Debt">
Valorizacion 08 Huanipaca Ok. (1) Ultimo
Valorizacion 08 Huanipaca Ok. (1) Ultimo
Valorizacion 08 Huanipaca Ok. (1) Ultimo
CONSORCIO Caleon
VALORIZACION Nº 07
(01 AL 30 DE SETIEMBRE 2020)
ENTIDAD : MUNICIPALIDAD DISTRITAL DE HUANIPACA
A: VALORIZACION CONTRACTUAL
B: REAJUSTES
0.00 0.00 0.00 0.00 0.00
TOTAL REAJUSTE (B) 0.00 0.00 0.00 0.00 0.00
C: DEDUCCIONES
DEDUCCION ADELANTO EN EFECTIVO 0.00 0.00 0.00 0.00
DEDUCCION ADELANTO DE MATERIAL 0.00 0.00 0.00 0.00
TOTAL DEDUCCION (C) 0.00 0.00 0.00 0.00
D: AMORTIZACIONES
AMORTIZACION ADELANTO EFECTIVO N°01 787,473.27 787,473.27 0.00 787,473.27 0.00
AMORTIZACION ADELANTO EFECTIVO N°02 393,736.64 393,736.64 0.00 393,736.64 0.00
AMORTIZACION ADELANTO DE MATERIAL 0.00 0.00 0.00 0.00 0.00
TOTAL AMORTIZACION (D) 1,181,209.91 1,181,209.91 0.00 1,181,209.91 0.00
E: RETENCIONES
GASTOS DE LICITACION 0.00 0.00 0.00 0.00 0.00
MULTA POR ATRASO DE OBRA 0.00 0.00 0.00 0.00 0.00
TOTAL (E) 0.00 0.00 0.00 0.00 0.00
0.00%
CONSORCIO CALEON
RESUMEN DE VALORIZACIÓN MENSUAL N°08 POR LOCALIDAD
“MEJORAMIENTO DEL SERVICIO EDUCATIVO EN LAS INSTITUCIONES EDUCATIVAS DEL NIVEL INICIAL CICLO II EN LAS LOCALIDADES DE HUANCHULLA, TACMARA, KIUÑALLA, KARQUEQUI, PACOBAMBA Y HUANIPACA DEL
OBRA
DISTRITO DE HUANIPACA, PROVINCIA ABANCAY - APURÍMAC”.
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE HUANIPACA
DISTRITO : HUANIPACA
PROVINCIA : ABANCAY
REGION : APURIMAC
CONTRATISTA : CONSORCIO COCHARCAS
SUPERVISION : CONSORCIO CALEON
FECHA Oct-20
SALDO POR
VALORIZACIÓN AVANCE ACUMULADO
VALORIZAR
MONTO DEL
DESCRIPCIÓN
CONTRATO S/. AGOSTO SETIEMBRE OCTUBRE ( NOVIEMBRE 22/11/2019 AL 16/03/2020 AL JULIO AGOSTO SETIEMBRE OCTUBRE (01-
(20 -1/2019) (01-30/2019) 01-31/2019) (01-21/2019) 16/03/2020 19/07/2020 (20-31/2020) (01-31/2020) (01-30/2020) 04/2020)
MONTO S/. % MONTO S/. %
I.E.I N° 156 HUANCHULLA 1,365,459.33 92,172.42 6.75 212,249.13 15.54 183,450.03 13.44 178,534.50 13.08 83,906.85 6.14 233,955.12 17.13 258,233.72 18.91 122,957.56 9.00 1,365,459.33 100.00 0.00 0.00
I.E.I N° 669 KARQUEQUI 1,245,971.25 72,800.71 5.84 194,203.90 15.59 172,772.41 13.87 194,936.98 15.65 58,914.93 4.73 204,989.38 16.45 241,505.20 19.38 105,847.74 8.50 1,245,971.25 100.00 0.00 0.00
I.E.I N° 1096 PACOBAMBA 1,154,796.37 90,138.00 7.81 199,792.36 17.30 186,296.48 16.13 183,107.50 15.86 82,312.32 7.13 163,486.97 14.16 164,052.06 14.21 85,610.68 7.41 1,154,796.37 100.00 0.00 0.00
I.E.I N° 157 KIUÑALLA 1,474,209.88 56,518.50 3.83 136,472.66 9.26 277,293.23 18.81 183,140.44 12.42 12,589.36 0.85 126,141.10 8.56 342,313.33 23.22 339,741.26 23.05 1,474,209.89 100.00 0.00 0.00
I.E.I N° 158 TACMARA 1,322,099.33 66,057.87 5.00 229,921.73 17.39 163,156.53 12.34 213,496.27 16.15 129,099.82 9.76 220,191.46 16.65 205,848.00 15.57 94,327.64 7.13 1,322,099.32 100.00 0.00 0.00
I.E.I N° 29 HUANIPACA 1,312,196.57 83,274.97 6.35 226,324.20 17.25 202,143.62 15.40 171,674.04 13.08 95,750.53 7.30 218,322.12 16.64 245,199.99 18.69 69,507.10 5.30 1,312,196.57 100.00 0.00 0.00
SUB TOTAL (A) 7,874,732.72 460,962.47 5.85 1,198,964.00 15.23 1,185,112.29 15.05 1,124,889.73 14.28 462,573.81 5.87 1,167,086.15 14.82 1,457,152.30 18.50 817,991.99 10.39 7,874,732.73 100.00 -0.01 0.00
IGV (18%) 1,417,451.89 82,973.24 215,813.52 213,320.21 202,480.15 83,263.29 210,075.51 262287.41% 147238.56% 1,417,451.89 0.00
PPTO. TOTAL S/. 9,292,184.61 543,935.71 5.85 1,414,777.52 15.23 1,398,432.50 15.05 1,327,369.88 14.28 545,837.10 5.87 1,377,161.66 14.82 1,719,439.71 18.50 965,230.55 10.39 9,292,184.63 100.00 -0.02 0.00
CONSORCIO CALEON
CALCULO DE LA AMORTIZACION DEL ADELANTO DIRECTO N° 08
OBRA "MEJORAMIENTO DEL SERVICIO EDUCATIVO EN LAS I. E. DEL NIVEL INICIAL CICLO II EN LA LOCALIDADES DE HUANCHULLA, TACMARA, KIUÑALLA,
OBRA KARQUEQUI, PACOMABAMBA Y HUANIPACA DEL DISTRITO DE HUANIPACA, PROVINCIA DE ABANCAY - APURIMAC"
TOTAL S/.
7,874,732.73 787,473.27 100 393,736.64 100.00 393,736.64 0.00
100.00% 0.00%
SALDO POR VALORIZAR (S/.) - 0.01
SALDO POR AMORTIZAR (S/.) 0.00
AMORTIZ. ACUMULADA (S/.) 393,736.64
AMORT. (OCTUBRE - 2020) S/. 131,312.79
CONSORCIO CALEON
CURVA DE AVANCE DE OBRA EJECUTADO VS. PROGRAMADO VIGENTE
VALORIZACION N° 08
ENTIDAD MUNICIPALIDAD DISTRITAL DE HUANIPACA
“MEJORAMIENTO DEL SERVICIO EDUCATIVO EN LAS INSTITUCIONES EDUCATIVAS DEL NIVEL INICIAL CICLO II EN LAS LOCALIDADES DE HUANCHULLA, TACMARA, KIUÑALLA, KARQUEQUI, PACOBAMBA Y HUANIPACA DEL
DISTRITO DE HUANIPACA, PROVINCIA DE ABANCAY - APURÍMAC”.
