FECHA: 09/01/2018
OBRA : HOME CENTER TUNJA
CONTRATANTE: CONSTRUCTORA COLPATRIA
Actividad del Presupuesto Insumo de presupuesto Und. Cant Ppto Vr Unit VR. TOTAL
A 8% $4,787,280
I 4% $2,393,640
U 4% $2,393,640
IVA/U 16% $382,982
TOTAL $ 69,798,542
Firma contratista :
Nit# 900.509.015-1
Empresa: CONDISCON SAS
Contacto: BORIS DAVID MENDOZA
Celular contacto: 3007975050
FORMATO DE PRODUCTIVIDAD Y LOGISTICA
WC
FORMATO Analisis de Precios Unitarios
MANO DE OBRA
DESCRIPCION UN CANT RENDIMIENTO VR. UNIT VR. TOTAL
OFICIAL DIA 1.00 8% $ 91,900 $ 7,352.00
AYUDANTE DIA 1.00 6% $ 67,350 $ 4,041.00
SUBTOTAL MANO DE OBRA 11,393
EQUIPO Y HERRAMIENTA
DESCRIPCION UN CANT RENDIMIENTO VR. UNIT VR. TOTAL
HERRAMIENTA MENOR GBL 1.00 2% $ 15,000 $ 300.00
PULIDORA DIA 1.00 2% $ 35,000 $ 700.00
EXTENCION DIA 1.00 3% $ 1,000 $ 30.00
TALADRO DEMOLEDOR DIA 1.00 3% $ 55,000 $ 1,650.00
ANDAMIO CERTIFICADO DIA 1.00 50% $ 3,500 $ 1,750.00
PUNTA PARA DEMOLEDOR DIA 1.00 20% $ 1,000 $ 200.00
BROCA PARA ANCLAJES UN 1.00 5% $ 9,000 $ 450.00
SUBTOTAL EQUIPO Y HERRAMIENTA 5,080
MATERIALES
DESCRIPCION UN CANT RENDIMIENTO VR. UNIT VR. TOTAL
ACRONAL KL 0.50 50% $ 3,700 $ 925.00
CEMENTO BLANCO KL 0.50 30% $ 1,200 $ 180.00
CEMENTO GRIS KL 1.00 10% $ 500 $ 50.00
SIKA TOP 121 KL 1.00 100% $ 4,800 $ 4,800.00
PIEDRA COPA UD 1.00 5% $ 45,000 $ 2,250.00
SUBTOTAL MATERIALES 8,205
MANO DE OBRA
DESCRIPCION UN CANT RENDIMIENTO VR. UNIT VR. TOTAL
OFICIAL DIA 1.00 4% $ 91,900 3,676 $
AYUDANTE DIA 1.00 4% $ 67,350 2,694 $
SUBTOTAL MANO DE OBRA 6,370
EQUIPO Y HERRAMIENTA
DESCRIPCION UN CANT RENDIMIENTO VR. UNIT VR. TOTAL
HERRAMIENTA MENOR GBL 1.00 2% $ 15,000 300 $
PULIDORA DIA 1.00 2% $ 35,000 700 $
EXTENCION DIA 1.00 3% $ 1,000 30 $
ANDAMIO CERTIFICADO DIA 1.00 30% $ 3,500 1,050 $
SUBTOTAL EQUIPO Y HERRAMIENTA 2,080
MATERIALES
DESCRIPCION UN CANT RENDIMIENTO VR. UNIT VR. TOTAL
ACRONAL GL 1.00 3% $ 28,500 855.00
CEMENTO BLANCO KL 0.50 30% $ 1,200 180.00
CEMENTO GRIS KL 1.00 20% $ 500 100.00
PIEDRA COPA UD 1.00 2% $ 45,000 900.00
SUBTOTAL MATERIALES 2,035