.00 18.48 Kg 9,288 Kg 171,641.00
Besi 16 222,441.00 2.01 Kg/m 12.00 24.12 Kg 9,222 Kg 222,441.00