OBRA
CONTRATISTA CONSORCIO COCHARCAS
SUPERVISON CONSORCIO CALEON
FECHA Oct-20
120.00%
100.00%
99.45%
100.00%
93.88%
89.61%
80.00% 78.81%
71.10%
63.00%
60.00%
56.10% 56.28%
50.41%
42.29%
40.00%
36.13%
23.73%
21.08%
20.00%
5.85%
0.00%
0.00%
20 de agosto 2019 Del 01 al 31 de agosto 2019 Del 01 al 30 de setiembre 2019 Del 01 al 31 de octubre 2019 Del 01 al 21 de noviembre 2019 suspension de plazo de ejecucion paralizacion de ejecucion de obra Del 20 al 31 de julio 2020 Del 01 al 31 de agosto 2020 Del 01 al 30 de setiembre 2020 Del 01 al 19 de octubre 2020
de obra (Precipitaciones (COVID-19)
pluviales)
paralizacion de ejecucion
DESCRIPCION
suspension de plazo de
Del 01 al 31 de agosto Del 01 al 30 de Del 01 al 31 de octubre Del 01 al 21 de Del 20 al 31 de julio Del 01 al 31 de agosto Del 01 al 30 de Del 01 al 19 de octubre
20 de agosto 2019
de obra (COVID-19)
ejecucion de obra
2019 setiembre 2019 2019 noviembre 2019 2020 2020 setiembre 2020 2020
PROG. MENSUAL 0.00% 5.85% 17.88% 18.56% 13.81% 6.90% 15.81% 15.07% 6.12%
ACUMULADO. PROG. 0.00% 5.85% 23.73% 42.29% 56.10% 63.00% 78.81% 93.88% 100.00%
EJEC. MENSUAL 0.00% 5.85% 15.23% 15.05% 14.28% 5.87% 14.82% 18.51% 9.84%
ACUMULADO. EJEC. 0.00% 5.85% 21.08% 36.13% 50.41% 56.28% 71.10% 89.61% 99.45%
0.55%
CONSORCIO CALEON
OBRA "MEJORAMIENTO DEL SERVICIO EDUCATIVO EN LAS I. E. DEL NIVEL INICIAL CICLO II EN LA LOCALIDADES DE HUANCHULLA, TACMARA, KIUÑALLA, KARQUEQUI, PACOMABAMBA Y HUANIPACA DEL DISTRITO DE HUANIPACA, PROVINCIA DE ABANCAY - APURIMAC"
100%
CONSORCIO CALEON
OBRA "MEJORAMIENTO DEL SERVICIO EDUCATIVO EN LAS I. E. DEL NIVEL INICIAL CICLO II EN LA LOCALIDADES DE HUANCHULLA, TACMARA, KIUÑALLA, KARQUEQUI, PACOMABAMBA Y HUANIPACA DEL DISTRITO DE HUANIPACA, PROVINCIA DE ABANCAY - APURIMAC"
02.01.04.08 PARAPETO
02.01.04.08 CONCRETO F'C= 175 KG/CM2 EN PARAPETOS m3 24.55 394.26 9,679.08 24.55 9,679.08 100% - 0% 24.55 9,679.08 100% 0.00 - 0%
02.01.04.08 ACERO CORRUGADO G-60 EN PARAPETOS kg 1088.70 4.20 4,572.54 1088.70 4,572.54 100% - 0% 1088.70 4,572.54 100% 0.00 - 0%
02.01.04.08 ENCOFRADO Y DESENCOFRADO DE PARAPETOS m2 404.82 32.00 12,954.24 404.82 12,954.24 100% - 0% 404.82 12,954.24 100% 0.00 - 0%
02.01.04.09 MESA DE CONCRETO
02.01.04.09 CONCRETO F'C= 175 KG/CM2 EN MESA DE CONCRETO m3 1.09 394.26 429.74 1.09 429.74 100% - 0% 1.09 429.74 100% 0.00 - 0%
02.01.04.09 ACERO CORRUGADO G-60 EN MESA DE CONCRETO kg 45.89 4.20 192.74 45.89 192.74 100% - 0% 45.89 192.74 100% 0.00 - 0%
02.01.04.09 ENCOFRADO Y DESENCOFRADO EN MESA DE CONCRETO m2 26.93 32.00 861.76 26.93 861.76 100% - 0% 26.93 861.76 100% 0.00 - 0%
02.02 PRUEBAS Y ENSAYOS DE LABORATORIO
02.02.01 ROTURA DE BRIQUETAS und 20.00 73.84 1,476.80 20.00 1,476.80 100% - 0% 20.00 1,476.80 100% 0.00 - 0%
02.02.02 DISEÑO DE MEZCLA und 10.00 350.00 3,500.00 10.00 3,500.00 100% - 0% 10.00 3,500.00 100% 0.00 - 0%
03 ARQUITECTURA
03.01 BLOQUES I, II, III, IV.
03.01.01 MUROS Y TABIQUES
03.01.01.01 MURO DE CABEZA LADRILLO KIN-KONG DE ARCILLA m2 176.71 133.27 23,550.14 176.71 23,550.14 100% - 0% 176.71 23,550.14 100% 0.00 - 0%
03.01.01.02 MURO DE SOGA LADRILLO KIN-KONG DE ARCILLA m2 110.35 88.36 9,750.53 110.35 9,750.53 100% - 0% 110.35 9,750.53 100% 0.00 - 0%
03.01.02 REVOQUES ENLUCIDOS Y MOLDURAS
03.01.02.01 TARRAJEO PRIMARIO RAYADO CON CEMENTO-ARENA 1:5 m2 140.51 22.75 3,196.60 140.51 3,196.60 100% - 0% 140.51 3,196.60 100% 0.00 - 0%
03.01.02.02 TARRAJEO EN MUROS INTERIORES MEZCLA 1:5 CEMENTO:ARE m2 401.62 29.30 11,767.47 401.62 11,767.47 100% - 0% 401.62 11,767.47 100% 0.00 - 0%
03.01.02.03 TARRAJEO EN MUROS EXTERIORES MEZCLA 1:5 CEMENTO:ARE m2 200.05 29.30 5,861.47 200.05 5,861.47 100% - 0% 200.05 5,861.47 100% 0.00 - 0%
03.01.02.04 TARRAJEO DE SUPERFICIE COLUMNAS INCL. ARISTAS MEZCLA m2 143.75 34.67 4,983.81 143.75 4,983.81 100% - 0% 143.75 4,983.81 100% 0.00 - 0%
03.01.02.05 TARRAJEO DE SUPERF.VIGAS INCL.ARISTAS, MEZCLA 1:5 CEME m2 298.51 34.67 10,349.34 298.51 10,349.34 100% - 0% 298.51 10,349.34 100% 0.00 - 0%
03.01.02.06 TARRAJEO CON IMPERMEABILIZANTE EN COBERTURAS m2 321.73 40.19 12,930.33 321.73 12,930.33 100% - 0% 321.73 12,930.33 100% 0.00 - 0%
03.01.02.07 TARRAJEO EN CUNETA DE EVACUACION PLUVIAL EXTERIOR - T m2 199.43 34.09 6,798.57 199.43 6,798.57 100% - 0% 199.43 6,798.57 100% 0.00 - 0%
03.01.02.08 TARRAJEO CON IMPERMEABILIZANTE EN CUNETA INTERIOR - T m2 147.42 38.34 5,652.08 147.42 5,652.08 100% - 0% 147.42 5,652.08 100% 0.00 - 0%
03.01.02.09 VESTIDURA DE DERRAMES m 221.04 16.02 3,541.06 221.04 3,541.06 100% - 0% 221.04 3,541.06 100% 0.00 - 0%
03.01.02.10 BRUÑA DE 1CM ENTRE MUROS Y ESTRUCTURAS COLUMNA m 418.40 2.15 899.56 418.40 899.56 100% - 0% 418.40 899.56 100% 0.00 - 0%
03.01.02.11 BRUÑA DE 1CM ENTRE MUROS Y ESTRUCTURAS VIGA m 245.69 2.73 670.73 245.69 670.73 100% - 0% 245.69 670.73 100% 0.00 - 0%
03.01.02.12 JUNTA DE CONSTRUCCION CON TEKNOPORT m 94.06 3.20 300.99 94.06 300.99 100% - 0% 94.06 300.99 100% 0.00 - 0%
03.01.03 ESTRUCTURAS METALICAS
03.01.03.01 CORREAS DE TUBO LAC 2"X2"X2mm m 407.00 22.54 9,173.78 407.00 9,173.78 100% - 0% 407.00 9,173.78 100% 0.00 - 0%
03.01.04 COBERTURA
03.01.04.01 COBERTURA DE TEJA ANDINA m2 327.56 29.66 9,715.43 327.56 9,715.43 100% - 0% 327.56 9,715.43 100% 0.00 - 0%
03.01.04.02 CUMBRERA DE TEJA ANDINA m 104.16 41.60 4,333.06 104.16 4,333.06 100% - 0% 104.16 4,333.06 100% 0.00 - 0%
03.01.05 CIELORRASOS
03.01.05.01 CIELORRASOS CON MEZCLA C:A 1:5 e= 1.5 CM m2 296.82 32.46 9,634.78 296.82 9,634.78 100% - 0% 296.82 9,634.78 100% 0.00 - 0%
03.01.06 PISOS Y PAVIMENTOS
03.01.06.01 FALSO PISO DE 4" DE CONCRETO 1:10 m2 227.49 32.43 7,377.50 227.49 7,377.50 100% - 0% 227.49 7,377.50 100% 0.00 - 0%
03.01.06.02 CONTRAPISO DE 48 MM. m2 227.49 19.71 4,483.83 227.49 4,483.83 100% - 0% 227.49 4,483.83 100% 0.00 - 0%
03.01.06.03 PISO DE CERAMICO ANTIDESLIZANTE AT. 0.30x0.30 M m2 110.07 40.54 4,462.24 110.07 4,462.24 100% - 0% 110.07 4,462.24 100% 0.00 - 0%
03.01.06.04 PISO DE MADERA MACHIHEMBRADA m2 117.42 49.65 5,829.90 117.42 5,829.90 100% - 0% 117.42 5,829.90 100% 0.00 - 0%
03.01.07 ZOCALOS Y CONTRAZOCALOS
03.01.07.01 ZOCALO DE CERAMICO 0.30 x 0.20 M m2 95.33 41.52 3,958.10 95.33 3,958.10 100% - 0% 95.33 3,958.10 100% 0.00 - 0%
CONSORCIO CALEON
OBRA "MEJORAMIENTO DEL SERVICIO EDUCATIVO EN LAS I. E. DEL NIVEL INICIAL CICLO II EN LA LOCALIDADES DE HUANCHULLA, TACMARA, KIUÑALLA, KARQUEQUI, PACOMABAMBA Y HUANIPACA DEL DISTRITO DE HUANIPACA, PROVINCIA DE ABANCAY - APURIMAC"
03.01.07.02 ZOCALO DE CEMENTO PULIDO C/MORTERO 1:5 DE 2CM. DE H= m 139.66 23.60 3,295.98 139.66 3,295.98 100% - 0% 139.66 3,295.98 100% 0.00 - 0%
03.01.07.03 CONTRAZOCALO DE CERAMICO DE 30 x 30 CM. H=10CM. - INTER m 97.04 14.15 1,373.12 97.04 1,373.12 100% - 0% 97.04 1,373.12 100% 0.00 - 0%
03.01.07.04 CONTRAZOCALO DE MADERA H=10CM m 67.20 22.58 1,517.38 0.00 - 0% 67.20 1,517.38 100% 67.20 1,517.38 100% 0.00 - 0%
03.01.08 CARPINTERIA DE MADERA
03.01.08.01 PUERTA DE MADERA AGUANO TABLERO REBAJADO SIN/SOBRE m2 31.36 332.04 10,412.77 24.98 8,294.36 80% 6.38 2,118.42 20% 31.36 10,412.78 100% 0.00 - 0%
03.01.08.02 PUERTA CONTRAPLACADA CON PLANCHA DE TRIPLAY DE 6 mm m2 17.24 315.98 5,447.50 13.82 4,366.84 80% 3.42 1,080.65 20% 17.24 5,447.49 100% 0.00 - 0%
03.01.09 CERRAJERIA
03.01.09.01 BISAGRA CAPUCHINA DE 4" und 54.00 17.93 968.22 43.00 770.99 80% 11.00 197.23 20% 54.00 968.22 100% 0.00 - 0%
03.01.09.02 CERRADURA PARA PUERTA DE TRES GOLPES und 11.00 104.09 1,144.99 9.00 936.81 82% 2.00 208.18 18% 11.00 1,144.99 100% 0.00 - 0%
03.01.09.03 CERRADURA DE PERILLA CON SEGURIDAD INTERIOR und 7.00 93.14 651.98 6.00 558.84 86% 1.00 93.14 14% 7.00 651.98 100% 0.00 - 0%
03.01.10 VIDRIOS, CRISTALES Y SIMILARES
03.01.10.01 VIDRIO SISTEMA NOVA INC. ACCESORIOS m2 41.82 114.89 4,804.70 21.00 2,412.69 50% 20.82 2,392.01 50% 41.82 4,804.70 100% 0.00 - 0%
03.01.10.02 VIDRIO CRUDO INCOLORO DE 6MM. m2 13.29 47.29 628.48 0.00 - 0% 13.29 628.48 100% 13.29 628.48 100% 0.00 - 0%
03.01.11 PINTURA
03.01.11.01 PINTURA EN CIELORRASO m2 296.82 15.25 4,526.51 296.82 4,526.51 100% - 0% 296.82 4,526.51 100% 0.00 - 0%
03.01.11.02 PINTURA EN INTERIORES m2 395.47 12.22 4,832.64 395.47 4,832.64 100% - 0% 395.47 4,832.64 100% 0.00 - 0%
03.01.11.03 PINTURA EN EXTERIORES m2 200.05 12.22 2,444.61 200.05 2,444.61 100% - 0% 200.05 2,444.61 100% 0.00 - 0%
03.01.11.04 PINTURA EN COLUMNAS m2 143.75 15.71 2,258.31 143.75 2,258.31 100% - 0% 143.75 2,258.31 100% 0.00 - 0%
03.01.11.05 PINTURA EN VIGA m2 302.06 15.71 4,745.36 302.06 4,745.36 100% - 0% 302.06 4,745.36 100% 0.00 - 0%
03.01.11.06 PINTURA EN DERRAME m2 221.04 10.68 2,360.71 221.04 2,360.71 100% - 0% 221.04 2,360.71 100% 0.00 - 0%
03.01.11.07 PINTURA EN CONTRAZOCALOS Y ZOCALOS H= 0.40M C/ESMALT m 124.90 6.53 815.60 0.00 - 0% 124.90 815.60 100% 124.90 815.60 100% 0.00 - 0%
03.01.11.08 PINTURA EN PUERTAS C/BARNIZ 2 MANOS m2 78.39 12.32 965.76 0.00 - 0% 78.39 965.76 100% 78.39 965.76 100% 0.00 - 0%
04 INSTALACIONES SANITARIAS
04.01 APARATOS SANITARIOS Y ACCESORIOS BLOQUES I, II, III, IV.
04.01.01 SUMINISTRO DE APARATO SANITARIOS
04.01.01.01 LAVADERO DE COCINA DE ACERO INOXIDABLE (INCLUYE ACCE und 3.00 150.00 450.00 3.00 450.00 100% - 0% 3.00 450.00 100% 0.00 - 0%
04.01.01.02 INODORO SIFON JEET COLOR BLANCO und 3.00 180.00 540.00 0.00 - 0% 3.00 540.00 100% 3.00 540.00 100% 0.00 - 0%
04.01.01.03 LAVATORIO TIPO ESTANDAR BLANCO und 5.00 144.00 720.00 0.00 - 0% 5.00 720.00 100% 5.00 720.00 100% 0.00 - 0%
04.01.01.04 INODORO BABY FRESH COLOR BLANCO und 2.00 228.00 456.00 0.00 - 0% 2.00 456.00 100% 2.00 456.00 100% 0.00 - 0%
04.01.01.05 URINARIO BAMBI DE LOSA BLANCO und 1.00 118.00 118.00 0.00 - 0% 1.00 118.00 100% 1.00 118.00 100% 0.00 - 0%
04.01.02 INSTALACION DE APARATOS SANITARIOS
04.01.02.01 COLOCACION DE APARATOS SANITARIOS und 14.00 53.74 752.36 7.00 376.18 50% 7.00 376.18 50% 14.00 752.36 100% 0.00 - 0%
04.01.03 SUMINISTRO DE ACCESORIOS
04.01.03.01 JABONERA DE LOSA COLOR BLANCO und 2.00 16.90 33.80 0.00 - 0% 2.00 33.80 100% 2.00 33.80 100% 0.00 - 0%
04.01.03.02 PAPELERA DE LOSA COLOR BLANCO und 5.00 14.50 72.50 0.00 - 0% 5.00 72.50 100% 5.00 72.50 100% 0.00 - 0%
04.01.03.03 DISPENSADORA DE JABON LIQUIDO und 5.00 16.90 84.50 0.00 - 0% 5.00 84.50 100% 5.00 84.50 100% 0.00 - 0%
04.01.03.04 ESPEJO DE 4MM DE 1.20 x 0.50M. und 5.00 35.00 175.00 0.00 - 0% 5.00 175.00 100% 5.00 175.00 100% 0.00 - 0%
04.01.04 INSTALACION DE ACCESORIOS
04.01.04.01 COLOCACION DE ACCESORIOS SANITARIOS und 17.00 26.87 456.79 0.00 - 0% 17.00 456.79 100% 17.00 456.79 100% 0.00 - 0%
04.01.05 SISTEMA DE AGUA FRIA Y ALIMENTADORES
04.01.05.01 SALIDA DE AGUA FRIA
04.01.05.01 SALIDA DE AGUA FRIA CON TUBERIA DE PVC-SAP 1/2" pto 21.00 36.15 759.15 21.00 759.15 100% - 0% 21.00 759.15 100% 0.00 - 0%
04.01.05.02 REDES DE DISTRIBUCION DE AGUA FRIA
CONSORCIO CALEON
OBRA "MEJORAMIENTO DEL SERVICIO EDUCATIVO EN LAS I. E. DEL NIVEL INICIAL CICLO II EN LA LOCALIDADES DE HUANCHULLA, TACMARA, KIUÑALLA, KARQUEQUI, PACOMABAMBA Y HUANIPACA DEL DISTRITO DE HUANIPACA, PROVINCIA DE ABANCAY - APURIMAC"
04.01.05.02 RED DE DISTRIBUCION TUBERIA PVC SAP C-10 Ø DE 1/2" m 38.56 17.08 658.60 38.56 658.60 100% - 0% 38.56 658.60 100% 0.00 - 0%
04.01.05.02 RED DE DISTRIBUCION TUBERIA PVC SAP C-10 Ø DE 3/4" m 12.22 17.43 212.99 12.22 212.99 100% - 0% 12.22 212.99 100% 0.00 - 0%
04.01.05.02 SUMINISTRO E INSTALACION DE ACCESORIOS GLB 1.00 67.41 67.41 1.00 67.41 100% - 0% 1.00 67.41 100% 0.00 - 0%
04.01.05.03 VALVULA Y ACCESORIOS DE AGUA FRIA
04.01.05.03 VALVULA COMPUERTA DE BRONCE Ø 1/2" und 6.00 74.44 446.64 6.00 446.64 100% - 0% 6.00 446.64 100% 0.00 - 0%
04.01.05.03 VALVULA COMPUERTA DE BRONCE Ø 3/4" und 4.00 80.01 320.04 4.00 320.04 100% - 0% 4.00 320.04 100% 0.00 - 0%
04.01.06 SISTEMA DE DESAGUE Y VENTILACION
04.01.06.01 SALIDA DE DESAGUE Y VENTILACION
04.01.06.01 SALIDAS DE PVC SAL PARA DESAGUE DE 2" pto 32.00 31.10 995.20 32.00 995.20 100% - 0% 32.00 995.20 100% 0.00 - 0%
04.01.06.01 SALIDAS DE PVC SAL PARA DESAGUE DE 4" pto 7.00 45.09 315.63 7.00 315.63 100% - 0% 7.00 315.63 100% 0.00 - 0%
04.01.06.01 SALIDAS DE PVC SAL PARA VENTILACION DE 2" pto 7.00 25.64 179.48 7.00 179.48 100% - 0% 7.00 179.48 100% 0.00 - 0%
04.01.06.01 SOMBRERO VENTILACION PVC DE 2" pza 7.00 11.01 77.07 7.00 77.07 100% - 0% 7.00 77.07 100% 0.00 - 0%
04.01.06.02 REDES DE DERIVACION
04.01.06.02 RED DE DESAGUE TUBERIA PVC DE 2" m 43.63 13.67 596.42 43.63 596.42 100% - 0% 43.63 596.42 100% 0.00 - 0%
04.01.06.02 RED DE DESAGUE TUBERIA PVC DE 4" m 24.79 25.11 622.48 24.79 622.48 100% - 0% 24.79 622.48 100% 0.00 - 0%
04.01.06.03 REGISTRO Y SUMIDEROS
04.01.06.03 REGISTROS DE BRONCE DE 4" pza 5.00 32.79 163.95 5.00 163.95 100% - 0% 5.00 163.95 100% 0.00 - 0%
04.01.06.03 SUMIDEROS DE 2" pza 16.00 37.80 604.80 16.00 604.80 100% - 0% 16.00 604.80 100% 0.00 - 0%
04.01.06.04 CAJAS DE INSPECCION Y RETENCION
04.01.06.04 CAJA DE REGISTRO DE DESAGUE 10" X 20" x(h=mayor a 0.60m) und 10.00 145.15 1,451.50 10.00 1,451.50 100% - 0% 10.00 1,451.50 100% 0.00 - 0%
04.01.06.05 PRUEBAS HIDRAULICA
04.01.06.05 PRUEBA HIDRAULICA TUBERIA DE DESAGUE GLB 1.00 200.00 200.00 0.00 - 0% 1.00 200.00 100% 1.00 200.00 100% 0.00 - 0%
04.01.07 SISTEMA DE DRENAJE PLUVIAL
04.01.07.01 CAJAS DE INSPECCION Y RETENCION
04.01.07.01 CAJA DE REGISTRO 10" X 20" x(h=mayor a 0.60m) und 16.00 145.15 2,322.40 16.00 2,322.40 100% - 0% 16.00 2,322.40 100% 0.00 - 0%
04.01.07.02 SISTEMA DE BAJADA MONTANTE (PLUVIAL)
04.01.07.02 INSTALACION DE TUB. PVC SAP C-10 Ø 4" m 53.20 9.20 489.44 53.20 489.44 100% - 0% 53.20 489.44 100% 0.00 - 0%
04.01.07.02 TARRAJEO DE SUPERFICIE COLUMNETAS INCL. ARISTAS MEZ m2 31.92 32.32 1,031.65 31.92 1,031.65 100% - 0% 31.92 1,031.65 100% 0.00 - 0%
04.01.07.02 ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNETAS m2 31.92 45.47 1,451.40 31.92 1,451.40 100% - 0% 31.92 1,451.40 100% 0.00 - 0%
04.01.07.02 CONCRETO FC=175 KG/CM2 EN COLUMNETAS m3 2.21 493.65 1,090.97 2.21 1,090.97 100% - 0% 2.21 1,090.97 100% 0.00 - 0%
04.01.07.02 ABRAZADERA DE FIJACION DE TUBO und 57.00 23.86 1,360.02 0.00 - 0% 57.00 1,360.02 100% 57.00 1,360.02 100% 0.00 - 0%
04.02 OBRAS EXTERIORES
04.02.01 SISTEMA DE AGUA FRIA
04.02.01.01 INSTALACIONES EXTERIORES
04.02.01.01 TRAZO Y REPLANTEO m 122.54 3.05 373.75 122.54 373.75 100% - 0% 122.54 373.75 100% 0.00 - 0%
04.02.01.01 EXCAVACION DE ZANJAS REFINE Y CAMA DE APOYO m 122.54 24.23 2,969.14 122.54 2,969.14 100% - 0% 122.54 2,969.14 100% 0.00 - 0%
04.02.01.01 RELLENO CON MATERIAL PROPIO m 122.54 10.46 1,281.77 122.54 1,281.77 100% - 0% 122.54 1,281.77 100% 0.00 - 0%
04.02.01.01 INSTALACION DE TUB. PVC SAP C-10 Ø 3/4" m 134.79 7.83 1,055.41 134.79 1,055.41 100% - 0% 134.79 1,055.41 100% 0.00 - 0%
04.02.01.01 GRIFO DE RIEGO STANDARD - LLAVE DE 1/2" und 2.00 35.00 70.00 2.00 70.00 100% - 0% 2.00 70.00 100% 0.00 - 0%
04.02.02 SISTEMA DE DESAGUE
04.02.02.01 REDES DE DESAGUE
04.02.02.01 TRAZO Y REPLANTEO m 88.36 3.05 269.50 88.36 269.50 100% - 0% 88.36 269.50 100% 0.00 - 0%
04.02.02.01 EXCAVACION DE ZANJA MANUAL m3 37.11 33.36 1,237.99 37.11 1,237.99 100% - 0% 37.11 1,237.99 100% 0.00 - 0%
CONSORCIO CALEON
OBRA "MEJORAMIENTO DEL SERVICIO EDUCATIVO EN LAS I. E. DEL NIVEL INICIAL CICLO II EN LA LOCALIDADES DE HUANCHULLA, TACMARA, KIUÑALLA, KARQUEQUI, PACOMABAMBA Y HUANIPACA DEL DISTRITO DE HUANIPACA, PROVINCIA DE ABANCAY - APURIMAC"
04.02.02.01 RELLENO CON MATERIAL PROPIO SELECCIONADO m3 37.11 29.45 1,092.89 37.11 1,092.89 100% - 0% 37.11 1,092.89 100% 0.00 - 0%
04.02.02.01 RED DE DESAGUE TUBERIA PVC UF Ø DE 4" m 88.36 10.80 954.29 88.36 954.29 100% - 0% 88.36 954.29 100% 0.00 - 0%
04.02.02.02 CAJAS DE INSPECCION Y RETENCION
04.02.02.02 CAJA DE REGISTRO DE DESAGUE 24" X 24" - CONSTRUCION und 1.00 181.80 181.80 1.00 181.80 100% - 0% 1.00 181.80 100% 0.00 - 0%
04.02.02.03 INSTALACION A LA RED COLECTORA PUBLICA
04.02.02.03 INSTALACION A LA RED COLECTORA PUBLICA GLB 1.00 1,250.00 1,250.00 0.00 - 0% 1.00 1,250.00 100% 1.00 1,250.00 100% 0.00 - 0%
04.02.03 SISTEMA DE EVACUACION DE AGUAS PLUVIALES
04.02.03.01 AGUAS PLUVIALES
04.02.03.01 RED COLECTORA PARA AGUAS PLUVIALES TUB. PVC UF Ø DE m 205.25 20.64 4,236.36 205.25 4,236.36 100% - 0% 205.25 4,236.36 100% 0.00 - 0%
04.02.03.01 CONCRETO EN CUNETA F'C= 175KG/CM2 m3 7.61 463.44 3,526.78 7.61 3,526.78 100% - 0% 7.61 3,526.78 100% 0.00 - 0%
04.02.03.01 ENCOFRADO Y DESENCOFRADO PARA CUNETA m2 65.00 40.95 2,661.75 65.00 2,661.75 100% - 0% 65.00 2,661.75 100% 0.00 - 0%
04.02.03.01 TARRAJEO EN CUNETAS DE EVACUACION PLUVIAL m2 87.50 31.18 2,728.25 87.50 2,728.25 100% - 0% 87.50 2,728.25 100% 0.00 - 0%
04.02.03.01 REJILLA DE FIERRO PARA CANAL EVACUACION m 50.00 58.93 2,946.50 50.00 2,946.50 100% - 0% 50.00 2,946.50 100% 0.00 - 0%
04.03 ESTRUCTURA DE TANQUE ELEVADO
04.03.01 TANQUE DE POLIETILENO
04.03.01.01 TANQUE ELEVADO DE POLIETILENO C/ACCESORIOS pza 1.00 1,564.94 1,564.94 0.50 782.47 50% 0.50 782.47 50% 1.00 1,564.94 100% 0.00 - 0%
04.04 BIODIGESTOR Y POZO PERCOLADOR
04.04.01 TRABAJOS PRELIMINARES
04.04.01.01 LIMPIEZA DE TERRENO MANUAL m2 4.00 0.60 2.40 4.00 2.40 100% - 0% 4.00 2.40 100% 0.00 - 0%
04.04.02 MOVIMIENTO DE TIERRAS
04.04.02.01 EXCAVACION m3 5.62 34.01 191.14 5.62 191.14 100% - 0% 5.62 191.14 100% 0.00 - 0%
04.04.02.02 RELLENO CON MATERIAL PROPIO SELECCIONADO m3 0.48 29.45 14.14 0.48 14.14 100% - 0% 0.48 14.14 100% 0.00 - 0%
04.04.02.03 ACARREO INTERNO, MATERIAL PROCEDENTE DE EXCAVACION m3 1.20 19.46 23.35 1.20 23.35 100% - 0% 1.20 23.35 100% 0.00 - 0%
04.04.02.04 ELIMINACION DE MATERIAL EXCEDENTE m3 4.32 29.19 126.10 4.32 126.10 100% - 0% 4.32 126.10 100% 0.00 - 0%
04.04.03 CONCRETO SIMPLE
04.04.03.01 SOLADO E= 4" MEZCLA 1:12 EN ZAPATAS m2 0.29 37.97 11.01 0.00 - 0% 0.29 11.01 100% 0.29 11.01 100% 0.00 - 0%
04.04.04 POZO PERCOLADOR
04.04.04.01 FILTRO DE GRAVA CON PIEDRA MEDIANA m3 0.43 98.27 42.26 0.00 - 0% 0.43 42.26 100% 0.43 42.26 100% 0.00 - 0%
04.04.05 BIODIGESTOR DE 1300LT
04.04.05.01 BIODIGESTOR (1.3 m3) C/ACCESORIOS pza 1.00 1,664.94 1,664.94 0.50 832.47 50% 0.50 832.47 50% 1.00 1,664.94 100% 0.00 - 0%
04.05 SISTEMA CONTRA INCENDIO
04.05.01 EXTINTOR PQS (POLVO QUIMICO SECO) und 2.00 157.83 315.66 0.00 - 0% 2.00 315.66 100% 2.00 315.66 100% 0.00 - 0%
05 INSTALACIONES ELECTRICAS
05.01 BLOQUE - 1 AULAS PEDAGOGICAS
05.01.01 INSTALACIONES ELECTRICAS
05.01.01.01 SALIDA PARA CENTRO DE LUZ
05.01.01.01 SALIDA PARA LUMINARIA EN TECHO pto 11.00 76.71 843.81 11.00 843.81 100% - 0% 11.00 843.81 100% 0.00 - 0%
05.01.01.01 SALIDA PARA LUMINARIA DE EMERGENCIA pto 3.00 131.08 393.24 3.00 393.24 100% - 0% 3.00 393.24 100% 0.00 - 0%
05.01.01.02 SALIDA PARA INTERRUPTOR DE LUZ
05.01.01.02 SALIDA PARA INTERRUPTOR SIMPLE pto 7.00 54.67 382.69 7.00 382.69 100% - 0% 7.00 382.69 100% 0.00 - 0%
05.01.01.03 SALIDA PARA TOMACORRIENTES
05.01.01.03 SALIDA PARA TOMACORRIENTE DOBLE, CON TOMA A TIERRA pto 12.00 85.45 1,025.40 12.00 1,025.40 100% - 0% 12.00 1,025.40 100% 0.00 - 0%
05.01.01.04 INTERRUPTORES TERMOMAGNETICOS
CONSORCIO CALEON
OBRA "MEJORAMIENTO DEL SERVICIO EDUCATIVO EN LAS I. E. DEL NIVEL INICIAL CICLO II EN LA LOCALIDADES DE HUANCHULLA, TACMARA, KIUÑALLA, KARQUEQUI, PACOMABAMBA Y HUANIPACA DEL DISTRITO DE HUANIPACA, PROVINCIA DE ABANCAY - APURIMAC"
05.01.01.04 Interruptor magnetotérmico (II polos, 15 A, 220 V, 10 kA) pza 2.00 73.88 147.76 2.00 147.76 100% - 0% 2.00 147.76 100% 0.00 - 0%
05.01.01.04 Interruptor magnetotérmico (II polos, 20 A, 220 V, 10 kA) pza 2.00 83.88 167.76 2.00 167.76 100% - 0% 2.00 167.76 100% 0.00 - 0%
05.01.01.04 Interruptor magnetotérmico (II polos, 30 A, 220 V, 10 kA) pza 1.00 83.88 83.88 1.00 83.88 100% - 0% 1.00 83.88 100% 0.00 - 0%
05.01.01.04 Interruptor diferencial (II polos, 20 A, 220 V, 30mA) pza 2.00 119.88 239.76 2.00 239.76 100% - 0% 2.00 239.76 100% 0.00 - 0%
05.01.01.04 Interruptor diferencial (II polos, 25 A, 220 V, 30mA) pza 2.00 125.58 251.16 2.00 251.16 100% - 0% 2.00 251.16 100% 0.00 - 0%
05.01.01.05 TABLEROS
05.01.01.05 TABLERO DE DISTRIBUCION TD01 und 1.00 707.99 707.99 1.00 707.99 100% - 0% 1.00 707.99 100% 0.00 - 0%
05.01.01.05 TABLERO ELECTRICO GENERAL und 1.00 853.98 853.98 1.00 853.98 100% - 0% 1.00 853.98 100% 0.00 - 0%
05.01.01.06 ARTEFACTOS ELECTRICOS
05.01.01.06 Luminaria 2x18W con 2 fluorescentes lineales con rejilla y sistema o und 4.00 60.36 241.44 4.00 241.44 100% - 0% 4.00 241.44 100% 0.00 - 0%
05.01.01.06 Luminaria 4x18W con 4 fluorescentes lineales con rejilla y sistema o und 7.00 77.96 545.72 7.00 545.72 100% - 0% 7.00 545.72 100% 0.00 - 0%
05.01.01.06 ARTEFACTO AUTÓNOMO DE ALUMBRADO DE EMERGENCIA, C und 3.00 130.96 392.88 3.00 392.88 100% - 0% 3.00 392.88 100% 0.00 - 0%
05.01.01.07 PRUEBAS ELECTRICAS
05.01.01.07 PRUEBAS DE AISLAMIENTO Y RESISTIVIDAD RED GENERAL GLB 1.00 400.00 400.00 0.00 - 0% 1.00 400.00 100% 1.00 400.00 100% 0.00 - 0%
05.01.02 INSTALACIONES ESPECIALES
05.01.02.01 SALIDA DE SISTEMAS ESPECIALES
05.01.02.01 SALIDA PARA TELEFONO pto 2.00 359.05 718.10 2.00 718.10 100% - 0% 2.00 718.10 100% 0.00 - 0%
05.01.02.01 SALIDA PARA PUNTO DE TV-CABLE pto 1.00 77.55 77.55 1.00 77.55 100% - 0% 1.00 77.55 100% 0.00 - 0%
05.01.02.01 SALIDA PARA DATA EN PARED pto 8.00 101.86 814.88 8.00 814.88 100% - 0% 8.00 814.88 100% 0.00 - 0%
05.02 BLOQUE - 2 SALON DE USO MULTIPLE
05.02.01 INSTALACIONES ELECTRICAS
05.02.01.01 SALIDA PARA CENTRO DE LUZ
05.02.01.01 SALIDA PARA LUMINARIA EN TECHO pto 10.00 76.71 767.10 10.00 767.10 100% - 0% 10.00 767.10 100% 0.00 - 0%
05.02.01.01 SALIDA PARA LUMINARIA DE EMERGENCIA pto 1.00 131.08 131.08 1.00 131.08 100% - 0% 1.00 131.08 100% 0.00 - 0%
05.02.01.02 SALIDA PARA INTERRUPTOR DE LUZ
05.02.01.02 SALIDA PARA INTERRUPTOR SIMPLE pto 4.00 54.67 218.68 4.00 218.68 100% - 0% 4.00 218.68 100% 0.00 - 0%
05.02.01.03 SALIDA PARA TOMACORRIENTES
05.02.01.03 SALIDA PARA TOMACORRIENTE DOBLE, CON TOMA A TIERRA pto 8.00 85.45 683.60 8.00 683.60 100% - 0% 8.00 683.60 100% 0.00 - 0%
05.02.01.03 SALIDA PARA TOMACORRIENTE EN CAJA POP-UP CON TOMA pto 1.00 90.69 90.69 1.00 90.69 100% - 0% 1.00 90.69 100% 0.00 - 0%
05.02.01.04 INTERRUPTORES TERMOMAGNETICOS
05.02.01.04 Interruptor magnetotérmico (II polos, 15 A, 220 V, 10 kA) pza 2.00 73.88 147.76 2.00 147.76 100% - 0% 2.00 147.76 100% 0.00 - 0%
05.02.01.04 Interruptor magnetotérmico (II polos, 20 A, 220 V, 10 kA) pza 2.00 83.88 167.76 2.00 167.76 100% - 0% 2.00 167.76 100% 0.00 - 0%
05.02.01.04 Interruptor magnetotérmico (II polos, 30 A, 220 V, 10 kA) pza 1.00 83.88 83.88 1.00 83.88 100% - 0% 1.00 83.88 100% 0.00 - 0%
05.02.01.04 Interruptor diferencial (II polos, 20 A, 220 V, 30mA) pza 2.00 119.88 239.76 2.00 239.76 100% - 0% 2.00 239.76 100% 0.00 - 0%
05.02.01.04 Interruptor diferencial (II polos, 25 A, 220 V, 30mA) pza 2.00 125.58 251.16 2.00 251.16 100% - 0% 2.00 251.16 100% 0.00 - 0%
05.02.01.05 TABLEROS
05.02.01.05 TABLERO DE DISTRIBUCION TD01 und 1.00 707.99 707.99 1.00 707.99 100% - 0% 1.00 707.99 100% 0.00 - 0%
05.02.01.06 ARTEFACTOS ELECTRICOS
05.02.01.06 Luminaria 2x18W con 2 fluorescentes lineales con rejilla y sistema o und 4.00 60.36 241.44 4.00 241.44 100% - 0% 4.00 241.44 100% 0.00 - 0%
05.02.01.06 Luminaria 4x18W con 4 fluorescentes lineales con rejilla y sistema o und 6.00 77.96 467.76 6.00 467.76 100% - 0% 6.00 467.76 100% 0.00 - 0%
05.02.01.06 ARTEFACTO AUTÓNOMO DE ALUMBRADO DE EMERGENCIA, C und 1.00 130.96 130.96 1.00 130.96 100% - 0% 1.00 130.96 100% 0.00 - 0%
05.02.01.07 PRUEBAS ELECTRICAS
05.02.01.07 PRUEBAS DE AISLAMIENTO Y RESISTIVIDAD RED GENERAL GLB 1.00 400.00 400.00 0.00 - 0% 1.00 400.00 100% 1.00 400.00 100% 0.00 - 0%
CONSORCIO CALEON
OBRA "MEJORAMIENTO DEL SERVICIO EDUCATIVO EN LAS I. E. DEL NIVEL INICIAL CICLO II EN LA LOCALIDADES DE HUANCHULLA, TACMARA, KIUÑALLA, KARQUEQUI, PACOMABAMBA Y HUANIPACA DEL DISTRITO DE HUANIPACA, PROVINCIA DE ABANCAY - APURIMAC"
06.09.01.02 CORTE DE MATERIAL SUELTO CON MAQUINARIA m3 109.53 4.93 539.98 109.53 539.98 100% - 0% 109.53 539.98 100% 0.00 - 0%
06.09.01.02 RELLENO COMPACTADO CON MATERIAL PROPIO EN CAPAS D m3 93.43 14.15 1,322.03 93.43 1,322.03 100% - 0% 93.43 1,322.03 100% 0.00 - 0%
06.09.01.03 MUROS DE CONTENCION DE CONCRETO CICLOPEO
06.09.01.03 CONCRETO CICLOPEO FC=140 KG/CM2 + 70 % PG. EN CIMIEN m3 153.33 327.84 50,267.71 153.33 50,267.71 100% - 0% 153.33 50,267.71 100% 0.00 - 0%
06.09.02 CERCO PERIMETRICO EN MURO DE CONTENCION
06.09.02.01 CONCRETO ARMADO
06.09.02.01 COLUMNAS
06.09.02.01 CONCRETO EN COLUMNAS F'C=210 KG/CM2 m3 5.26 437.73 2,302.46 5.26 2,302.46 100% - 0% 5.26 2,302.46 100% 0.00 - 0%
06.09.02.01 ACERO CORRUGADO G-60 EN COLUMNAS kg 531.98 4.20 2,234.32 531.98 2,234.32 100% - 0% 531.98 2,234.32 100% 0.00 - 0%
06.09.02.01 ENCOFRADO Y DESENCOFRADO m2 76.50 32.00 2,448.00 76.50 2,448.00 100% - 0% 76.50 2,448.00 100% 0.00 - 0%
06.09.02.01 VIGAS DE CORONACION
06.09.02.01 CONCRETO EN VIGAS F'C=210 KG/CM2 m3 4.20 437.73 1,838.47 4.20 1,838.47 100% - 0% 4.20 1,838.47 100% 0.00 - 0%
06.09.02.01 ACERO CORRUGADO G-60 EN VIGAS kg 394.75 4.20 1,657.95 394.75 1,657.95 100% - 0% 394.75 1,657.95 100% 0.00 - 0%
06.09.02.01 ENCOFRADO Y DESNCOFRADO NORMAL EN VIGAS m2 56.00 32.00 1,792.00 56.00 1,792.00 100% - 0% 56.00 1,792.00 100% 0.00 - 0%
06.09.02.02 JUNTAS DE CONSTRUCCION
06.09.02.02 JUNTAS DE DILATACION ASFALTICA m 39.00 4.51 175.89 39.00 175.89 100% - 0% 39.00 175.89 100% 0.00 - 0%
06.09.02.03 CARPINTERIA METALICA
06.09.02.03 CERCO DE MALLA ELECTROSOLDADA, ALAMBRE Nro 10, PERF m2 175.91 80.00 14,072.80 175.91 14,072.80 100% - 0% 175.91 14,072.80 100% 0.00 - 0%
07 ARQUITECTURA - OBRAS EXTERIORES
07.01 PATIO, ACCESO Y AREAS LIBRES
07.01.01 PISOS Y PAVIMENTOS
07.01.01.01 PISO DE CEMENTO FROTACHADO BRUÑADO m2 222.84 18.60 4,144.82 222.84 4,144.82 100% - 0% 222.84 4,144.82 100% 0.00 - 0%
07.01.01.02 PISO DE ARENA FINA e=30 cm m2 68.50 38.57 2,642.05 0.00 - 0% 68.50 2,642.05 100% 68.50 2,642.05 100% 0.00 - 0%
07.01.02 TRATAMIENTO DE AREAS VERDES
07.01.02.01 SEMBRADO DE GRASS m2 492.79 3.37 1,660.70 0.00 - 0% 492.79 1,660.70 100% 492.79 1,660.70 100% 0.00 - 0%
07.02 VEREDAS
07.02.01 PISOS Y PAVIMENTOS
07.02.01.01 PISO DE CEMENTO FROTACHADO BRUÑADO m2 157.76 18.60 2,934.34 157.76 2,934.34 100% - 0% 157.76 2,934.34 100% 0.00 - 0%
07.02.01.02 BRUÑA DE 1CM EN VEREDA m 442.80 2.15 952.02 442.80 952.02 100% - 0% 442.80 952.02 100% 0.00 - 0%
07.03 HALL DE INGRESO
07.03.01 PISOS Y PAVIMENTOS
07.03.01.01 PISO DE ENCHAPADO DE PIEDRA m2 47.42 142.07 6,736.96 47.42 6,736.96 100% - 0% 47.42 6,736.96 100% 0.00 - 0%
07.03.01.02 BRUÑA DE 1CM EN VEREDA m 88.00 2.15 189.20 88.00 189.20 100% - 0% 88.00 189.20 100% 0.00 - 0%
07.04 RAMPA
07.04.01 TARRAJEO EN PARAPETOS
07.04.01.01 TARRAJEO EN PARAPETO MEZCLA 1:5 CEMENTO:ARENA m2 138.60 25.49 3,532.91 138.60 3,532.91 100% - 0% 138.60 3,532.91 100% 0.00 - 0%
07.04.02 PISOS Y PAVIMENTOS
07.04.02.01 PISO DE CEMENTO FROTACHADO BRUÑADO m2 44.88 18.60 834.77 44.88 834.77 100% - 0% 44.88 834.77 100% 0.00 - 0%
07.04.02.02 BRUÑA DE 1CM EN VEREDA m 275.30 2.15 591.90 275.30 591.90 100% - 0% 275.30 591.90 100% 0.00 - 0%
07.04.03 PINTURA
07.04.03.01 PINTURA EN PARAPETOS m2 36.20 8.46 306.25 0.00 - 0% 36.20 306.25 100% 36.20 306.25 100% 0.00 - 0%
07.04.04 CARPINTERIA METALICA
07.04.04.01 BARANDAS METALICAS m 59.48 80.00 4,758.40 0.00 - 0% 59.48 4,758.40 100% 59.48 4,758.40 100% 0.00 - 0%
CONSORCIO CALEON
OBRA "MEJORAMIENTO DEL SERVICIO EDUCATIVO EN LAS I. E. DEL NIVEL INICIAL CICLO II EN LA LOCALIDADES DE HUANCHULLA, TACMARA, KIUÑALLA, KARQUEQUI, PACOMABAMBA Y HUANIPACA DEL DISTRITO DE HUANIPACA, PROVINCIA DE ABANCAY - APURIMAC"
07.08.01 TARRAJEO EN MASTIL m2 5.73 16.00 91.68 0.00 - 0% 5.73 91.68 100% 5.73 91.68 100% 0.00 - 0%
07.08.02 MASTIL DE F°G° 4" - SEGUN DISEÑO GLB 2.00 650.00 1,300.00 0.00 - 0% 2.00 1,300.00 100% 2.00 1,300.00 100% 0.00 - 0%
07.09 CERCO PERIMETRICO
07.09.01 MUROS Y TABIQUES
07.09.01.01 MURO DE SOGA LADRILLO KIN-KONG CARAVISTA m2 248.58 107.19 26,645.29 248.58 26,645.29 100% - 0% 248.58 26,645.29 100% 0.00 - 0%
07.09.02 REVOQUES ENLUCIDOS Y MOLDURAS
07.09.02.01 TARRAJEO DE SUPERFICIE COLUMNAS INCL. ARISTAS MEZCLA m2 62.48 34.67 2,166.18 62.48 2,166.18 100% - 0% 62.48 2,166.18 100% 0.00 - 0%
07.09.02.02 TARRAJEO DE SUPERF.VIGAS INCL.ARISTAS, MEZCLA 1:5 CEME m2 72.17 34.67 2,502.13 72.17 2,502.13 100% - 0% 72.17 2,502.13 100% 0.00 - 0%
07.09.03 PINTURA
07.09.03.01 PINTURA EN CERCO m2 134.64 15.71 2,115.19 0.00 - 0% 134.64 2,115.19 100% 134.64 2,115.19 100% 0.00 - 0%
08 MITIGACION DE IMPACTO AMBIENTAL
08.01 IMPLEMENTACION DEL PLAN DE MANEJO AMBIENTAL
08.01.01 CONTENEDORES DE RESIDUOS SOLIDOS und 9.00 180.00 1,620.00 9.00 1,620.00 100% - 0% 9.00 1,620.00 100% 0.00 - 0%
08.01.02 CONSTRUCCION DE HOYOS PARA DEPOSITO DE BASURA Y SELL und 2.00 227.13 454.26 2.00 454.26 100% - 0% 2.00 454.26 100% 0.00 - 0%
08.01.03 CONSTRUCCION DE LETRINAS DE ARRASTRE HIDRAULICO und 1.00 300.00 300.00 1.00 300.00 100% - 0% 1.00 300.00 100% 0.00 - 0%
08.02 PROGRAMA DE MITIGACION AMBIENTAL
08.02.01 CHARLAS DE SENSIBILIZACION GLB 4.00 1,000.00 4,000.00 4.00 4,000.00 100% - 0% 4.00 4,000.00 100% 0.00 - 0%
08.02.02 MONITOREO AMBIENTAL GLB 2.00 3,500.00 7,000.00 1.90 6,650.00 95% 0.10 350.00 5% 2.00 7,000.00 100% 0.00 - 0%
08.03 PLAN DE CIERRE
08.03.01 DESMONTAJE DE INSTALACIONES PROVICIONALES GLB 1.00 899.01 899.01 1.00 899.01 100% - 0% 1.00 899.01 100% 0.00 - 0%
08.03.02 LIMPIEZA PERMANENTE Y FINAL DE OBRA GLB 1.00 3,500.00 3,500.00 0.95 3,325.00 95% 0.05 175.00 5% 1.00 3,500.00 100% 0.00 - 0%
08.04 PLAN DE CONTINGENCIA
08.04.01 BRIGADA DE EMERGENCIAS, 01 PERSONA EQUIPO DE EMERGEN GLB 1.00 2,000.00 2,000.00 1.00 2,000.00 100% - 0% 1.00 2,000.00 100% 0.00 - 0%
08.04.02 CAPACITACIONES DE INDUCCION AL PERSONAL DE OBRA GLB 4.00 300.00 1,200.00 4.00 1,200.00 100% - 0% 4.00 1,200.00 100% 0.00 - 0%
08.04.03 EQUIPO CONTRA INCENDIOS (Extintor 9kg) GLB 4.00 100.00 400.00 4.00 400.00 100% - 0% 4.00 400.00 100% 0.00 - 0%
08.05 MONITERO AMBIENTAL
08.05.01 MONITOREO DE LA CALIDAD DEL AIRE GLB 2.00 900.00 1,800.00 2.00 1,800.00 100% - 0% 2.00 1,800.00 100% 0.00 - 0%
08.05.02 MONITOREO DE LA CALIDAD DEL RUIDO GLB 2.00 900.00 1,800.00 2.00 1,800.00 100% - 0% 2.00 1,800.00 100% 0.00 - 0%
09 MOBILIARIO
09.01 MOBILIARIO ESCOLAR GLB 1.00 31,787.00 31,787.00 0.80 25,429.60 80% 0.20 6,357.40 20% 1.00 31,787.00 100% 0.00 - 0%
10 EQUIPAMIENTO
10.01 EQUIPAMIENTO ESCOLAR GLB 1.00 42,217.56 42,217.56 0.80 33,774.05 80% 0.20 8,443.51 20% 1.00 42,217.56 100% 0.00 - 0%
11 CAPACITACION DOCENTE Y SOCIAL
11.01 CAPACITACION DOCENTE Y SOCIAL GLB 1.00 6,545.00 6,545.00 0.00 - 0% 1.00 6,545.00 100% 1.00 6,545.00 100% 0.00 - 0%
12 CAPACITACION PADRES DE FAMILIA
12.01 CAPACITACION PADRES DE FAMILIA GLB 1.00 7,593.00 7,593.00 0.00 - 0% 1.00 7,593.00 100% 1.00 7,593.00 100% 0.00 - 0%
13 MATERIALES DIDACTICO
13.01 MATERIALES DIDACTICO PARA ALUMNOS GLB 1.00 5,874.00 5,874.00 0.00 - 0% 1.00 5,874.00 100% 1.00 5,874.00 100% 0.00 - 0%
14 GESTION DE RIESGOS
14.01 GESTION DE RIESGOS GLB 1.00 14,150.00 14,150.00 1.00 14,150.00 100% - 0% 1.00 14,150.00 100% 0.00 - 0%
15 FLETE TERRESTRE
15.01 FLETE TERRESTRE (KARQUEQUI) GLB 1.00 44,321.61 44,321.61 0.98 43,435.18 98% 0.02 886.43 2% 1.00 44,321.61 100% 0.00 - 0%
COSTO DIRECTO 1,038,422.77 950,206.65 88,216.12 1,038,422.77 -
CONSORCIO CALEON
OBRA "MEJORAMIENTO DEL SERVICIO EDUCATIVO EN LAS I. E. DEL NIVEL INICIAL CICLO II EN LA LOCALIDADES DE HUANCHULLA, TACMARA, KIUÑALLA, KARQUEQUI, PACOMABAMBA Y HUANIPACA DEL DISTRITO DE HUANIPACA, PROVINCIA DE ABANCAY - APURIMAC"
I.E.I N° 29 HUANIPACA
01 OBRAS PROVISIONALES, DEMOLICION, EXPLANACION, SAGURIDAD Y SALUD
01.01 CONSTRUCCIONES PROVISIONALES
01.01.01 OBRAS PROVISIONALES
01.01.01.01 CONSTRUCCION DE ALMACEN Y GUARDIANIA und 1.00 5,176.28 5,176.28 1.00 5,176.28 100% - 0% 1.00 5,176.28 100% 0.00 - 0%
01.01.01.02 CARTEL DE IDENTIFICACION DE LA OBRA DE 5.40M X 4.20M. und 1.00 975.04 975.04 1.00 975.04 100% - 0% 1.00 975.04 100% 0.00 - 0%
01.01.01.03 INSTALACION DE CERCO PERIMETRICO PROVISIONAL m 147.58 9.50 1,402.01 147.58 1,402.01 100% - 0% 147.58 1,402.01 100% 0.00 - 0%
01.01.01.04 INSTALACION DE AGUA PARA LA CONSTRUCCION GLB 1.00 138.29 138.29 1.00 138.29 100% - 0% 1.00 138.29 100% 0.00 - 0%
01.01.01.05 INSTALACIONES ELECTRICAS PROVISIONALES mes 4.00 450.00 1,800.00 4.00 1,800.00 100% - 0% 4.00 1,800.00 100% 0.00 - 0%
01.02 TRABAJOS PRELIMINARES
01.02.01 LIMPIEZA DE TERRENO
01.02.01.01 LIMPIEZA DE TERRENO MANUAL m2 1048.58 0.60 629.15 1048.58 629.15 100% - 0% 1048.58 629.15 100% 0.00 - 0%
01.02.02 TRAZOS, NIVELES Y REPLANTEO
01.02.02.01 TRAZO, NIVELES Y REPLANTEO PRELIMINAR CON VALLAS AISLADAS m2 1048.58 2.14 2,243.96 1048.58 2,243.96 100% - 0% 1048.58 2,243.96 100% 0.00 - 0%
01.02.02.02 TRAZO, NIVELES Y REPLANTEO DURANTE EL PROCESO m2 1048.58 1.52 1,593.84 1048.58 1,593.84 100% - 0% 1048.58 1,593.84 100% 0.00 - 0%
01.03 DESMONTAJE Y DEMOLICION
01.03.01 DEMOLICIONES
01.03.01.01 DEMOLICION DE MUROS DE DE ADOBE m2 127.50 3.34 425.85 127.50 425.85 100% - 0% 127.50 425.85 100% 0.00 - 0%
01.04 PLAN DE SEGURIDAD Y SALUD OCUPACIONAL
01.04.01 ELABORACION, IMPLEMENTACION Y ADMINISTRACION DEL PLAN DE SEG GLB 1.00 2,540.00 2,540.00 1.00 2,540.00 100% - 0% 1.00 2,540.00 100% 0.00 - 0%
01.04.02 EQUIPOS DE PROTECCIÓN INDIVIDUAL GLB 1.00 5,000.00 5,000.00 1.00 5,000.00 100% - 0% 1.00 5,000.00 100% 0.00 - 0%
01.04.03 EQUIPOS DE PROTECCIÓN COLECTIVA GLB 1.00 3,600.00 3,600.00 1.00 3,600.00 100% - 0% 1.00 3,600.00 100% 0.00 - 0%
01.04.04 CAPACITACIÓN EN SEGURIDAD Y SALUD GLB 1.00 3,140.00 3,140.00 1.00 3,140.00 100% - 0% 1.00 3,140.00 100% 0.00 - 0%
01.04.05 SEÑALIZACIÓN TEMPORAL DE SEGURIDAD GLB 1.00 1,255.00 1,255.00 1.00 1,255.00 100% - 0% 1.00 1,255.00 100% 0.00 - 0%
01.04.06 RECURSOS PARA RESPUESTAS ANTE EMERGENCIAS EN SEGURIDAD Y GLB 1.00 1,360.00 1,360.00 1.00 1,360.00 100% - 0% 1.00 1,360.00 100% 0.00 - 0%
02 ESTRUCTURAS
02.01 BLOQUES I, II, III, IV.
02.01.01 TRABAJOS PRELIMINARES
02.01.01.01 LIMPIEZA DE TERRENO MANUAL m2 424.74 0.98 416.25 424.74 416.25 100% - 0% 424.74 416.25 100% 0.00 - 0%
02.01.01.02 TRAZO Y REPLANTEO m2 424.74 1.85 785.77 424.74 785.77 100% - 0% 424.74 785.77 100% 0.00 - 0%
02.01.02 MOVIMIENTO DE TIERRAS
02.01.02.01 EXCAVACION PARA CIMIENTOS-ZAPATAS m3 200.69 32.71 6,564.57 200.69 6,564.57 100% - 0% 200.69 6,564.57 100% 0.00 - 0%
02.01.02.02 RELLENO COMPACTADO CON MATERIAL PROPIO EN CAPAS DE 0.20m. m3 92.86 24.73 2,296.43 92.86 2,296.43 100% - 0% 92.86 2,296.43 100% 0.00 - 0%
02.01.02.03 NIVELACION Y COMPACTACION DE TERRENO m2 424.75 8.43 3,580.64 424.75 3,580.64 100% - 0% 424.75 3,580.64 100% 0.00 - 0%
02.01.02.04 ELIMINACION DE MATERIAL EXCEDENTE m3 168.49 9.73 1,639.41 168.49 1,639.41 100% - 0% 168.49 1,639.41 100% 0.00 - 0%
02.01.03 CONCRETO SIMPLE
02.01.03.01 SOLADO E= 4" MEZCLA 1:12 EN ZAPATAS m2 93.18 12.82 1,194.57 93.18 1,194.57 100% - 0% 93.18 1,194.57 100% 0.00 - 0%
02.01.03.02 SOLADO E= 2" MEZCLA 1:12 EN VIGAS DE CIMENTACION m2 50.26 12.82 644.33 50.26 644.33 100% - 0% 50.26 644.33 100% 0.00 - 0%
02.01.03.03 CIMIENTOS CORRIDOS MEZCLA 1:10 CEMENTO-HORMIGON 30% PIEDR m3 75.63 230.72 17,449.35 75.63 17,449.35 100% - 0% 75.63 17,449.35 100% 0.00 - 0%
02.01.03.04 CONCRETO 1:8+25% P.M. PARA SOBRECIMIENTOS m3 15.77 301.55 4,755.44 15.77 4,755.44 100% - 0% 15.77 4,755.44 100% 0.00 - 0%
02.01.03.05 ENCOFRADO Y DESENCOFRADO NORMAL PARA SOBRECIMIENTOS HA m2 144.48 28.53 4,122.01 144.48 4,122.01 100% - 0% 144.48 4,122.01 100% 0.00 - 0%
02.01.04 CONCRETO ARMADO
02.01.04.01 ZAPATAS
02.01.04.01.01 CONCRETO PARA ZAPATAS F'C=210 KG/CM2 m3 33.02 437.72 14,453.51 33.02 14,453.51 100% - 0% 33.02 14,453.51 100% 0.00 - 0%
02.01.04.01.02 ACERO CORRUGADO G-60 EN ZAPATAS kg 1408.04 4.20 5,913.77 1408.04 5,913.77 100% - 0% 1408.04 5,913.77 100% 0.00 - 0%
02.01.04.02 VIGAS DE CIMENTACION
02.01.04.02.01 CONCRETO F'C= 210 KG/CM2 EN VIGAS DE CIMENTACIÓN m3 15.22 437.72 6,662.10 15.22 6,662.10 100% - 0% 15.22 6,662.10 100% 0.00 - 0%
02.01.04.02.02 ACERO F'Y=4200 KG/CM2 GRADO 60 EN VIGAS DE CIMENTACIÓN kg 2519.21 4.20 10,580.68 2519.21 10,580.68 100% - 0% 2519.21 10,580.68 100% 0.00 - 0%
02.01.04.02.03 ENCOFRADO Y DESENCOFRADO DE VIGAS DE CIMENTACIÓN m2 128.87 32.00 4,123.84 128.87 4,123.84 100% - 0% 128.87 4,123.84 100% 0.00 - 0%
02.01.04.03 COLUMNAS
02.01.04.03.01 CONCRETO EN COLUMNAS F'C=210 KG/CM2 m3 21.95 437.72 9,607.95 21.95 9,607.95 100% - 0% 21.95 9,607.95 100% 0.00 - 0%
02.01.04.03.02 ACERO CORRUGADO G-60 EN COLUMNAS kg 3720.51 4.20 15,626.14 3720.51 15,626.14 100% - 0% 3720.51 15,626.14 100% 0.00 - 0%
02.01.04.03.03 ENCOFRADO Y DESENCOFRADO m2 300.40 32.00 9,612.80 300.40 9,612.80 100% - 0% 300.40 9,612.80 100% 0.00 - 0%
CONSORCIO CALEON
OBRA "MEJORAMIENTO DEL SERVICIO EDUCATIVO EN LAS I. E. DEL NIVEL INICIAL CICLO II EN LA LOCALIDADES DE HUANCHULLA, TACMARA, KIUÑALLA, KARQUEQUI, PACOMABAMBA Y HUANIPACA DEL DISTRITO DE HUANIPACA, PROVINCIA DE ABANCAY - APURIMAC"
VALORIZACION DE OBRA Nº 08 - 2020
Meta: I.E.I N° 29 -HUANIPACA
Del 01/10/2020 Al 19/10/2020
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE HUANIPACA
EJECUTA : CONSORCIO COCHARCAS
SUPERVISA : CONSORCIO CALEON
PLAZO : 150 DIAS CALENDARIOS
SUPERVISOR : ING. JUSTINIANO CRUZ CARDENAS
RESIDENTE ; ARQ. FREDDY LOAYZA ENCALADA